Method for deep extraction of coal bed gas through horizontal well
By using a sand control device in a horizontal well to lower the pump hanging position and prevent silt from entering, the problem of underground powder and sand spitting in the existing technology is solved, the continuous and stable operation of the pump is achieved, the coalbed methane is further released, and the output is increased.
Patent Information
- Application Number
- CN202411078738.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-07
- Publication Date
- 2024-10-11
- Estimated Expiration
- 2044-08-07
AI Technical Summary
In the existing horizontal well drainage technology, it is difficult to lower the pump mounting position, which results in spitting out powder and sand downhole, affecting the continuous and stable operation of the pump, and the reservoir energy is not fully released, resulting in reduced production.
A sand control device for horizontal wells is adopted. Through the diversion channel structure of the outer and inner pipes, the pump hanging position is lowered so that the suction inlet of the pump goes deep into the depth of the horizontal well. Multi-stage sand control steps are used to prevent silt from entering the pump to ensure the continuous stability of the pump. run.
The pump hanging position is lowered to the landing point, and the suction inlet reaches deep into the horizontal section. The pump can run continuously and smoothly, further releasing the coalbed methane, increasing production, and reducing the frequency of maintenance.
Smart Images

Figure CN118757128A_ABST
Abstract
Description
Technical Field
[0001] The invention discloses a method for deeply extracting coalbed methane through a horizontal well, belonging to the technical field of extracting coalbed methane through a horizontal well. Background Art
[0002] The gas volume of a single well in a coalbed methane pre-extraction horizontal well gradually decreases with the drainage time. In order to further release the reservoir energy, the pump hanger needs to be further lowered. However, after the pump hanger is lowered, the underground spitting of powder and sand affects the continuous and stable operation of the underground pump. Moreover, as time goes by, the horizontal section fluctuates unsteadily, and sand bridges are easily formed at the trough position, affecting the extraction effect. At present, the lowest position of the pump hanger in the horizontal well that has been put into operation is 80-85° inclination, and there is a flow pressure of 0.1-0.15MPa from the coal seam, and the reservoir energy has not been further released. How to lower the pump hanger position under the premise that the pump can operate continuously and stably, so that the water deeper in the horizontal well can be further discharged, the coalbed methane can be further released, and thus the production can be increased is a major problem in this industry. Summary of the invention
[0003] In view of the deficiencies in the prior art, the purpose of the present invention is to provide a method for deep extraction of coalbed methane in horizontal wells, so that the pump hanging position in the horizontal well can be as low as the landing point, the suction port of the pump can be deep into the horizontal well, and can operate continuously and stably.
[0004] To achieve the above object, the present invention adopts the following technical solution, a method for deep extraction of coalbed methane from a horizontal well, comprising the following steps:
[0005] The first step is to determine the pump hanging position as the landing point of the horizontal well or within 50m above the landing point according to the actual drilling trajectory data of the horizontal well, the position of the second suction port in the horizontal well sand control device is: 10m-80m beyond the first perforation section near the wellbore along the horizontal section drilling direction, and the position of the inner tube liquid inlet is the middle of the first suction port and the second suction port in the horizontal well sand control device;
[0006] The second step is to clean the horizontal well;
[0007] The third step is to assemble the sand control device for the horizontal well according to the positions of the components determined in the first step, and connect the sand control device for the horizontal well to the bottom of the pump, and connect the relevant pipe string and cable to the top of the pump;
[0008] Step 4: Smoothly lower the device connected in step 3 into the horizontal well at a speed not exceeding 200 m / h;
[0009] The fifth step is to connect the tubing wellhead hanger and place the tubing wellhead hanger into the wellhead big four-way, tighten and install all the big four-way bolts and top screws;
[0010] Step 6: Install the ground extraction equipment, connect the high-pressure water line, and fill the ground facility water tank with water;
[0011] Step 7: Test pressure for 20 minutes;
[0012] Step 8: Use clean water to wash the well. After the circulation is established, wash the well continuously for 30 minutes to clean the underground unit.
[0013] The ninth step is to start the pumping equipment until liquid is discharged and test the pump efficiency. A pump efficiency of more than 80% is acceptable.
[0014] Preferably, in the first step, the vertical depths at the positions of the first suction port and the second suction port are both higher than the vertical depth at the position of the liquid inlet.
[0015] Preferably, in the second step, the process of cleaning the horizontal well is: first pull out all the pipes in the horizontal well, then use a diameter gauge to clear the well to 30-50 meters behind the second suction port position of the horizontal well sand control device, and then bailing sand to the bottom of the artificial well.
[0016] Preferably, the method further includes a tenth step, that is, after six months of operation, all equipment and tubings lowered into the horizontal well are pulled out for maintenance. During the maintenance, the silt in the sand control device for the horizontal well is cleaned, and the silt situation in the well is judged based on the amount of silt therein. If the sand accumulation is serious, the sand is bailed out, and then all equipment is lowered into the horizontal well to continue operation, and the next maintenance time is determined.
[0017] Preferably, the pump is a hydraulic tube pump.
[0018] In the above steps, the horizontal well sand control device used includes an outer tube and an inner tube, the front end of the outer tube is open, and the tail end is connected to the outer tube plug, the front end of the inner tube is open, and the tail end is connected to the inner tube plug, the outer tube is sleeved outside the inner tube, and the inner wall of the outer tube and the outer wall of the inner tube are between the guide channel, the tube walls at both ends of the outer tube are densely covered with outer tube sieve holes, and the tube wall in the middle of the inner tube is densely covered with inner tube sieve holes;
[0019] The inner wall of the outer tube is evenly distributed with multiple sections of annular grooves, which serve as sand prevention steps;
[0020] The front end of the inner tube is flush with the front end of the outer tube, and the rear end is located at the outer tube sieve hole at the rear end of the outer tube;
[0021] The outer tube sieve hole at the front end of the outer tube is the first suction port, the outer tube sieve hole at the rear end of the outer tube is the second suction port, and the inner tube sieve hole on the inner tube is the inner tube liquid inlet.
[0022] Preferably, the outer pipe comprises a first oil pipe, a second oil pipe and an outer screen pipe, a plurality of first oil pipes are arranged in a row from front to back, a second oil pipe is connected between two adjacent first oil pipes, the outer diameter of the second oil pipe is adapted to the inner diameter of the first oil pipe, both ends of the second oil pipe are respectively sleeved in the end heads of the adjacent first oil pipes, the two first oil pipes at both ends are respectively connected to an outer screen pipe, the outer screen pipe is densely covered with outer pipe screen holes, the outer screen pipe at the tail end is connected to the outer pipe wire plug, and the inner wall of the first oil pipe and the pipe thickness of the two adjacent second oil pipes form a sand prevention step.
[0023] Preferably, the inner tube includes a third oil tube, a fourth oil tube and an inner screen tube, one end of the third oil tube is a front end, and the other end is connected to one end of the inner screen tube, the other end of the inner screen tube is connected to one end of the fourth oil tube, the other end of the fourth oil tube is a tail end, and is connected to the inner tube wire plug, and the inner screen tube is densely covered with inner tube screen holes.
[0024] Preferably, both the outer tube and the inner tube are hoses.
[0025] Preferably, the third oil pipe and the fourth oil pipe are both formed by connecting multiple oil pipes in sequence.
[0026] Compared with the prior art, the present invention has the following beneficial effects.
[0027] 1. The present invention realizes that the pump hanging position is lowered to the landing point. After the suction port penetrates deep into the horizontal section, the pump can still run continuously and stably, so that the coalbed methane in the horizontal well is further released, greatly improving the output.
[0028] 2. In the sand control device for horizontal wells, a diversion channel is formed between the outer tube and the inner tube. The accumulated liquid entering from both ends of the outer tube enters the inner tube through the diversion channel, avoiding the influence of the sand bridge in the horizontal section on the extraction effect.
[0029] 3. In the sand control device for horizontal wells, after the accumulated liquid enters the diversion channel from both ends of the outer tube, the flow rate of the accumulated liquid in the diversion channel is slow and is not affected by gas disturbance, which is conducive to the sedimentation of silt. At the same time, the sand will be deposited through multiple sections of sand control steps, effectively preventing silt from entering the working pump, optimizing the working environment of the pump, and providing technical support for the discharge of mixed sand and accumulated liquid in deeper parts of the horizontal section, thereby improving production capacity. In general horizontal wells, the pump can run stably and continuously for more than half a year, reducing the frequency of maintenance and replacement of the working pump. BRIEF DESCRIPTION OF THE DRAWINGS
[0030] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings required to be used in the embodiments are briefly introduced below.
[0031] Figure 1 It is a schematic diagram of the position of the pump and the horizontal well sand control device after being lowered into the horizontal well in the present invention.
[0032] Figure 2 It is a schematic structural diagram of the sand control device for horizontal wells in the present invention.
[0033] In the figure: 1 is an outer pipe, 11 is an outer pipe sieve hole, 12 is a first oil pipe, 13 is a second oil pipe, 14 is an outer sieve pipe, 2 is an inner pipe, 21 is an inner pipe sieve hole, 22 is a third oil pipe, 23 is a fourth oil pipe, 24 is an inner sieve pipe, 3 is an outer pipe thread plug, 4 is an inner pipe thread plug, 5 is a diversion channel, 6 is a sand control step, 7 is a pump, 8 is a sand control device for horizontal wells, and 9 is a first perforating section. DETAILED DESCRIPTION
[0034] The technical solution of the present invention is described clearly and completely below in conjunction with the accompanying drawings. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other implementation methods obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0035] The present invention provides the following embodiments.
[0036] like Figure 1 As shown, the method for deep extraction of coalbed methane from a horizontal well of the present invention comprises the following steps:
[0037] The first step is to determine the position of the pump 7 as the landing point of the horizontal well or within 50m above the landing point according to the actual drilling trajectory data of the horizontal well, and the position of the second suction port in the horizontal well sand control device 8 is: a distance exceeding the first perforation section 9 near the wellbore along the horizontal section drilling direction, such as 10m-80m, and the position of the inner tube liquid inlet is the middle of the first suction port and the second suction port in the horizontal well sand control device 8, and the vertical depths at the positions of the first suction port and the second suction port are higher than the vertical depth at the position of the liquid inlet;
[0038] The pump 7 is a rodless pump, specifically a hydraulic tube pump, model YFWGB70-44-3.7.
[0039] The second step is to clean the horizontal well. The cleaning process is as follows: first, pull out all the pipes in the horizontal well, then use a diameter gauge to clear the well to 30-50 meters behind the second suction port position of the horizontal well sand control device 8, and then scoop sand to the bottom of the artificial well;
[0040] The third step is to assemble the horizontal well sand control device 8 according to the positions of the components determined in the first step, and connect the horizontal well sand control device 8 to the bottom of the pump 7, and connect the top of the pump 7 to the relevant pipe string and cables, including the pressure gauge holder, the electronic pressure gauge, the central pipe, etc.;
[0041] Step 4: The device connected in step 3 is lowered steadily into the horizontal well at a lowering speed of no more than 200 m / h. During the process, the horizontal well sand control device 8 is lowered for every 100 m, and clean water is poured into the outer pipe 1 and the inner pipe 2 to ensure that the fixed valve on the pump 7 is in a closed state.
[0042] The fifth step is to connect the tubing wellhead hanger and place the tubing wellhead hanger into the wellhead big four-way, tighten and install all the big four-way bolts and top screws;
[0043] Step 6: Install the ground extraction device, connect the high-pressure water line, and fill the ground facility water tank with water;
[0044] Step 7: Test pressure for 20 minutes;
[0045] Step 8: Use clean water to wash the well. After the circulation is established, wash the well continuously for 30 minutes to clean the underground unit.
[0046] The ninth step is to start the pumping equipment until the liquid is discharged and test the pump efficiency. The pump efficiency is qualified if it is more than 80%;
[0047] Step 10. After half a year of operation, all equipment and pipes lowered into the horizontal well are taken out for maintenance. During the maintenance, the silt in the horizontal well sand control device 8 is cleaned, and the silt situation in the well is judged according to the amount of silt therein. If the accumulated sand occupies more than half of the cross-section of the diversion channel, the sand is bailed out, and then all equipment is lowered into the horizontal well to continue operation, and the next maintenance time is determined.
[0048] like Figure 2 As shown, the horizontal well sand control device 8 comprises an outer tube 1 and an inner tube 2, the front end of the outer tube 1 is open, and the tail end is connected to the outer tube plug 3, the front end of the inner tube 2 is open, and the tail end is connected to the inner tube plug 4, the outer tube 1 is sleeved on the outside of the inner tube 2, and the inner wall of the outer tube 1 and the outer wall of the inner tube 2 are between the guide channel 5, the tube walls at both ends of the outer tube 1 are densely covered with outer tube sieve holes 11, and the tube wall in the middle of the inner tube 2 is densely covered with inner tube sieve holes 21;
[0049] The inner wall of the outer tube 1 is evenly distributed with multiple annular grooves, which are sand-proof steps 6;
[0050] The front end of the inner tube 2 is flush with the front end of the outer tube 1, and the rear end is located at the outer tube sieve hole 11 at the rear end of the outer tube 1;
[0051] The outer tube sieve hole 11 at the front end of the outer tube 1 is the first suction port, the outer tube sieve hole 11 at the rear end of the outer tube 1 is the second suction port, and the inner tube sieve hole 21 on the inner tube 2 is the inner tube liquid inlet.
[0052] The outer pipe 1 includes a first oil pipe 12, a second oil pipe 13 and an outer screen pipe 14. A plurality of first oil pipes 12 are arranged in a row from front to back. A second oil pipe 13 is connected between two adjacent first oil pipes 12. The outer diameter of the second oil pipe 13 is adapted to the inner diameter of the first oil pipe 12. Both ends of the second oil pipe 13 are respectively sleeved in the ends of the adjacent first oil pipes 12. The two first oil pipes 12 at both ends are respectively connected to an outer screen pipe 14. The outer screen pipe 14 is densely covered with outer pipe sieve holes 11. The outer screen pipe 14 at the tail end is connected to the outer pipe wire plug 3. The inner wall of the first oil pipe 12 and the pipe thickness of the two adjacent second oil pipes 13 form a sand prevention step 6.
[0053] The inner tube 2 includes a third oil tube 22, a fourth oil tube 23 and an inner screen tube 24. One end of the third oil tube 22 is a front end, and the other end is connected to one end of the inner screen tube 24. The other end of the inner screen tube 24 is connected to one end of the fourth oil tube 23. The other end of the fourth oil tube 23 is a tail end, which is connected to the inner tube wire plug 4. The inner screen tube 24 is densely covered with inner tube sieve holes 21.
[0054] The outer tube 1 and the inner tube 2 are both soft tubes.
[0055] The third oil pipe 22 and the fourth oil pipe 23 are both formed by connecting a plurality of oil pipes in sequence.
[0056] In the present invention, as described in the first step, after the pump hanging position, the positions of the second suction port and the inner tube liquid inlet are determined, the total length of the outer tube 1 and the length of the third oil pipe 22 in the horizontal well sand control device 8 are determined, and the specific lengths of the first oil pipe 12, the second oil pipe 13, the outer screen pipe 14, the fourth oil pipe 23 and the inner screen pipe 24 are specifically allocated and designed. In the specific design process, the pump hanging position, the second suction port and the inner tube liquid inlet can also be fine-tuned according to the length of the existing oil pipe.
[0057] During the construction process of the present invention, the following requirements and matters needing attention shall be met.
[0058] The ground process construction requirements are:
[0059] (1) Carefully remove iron filings, rust, welding slag and other foreign matter in equipment, valves and pipelines to prevent large particles from clogging the nozzle.
[0060] (2) Ground pipelines must be tested for tightness to ensure that there is no leakage in the process.
[0061] (3) The wellhead and ground processes should be subjected to necessary anti-corrosion and thermal insulation as required.
[0062] Pay attention to the following during construction:
[0063] (1) To ensure a successful operation, a weight gauge must be installed when raising and lowering the pipe string. The operation must be smooth. Sudden braking and releasing are strictly prohibited, and objects are strictly prohibited from falling into the well.
[0064] (2) The well washing fluid must be clean, and the downhole tools and oil pipes must not fall to the ground and must be kept clean.
[0065] (3) Downhole equipment and tools must be carefully inspected before being lowered into the well to ensure that the model is correct and the oil pipe connections are sealed reliably.
[0066] (4) Carefully check the oil pipes in the outer pipe 1 and the inner pipe 2 to ensure they are intact and free of defects such as damage, cracks, holes, etc.
[0067] (5) All external oil pipes, short circuits, joints, internal oil pipes and adjustment short circuits from the pump working cylinder to the wellhead must use an oil pipe gauge and pass by their own weight. Those that fail to pass are strictly prohibited from being lowered into the well. The external pipe 1 must be passed with a Φ50mm gauge.
[0068] (6) The oil pipes lowered into the well should be measured one by one and recorded. During the process of lowering the pipe string, it is strictly forbidden to lower the pipe rigidly without getting stuck in the middle;
[0069] (7) Each oil pipe joint must be coated with high-pressure sealing grease (applied to the male buckle) or wrapped with polytetraethylene raw tape, and fully tightened to the specified torque.
[0070] (8) The inner tube is manually screwed without hydraulic clamps. During the lowering process, the thread must be fully tightened to control the lowering speed.
[0071] The present invention has been specifically applied to actual horizontal well reconstruction, with very good results, which will be specifically described below with examples.
[0072] The well is located in Xuchang City, Henan Province. Some of the actual drilling trajectory data of the horizontal well are shown in Table 1. The positions of the pump hanger, the first suction port, the second suction port, and the inner tube liquid inlet determined according to the actual drilling trajectory data are all marked.
[0073]
[0074] Table 1 Part of the actual drilling trajectory data of horizontal wells
[0075] When cleaning the horizontal well, all the pipes in the horizontal well were first removed, then the well was cleared to 1,100 meters using a bore gauge, and then sand was bailed to the bottom of the artificial well.
[0076] In the horizontal well sand control device 8 used in the horizontal well, the outer screen pipe 14 is a 2.0m long drilled screen pipe, the diameter of the outer pipe screen hole 11 is 8mm, the first oil pipe 12 is a 89 oil pipe with a length of 5.5m and an outer diameter of 88.9mm, the second oil pipe 13 is a 73 oil pipe with a length of 0.5m and an outer diameter of 73mm, the third oil pipe 22 is formed by connecting 6 oil pipes with a length of 7m and an outer diameter of 36mm, the fourth oil pipe 23 is also formed by connecting 6 oil pipes with a length of 7m and an outer diameter of 36mm, the inner screen pipe 34 is a 6m long screen pipe with an outer diameter of 36mm, the total length of the horizontal well sand control device 8 is 100 meters, and the total length of the inner pipe 2 is 90 meters.
[0077] In addition, the pump is a YFWGB70-44-3.7 hydraulic tube pump with a stroke of 3.7m, a stroke rate of 0-3 times / min, and a theoretical displacement of 31m 3 / d, maximum outer diameter 101.2mm, length 8500mm, and downhole depth 948m.
[0078] There are also other accessories such as Ф73mm 939.5m long pressure gauge holder, Ф73mm flat oil pipe hanger, etc.
[0079] The above is only a preferred specific embodiment of the present invention, but the protection scope of the present invention is not limited thereto. Any changes or substitutions that can be easily thought of by a person skilled in the art within the technical scope disclosed by the present invention should be included in the protection scope of the present invention. Therefore, the protection scope of the present invention shall be based on the protection scope of the claims.
Claims
1. A method for deep extraction of coalbed methane from a horizontal well, characterized in that The following steps are involved: The first step is to determine the pump hanging position to be the landing point of the horizontal well or within 50 meters above the landing point according to the actual drilling trajectory data of the horizontal well, the position of the second suction port in the horizontal well sand control device (8) to be 10 meters to 80 meters beyond the first perforation section (9) near the wellbore along the horizontal section drilling direction, and the position of the inner tube liquid inlet to be the middle of the first suction port and the second suction port in the horizontal well sand control device (8); The second step is to clean the horizontal well; The third step is to assemble the horizontal well sand control device (8) according to the positions of the components determined in the first step, and connect the horizontal well sand control device (8) to the bottom of the pump (7), and connect the relevant pipe string and cable to the top of the pump (7); Step 4: Smoothly lower the device connected in step 3 into the horizontal well at a speed not exceeding 200 m / h; The fifth step is to connect the tubing wellhead hanger and place the tubing wellhead hanger into the wellhead big four-way, tighten and install all the big four-way bolts and top screws; Step 6: Install the ground extraction equipment, connect the high-pressure water line, and fill the ground facility water tank with water; Step 7: Test pressure for 20 minutes; Step 8: Use clean water to wash the well. After the circulation is established, wash the well continuously for 30 minutes to clean the underground unit. The ninth step is to start the pumping equipment until liquid is discharged and test the pump efficiency. A pump efficiency of more than 80% is acceptable.
2. The method for deep extraction of coalbed methane from a horizontal well according to claim 1, characterized in that: In the first step, the vertical depths at the positions of the first suction port and the second suction port are both higher than the vertical depth at the position of the liquid inlet.
3. The method for deep extraction of coalbed methane from a horizontal well according to claim 1, characterized in that: In the second step, the process of cleaning the horizontal well is as follows: first, all the pipes in the horizontal well are pulled out, then the well is cleared with a diameter gauge to 30-50 meters behind the second suction port of the horizontal well sand control device (8), and then the sand is bailed to the bottom of the artificial well.
4. The method for deep extraction of coalbed methane from a horizontal well according to claim 1, characterized in that: The method further comprises a tenth step, wherein after half a year of operation, all equipment and pipes lowered into the horizontal well are taken out for inspection and maintenance. During the inspection and maintenance, the silt in the horizontal well sand control device (8) is cleaned, and the silt situation in the well is judged according to the amount of silt therein. If the sand accumulation is serious, the sand is bailed out, and then all equipment is lowered into the horizontal well to continue operation, and the next inspection and maintenance time is determined.
5. The method for deep extraction of coalbed methane from a horizontal well according to claim 1, characterized in that: The pump (7) is a hydraulic tube pump.
6. The method for deep extraction of coalbed methane from a horizontal well according to claim 1, characterized in that: The sand control device (8) for a horizontal well comprises an outer tube (1) and an inner tube (2); the outer tube (1) has an opening at the front end and is connected to an outer tube plug (3) at the rear end; the inner tube (2) has an opening at the front end and is connected to an inner tube plug (4) at the rear end; the outer tube (1) is sleeved outside the inner tube (2); a flow guide channel (5) is provided between the inner wall of the outer tube (1) and the outer wall of the inner tube (2); outer tube sieve holes (11) are densely distributed on the tube walls at both ends of the outer tube (1); and inner tube sieve holes (21) are densely distributed on the tube wall in the middle of the inner tube (2); The inner wall of the outer tube (1) is evenly distributed with a plurality of annular grooves, which serve as sand prevention steps (6); The front end of the inner tube (2) is flush with the front end of the outer tube (1), and the rear end is located at the outer tube sieve hole (11) at the rear end of the outer tube (1); The outer tube sieve hole (11) at the front end of the outer tube (1) is a first suction port, the outer tube sieve hole (11) at the rear end of the outer tube (1) is a second suction port, and the inner tube sieve hole (21) on the inner tube (2) is an inner tube liquid inlet.
7. A multi-stage suction sand control device for horizontal wells according to claim 6, characterized in that: The outer pipe (1) comprises a first oil pipe (12), a second oil pipe (13) and an outer screen pipe (14). A plurality of first oil pipes (12) are arranged in a row from front to back. A second oil pipe (13) is connected between two adjacent first oil pipes (12). The outer diameter of the second oil pipe (13) is adapted to the inner diameter of the first oil pipe (12). Both ends of the second oil pipe (13) are respectively sleeved in the ends of the adjacent first oil pipes (12). The two first oil pipes (12) at both ends are respectively connected to an outer screen pipe (14). The outer screen pipe (14) is densely covered with outer pipe screen holes (11). The outer screen pipe (14) at the rear end is connected to an outer pipe thread plug (3). The inner wall of the first oil pipe (12) and the thickness of the two adjacent second oil pipes (13) form a sand prevention step (6).
8. A multi-stage suction sand control device for horizontal wells according to claim 6 or 7, characterized in that: The inner tube (2) comprises a third oil tube (22), a fourth oil tube (23) and an inner screen tube (24); one end of the third oil tube (22) is a front end, and the other end is connected to one end of the inner screen tube (24); the other end of the inner screen tube (24) is connected to one end of the fourth oil tube (23); the other end of the fourth oil tube (23) is a rear end, and is connected to an inner tube thread plug (4); and the inner screen tube (24) is densely covered with inner tube screen holes (21).
9. A method for deep extraction of coalbed methane from a horizontal well according to claim 6 or 7, characterized in that: The outer tube (1) and the inner tube (2) are both soft tubes.
10. The method for deep extraction of coalbed methane from a horizontal well according to claim 8, characterized in that: The third oil pipe (22) and the fourth oil pipe (23) are both formed by connecting a plurality of oil pipes in sequence.
Citation Information
Patent Citations
Method and device for well completion of roadway type horizontal well
CN115898269A
Double-channel sand setting tail pipe column of sand production well
CN202100244U
Filter type sieve tube for sand-prevention oil well
CN203822270U
Sand-blocking gas anchor device
CN219993682U
Inflow control including fluid separation features
US20200386086A1