Cost cause and effect relationship-based power system flexibility adjustment cost allocation method
By constructing an ideal scenario without volatility and establishing a dispatch model for deep peak shaving and virtual power plant regulation, and using the Shapley value to calculate the cost sharing coefficient, the issue of fairness in the cost sharing of power system flexibility adjustment is solved, and the balance between thermal power units and virtual power plants is realized. Fair cost sharing supports the normalization of power regulation.
Patent Information
- Application Number
- CN202410723515.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Priority Date
- 2023-12-12
- Filing Date
- 2024-06-05
- Publication Date
- 2024-10-08
AI Technical Summary
The existing technology is difficult to objectively and fairly share the cost of power system flexibility adjustment, especially in terms of deep peak shaving of thermal power units and demand-side virtual power plant adjustment, and fails to effectively consider the contribution of thermal power units and demand-side flexibility.
Construct an ideal scenario without volatility, establish a dispatch model that takes into account deep peak shaving and virtual power plant adjustment, calculate the flexibility adjustment cost sharing coefficient of each cost driver through the Shapley value, and fairly share the flexibility adjustment cost of thermal power units and virtual power plants. .
It has realized the quantified allocation of the cost of deep peak shaving of thermal power units and virtual power plant adjustment, forming a long-term and stable capital pool to support the normal development of power flexibility adjustment.
Smart Images

Figure CN118748434A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of power systems, and in particular to a method for allocating power system flexibility regulation costs based on cost causality. Background Art
[0002] In the new energy power system, with the continuous penetration of renewable energy (RE), the deterministic power generation fluctuations on various time scales have become increasingly severe, so higher flexibility requirements are put forward for the power system to absorb renewable energy and ensure power balance. On the power generation side, thermal power units (TPUs) are the main resources used to provide flexibility to mitigate power fluctuations. They can provide flexibility through deep peak regulation (DPR), flexible ramping, and fast start and stop. On the demand side, with the rapid growth of distributed energy and flexible loads, huge flexibility potential needs to be released and utilized. Virtual power plants (VPPs) play an important role in mitigating power fluctuations by aggregating a large number of flexible resources on the demand side and shifting power consumption to the appropriate time.
[0003] Although the existing technology has studied the optimal operation of power regulation involving both power generation and demand, the following problems still exist: First, how to objectively allocate the flexibility regulation costs to form a stable funding pool to support normalized power regulation services needs to be solved urgently; second, document 1 (M. Illigan and B. Kirby, "Calculating wind integration costs: Separating wind energy value from integration cost impacts", 2009. [Online]. Available: https: / / www.nrel.gov / docs / fy09osti / 46275.pdf) proposes that cost causality is the basic principle to be followed when designing cost allocation methods, and participants who incur costs should pay an amount that is positively correlated with the degree of their induction. On this basis, Reference 2 (L. Li, Y. Zheng, C. Chen, et al. "Calculation of Wind Power Variation Costs and its Application Research," Proceedings of the CSEE, China, vol. 36, pp. 5155-5163, October 2016.) constructs a scenario without wind power fluctuations by introducing the method of "equal power follows load" and calculates the cost of wind power fluctuations. Reference 3 (J. Mays, "Cost Allocation and Net Load Variability," IEEE Transactions on Power Systems, vol. 33, no. 2, pp. 2030-2039, March 2018.) proposes a method to objectively and fairly allocate the volatility cost of net load to different types of power generation and power consumption resources. However, on the one hand, when calculating the regulation cost, the participation of thermal power units in deep peak-valley regulation to provide flexibility is not considered; on the other hand, the flexibility of the demand side is ignored, that is, the load is regarded as inflexible and cannot participate in power regulation through load adjustment. As the burden of power regulation increases, deep peak regulation of thermal power units and flexibility on the demand side become crucial in solving the challenge of power balance. Therefore, it is urgent to propose a cost allocation method for power system flexibility regulation based on cost causality. Summary of the invention
[0004] The purpose of the present invention is to provide a cost allocation method for flexibility regulation of a power system based on cost causality, so as to solve the problems raised in the above-mentioned background technology.
[0005] To achieve the above-mentioned purpose, the present invention provides the following technical solution: a cost allocation method for power system flexibility regulation based on cost causality, comprising the following steps: step 1, constructing an ideal scenario without volatility; step 2, establishing a dispatching model taking into account deep peak regulation and virtual power plant regulation; step 3, calculating the allocation coefficient;
[0006] In the above step 1, an ideal scenario without power fluctuation is constructed for potential flexibility regulation cost inducing;
[0007] In the above step 2, for each potential cost initiator, a dispatch model taking into account deep peak load regulation and virtual power plant regulation is established, and the flexibility dispatch cost generated under all possible volatility scenarios is calculated based on the model;
[0008] In the above step 3, the actual flexibility of each cost contributor is obtained by weighting based on the Shapley value to adjust the cost sharing coefficient.
[0009] Preferably, in step one, the cost drivers are renewable energy and rigid loads.
[0010] Preferably, in step 1, specifically: set Represents a rigid load, and the output of each rigid load is D n,t ; represents renewable energy, and the maximum output of each renewable energy is When the total energy is constant, the corresponding power fluctuation can be calculated:
[0011]
[0012] When calculating the power fluctuation of renewable energy, its output is regarded as a negative value, that is, a “negative load”, as shown in formula (2). Let is the set of potential cost contributors, each potential cost contributor The power fluctuation is:
[0013]
[0014] Obviously, yes The power fluctuation vector satisfies:
[0015]
[0016] Therefore, the power curve Q with power fluctuations and the ideal scenario without power fluctuations that need to be balanced by TPU and VPP are
[0017]
[0018] Preferably, the formula (7) represents the variables Q and The relationship between can be proved by simple mathematical transformation. The power fluctuation to be balanced can be expressed as The power regulation requirement is defined as the inverse of the power fluctuation to be balanced:
[0019]
[0020] Preferably, in step 2, specifically: since the closer the profile of the virtual power plant (VPP) power curve is to the ideal load curve, the greater its contribution to smoothing the system power fluctuation, the power regulation demand ΔQ demand As the ideal load curve, the external output curve of the dispatched VPP is close to the ideal load curve to a certain extent, and the incentive cost of the VPP is proportional to the similarity of the two curves; therefore, the dispatch objective function is to minimize the sum of the TPU operation cost (Equation 10), the startup and shutdown costs (Equation 11), the VPP incentive cost (Equation 12), and the renewable energy curtailment cost (Equation 13):
[0021]
[0022]
[0023] Preferably, the P i,t Indicates the period t Power generation; L j yes The output power vector of m is the actual output vector of renewable energy source RE m, c(P i,t ) is the power generation power P i,t The quadratic function, P i DPR represents the DPR threshold of TPU i; the second term of the DPR stage in f1 is the fatigue life loss cost, which is the actual operating loss coefficient μ i , fatigue loss coefficient β i and unit investment cost The product of i As the load rate of TPU i increases, u i,t ,y i,t , z i,t are the indexes of the running status, startup and shutdown of TPU i in period t respectively; and are the startup and shutdown costs of TPU i in period t respectively.
[0024] Preferably, in the formula (12), ε is the excitation coefficient, and the second term in the product describes the power regulation demand ΔQ demandVPP power fluctuation curve ΔL j The similarity between j As shown in formula (14); ΔL j and ΔQ demand After l-1 norm normalization, we get and The normalization method is shown in formula (15). In formula (13), ξ is the unit power abandonment cost of renewable energy:
[0025]
[0026] The constraints considered include:
[0027] System-level constraints:
[0028]
[0029] Preferably, the formula (16) is a power balance constraint, the formula (17) is a standby constraint, P i max and P i min Represent the maximum and minimum output of TPUi, P t RSU and P t RSD They are upper standby and lower standby requirements;
[0030] TPU constraints:
[0031] u i,t P i min ≤P i,t ≤u i,t P i max (18)
[0032]
[0033] y i,t -z i,t =u i,t =u i,t1 (twenty one)
[0034] y i,t +z i,t ≤1 (22)
[0035]
[0036] Preferably, formula (18) is the power generation constraint, formulas (19)-(20) are the ramp constraints, formulas (21)-(22) are the operating state constraints, formula (23) is the minimum continuous shutdown and startup time limit, Pi RU , P i RD , P i RU,start and P i RD,shut Respectively represent the maximum uphill climbing, downhill climbing, starting, and shutting down power limits. is the shutdown and startup time of TPU i in period t-1, T i off and T i on is the minimum continuous off and on time of TPU i,
[0037]
[0038] L j ∈Ω j (25)
[0039] Constraint (24) represents the power generation constraint of renewable energy, and constraint (25) represents the generalized operation constraint of VPP j, where Ω j It is the feasible domain of VPP operation.
[0040] Preferably, in step 3, specifically: when a power curve Q with power fluctuation is given, the total system cost is obtained as F(Q) based on the scheduling model. For the case of no power fluctuation, the total cost of the system can be obtained as Therefore, the regulation cost F caused by power fluctuation is V It can be expressed as:
[0041]
[0042] For potential cost instigator v, in a specific scenario The regulation cost caused by the above can be expressed as the difference between the dispatching costs with and without power fluctuations:
[0043]
[0044] In the scene middle, represents the adjustment cost caused by v, among which Potential cost drivers of have power fluctuations, while other potential cost drivers do not have power fluctuations;
[0045] The Shapley value in cooperative game theory can effectively characterize the weighted average cost of each potential cost cause in a scenario where there is mutual influence between cost causes. Therefore, the Shapley value is used to calculate the weighted average cost of the adjustment caused by the potential cost cause v in all scenarios. v :
[0046]
[0047] Based on the characteristics of Shapley values, the following relationship can be obtained:
[0048]
[0049] The weighted average regulation cost of each potential cost contributor reflects its average contribution to the total regulation cost of the system. It can be inferred that the weighted average regulation cost of some potential cost contributors may be negative, which indicates that they have contributed to the regulation of the system compared to the case where they have no power fluctuations. Therefore, they are excluded from the allocation of regulation costs. The flexibility regulation cost allocation coefficient A of each potential cost contributor is v The calculation is as follows:
[0050]
[0051] Compared with the prior art, the beneficial effects of the present invention are as follows: the present invention can quantify the degree to which system members induce system flexibility adjustment costs taking into account deep peak adjustment and virtual power plant adjustment. The proposed comprehensive dispatching model taking into account deep peak adjustment and virtual power plant participation in regulation can be used to calculate the total dispatching and operating costs of the system. The present invention will fairly and objectively allocate the flexibility adjustment costs caused by power fluctuations of renewable energy and rigid non-adjustable loads, including the costs of thermal power unit operation, deep peak adjustment of thermal power units, and demand-side virtual power plant dispatching, to the corresponding cost initiators, thereby forming a long-term and stable capital pool to support the normalization of power flexibility adjustment. BRIEF DESCRIPTION OF THE DRAWINGS
[0052] Figure 1 is the power curve to be balanced and its fluctuation;
[0053] Figure 2 is the scheduling result;
[0054] Figure 3 dispatching power for virtual power plants;
[0055] Figure 4 is the total system cost under different volatility scenarios;
[0056] Figure 5 The weighted average regulation costs incurred for renewable energy and rigid loads;
[0057] Figure 6 Adjusting cost-sharing factors for flexibility;
[0058] Figure 7 is a flow chart of the method of the present invention;
[0059] Note: Figure 1 a is the wind power curve, Figure 1 b is the photovoltaic power curve, Figure 1 c is the power curve of rigid load 1, Figure 1 d is the power curve of rigid load 2, Figure 1 e is the power curve of rigid load 3, Figure 1 f is the total power curve to be balanced (rigid load-new energy);
[0060] Figure 2 a is the ideal power curve without power fluctuation, Figure 2 b is the power curve of the actual dispatch situation;
[0061] Figure 3 a is the dispatching power of virtual power plant 1, Figure 3 b is the dispatching power of virtual power plant 2. DETAILED DESCRIPTION
[0062] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0063] See also Figure 1-7 , an embodiment provided by the present invention: a cost allocation method for power system flexibility regulation based on cost causality, comprising the following steps: step one, constructing an ideal scenario without volatility; step two, establishing a dispatching model taking into account deep peak regulation and virtual power plant regulation; step three, calculating the allocation coefficient;
[0064] In the above step 1, an ideal scenario without power fluctuation is constructed for potential flexibility regulation cost drivers, namely renewable energy and rigid loads, as follows: Represents a rigid load, and the output of each rigid load is D n,t ; represents renewable energy, and the maximum output of each renewable energy is When the total energy is constant, the corresponding power fluctuation can be calculated:
[0065]
[0066] When calculating the power fluctuation of renewable energy, its output is regarded as a negative value, that is, a “negative load”, as shown in formula (2). Let is the set of potential cost contributors, each potential cost contributor The power fluctuation is:
[0067]
[0068] Obviously, yes The power fluctuation vector satisfies:
[0069]
[0070] Therefore, the power curve Q with power fluctuations and the ideal scenario without power fluctuations that need to be balanced by TPU and VPP are
[0071]
[0072]
[0073] Formula (7) represents the variables Q and The relationship between can be proved by simple mathematical transformation. The power fluctuation to be balanced can be expressed as The power regulation requirement is defined as the inverse of the power fluctuation to be balanced:
[0074]
[0075] In the above step 2, for each potential cost initiator, a dispatch model taking into account deep peak regulation and virtual power plant regulation is established, and the flexibility dispatch cost generated under all possible volatility scenarios is calculated based on the model. Specifically, since the closer the contour of the virtual power plant (VPP) power curve is to the ideal load curve, the greater its contribution to smoothing the system power fluctuation, the power regulation demand ΔQ demand As the ideal load curve, the external output curve of the dispatched VPP is close to the ideal load curve to a certain extent, and the incentive cost of the VPP is proportional to the similarity of the two curves; therefore, the dispatch objective function is to minimize the sum of the TPU operation cost (Equation 10), the startup and shutdown costs (Equation 11), the VPP incentive cost (Equation 12), and the renewable energy curtailment cost (Equation 13):
[0076]
[0077]
[0078] P i,t Indicates the period t Power generation; L j yes The output power vector of m is the actual output vector of renewable energy REm, c(P i,t ) is the power generation P i,t The quadratic function, P i DPR represents the DPR threshold of TPU i; the second term of the DPR stage in f1 is the fatigue life loss cost, which is the actual operating loss coefficient μ i , fatigue loss coefficient β i and unit investment cost The product of i As the load rate of TPU i increases, u i,t ,y i,t , z i,t are the indexes of the running status, startup and shutdown of TPU i in period t respectively; and are respectively the startup and shutdown costs of TPU i in period t. In formula (12), ε is the incentive coefficient, and the second term in the product describes the power regulation demand ΔQ demand VPP power fluctuation curve ΔL j The similarity between j As shown in formula (14); ΔL j and ΔQ demand After l-1 norm normalization, we get and The normalization method is shown in formula (15). In formula (13), ξ is the unit power abandonment cost of renewable energy:
[0079]
[0080] The constraints considered include:
[0081] System-level constraints:
[0082]
[0083]
[0084] Formula (16) is the power balance constraint, Formula (17) is the backup constraint, P i max and P i min denote the maximum and minimum output of TPU i, P t RSU and P t RSD They are upper standby and lower standby requirements;
[0085] TPU constraints:
[0086] u i,t P i min ≤P i,t ≤u i,t P i max (18)
[0087]
[0088] y i,t -z i,t =u i,t -u i,t1-1 (twenty one)
[0089] y i,t +z i,t ≤1 (22)
[0090]
[0091] Formula (18) is the power generation constraint, Formula (19)-(20) is the ramp constraint, Formula (21)-(22) is the operating state constraint, Formula (23) is the minimum continuous shutdown and startup time limit, P i RU , P i RD , P i RU,start and P i RD,shut Respectively represent the maximum uphill climbing, downhill climbing, starting, and shutting down power limits. is the shutdown and startup time of TPU i in period t-1, T i off and T i on is the minimum continuous off and on time of TPU i,
[0092]
[0093] L j ∈Ω j (25)
[0094] Constraint (24) represents the power generation constraint of renewable energy, and constraint (25) represents the generalized operation constraint of VPP j, where Ω j It is the feasible domain of VPP operation;
[0095] In the above step 3, the actual flexibility adjustment cost sharing coefficient of each cost contributor is obtained by weighting based on the Shapley value. Specifically, when a power curve Q with power fluctuation is given, the total system cost is F(Q) based on the scheduling model. For the case of no power fluctuation, the total cost of the system can be obtained Therefore, the regulation cost F caused by power fluctuation is V It can be expressed as:
[0096]
[0097] For potential cost instigator v, in a specific scenario The regulation cost caused by the above can be expressed as the difference between the dispatching costs with and without power fluctuations:
[0098]
[0099] In the scene middle, represents the adjustment cost caused by v, among which Potential cost drivers of have power fluctuations, while other potential cost drivers do not have power fluctuations;
[0100] The Shapley value in cooperative game theory can effectively characterize the weighted average cost of each potential cost cause in a scenario where there is mutual influence between cost causes. Therefore, the Shapley value is used to calculate the weighted average cost of the adjustment caused by the potential cost cause v in all scenarios. v :
[0101]
[0102] Based on the characteristics of Shapley values, the following relationship can be obtained:
[0103]
[0104] The weighted average regulation cost of each potential cost contributor reflects its average contribution to the total regulation cost of the system. It can be inferred that the weighted average regulation cost of some potential cost contributors may be negative, which indicates that they have contributed to the regulation of the system compared to the case where they have no power fluctuations. Therefore, they are excluded from the allocation of regulation costs. The flexibility regulation cost allocation coefficient A of each potential cost contributor is v The calculation is as follows:
[0105]
[0106] Using the method provided in the above embodiment, a flexibility adjustment cost allocation method is proposed for the following power system, which consists of two thermal power units (TPUs), one wind power, one photovoltaic, three rigid loads and two virtual power plants; wherein the actual operation loss coefficient of TPUs in DPR is set to 1.2, the investment costs of TPU1 and TPU2 are 627 $ / kW and 520 $ / Kw respectively, and the relationship between the fatigue loss coefficient value and the TPU load rate is shown in the following table:
[0107]
[0108]
[0109] Ideal scenario results without fluctuations: Figure 1 The power curves of potential cost drivers (including new energy and rigid loads) and the ideal scenario, i.e., a power curve without fluctuations, are given. It can be seen that photovoltaic power, as the main source of volatility, causes an increase in positive power fluctuations during the 1-9 o'clock and 20-24 o'clock periods, and negative power fluctuations during the 10-19 o'clock period. Wind power and rigid load 1 also contribute to the generation of volatility to a certain extent. The power fluctuation trend of rigid load 2 is opposite to the trend of the total power curve to be balanced, while the power fluctuation of rigid load 3 is relatively small. Figure 1 (f) The total power curve to be balanced shows that the system has a significant "load" reduction from noon to afternoon, and the output of TPU needs to be reduced to achieve balance. At the same time, the power consumption of VPP needs to be increased during these periods, while the opposite is true for other periods.
[0110] Scheduling results: Figure 2 The scheduling results under the ideal scenario without power fluctuation and the actual situation are presented. In the ideal scenario, there is no power fluctuation for both rigid load and renewable energy. Therefore, except for some power fluctuation of TPU in the initial period due to the constraints of the initial state of scheduling, the power curves of TPU and VPP remain basically horizontal. In contrast, in the actual situation, the reduction of rigid load and the increase of renewable energy generation from noon to afternoon force TPU to reduce its output to achieve power balance. Obviously, the output of TPU1 from 11:00 to 18:00 and TPU from 12:00 to 16:00 drops below their respective DPR thresholds, indicating that they have entered the DPR stage, thus generating the relevant fatigue life loss costs. For VPP, the scheduling results are as follows: Figure 3As shown in the figure, they introduced positive power fluctuations from noon to afternoon, thus helping to balance power fluctuations; the scheduling results of the two VPPs showed different trends in the power curves of certain periods, such as the 17th to 19th period, and these differences were mainly attributed to the specific feasible domain constraints of the two VPPs; in summary, it was found that the power fluctuations caused by rigid loads and new energy sources were effectively smoothed out through the scheduling of TPU and VPP, thus ensuring power balance at every moment;
[0111] Flexibility to adjust cost allocation: Figure 4 The total cost of system operation under different volatility scenarios is shown; Figure 5 The sum of the adjustment costs incurred by each member is equal to Figure 4 The difference between scenario "11111" (31) and scenario "00000" (0), i.e., the total regulation cost is $2672.55, which satisfies equation (29); in addition, it can be seen that the system cost increases significantly when transitioning from scenario "00111" (7) to scenario "01000" (8), indicating that in the scenario with only PV power fluctuations, the system regulation burden increases significantly, while in the scenario with only rigid load power fluctuations, the regulation burden is relatively light; Figure 5 The weighted average adjustment costs incurred by potential cost initiators are shown; Figure 6 The specific flexibility regulation cost allocation coefficient is given; photovoltaics causes the highest regulation cost, corresponding to the largest sharing coefficient, because a large part of the power fluctuation comes from photovoltaics; rigid load 1 and wind power also contribute to the generation of regulation costs to a certain extent, because they are also one of the sources of volatility; since the power fluctuation of rigid load 3 is small, the regulation cost it causes is the lowest, corresponding to the smallest sharing coefficient; the regulation cost caused by rigid load 2 is negative, which means that it contributes to system regulation and is therefore exempt from cost sharing, which is consistent with the phenomenon that its power fluctuation is opposite to the fluctuation trend of the power curve to be balanced; based on the above analysis, the sharing coefficient effectively reflects the degree to which potential cost causes cause flexibility regulation costs, and the method proposed in the embodiment follows the cost causality principle well.
[0112] Based on the above, the advantage of the present invention is that when the present invention is used, an ideal scenario without volatility is first constructed, and then a scheduling model taking into account deep peak regulation and virtual power plant regulation is established and the flexibility scheduling costs generated by potential cost initiators under all possible volatility scenarios are calculated. Finally, the flexibility regulation cost sharing coefficient is solved based on the Shapley value. The cost sharing method proposed in the present invention follows the cost causal relationship and can fairly and objectively share the flexibility regulation costs taking into account deep peak regulation of thermal power units and virtual power plant participation in scheduling to the corresponding cost initiators, thereby forming a stable capital pool to support the normalization of power flexibility regulation.
[0113] It will be apparent to those skilled in the art that the invention is not limited to the details of the exemplary embodiments described above and that the invention can be implemented in other specific forms without departing from the spirit or essential features of the invention. Therefore, the embodiments should be considered exemplary and non-limiting in all respects, and the scope of the invention is defined by the appended claims rather than the foregoing description, and it is intended that all variations falling within the meaning and scope of the equivalent elements of the claims be included in the invention. Any reference numeral in a claim should not be considered as limiting the claim to which it relates.
Claims
1. A cost allocation method for power system flexibility regulation based on cost causality, comprising the following steps: Step 1: construct an ideal scenario without volatility; Step 2: establish a dispatching model that takes into account deep peak regulation and virtual power plant regulation; Step 3: calculate the allocation coefficient; It is characterized by: In the above step 1, an ideal scenario without power fluctuation is constructed for potential flexibility regulation cost inducing; In the above step 2, for each potential cost initiator, a dispatch model taking into account deep peak load regulation and virtual power plant regulation is established, and the flexibility dispatch cost generated under all possible volatility scenarios is calculated based on the model; In the above step 3, the actual flexibility of each cost contributor is obtained by weighting based on the Shapley value to adjust the cost sharing coefficient.
2. The cost allocation method for power system flexibility regulation based on cost causality according to claim 1 is characterized by: In step 1, the cost drivers are renewable energy and rigid loads.
3. The cost allocation method for power system flexibility regulation based on cost causality according to claim 1 is characterized by: In the step 1, specifically: Represents a rigid load, and the output of each rigid load is D n,t ; represents renewable energy, and the maximum output of each renewable energy is When the total energy is constant, the corresponding power fluctuation can be calculated: When calculating the power fluctuation of renewable energy, its output is regarded as a negative value, that is, "negative load", as shown in formula (2), let is the set of potential cost contributors, each potential cost contributor The power fluctuation is: Obviously, yes The power fluctuation vector satisfies: Therefore, the power curve Q with power fluctuations and the ideal scenario without power fluctuations that need to be balanced by TPU and VPP are 4. The cost allocation method for power system flexibility regulation based on cost causality according to claim 3 is characterized by: The formula (7) represents the variables Q and The relationship between can be proved by simple mathematical transformation. The power fluctuation to be balanced can be expressed as The power regulation requirement is defined as the inverse of the power fluctuation to be balanced:
5. The cost allocation method for power system flexibility regulation based on cost causality according to claim 1 is characterized by: In the step 2, specifically: since the closer the profile of the virtual power plant (VPP) power curve is to the ideal load curve, the greater its contribution to smoothing the system power fluctuation, the power regulation demand ΔQ demand As the ideal load curve, the external output curve of the dispatched VPP is close to the ideal load curve to a certain extent, and the incentive cost of the VPP is proportional to the similarity of the two curves; therefore, the dispatch objective function is to minimize the sum of the TPU operation cost (Equation 10), the startup and shutdown costs (Equation 11), the VPP incentive cost (Equation 12), and the renewable energy curtailment cost (Equation 13):
6. The cost allocation method for power system flexibility regulation based on cost causality according to claim 5 is characterized by: The P i,t Indicates the period t Power generation; L j yes The output power vector of m is the actual output vector of renewable energy REm, c(P i,t ) is the power generation P i,t The quadratic function, P i DPR represents the DPR threshold of TPUi; the second term of the DPR stage in f1 is the fatigue life loss cost, which is the actual operating loss coefficient μ i , fatigue loss coefficient β i and unit investment cost The product of i As the load rate of TPUi increases, u i,t ,y i,t , z i,t are the indexes of the running status, startup and shutdown of TPUi in period t respectively; and They are respectively the startup and shutdown costs of TPUi in period t.
7. The cost allocation method for power system flexibility regulation based on cost causality according to claim 5 is characterized by: In the formula (12), ε is the excitation coefficient, and the second term in the product describes the power regulation demand ΔQ demand VPP power fluctuation curve ΔL j The similarity between j As shown in formula (14); ΔL j and ΔQ demand After l-1 norm normalization, we get and The normalization method is shown in formula (15). In formula (13), ξ is the unit power abandonment cost of renewable energy: The constraints considered include: System-level constraints:
8. The cost allocation method for power system flexibility regulation based on cost causality according to claim 7 is characterized by: Formula (16) is the power balance constraint, Formula (17) is the standby constraint, P i max and P i min Represent the maximum and minimum output of TPUi, P t RSU and P t RSD They are upper standby and lower standby requirements; TPU constraints: yes i,t -z i,t =u i,t =u i,t1 (21) y i,t +z i,t ≤1 (22) 9. The cost allocation method for power system flexibility regulation based on cost causality according to claim 8 is characterized by: Formula (18) is the power generation constraint, Formulas (19)-(20) are the ramp constraints, Formulas (21)-(22) are the operating state constraints, Formula (23) is the minimum continuous shutdown and startup time limit, P i RU , P i RD , P i RU,start and P i RD,shut Respectively represent the maximum uphill climbing, downhill climbing, starting, and shutting down power limits. is the shutdown and startup time of TPUi in period t-1, T i off and T i on is the minimum continuous off and on time of TPUi, L j ∈Ω j (25) Constraint equation (24) represents the power generation constraint of renewable energy, and constraint equation (25) represents the generalized operation constraint of VPPj, where Ω j It is the feasible domain of VPP operation.
10. The cost allocation method for power system flexibility regulation based on cost causality according to claim 1, characterized in that: In step 3, specifically, when a power curve Q with power fluctuation is given, the total system cost is F(Q) based on the scheduling model. For the case without power fluctuation, the total cost of the system can be obtained as Therefore, the regulation cost F caused by power fluctuation is V It can be expressed as: For potential cost instigators υ, in a specific scenario The regulation cost caused by the above can be expressed as the difference between the dispatching costs with and without power fluctuations: In the scene middle, represents the adjustment cost caused by υ, among which Potential cost drivers of have power fluctuations, while other potential cost drivers do not have power fluctuations; The Shapley value in cooperative game theory can effectively characterize the weighted average cost of each potential cost cause in a scenario where there is mutual influence between cost causes. Therefore, the Shapley value is used to calculate the weighted average cost of the adjustment cost caused by the potential cost cause υ in all scenarios. υ : Based on the characteristics of Shapley values, the following relationship can be obtained: The weighted average regulation cost of each potential cost contributor reflects its average contribution to the total regulation cost of the system. It can be inferred that the weighted average regulation cost of some potential cost contributors may be negative, which indicates that they have contributed to the regulation of the system compared to the case where they have no power fluctuations. Therefore, they are excluded from the allocation of regulation costs. The flexibility regulation cost allocation coefficient A of each potential cost contributor is υ The calculation is as follows: