Energy consumption management method and storage medium

By dividing subsystem categories according to historical data and outdoor temperature, and using neural network models to predict energy consumption, the problem of building energy consumption management that is difficult to separate subsystem energy consumption is solved, and more accurate energy consumption management and early warning are achieved.

CN118735731APending Publication Date: 2024-10-01BEIJING FUTURE TECH CITY DEV CO LTD +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202310321627.6
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2023-03-29
Publication Date
2024-10-01

AI Technical Summary

Technical Problem

The existing building energy consumption management model is difficult to split the total energy consumption into various subsystems, making it difficult for managers to manage the energy consumption of subsystems in a targeted manner.

Method used

By determining the subsystem category based on the historical energy consumption and historical outdoor temperature of each subsystem, the pre-trained neural network model is used to obtain the predicted energy consumption of each subsystem, and the daily predicted energy consumption is calculated based on the set energy consumption, and finally the energy consumption is calculated. To manage.

Benefits of technology

It achieves more accurate prediction and management of building subsystem energy consumption, can more accurately control energy consumption, and provide early warning or alarm through energy consumption progress values.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118735731A_ABST
    Figure CN118735731A_ABST
Patent Text Reader

Abstract

The invention discloses an energy consumption management method and a storage medium. The category of each subsystem is determined according to historical energy consumption and historical outdoor temperature of each subsystem, the category comprises a first category of subsystems and a second category of subsystems, and first predicted energy consumption corresponding to the first category of subsystems is obtained through a pre-trained neural network model. And acquiring second predicted energy consumption corresponding to the second type of subsystems according to the historical energy consumption, determining total predicted energy consumption according to the first predicted energy consumption and the second predicted energy consumption, determining daily predicted energy consumption of each subsystem according to set energy consumption and the total predicted energy consumption, and managing the energy consumption according to the daily predicted energy consumption. Therefore, the energy consumption of the subsystem can be predicted more accurately, and the energy consumption condition can be controlled more accurately.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the field of energy management, and in particular to an energy consumption management method and a storage medium. Background Art

[0002] Building energy consumption management plays an important role in energy conservation and emission reduction. Building energy consumption can usually be divided into multiple subsystems. However, in practical applications, building energy consumption is generally managed through the total energy consumption of the building. However, this management model makes it difficult to divide the total energy consumption into each subsystem, and it is difficult for managers to manage the energy consumption of the subsystem in a targeted manner. Summary of the invention

[0003] In view of this, an object of the present invention is to provide an energy consumption management method and a storage medium, which can more accurately predict and manage the energy consumption of subsystems of a building.

[0004] In a first aspect, an embodiment of the present invention provides an energy consumption management method, the method comprising:

[0005] Determine the category of each subsystem according to the historical energy consumption and the historical outdoor temperature of each subsystem, wherein the category includes a first category subsystem and a second category subsystem;

[0006] Obtaining a first predicted energy consumption corresponding to the first type of subsystem through a pre-trained neural network model;

[0007] Acquire a second predicted energy consumption corresponding to the second type of subsystem according to the historical energy consumption;

[0008] Determining a total predicted energy consumption according to the first predicted energy consumption and the second predicted energy consumption;

[0009] Determine the daily predicted energy consumption of each subsystem according to the set energy consumption and the total predicted energy consumption;

[0010] Energy consumption is managed based on the daily predicted energy consumption.

[0011] Preferably, determining the category of each subsystem according to the historical energy consumption and historical outdoor temperature of each subsystem includes:

[0012] Determine the classification index of each subsystem based on the historical energy consumption and historical outdoor temperature of each subsystem;

[0013] In response to the classification index corresponding to the subsystem being greater than or equal to a predetermined threshold, determining the corresponding subsystem as a first-category subsystem;

[0014] In response to the classification index corresponding to the subsystem being less than a predetermined threshold, the corresponding subsystem is determined as a second-category subsystem.

[0015] Preferably, obtaining the first predicted energy consumption corresponding to the first type of subsystem by using a pre-trained neural network model includes:

[0016] Calculating a first type of temperature value and a second type of temperature value according to the historical outdoor temperature and a predetermined reference temperature;

[0017] Calculating the daily predicted energy consumption of the first type of subsystem according to the first type of temperature value and the second type of temperature value; and

[0018] The first predicted energy consumption of each first-category subsystem is determined according to the daily predicted energy consumption.

[0019] Preferably, the total predicted energy consumption is the predicted energy consumption for each month;

[0020] Wherein, determining the daily predicted energy consumption of each subsystem according to the set energy consumption and the total predicted energy consumption includes:

[0021] For the months in which the set energy consumption is consistent with the total predicted energy consumption, determining the daily predicted energy consumption corresponding to the first predicted energy consumption as the daily predicted energy consumption of the first type of subsystem, and determining the daily predicted energy consumption of the second type of subsystem according to the second predicted energy consumption by using the sliding cycle coefficient method; and

[0022] For the months when the set energy consumption is inconsistent with the total predicted energy consumption, the daily predicted energy consumption of each subsystem is obtained by the sliding week coefficient method.

[0023] Preferably, determining the daily predicted energy consumption of the second type of subsystem according to the second predicted energy consumption by using the sliding cycle coefficient method includes:

[0024] Obtain historical energy consumption of the second type of subsystem for one consecutive week in history;

[0025] Calculating a sliding week proportional coefficient of the second type of subsystem according to the historical energy consumption of the second type of subsystem for the consecutive week; and

[0026] The daily predicted energy consumption of the second type of subsystem is obtained according to the sliding cycle proportional coefficient and the second predicted energy consumption.

[0027] Preferably, obtaining the daily predicted energy consumption of each subsystem by the sliding cycle coefficient method includes:

[0028] Obtain the historical energy consumption of each subsystem for a consecutive week in history;

[0029] Calculating the sliding cycle proportional coefficient of each subsystem according to the historical energy consumption of each subsystem for one consecutive week in the history; and

[0030] The daily predicted energy consumption of each subsystem is obtained according to the sliding week proportional coefficient and the monthly set energy consumption of each subsystem.

[0031] Preferably, the monthly set energy consumption corresponding to the first type of subsystem is the ratio of each first predicted energy consumption to the total predicted energy consumption multiplied by the set energy consumption, and the monthly set energy consumption corresponding to the second type of subsystem is the ratio of each second predicted energy consumption to the total predicted energy consumption multiplied by the set energy consumption.

[0032] Preferably, managing energy consumption according to the daily predicted energy consumption includes:

[0033] Obtaining the energy consumption progress value for the month based on the daily predicted energy consumption; and

[0034] An early warning or alarm is issued for the energy consumption of the current month according to the energy consumption progress value.

[0035] Preferably, managing energy consumption according to the daily predicted energy consumption and the energy consumption progress value includes:

[0036] Obtaining the actual energy consumption of the current month, where the actual energy consumption is the sum of the actual daily energy consumption of the days that have occurred in the current month;

[0037] Obtain the predicted energy consumption that has not occurred in the current month, where the predicted energy consumption that has not occurred is the sum of the daily predicted energy consumption of the days that have not occurred in the current month;

[0038] Acquire simulated energy consumption for the current month according to the actual energy consumption and the predicted energy consumption that has not occurred, wherein the simulated energy consumption is the sum of the actual energy consumption and the predicted energy consumption that has not occurred; and

[0039] Calculate the energy consumption progress value according to the simulated energy consumption and the set energy consumption of the month, wherein the energy consumption progress value is the ratio of the simulated energy consumption to the set energy consumption;

[0040] According to the interval range of the energy consumption progress value, an early warning or alarm is issued for the energy consumption of the current month.

[0041] In a second aspect, an embodiment of the present invention provides a computer-readable storage medium storing computer program instructions, wherein the computer program instructions implement the method described in the first aspect when executed by a processor.

[0042] The embodiment of the present invention determines the category of each subsystem according to the historical energy consumption and historical outdoor temperature of each subsystem, the category includes a first category subsystem and a second category subsystem, obtains the first predicted energy consumption corresponding to the first category subsystem through a pre-trained neural network model, obtains the second predicted energy consumption corresponding to the second category subsystem according to the historical energy consumption, determines the total predicted energy consumption according to the first predicted energy consumption and the second predicted energy consumption, determines the daily predicted energy consumption of each subsystem according to the set energy consumption and the total predicted energy consumption, and manages the energy consumption according to the daily predicted energy consumption. In this way, the energy consumption of the subsystems of the building can be predicted more accurately to more accurately control the energy consumption of the building. BRIEF DESCRIPTION OF THE DRAWINGS

[0043] The above and other objects, features and advantages of the present invention will become more apparent through the following description of the embodiments of the present invention with reference to the accompanying drawings, in which:

[0044] Figure 1 is a flow chart of a building energy consumption budget management method according to an embodiment of the present invention;

[0045] Figure 2 is a flow chart of determining the categories of each subsystem according to an embodiment of the present invention;

[0046] Figure 3 is a flow chart of obtaining a first predicted energy consumption according to an embodiment of the present invention;

[0047] Figure 4 is a flow chart of the SVM algorithm of an embodiment of the present invention;

[0048] Figure 5 is a flow chart of obtaining the second predicted energy consumption according to an embodiment of the present invention;

[0049] Figure 6 is a flow chart of determining the daily predicted energy consumption of each subsystem according to an embodiment of the present invention;

[0050] Figure 7 is a flow chart of determining the daily predicted energy consumption of the second type of subsystem according to an embodiment of the present invention;

[0051] Figure 8 is a flow chart of obtaining the daily predicted energy consumption of each subsystem by using the sliding cycle coefficient method in an embodiment of the present invention;

[0052] Fig. 9 is a flow chart of managing energy consumption according to an embodiment of the present invention;

[0053] Fig.10 is a schematic diagram of an electronic device according to an embodiment of the present invention. DETAILED DESCRIPTION

[0054] The present invention is described below based on embodiments, but the present invention is not limited to these embodiments. In the detailed description of the present invention below, some specific details are described in detail. It is possible for a person skilled in the art to fully understand the present invention without the description of these details. In order to avoid confusing the essence of the present invention, known methods, processes, flows, components and circuits are not described in detail.

[0055] In addition, persons of ordinary skill in the art will appreciate that the drawings provided herein are for illustration purposes and are not necessarily drawn to scale.

[0056] Unless the context clearly requires otherwise, the words "include", "comprising" and similar words throughout the application should be interpreted as including rather than exclusive or exhaustive; that is, the meaning is "including but not limited to".

[0057] In the description of the present invention, it should be understood that the terms "first", "second", etc. are only used for descriptive purposes and cannot be understood as indicating or implying relative importance. In addition, in the description of the present invention, unless otherwise specified, "plurality" means two or more.

[0058] Figure 1 is a flow chart of a building energy budget management method according to an embodiment of the present invention. The building energy budget management method according to an embodiment of the present invention is used to manage energy consumption of subsystems in a building, wherein the subsystems include a lighting system, a power system, an air conditioning system, etc. Specifically, Figure 1 As shown, the method of this embodiment includes:

[0059] Step S100: determining the category of each subsystem according to the historical energy consumption and the historical outdoor temperature of each subsystem, wherein the category includes a first category subsystem and a second category subsystem.

[0060] Step S200: obtaining a first predicted energy consumption corresponding to the first type of subsystem through a pre-trained neural network model.

[0061] Step S300: obtaining a second predicted energy consumption corresponding to the second type of subsystem according to the historical energy consumption.

[0062] Step S400: determining a total predicted energy consumption according to the first predicted energy consumption and the second predicted energy consumption.

[0063] Step S500, determining the daily predicted energy consumption of each subsystem according to the set energy consumption and the total predicted energy consumption.

[0064] Step S600: managing energy consumption according to the daily predicted energy consumption.

[0065] For step S100, the process of determining the categories of each subsystem in the embodiment of the present invention can refer to Figure 2 , including the following steps:

[0066] Step S110, determining the classification index of each subsystem according to the historical energy consumption and historical outdoor temperature of each subsystem.

[0067] In this embodiment, the classification index of each subsystem is calculated according to the Pearson product-moment correlation coefficient algorithm.

[0068] The value of the classification index is between [0, 1]. Assuming that the predetermined threshold is F (0<F<1), [0, F) represents weak correlation and [F, 1] represents strong correlation.

[0069] Step S120: In response to the classification index corresponding to the subsystem being greater than or equal to a predetermined threshold, the corresponding subsystem is determined as a first-category subsystem.

[0070] Step S130: in response to the classification index corresponding to the subsystem being less than a predetermined threshold, determining the corresponding subsystem as a second-category subsystem.

[0071] In this implementation, the subsystems whose classification index is in the strong correlation interval are marked as first-category subsystems, and the subsystems whose classification index is in the weak correlation interval are marked as second-category subsystems.

[0072] For step S200, Figure 3 is a schematic diagram of obtaining the first predicted energy consumption according to an embodiment of the present invention. Specifically, Figure 3 As shown, the following steps are included:

[0073] Step S210, calculating a first type of temperature value and a second type of temperature value according to the historical outdoor temperature and a predetermined reference temperature.

[0074] The first type of temperature value refers to the degree by which the average daily outdoor temperature is higher than the base temperature on each day during the cooling period.

[0075] The second type of temperature value refers to the degree by which the average daily outdoor temperature is lower than the base temperature on each day during the heating period.

[0076] In this embodiment, the stability coefficient of each month in the historical year is calculated based on the daily historical outdoor temperature, and the standard year is obtained based on the stability coefficient. The standard year is composed of the month with the smallest stability coefficient selected from the same month in the historical year. The first type temperature value and the second type temperature value are calculated based on the outdoor temperature of the standard year.

[0077] Step S220: Calculate the daily predicted energy consumption of the first-category subsystem according to the first-category temperature value and the second-category temperature value.

[0078] In this embodiment, the daily predicted energy consumption of the first-category subsystem is calculated according to the first-category temperature value and the second-category temperature value by using a SVM (Support Vector Machine) algorithm, which uses an optimized nonlinear kernel function SVM method.

[0079] The process of the SVM algorithm of the embodiment of the present invention can refer to Figure 4 , including the following steps:

[0080] Step S221, obtaining training data, wherein the training data includes a first temperature value, a second temperature value, and historical energy consumption of the subsystem.

[0081] Step S222, feature extraction, the selected features are the first temperature value and the second temperature value. The learning sample is the historical energy consumption of the subsystem.

[0082] Step S223, obtaining corresponding conditional branches according to the training data.

[0083] Step S224, SVM algorithm training, returning the test results.

[0084] Specifically, the SVM algorithm is a generalized linear classifier that performs binary classification of data in a supervised learning manner, and its decision boundary is the maximum margin hyperplane solved for the learning sample. It is a relatively good method to implement the idea of ​​structural risk minimization, and its machine learning strategy is the principle of structural risk minimization.

[0085] In this embodiment, the prediction model can be obtained according to the training input data and the corresponding training samples.

[0086] Step S225, save the prediction model.

[0087] Step S226, obtaining test input data.

[0088] Step S227, obtaining the daily predicted energy consumption of each subsystem according to the prediction model.

[0089] Therefore, the daily predicted energy consumption of each subsystem of the first type of subsystem every day throughout the year can be obtained according to the SVM algorithm.

[0090] Step S230: determining a first predicted energy consumption of each first-category subsystem according to the daily predicted energy consumption.

[0091] In this embodiment, the daily predicted energy consumption of the first-category subsystems corresponding to each month of the year is accumulated to obtain the first predicted energy consumption of each subsystem of the first-category subsystems in each month of the year.

[0092] It should be noted that the above-mentioned first predicted energy consumption is the predicted energy consumption of the first type of subsystem in each month.

[0093] For step S300, the process of obtaining the second predicted energy consumption in the embodiment of the present invention can refer to Figure 5 , including the following steps:

[0094] Step S310, calculating the average value of the historical monthly energy consumption of each subsystem in each month of the year according to the historical mid-year monthly energy consumption data.

[0095] Step S320, calculating the average growth rate of the monthly energy consumption of each subsystem in each month of the historical year according to the predicted energy consumption of each subsystem in the historical year.

[0096] Step S330, calculating the second predicted energy consumption of each subsystem of the second type of subsystem in each month of the year based on the average historical monthly energy consumption of each subsystem in each month of the year and the average growth rate of the predicted energy consumption of each subsystem in the corresponding month.

[0097] For step S400, the total predicted energy consumption is determined according to the first predicted energy consumption and the second predicted energy consumption.

[0098] The total predicted energy consumption is the sum of the first predicted energy consumption and the second predicted energy consumption.

[0099] For step S500, the process of determining the daily predicted energy consumption of each subsystem according to the set energy consumption and the total predicted energy consumption can refer to Figure 6 , including the following steps:

[0100] Step S510, for the months in which the set energy consumption is consistent with the total predicted energy consumption, the daily predicted energy consumption corresponding to the first predicted energy consumption is determined as the daily predicted energy consumption of the first type of subsystem, and the daily predicted energy consumption of the second type of subsystem is determined according to the second predicted energy consumption by the sliding cycle coefficient method.

[0101] In this embodiment, for the months in which the set energy consumption is consistent with the total predicted energy consumption, the first and second subsystems have different ways of obtaining the predicted energy consumption. For the first subsystem, the daily predicted energy consumption corresponding to the first predicted energy consumption is determined as the daily predicted energy consumption of the first subsystem. For the second subsystem, the daily predicted energy consumption of the second subsystem is determined according to the second predicted energy consumption by the sliding cycle coefficient method. The specific process is as follows: Figure 7 As shown, the following steps are included:

[0102] Step S511, obtaining the historical energy consumption of the second-type subsystem for one consecutive week in history.

[0103] Step S512: calculating the sliding cycle proportional coefficient of the second type of subsystem according to the historical energy consumption of the second type of subsystem for the consecutive week.

[0104] Step S513: obtaining the daily predicted energy consumption of the second type of subsystem according to the sliding cycle proportional coefficient and the second predicted energy consumption.

[0105] Step S520: For the months when the set energy consumption is inconsistent with the total predicted energy consumption, the daily predicted energy consumption of each subsystem is obtained by a sliding week coefficient method.

[0106] The process of obtaining the daily predicted energy consumption of each subsystem by the sliding cycle coefficient method is as follows: Figure 8 As shown, the specific steps include:

[0107] Step S521, obtaining the historical energy consumption of each subsystem for one consecutive week in history.

[0108] Step S522, calculating the sliding cycle proportional coefficient of each subsystem according to the historical energy consumption of each subsystem for one consecutive week in the historical energy consumption.

[0109] Step S523, obtaining the daily predicted energy consumption of each subsystem according to the sliding week proportional coefficient and the monthly set energy consumption of each subsystem.

[0110] Among them, the monthly set energy consumption corresponding to the first type of subsystem is the ratio of each first predicted energy consumption to the total predicted energy consumption multiplied by the set energy consumption, and the monthly set energy consumption corresponding to the second type of subsystem is the ratio of each second predicted energy consumption to the total predicted energy consumption multiplied by the set energy consumption.

[0111] Step S530, obtaining the daily predicted energy consumption of each subsystem according to the sliding week proportional coefficient and the monthly set energy consumption of each subsystem.

[0112] In an optional implementation, if Figure 1 As shown, the method of the embodiment of the present invention also includes:

[0113] For step S600, the process of managing energy consumption according to the daily predicted energy consumption includes the following steps:

[0114] Step S610, obtaining the energy consumption progress value of the current month according to the daily predicted energy consumption.

[0115] in, Fig. 9 is a flow chart of obtaining energy consumption progress value according to an embodiment of the present invention. Fig. 9 In the illustrated embodiment, obtaining the energy consumption progress value of the current month according to the daily predicted energy consumption includes the following steps:

[0116] Step S611, obtaining the actual energy consumption of the current month, where the actual energy consumption is the sum of the actual daily energy consumption of the days that have occurred in the current month.

[0117] Step S612, obtaining predicted energy consumption that has not occurred in the current month, wherein the predicted energy consumption that has not occurred is the sum of the daily predicted energy consumption of the days that have not occurred in the current month.

[0118] Step S613, obtaining the simulated energy consumption of the current month according to the actual energy consumption and the predicted energy consumption that has not occurred, wherein the simulated energy consumption is the sum of the actual energy consumption and the predicted energy consumption that has not occurred.

[0119] Step S614, calculating an energy consumption progress value according to the simulated energy consumption and the set energy consumption of the current month, wherein the energy consumption progress value is a ratio of the simulated energy consumption to the set energy consumption.

[0120] Step S620: issuing a warning or alarm for the energy consumption of the current month according to the interval range of the energy consumption progress value.

[0121] Specifically, an early warning or alarm is issued for the energy consumption of the current month according to the energy consumption progress value.

[0122] For early warning of energy consumption in the current month, the sensitivity value can be set according to the actual situation so that an early warning signal is issued at the corresponding energy consumption progress value. For example, for buildings with relatively low energy consumption requirements, their sensitivity to energy consumption is relatively low, and the sensitivity can be set when the energy consumption progress value is large (for example, P = 90%) to issue an early warning. For buildings with relatively high energy consumption requirements, their sensitivity to energy consumption is relatively high, and the sensitivity can be set when the progress value is low (for example, P = 60%) to issue an early warning.

[0123] Therefore, early warning can be issued at different energy consumption progress values ​​according to the actual situation of the building.

[0124] For alarming the energy consumption of the current month, the sensitivity value can be set according to the actual situation so that an alarm signal is issued at the corresponding energy consumption progress value. For example, for buildings with relatively low energy consumption requirements, the sensitivity to energy consumption is low, and the sensitivity can be set to alarm when the energy consumption progress value is large. For buildings with relatively high energy consumption requirements, the sensitivity to energy consumption is high, and the sensitivity can be set to alarm when the energy consumption progress value is low.

[0125] At the same time, the energy consumption can also be alarmed according to the excess rate.

[0126] Thus, the energy consumption progress value and risk rate can be obtained.

[0127] The present invention determines the category of each subsystem according to the historical energy consumption and historical outdoor temperature of each subsystem, the category includes a first category subsystem and a second category subsystem, obtains the first predicted energy consumption corresponding to the first category subsystem through a pre-trained neural network model, obtains the second predicted energy consumption corresponding to the second category subsystem according to the historical energy consumption, determines the total predicted energy consumption according to the first predicted energy consumption and the second predicted energy consumption, determines the daily predicted energy consumption of each subsystem according to the set energy consumption and the total predicted energy consumption, and manages the energy consumption according to the daily predicted energy consumption. In this way, the energy consumption of the subsystem can be predicted more accurately to control the energy consumption more accurately.

[0128] Fig.10 is a schematic diagram of an electronic device according to an embodiment of the present invention. Fig.10The electronic device shown is a general data processing device, which includes a general computer hardware structure, which at least includes a processor 101 and a memory 102. The processor 101 and the memory 102 are connected via a bus 103. The memory 102 is suitable for storing instructions or programs executable by the processor 101. The processor 101 can be an independent microprocessor or a collection of one or more microprocessors. Thus, the processor 101 executes the instructions stored in the memory 102, thereby executing the method flow of the embodiment of the present invention as described above to realize the processing of data and the control of other devices. The bus 103 connects the above-mentioned multiple components together, and at the same time connects the above-mentioned components to the display controller 104 and the display device and the input / output (I / O) device 105. The input / output (I / O) device 105 can be a mouse, a keyboard, a modem, a network interface, a touch input device, a somatosensory input device, a printer, and other devices known in the art. Typically, the input / output device 105 is connected to the system through an input / output (I / O) controller 106.

[0129] It should be understood by those skilled in the art that the embodiments of the present invention may be provided as methods, devices (equipment) or computer program products. Therefore, the present invention may take the form of a complete hardware embodiment, a complete software embodiment or an embodiment combining software and hardware. Moreover, the present invention may take the form of a computer program product implemented on one or more computer-readable storage media (including but not limited to disk storage, CD-ROM, optical storage, etc.) containing computer-usable program codes.

[0130] The present invention is described with reference to flowcharts of methods, apparatuses (devices) and computer program products according to embodiments of the present application. It should be understood that each process in the flowchart can be implemented by computer program instructions.

[0131] These computer program instructions may be stored in a computer readable memory capable of directing a computer or other programmable data processing device to operate in a specific manner, so that the instructions stored in the computer readable memory produce an article of manufacture including an instruction device that implements the process Figure 1 A function specified in a process or multiple processes.

[0132] These computer program instructions may also be provided to a processor of a general-purpose computer, a special-purpose computer, an embedded processor, or other programmable data processing device to produce a machine, so that the instructions executed by the processor of the computer or other programmable data processing device produce the instructions for implementing the process Figure 1 A device that specifies functions in a process or multiple processes.

[0133] The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. For those skilled in the art, the present invention may have various modifications and variations. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present invention shall be included in the protection scope of the present invention.

Claims

1. An energy consumption management method, characterized in that: The method comprises: Determine the category of each subsystem according to the historical energy consumption and historical outdoor temperature of each subsystem, wherein the category includes a first category subsystem and a second category subsystem; Obtaining a first predicted energy consumption corresponding to the first type of subsystem through a pre-trained neural network model; Obtaining a second predicted energy consumption corresponding to the second type of subsystem based on the historical energy consumption; determining a total predicted energy consumption based on the first predicted energy consumption and the second predicted energy consumption; Determine the daily predicted energy consumption of each subsystem based on the set energy consumption and the total predicted energy consumption; Energy consumption is managed based on the daily predicted energy consumption.

2. The method according to claim 1, characterized in that Determining the category of each subsystem based on the historical energy consumption and historical outdoor temperature of each subsystem includes: Determine the classification index of each subsystem based on its historical energy consumption and historical outdoor temperature; In response to a classification index corresponding to the subsystem being greater than or equal to a predetermined threshold, determining the corresponding subsystem as a first-category subsystem; In response to the classification index corresponding to the subsystem being smaller than a predetermined threshold, the corresponding subsystem is determined as a second-category subsystem.

3. The method according to claim 1, characterized in that The obtaining of the first predicted energy consumption corresponding to the first type of subsystem by using the pre-trained neural network model includes: Calculating a first-category temperature value and a second-category temperature value according to the historical outdoor temperature and a predetermined reference temperature; Calculating the daily predicted energy consumption of the first type of subsystem according to the first type of temperature value and the second type of temperature value; and The first predicted energy consumption of each first-category subsystem is determined according to the daily predicted energy consumption.

4. The method according to claim 3, characterized in that The total predicted energy consumption is the sum of the first predicted energy consumption and the second predicted energy consumption; The step of determining the daily predicted energy consumption of each subsystem based on the set energy consumption and the total predicted energy consumption includes: For the months in which the set energy consumption is consistent with the total predicted energy consumption, determining the daily predicted energy consumption corresponding to the first predicted energy consumption as the daily predicted energy consumption of the first type of subsystem, and determining the daily predicted energy consumption of the second type of subsystem based on the second predicted energy consumption by using a sliding cycle coefficient method; and For the months when the set energy consumption is inconsistent with the total predicted energy consumption, the daily predicted energy consumption of each subsystem is obtained by the sliding week coefficient method.

5. The method according to claim 4, characterized in that Determining the daily predicted energy consumption of the second type of subsystem according to the second predicted energy consumption by using the sliding cycle coefficient method includes: Obtain historical energy consumption of the second type of subsystem for one consecutive week in history; Calculating a sliding week proportional coefficient of the second type of subsystem according to the historical energy consumption of the second type of subsystem for the consecutive week; and The daily predicted energy consumption of the second type of subsystem is obtained according to the sliding cycle proportional coefficient and the second predicted energy consumption.

6. The method according to claim 4, characterized in that The daily predicted energy consumption of each subsystem obtained by the sliding cycle coefficient method includes: Obtain the historical energy consumption of each subsystem for a consecutive week; Calculating a sliding week proportional coefficient for each subsystem based on the historical energy consumption of each subsystem for one consecutive week in the historical energy consumption; and The daily predicted energy consumption of each subsystem is obtained according to the sliding cycle proportional coefficient of each subsystem and the corresponding set energy consumption.

7. The method according to claim 6, characterized in that The monthly set energy consumption corresponding to the first type of subsystem is the ratio of each first predicted energy consumption to the total predicted energy consumption multiplied by the set energy consumption, and the monthly set energy consumption corresponding to the second type of subsystem is the ratio of each second predicted energy consumption to the total predicted energy consumption multiplied by the set energy consumption.

8. The method according to claim 1, characterized in that The managing of energy consumption according to the daily predicted energy consumption includes: Obtaining a monthly energy consumption progress value based on the daily predicted energy consumption; and An early warning or alarm is issued for the energy consumption of the current month based on the energy consumption progress value.

9. The method according to claim 8, characterized in that The step of obtaining the energy consumption progress value for the current month based on the daily predicted energy consumption includes: Get the actual energy consumption of the month, which is the actual daily DA2205998 of the days that have occurred in the month The sum of energy consumption; Obtain the predicted energy consumption that has not occurred in the current month, where the predicted energy consumption that has not occurred is the sum of the daily predicted energy consumption for the days that have not occurred in the current month; Obtaining simulated energy consumption for the current month based on the actual energy consumption and the predicted energy consumption that has not occurred, wherein the simulated energy consumption is the sum of the actual energy consumption and the predicted energy consumption that has not occurred; and An energy consumption progress value is calculated based on the simulated energy consumption and the set energy consumption for the month, and the energy consumption progress value is a ratio of the simulated energy consumption to the set energy consumption.

10. The method according to claim 8, characterized in that The specific steps of providing early warning or alarm for energy consumption of the current month according to the energy consumption progress value are as follows: According to the interval range of the energy consumption progress value, an early warning or alarm is issued for the energy consumption of the current month.

11. A computer-readable storage medium storing computer program instructions, characterized in that: The computer program instructions implement the method according to any one of claims 1 to 10 when executed by a processor.