Manipulator motion control method and device, computer equipment and storage medium
By obtaining the target position and usage of the equipment, generating a robot task list and calculating the best path, it solves the problem of high coupling between the equipment structure and the control program when the curing process changes, and improves production efficiency and equipment utilization.
Patent Information
- Application Number
- CN202411051256.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-01
- Publication Date
- 2024-10-11
- Estimated Expiration
- Not applicable · inactive patent
AI Technical Summary
When the existing curing process needs to be changed, the coupling between the equipment structure and the control program is high, resulting in low freedom of the production process, which in turn affects production efficiency.
By obtaining the target position coordinates and equipment usage of different devices, a robot task list is generated, the optimal path of the robot is calculated, and motion instructions are input to achieve precise control, optimize production scheduling and resource utilization.
It improves production efficiency, reduces waste of human resources, ensures the stability and consistency of the production process, and reduces energy consumption and production interruptions.
Smart Images

Figure CN118752489A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of robot control, and in particular to a robot motion control method, device, computer equipment and storage medium. Background Art
[0002] At present, the curing process is more and more widely used in various industries, especially in the electronics industry. It is a production process that heats parts, cures resin and dries in order to enhance the stress of material bonding.
[0003] Currently, in curing furnaces, curing is usually carried out in coordination with a structure and a simple control program. In the entire curing process, the coupling degree between the structure and control program of different equipment is high. When the curing process needs to be changed, the curing furnace structure needs to be considered, and the freedom of the entire production process is low.
[0004] The above-mentioned existing technical solutions have the following defects: the process in the curing process is relatively fixed, resulting in large changes in the system program when the process changes, so there is room for improvement. Summary of the invention
[0005] In order to improve the flexibility of the curing process and thus improve the production efficiency of the product, the present application provides a robot motion control method, device, computer equipment and storage medium.
[0006] The above-mentioned invention objective of the present application is achieved through the following technical solutions: A manipulator motion control method, the manipulator motion control method comprising: Obtain target position coordinates and device usage of different devices, and generate a corresponding manipulator task list according to the target position coordinates and the device usage; Obtaining task coordinates from the manipulator task list, and calculating the best path for the manipulator according to the task coordinates; The optimal path of the manipulator is input into the manipulator control terminal to generate a manipulator motion instruction.
[0007] By adopting the above-mentioned technical scheme, since in existing curing furnaces, curing is usually carried out in coordination with a structure and a simple control program, the coupling degree between the structure and the control program of different equipment in the entire curing process is relatively high. When the curing process needs to be changed, the curing furnace structure needs to be considered, and the freedom of the entire production process is relatively low. Therefore, the present application can achieve comprehensive monitoring and management of production equipment and tasks by obtaining the target position coordinates and equipment usage of different equipment, which helps to understand the equipment status, production progress and resource utilization in real time, thereby performing effective scheduling and optimization; by generating a robot according to the target position coordinates and equipment usage The task list can realize automatic allocation and scheduling of tasks, which can improve production efficiency, reduce waste of human resources, and ensure the smooth progress of the production process; by obtaining the task coordinates in the robot task list and calculating the optimal path of the robot based on these coordinates, it can ensure that the path planning of the robot is reasonable when performing tasks, reduce movement time and energy consumption, and improve work efficiency; the calculated optimal path of the robot is input into the robot control terminal to generate robot motion instructions, which can realize precise control and operation of the robot, which helps to ensure that the robot performs tasks according to the predetermined path and speed, and improve the stability and consistency of the production line.
[0008] In a preferred example, the present application can be further configured as follows: the target position coordinates and device usage of different devices are obtained, and a corresponding manipulator task list is generated according to the target position coordinates and the device usage, specifically including: Acquire printing progress data, and when the printing progress data reaches a progress value preset by the system, trigger a printing end message, and generate a material loading instruction according to the printing end message; Obtain the working status of all chambers. When the chamber working status is idle, obtain the coordinates of the idle chamber and generate a corresponding robot loading task list. When the chamber working status is working, obtain the chamber working progress and generate the corresponding robot task list according to the chamber working progress.
[0009] By adopting the above technical solution, by acquiring printing progress data and triggering a printing end message when the system preset progress value is reached, real-time monitoring and control of the printing process can be achieved, which helps to timely discover printing problems or complete printing tasks, thereby improving printing efficiency and quality; by generating loading instructions based on the printing end message, seamless connection between printing tasks and loading tasks can be achieved, which helps to reduce production interruptions and waiting time, and improve the continuity and efficiency of the production line; by acquiring the working status of all chambers, real-time monitoring and management of the chambers inside the curing furnace can be achieved. When the chamber is idle, the idle chamber coordinates can be acquired in time and a robot loading task list can be generated, thereby optimizing the production scheduling and resource utilization of the curing furnace. When the chamber is working, the work progress can be acquired and a corresponding robot task list can be generated to ensure that the robot and the chamber work synchronously, thereby improving production efficiency.
[0010] In a preferred example, the present application can be further configured as follows: when the chamber working state is in working state, the chamber working progress is obtained, and the corresponding manipulator task list is generated according to the chamber working progress, specifically including: When the chamber work progress is that the material processing is completed, the completed chamber coordinates are obtained, and a corresponding manipulator unloading task list is generated; When the chamber working progress is that material processing is not completed, an initial re-judgment message is generated.
[0011] By adopting the above technical solution, when the material processing in the chamber is completed, the completed chamber coordinates are obtained and the corresponding robot unloading task list is generated, so that timely response and optimized scheduling of the production process can be achieved, which helps to release chamber resources in time, reduce idle time, and improve equipment utilization and production efficiency; when the material processing in the chamber is not completed, an initial re-judgment message is generated, and relevant personnel or systems can be notified for further processing and decision-making, which helps to timely discover production problems or abnormal situations, and take corresponding measures to solve them, thereby ensuring the smooth progress of the production process.
[0012] In a preferred example, the present application may be further configured as follows: the construction of the loading task list and the unloading task list specifically includes: When the number of the idle chamber coordinates or the completed chamber coordinates acquired at a single time is only a single number, the idle chamber coordinates or the completed chamber coordinates are stored in a data queue; When the number of the idle chamber coordinates or the completed chamber coordinates obtained at a single time is multiple, obtaining the use rounds of the idle chambers or the completed chambers, and storing the idle chambers or the completed chambers in the data queue according to the number of use rounds; When the idle chamber or the completed chamber has the same usage round, the target task distance is obtained by calculating according to the idle chamber coordinates or the completed chamber coordinates and the corresponding robot coordinates, and the target task distance is input into the data queue from small to large.
[0013] By adopting the above technical scheme, by storing the idle chamber coordinates or completed chamber coordinates obtained at a single time into a data queue, the coordinate data can be orderly managed and stored, which helps to more conveniently obtain and use these coordinate information in the subsequent task scheduling and processing process; when the number of idle chamber coordinates or completed chamber coordinates obtained at a single time is multiple, by obtaining the use rounds of these coordinates and selecting the coordinates with smaller rounds, the reasonable allocation and utilization of resources can be achieved, which helps to avoid resource waste and conflict, and improve production efficiency and resource utilization; when the use rounds of idle chambers or completed chambers are the same, the target task distance is calculated according to the distance between the coordinates and the robot coordinates, and the data queue is entered in ascending order, the task execution order can be optimized, which helps to improve the task execution efficiency, reduce the idle waiting time of the robot, and thus optimize the production process.
[0014] In a preferred example, the present application can be further configured as follows: obtaining task coordinates from the manipulator task list and calculating the best manipulator path according to the task coordinates specifically includes: Obtain path obstacle information, and calculate the manipulator motion path according to the RRT algorithm preset by the system and the path obstacle information; The path length of the manipulator motion path is calculated, and the shortest path length is selected as the optimal path of the manipulator.
[0015] By adopting the above technical solution and obtaining path obstacle information, it is possible to identify and analyze obstacles that may exist in the robot's motion path, which helps to discover potential obstacles in advance and take these obstacles into consideration in path planning, thereby avoiding the robot from encountering obstacles during movement; by calculating the robot's motion path according to the system's preset RRT algorithm and path obstacle information, the RRT algorithm has the advantages of quickly generating paths and adapting to complex environments, and can effectively plan the robot's motion path; by calculating the path length of the calculated robot's motion path and selecting the shortest path length as the robot's optimal path, this helps to optimize the robot's motion trajectory, reduce motion time and energy consumption, and improve the robot's motion efficiency and performance.
[0016] In a preferred example, the present application can be further configured as follows: the manipulator motion control method further includes: The curing heating temperature and the material cooling temperature are obtained, and the curing heating temperature and the material cooling temperature are corrected according to a temperature compensation function preset by the system.
[0017] By adopting the above technical solution, precise temperature control can be achieved by correcting the curing heating temperature and the material cooling temperature, which helps to ensure that the temperature is stable within the set range during the curing and cooling process, thereby improving product quality and consistency; through temperature correction, energy waste caused by excessively high or low temperatures can be avoided, and optimizing temperature control can reduce energy consumption and reduce production costs; through temperature correction, the stable production process can be ensured, avoiding production interruptions or quality problems caused by unstable temperature, which helps to improve production efficiency and output.
[0018] The second object of the invention is achieved by the following technical solutions: A manipulator motion control device, the manipulator motion control device comprising: A task list building module is used to obtain the target position coordinates and device usage of different devices, and generate a corresponding manipulator task list according to the target position coordinates and the device usage; An optimal path calculation module, used to obtain task coordinates from the manipulator task list and calculate the optimal path of the manipulator according to the task coordinates; The control instruction generation module is used to input the optimal path of the manipulator into the manipulator control terminal to generate a manipulator movement instruction.
[0019] By adopting the above-mentioned technical scheme, since in existing curing furnaces, curing is usually carried out in coordination with a structure and a simple control program, the coupling degree between the structure and the control program of different equipment in the entire curing process is relatively high. When the curing process needs to be changed, the curing furnace structure needs to be considered, and the freedom of the entire production process is relatively low. Therefore, the present application can achieve comprehensive monitoring and management of production equipment and tasks by obtaining the target position coordinates and equipment usage of different equipment, which helps to understand the equipment status, production progress and resource utilization in real time, thereby performing effective scheduling and optimization; by generating a robot according to the target position coordinates and equipment usage The task list can realize automatic allocation and scheduling of tasks, which can improve production efficiency, reduce waste of human resources, and ensure the smooth progress of the production process; by obtaining the task coordinates in the robot task list and calculating the optimal path of the robot based on these coordinates, it can ensure that the path planning of the robot is reasonable when performing tasks, reduce movement time and energy consumption, and improve work efficiency; the calculated optimal path of the robot is input into the robot control terminal to generate robot motion instructions, which can realize precise control and operation of the robot, which helps to ensure that the robot performs tasks according to the predetermined path and speed, and improve the stability and consistency of the production line.
[0020] The third objective of the present application is achieved through the following technical solutions: A computer device comprises a memory, a processor and a computer program stored in the memory and executable on the processor, wherein the processor implements the steps of the above-mentioned manipulator motion control method when executing the computer program.
[0021] The fourth objective of the present application is achieved through the following technical solutions: A computer-readable storage medium stores a computer program, and when the computer program is executed by a processor, the steps of the above-mentioned manipulator motion control method are implemented.
[0022] In summary, the present application includes at least one of the following beneficial technical effects: 1. By acquiring the printing progress data and triggering the printing end message when the system preset progress value is reached, the printing process can be monitored and controlled in real time, which helps to find printing problems or complete printing tasks in time, and improve printing efficiency and quality; by generating loading instructions according to the printing end message, the seamless connection between printing tasks and loading tasks can be achieved, which helps to reduce production interruptions and waiting time, and improve the continuity and efficiency of the production line; by acquiring the working status of all chambers, the internal chambers of the curing furnace can be monitored and managed in real time. When the chamber is idle, the idle chamber coordinates can be obtained in time and the robot loading task list can be generated, thereby optimizing the production scheduling and resource utilization of the curing furnace. When the chamber is working, the work progress can be obtained and the corresponding robot task list can be generated to ensure that the robot and the chamber work synchronously, thereby improving production efficiency; 2. By storing the idle chamber coordinates or completed chamber coordinates acquired at a single time into the data queue, the coordinate data can be orderly managed and stored, which is helpful to more conveniently acquire and use these coordinate information in the subsequent task scheduling and processing process; when the number of idle chamber coordinates or completed chamber coordinates acquired at a single time is multiple, by acquiring the use rounds of these coordinates and selecting the coordinates with smaller rounds, the reasonable allocation and utilization of resources can be achieved, which helps to avoid resource waste and conflict, and improve production efficiency and resource utilization; when the use rounds of idle chambers or completed chambers are the same, the target task distance is calculated according to the distance between the coordinates and the manipulator coordinates, and the data queue is input in ascending order, the task execution order can be optimized, which helps to improve the task execution efficiency, reduce the idle waiting time of the manipulator, and thus optimize the production process; 3. By obtaining path obstacle information, it is possible to identify and analyze obstacles that may exist in the robot's motion path, which helps to discover potential obstacles in advance and take these obstacles into account in path planning, thereby avoiding the robot encountering obstacles during movement; by calculating the robot's motion path based on the system's preset RRT algorithm and path obstacle information, the RRT algorithm has the advantages of quickly generating paths and adapting to complex environments, and can effectively plan the robot's motion path; by calculating the path length of the calculated robot's motion path and selecting the shortest path length as the robot's optimal path, this helps to optimize the robot's motion trajectory, reduce motion time and energy consumption, and improve the robot's motion efficiency and performance. BRIEF DESCRIPTION OF THE DRAWINGS
[0023] Figure 1 is a flow chart of a manipulator motion control method in one embodiment of the present application; Figure 2 is a flowchart for implementing step S10 in the manipulator motion control method in one embodiment of the present application; Figure 3 is a flowchart for implementing step S12 in the manipulator motion control method in one embodiment of the present application; Figure 4 It is a flowchart for implementing the construction of a manipulator loading task list and a manipulator unloading task list in a manipulator motion control method in an embodiment of the present application; Figure 5 is a flowchart for implementing step S20 in the manipulator motion control method in one embodiment of the present application; Figure 6 is another implementation flow chart of the manipulator motion control in one embodiment of the present application; Figure 7 This is a principle block diagram of a manipulator motion control device in one embodiment of the present application; Figure 8 It is a schematic diagram of a device in an embodiment of the present application. DETAILED DESCRIPTION
[0024] The present application is further described in detail below in conjunction with the accompanying drawings.
[0025] In one embodiment, if Figure 1 As shown, the present application discloses a manipulator motion control method, which specifically includes the following steps: S10: Obtain target position coordinates and device usage of different devices, and generate a corresponding manipulator task list according to the target position coordinates and device usage.
[0026] In this embodiment, the target position coordinates refer to the spatial coordinates of the location of the material to be moved. The equipment usage status refers to the current working status of different equipment. The manipulator task list refers to a list storing all pending tasks of the manipulator.
[0027] Specifically, the curing process includes multiple devices, such as PI printers, waiting platforms, curing furnaces, cooling chambers and export platforms. Each device is equipped with an infrared sensor to send the location of the device itself and obtain the location of the material. At the same time, different devices will display the current working status in real time and record work logs when working. The system will perform various calculations and judgments based on the target position coordinates and equipment usage of different devices, and obtain the robot task list through reasonable order arrangement.
[0028] S20: Obtain task coordinates from the robot task list, and calculate the best path for the robot according to the task coordinates.
[0029] In this embodiment, the task coordinates refer to the starting position and the ending position of the robot to perform the task. The best path of the robot refers to the route information that saves the most time when the robot performs the task.
[0030] Specifically, the task coordinates are obtained from the robot task list. Since the robot task list is a sorted queue, there is no need to make other task priority judgments. It is only necessary to calculate the best path from the starting point coordinates to the end point coordinates when executing the task.
[0031] S30: Inputting the optimal path of the robot into the robot control terminal to generate a robot motion instruction.
[0032] In this embodiment, the robot movement instruction refers to an instruction for controlling the robot to move.
[0033] Specifically, the calculated optimal path of the robot is input into the robot control terminal, and the control terminal generates a robot movement instruction to control the robot to move accordingly according to the set optimal path.
[0034] In this embodiment, since in the existing curing furnace, the structure and simple control program are usually used to coordinate the curing, the coupling degree between the structure and the control program of different equipment in the whole curing process is high. When the curing process needs to be changed, the curing furnace structure needs to be considered, and the freedom of the whole production process is low. Therefore, the present application can realize comprehensive monitoring and management of production equipment and tasks by obtaining the target position coordinates and equipment usage of different equipment, which helps to understand the equipment status, production progress and resource utilization in real time, so as to carry out effective scheduling and optimization; by generating a manipulator task list according to the target position coordinates and equipment usage, the automatic allocation and scheduling of tasks can be realized, which can improve production efficiency, reduce the waste of human resources, and ensure the smooth progress of the production process; by obtaining the task coordinates in the manipulator task list and calculating the optimal path of the manipulator according to these coordinates, it can ensure that the manipulator has a reasonable path planning when performing tasks, reduce moving time and energy consumption, and improve work efficiency; the calculated optimal path of the manipulator is input into the manipulator control terminal to generate the manipulator motion instruction, so as to realize the precise control and operation of the manipulator, which helps to ensure that the manipulator performs tasks according to the predetermined path and speed, and improves the stability and consistency of the production line.
[0035] In one embodiment, if Figure 2 As shown, in step S10, the target position coordinates and device usage of different devices are obtained, and a corresponding manipulator task list is generated according to the target position coordinates and device usage, specifically including: S11: Acquire printing progress data. When the printing progress data reaches a progress value preset by the system, trigger a printing end message, and generate a material loading instruction according to the printing end message.
[0036] In this embodiment, the printing progress data refers to the progress of the material during the printing process. The printing end message refers to the message triggered when the material printing is completed.
[0037] Specifically, the material needs to be printed with PI liquid before curing. The PI printer will print the material according to a pre-set printing program. When the printing operation is completed, it will trigger a printing end message and generate a loading instruction to control the robot to move the material to the waiting platform.
[0038] S12: Obtain the working status of all chambers. When the chamber working status is idle, obtain the coordinates of the idle chamber and generate a corresponding robot loading task list. When the chamber working status is working, obtain the chamber working progress and generate a corresponding robot task list based on the chamber working progress.
[0039] In this embodiment, the chamber working state refers to whether the chamber of the equipment is currently in working state. The manipulator loading task list refers to the task list used by the manipulator when performing the loading task.
[0040] Specifically, the printed materials need to be transported from the inspection platform to the curing chamber in the curing furnace, and then the materials processed in the curing furnace are transported to the cooling chamber. At this time, the system needs to determine whether there is material in the chamber. Therefore, the working status of all chambers is obtained. When the chamber working status is idle, the coordinates of the idle chambers are obtained and sorted accordingly to obtain the robot loading task list. When the chamber working status is working, there is material in the chamber. The working progress of the chamber is obtained, and the next step is performed according to whether the material in the chamber has been processed.
[0041] In one embodiment, if Figure 3 As shown, in step S12, that is, when the chamber working state is working, the chamber working progress is obtained, and a corresponding manipulator task list is generated according to the chamber working progress, specifically including: S121: When the chamber work progress is that the material processing is completed, the completed chamber coordinates are obtained, and a corresponding robot unloading task list is generated.
[0042] Specifically, according to the current work progress of the chamber, such as judging whether the current material has been heated according to the set curing heating temperature, when the material processing is completed, the completed chamber coordinates are obtained, and the corresponding robot unloading task list is generated to move the materials in the completed chamber out.
[0043] S122: When the chamber working progress is that the material processing is not completed, an initial re-judgment message is generated.
[0044] Specifically, when the chamber work progress is that the material processing is not completed, such as when the chamber in the curing furnace and the chamber in the cooling chamber are all processed, the system will generate a judgment message to re-judge the entire process.
[0045] In one embodiment, if Figure 4 As shown, the construction of the loading task list and the unloading task list specifically includes: S101: When the number of idle chamber coordinates or completed chamber coordinates acquired at a time is only a single number, the idle chamber coordinates or completed chamber coordinates are stored in a data queue.
[0046] Specifically, each time it is determined that there is an idle chamber or a completed chamber, the coordinates of the idle chamber will be obtained. When the obtained chamber is a single chamber, the obtained chamber coordinates can be directly input into the data queue for queuing as a robot loading queue or a robot unloading queue.
[0047] S102: When the number of idle chamber coordinates or completed chamber coordinates acquired at a time is multiple, the use rounds of the idle chambers or completed chambers are acquired, and the idle chambers or completed chambers are stored in a data queue according to the number of use rounds.
[0048] Specifically, when multiple idle chambers or completed chambers are obtained, the system will determine the usage rounds of the idle chambers or completed chambers based on the equipment's work log, and give priority to inputting chambers with fewer usage rounds into the task team to balance the usage rounds of each chamber, reduce the waste of chamber resources, and reduce the reduction in material accuracy caused by excessive heating time.
[0049] S103: When the idle chamber or the completed chamber has the same usage round, the target task distance is obtained by calculating the idle chamber coordinates or the completed chamber coordinates and the corresponding robot coordinates, and the target task distance is input into the data queue from small to large.
[0050] Specifically, when the use rounds of idle chambers or completed chambers are the same, the distance between the chamber and the robot will be calculated, and the chamber with a shorter distance will be input into the task queue first to increase the speed of the robot in performing tasks and improve the handling speed of the robot.
[0051] In one embodiment, if Figure 5 As shown, in step S20, the task coordinates are obtained from the manipulator task list, and the optimal path of the manipulator is calculated according to the task coordinates, which specifically includes: S21: Obtain path obstacle information, and calculate the manipulator motion path according to the system preset RRT algorithm and the path obstacle information.
[0052] Specifically, since the curing path, cooling chamber and internal chambers are all groove structures, when the robot is performing a handling operation, the side walls of the equipment will block the path of the robot. Therefore, obstacles need to be avoided accordingly during path calculation. Therefore, the system will obtain path obstacle information and search for the path according to the preset RRT algorithm. Since the RRT algorithm quickly searches for feasible paths through random sampling and tree expansion, the path found may not be the optimal path.
[0053] S22: Calculate the path length of the robot motion path meter and select the shortest path length as the optimal path of the robot.
[0054] Specifically, the path lengths of all paths calculated by the RRT algorithm are calculated, the calculated path lengths are compared, and the shortest path length is selected as the optimal path for the manipulator, which is then input into the manipulator control terminal to control the manipulator to move.
[0055] In one embodiment, if Figure 6 As shown, the manipulator motion control method also includes: S40: Acquire the curing heating temperature and the material cooling temperature, and correct the curing heating temperature and the material cooling temperature according to a temperature compensation function preset by the system.
[0056] Specifically, since the thermocouples for obtaining the temperature of the curing chamber and the cooling chamber are installed on the equipment, there will be a certain deviation when detecting the surface temperature of the material. Therefore, the system will couple the manually collected data with the temperature detected by the thermocouple to obtain a temperature compensation function for thermocouple detection in order to obtain the accurate progress of heating or cooling the material.
[0057] It should be understood that the size of the serial numbers of the steps in the above embodiments does not mean the order of execution. The execution order of each process should be determined by its function and internal logic, and should not constitute any limitation on the implementation process of the embodiments of the present application.
[0058] In one embodiment, a robot motion control device is provided, which corresponds one-to-one to the robot motion control method in the above embodiment. Figure 7 As shown, the robot motion control device includes a task list building module, an optimal path calculation module, and a control instruction generation module. The detailed description of each functional module is as follows: The task list building module is used to obtain the target position coordinates and equipment usage of different devices, and generate the corresponding manipulator task list according to the target position coordinates and equipment usage; The optimal path calculation module is used to obtain the task coordinates from the manipulator task list and calculate the optimal path of the manipulator according to the task coordinates; The control instruction generation module is used to input the optimal path of the robot into the robot control terminal and generate the robot movement instruction.
[0059] Optionally, the task list building module specifically includes: The material loading submodule is used to obtain the printing progress data. When the printing progress data reaches the progress value preset by the system, the printing end message is triggered, and the material loading instruction is generated according to the printing end message; The loading list construction submodule is used to obtain the working status of all chambers. When the chamber working status is idle, the idle chamber coordinates are obtained and the corresponding manipulator loading task list is generated. When the chamber working status is working, the chamber working progress is obtained and the corresponding manipulator task list is generated according to the chamber working progress.
[0060] Optionally, the load list build submodules specifically include: The unloading list building unit is used to obtain the completed chamber coordinates and generate the corresponding manipulator unloading task list when the chamber work progress is that the material processing is completed; The process re-judgment unit is used to generate an initial re-judgment message when the chamber work progress is that the material processing is not completed.
[0061] Optionally, build the loading task list and unloading task list, including: A single chamber processing unit, used for storing the idle chamber coordinates or the completed chamber coordinates into a data queue when the number of idle chamber coordinates or the completed chamber coordinates acquired at a single time is only a single number; A plurality of chamber processing units, for obtaining the use rounds of the idle chambers or the completed chambers when the number of idle chamber coordinates or the completed chamber coordinates obtained at a single time is multiple, and storing the idle chambers or the completed chambers in a data queue according to the number of use rounds; The chamber round processing unit is used to calculate the target task distance according to the coordinates of the idle chamber or the completed chamber and the corresponding robot coordinates when the use rounds of the idle chamber or the completed chamber are the same, and input the target task distance into the data queue from small to large.
[0062] Optionally, the optimal path calculation module specifically includes: The path acquisition submodule is used to obtain path obstacle information and calculate the manipulator motion path according to the system preset RRT algorithm and path obstacle information; The path selection submodule is used to calculate the path length of the robot motion path and select the shortest path length as the optimal path for the robot.
[0063] Optionally, the manipulator motion control method further includes: The temperature compensation module is used to obtain the curing heating temperature and the material cooling temperature, and to correct the curing heating temperature and the material cooling temperature according to the temperature compensation function preset by the system.
[0064] The specific definition of the manipulator motion control device can be found in the definition of the manipulator motion control method above, which will not be repeated here. Each module in the above-mentioned manipulator motion control device can be implemented in whole or in part by software, hardware and a combination thereof. The above-mentioned modules can be embedded in or independent of the processor in the computer device in the form of hardware, or can be stored in the memory in the computer device in the form of software, so that the processor can call and execute the operations corresponding to the above modules.
[0065] In one embodiment, a computer device is provided. The computer device may be a server, and its internal structure diagram may be as follows: Figure 8 As shown. The computer device includes a processor, a memory, a network interface and a database connected through a system bus. Among them, the processor of the computer device is used to provide computing and control capabilities. The memory of the computer device includes a non-volatile storage medium and an internal memory. The non-volatile storage medium stores an operating system, a computer program and a database. The internal memory provides an environment for the operation of the operating system and the computer program in the non-volatile storage medium. The database of the computer device is used to store equipment work records. The network interface of the computer device is used to communicate with an external terminal through a network connection. When the computer program is executed by the processor, a manipulator motion control method is implemented.
[0066] In one embodiment, a computer device is provided, including a memory, a processor, and a computer program stored in the memory and executable on the processor, wherein the processor implements the following steps when executing the computer program: Obtain the target position coordinates and equipment usage of different devices, and generate a corresponding manipulator task list based on the target position coordinates and equipment usage; Obtain task coordinates from the robot task list and calculate the best path for the robot based on the task coordinates; The optimal path of the robot is input into the robot control terminal to generate the robot movement instruction.
[0067] In one embodiment, a computer readable storage medium is provided, on which a computer program is stored, and when the computer program is executed by a processor, the following steps are implemented: Obtain the target position coordinates and equipment usage of different devices, and generate a corresponding manipulator task list based on the target position coordinates and equipment usage; Obtain task coordinates from the robot task list and calculate the best path for the robot based on the task coordinates; The optimal path of the robot is input into the robot control terminal to generate the robot movement instruction.
[0068] Those skilled in the art can understand that all or part of the processes in the above-mentioned embodiment methods can be completed by instructing the relevant hardware through a computer program, and the computer program can be stored in a non-volatile computer-readable storage medium. When the computer program is executed, it can include the processes of the embodiments of the above-mentioned methods. Among them, any reference to memory, storage, database or other media used in the embodiments provided in this application may include non-volatile and / or volatile memory. Non-volatile memory may include read-only memory (ROM), programmable ROM (PROM), electrically programmable ROM (EPROM), electrically erasable programmable ROM (EEPROM) or flash memory. Volatile memory may include random access memory (RAM) or external cache memory. As an illustration and not limitation, RAM is available in many forms, such as static RAM (SRAM), dynamic RAM (DRAM), synchronous DRAM (SDRAM), double data rate SDRAM (DDRSDRAM), enhanced SDRAM (ESDRAM), synchronous link (Synchlink) DRAM (SLDRAM), memory bus (Rambus) direct RAM (RDRAM), direct memory bus dynamic RAM (DRDRAM), and memory bus dynamic RAM (RDRAM).
[0069] Those skilled in the art can clearly understand that for the convenience and simplicity of description, only the division of the above-mentioned functional units and modules is used as an example. In actual applications, the above-mentioned functions can be distributed and completed by different functional units and modules as needed, that is, the internal structure of the device can be divided into different functional units or modules to complete all or part of the functions described above.
[0070] The embodiments described above are only used to illustrate the technical solutions of the present application, rather than to limit them. Although the present application has been described in detail with reference to the aforementioned embodiments, a person skilled in the art should understand that the technical solutions described in the aforementioned embodiments may still be modified, or some of the technical features may be replaced by equivalents. Such modifications or replacements do not deviate the essence of the corresponding technical solutions from the spirit and scope of the technical solutions of the embodiments of the present application, and should all be included in the protection scope of the present application.
Claims
1. A robot motion control method, characterized in that: The manipulator motion control method comprises: Obtain target position coordinates and device usage of different devices, and generate a corresponding manipulator task list according to the target position coordinates and the device usage; Obtaining task coordinates from the manipulator task list, and calculating the best path for the manipulator according to the task coordinates; The optimal path of the manipulator is input into the manipulator control terminal to generate a manipulator motion instruction.
2. The robot motion control method according to claim 1, characterized in that: The acquiring of target position coordinates and device usage of different devices, and generating a corresponding manipulator task list according to the target position coordinates and the device usage, specifically includes: Acquire printing progress data, and when the printing progress data reaches a progress value preset by the system, trigger a printing end message, and generate a material loading instruction according to the printing end message; Obtain the working status of all chambers. When the chamber working status is idle, obtain the coordinates of the idle chamber and generate a corresponding robot loading task list. When the chamber working status is working, obtain the chamber working progress and generate the corresponding robot task list according to the chamber working progress.
3. The robot motion control method according to claim 2, characterized in that: When the chamber working state is working, the chamber working progress is obtained, and the corresponding manipulator task list is generated according to the chamber working progress, specifically including: When the chamber work progress is that the material processing is completed, the completed chamber coordinates are obtained, and a corresponding manipulator unloading task list is generated; When the chamber working progress is that material processing is not completed, an initial re-judgment message is generated.
4. The manipulator motion control method according to any one of claims 2 and 3, characterized in that: The construction of the loading task list and the unloading task list specifically includes: When the number of the idle chamber coordinates or the completed chamber coordinates acquired at a single time is only a single number, the idle chamber coordinates or the completed chamber coordinates are stored in a data queue; When the number of the idle chamber coordinates or the completed chamber coordinates obtained at a single time is multiple, obtaining the use rounds of the idle chambers or the completed chambers, and storing the idle chambers or the completed chambers in the data queue according to the number of use rounds; When the idle chamber or the completed chamber has the same usage round, the target task distance is obtained by calculating according to the idle chamber coordinates or the completed chamber coordinates and the corresponding robot coordinates, and the target task distance is input into the data queue from small to large.
5. The robot motion control method according to claim 1, characterized in that: The step of obtaining the task coordinates from the manipulator task list and calculating the best path of the manipulator according to the task coordinates specifically includes: Obtain path obstacle information, and calculate the manipulator motion path according to the RRT algorithm preset by the system and the path obstacle information; The path length of the manipulator motion path is calculated, and the shortest path length is selected as the optimal path of the manipulator.
6. The robot motion control method according to claim 1, characterized in that: The manipulator motion control method also includes: The curing heating temperature and the material cooling temperature are obtained, and the curing heating temperature and the material cooling temperature are corrected according to a temperature compensation function preset by the system.
7. A robot motion control device, characterized in that: The manipulator motion control device comprises: A task list building module is used to obtain the target position coordinates and device usage of different devices, and generate a corresponding manipulator task list according to the target position coordinates and the device usage; An optimal path calculation module, used to obtain task coordinates from the manipulator task list and calculate the optimal path of the manipulator according to the task coordinates; The control instruction generation module is used to input the optimal path of the manipulator into the manipulator control terminal to generate a manipulator movement instruction.
8. The robot motion control device according to claim 7, characterized in that: The task list construction module specifically includes: The material loading submodule is used to obtain printing progress data, trigger a printing end message when the printing progress data reaches a progress value preset by the system, and generate a material loading instruction according to the printing end message; The loading list construction submodule is used to obtain the working status of all chambers. When the chamber working status is idle, the idle chamber coordinates are obtained and the corresponding manipulator loading task list is generated. When the chamber working status is working, the chamber working progress is obtained and the corresponding manipulator task list is generated according to the chamber working progress.
9. A computer device comprising a memory, a processor, and a computer program stored in the memory and executable on the processor, characterized in that: When the processor executes the computer program, the steps of the manipulator motion control method according to any one of claims 1 to 6 are implemented.
10. A computer-readable storage medium storing a computer program, characterized in that: When the computer program is executed by a processor, the steps of the manipulator motion control method according to any one of claims 1 to 6 are implemented.
Citation Information
Patent Citations
Manual feed apparatus of robot for calculating operable range of robot
CN106737770A
Mechanical arm scheduling method, device and system
CN111496788A
Printing workshop feeding control method, system and equipment
CN113387101A
Full-automatic sheet metal part production method and device, electronic equipment and storage medium
CN115202297A
Pump body rotation detection method
CN115750312A
Cited By
Mechanical arm path optimization dynamic scheduling method and device, equipment and storage medium
CN121267883A
Dynamic scheduling method, device, equipment and storage medium for robot path optimization
CN121267883B