Circulating pump testing method
Through the combination of the switchable waterway device and the test bench, the circulation pump suction force and durability performance test under different waterway lengths are realized, which solves the problems of low detection efficiency and large space occupation in the existing technology, and improves the testing efficiency and Space utilization.
Patent Information
- Application Number
- CN202410992991.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-24
- Publication Date
- 2024-10-11
- Estimated Expiration
- 2044-07-24
AI Technical Summary
The existing technology is difficult to quickly and effectively detect the pumping performance and durability performance of the circulating pump in different usage environments, and the test platform layout space is large and the efficiency is low.
Using a switchable waterway device and test bench, the test waterway is arranged in a serpentine coil structure to change the on and off control valves to simulate different waterway lengths. It integrates the suction and durability test stations to simplify the installation of the circulating pump. and testing process.
It is possible to quickly conduct suction tests under simulated working conditions of various waterway lengths without changing the installation position of the circulating pump, and simultaneously conduct durability performance tests of multiple circulating pumps, which reduces the layout space of the test platform and improves efficiency. Test efficiency, can quickly calculate whether the attenuation rate of pumping performance is qualified or not.
Smart Images

Figure CN118757387A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of circulating pump detection, and in particular to a circulating pump testing method. Background Art
[0002] The durability and suction performance of the circulating pump are important evaluation indicators of the circulating pump. The suction performance is generally reflected in the suction of the circulating pump under different path lengths; the durability performance is generally the attenuation degree of the suction before and after a large number of start-stop durability tests. The usage scenarios of water heaters are generally small rooms, ordinary rooms, multi-story duplexes or large flats, and the lengths of the water supply paths of the water heaters are different. The circulating pump is a key component for the stable operation of the water heater. In order to ensure that the water heater can maintain better durability and suction performance in different usage scenarios, each batch of circulating pumps needs to be sampled and tested. In order to facilitate the rapid detection of the suction of the circulating pump under different usage environments and the suction before and after the durability test, it is necessary to propose a circulating pump testing method to reduce the layout space of the test platform and improve the test efficiency. Summary of the invention
[0003] The present invention aims to solve at least one of the technical problems existing in the prior art. To this end, the present invention provides a circulating pump testing method.
[0004] The technical solution adopted by an embodiment of the present invention to solve the technical problem is: a circulating pump testing method, characterized by comprising: a switchable water channel device, a test bench and a main water tank;
[0005] The switchable water channel device includes a water inlet interface, a water outlet interface, a plurality of control valves and a test water channel arranged in a serpentine winding coil structure; by changing the on-off of the control valve, the water channel length of the test water channel can be changed;
[0006] The test bench includes a suction test station, a durability test station and a control center; the suction test station, the switchable water channel device and the main water tank are connected through pipelines; the durability test station is connected to the main water tank through pipelines; a circulating pump can be installed at the suction test station or the durability test station, and is electrically connected to the control center;
[0007] The test method includes the following steps:
[0008] S1, place the circulating pump at the suction test station, and measure the water flow rate U of the circulating pump at full load under the water path length of each test water path. 1 toU N ; Where N is the number of switchable lengths of the waterway;
[0009] S2, placing the circulating pump at the durability test station and performing a start-stop durability test T times;
[0010] S3, put the circulating pump after the endurance test again in the suction test station, and measure the water flow rate K of the circulating pump at full load under the water path length of each test water path. 1 To K N ;
[0011] S4, calculate the full load water flow K of the circulating pump after the durability test under various water channel length conditions N Before the endurance test, the circulating pump has a full load flow rate U N The ratio of the circulating pump after the durability test is obtained. N (F N =1-K N / U N );
[0012] S5, determine and calculate the attenuation rate F under various waterway length conditions N Whether qualified.
[0013] Optionally, the switchable water channel device includes a base frame, and a first test water channel, a second test water channel, a third test water channel and an output pipe arranged on the base frame;
[0014] The first test water circuit, the second test water circuit, the third test water circuit and the output pipe are connected in sequence; the first test water circuit is provided with a water inlet interface, and the output pipe is provided with a water outlet interface; the first test water circuit, the second test water circuit and the third test water circuit are arranged in a serpentine winding coil structure;
[0015] A first bypass pipe and a first control valve are provided between the end of the first test water circuit and the output pipe; a second bypass pipe and a second control valve are provided between the second test water circuit and the output pipe; and a third control valve is provided between the end of the third test water circuit and the output pipe.
[0016] Optionally, the first test water channel, the second test water channel and the third test water channel are composed of a plurality of vertical water pipes and horizontal water pipes arranged side by side; the horizontal water pipes are connected to the vertical water pipes via arc-shaped bends.
[0017] Optionally, the arc-shaped bend pipe is provided with a first arc-shaped bend pipe and a second arc-shaped bend pipe having different radii.
[0018] Optionally, two adjacent vertical water pipes are arranged in a periodic manner at two intervals, namely, a first interval and a second interval; the upper parts of several vertical water pipes are connected to the horizontal water pipes via a first arc-shaped bend pipe, and the lower parts are connected to the horizontal water pipes via a second arc-shaped bend pipe.
[0019] Optionally, the base frame includes a vertical frame; the first test water channel and the second test water channel are arranged on one side of the vertical frame, and the third test water channel is arranged on the other side of the vertical frame.
[0020] Optionally, the water channel lengths of the first test water channel and the second test water channel are both 15 meters; and the water channel length of the third test water channel is 30 meters.
[0021] Optionally, a cache auxiliary water tank is further provided between the endurance test station and the main water tank; and a cache control valve is provided between the cache auxiliary water tank and the main water tank.
[0022] Optionally, a plurality of the endurance test stations are provided, and the plurality of the endurance test stations are all connected to the cache auxiliary water tank via a pipeline.
[0023] Optionally, the control center is provided with control buttons and a display screen.
[0024] Beneficial effects of the present invention: the switchable water channel device is provided with a test water channel arranged in a serpentine winding coil structure. By changing the on-off of the control valve, the water channel length of the test water channel can be changed. Without changing the installation position of the circulating pump, a variety of water channel length simulation conditions can be quickly carried out, so that the suction performance under different water channel length simulation conditions can be measured at the suction test station; and the durability test station of the test bench can also perform the start-stop durability test of other circulating pumps at the same time. The present invention integrates the suction test under different water channel length simulation conditions on a test system of a circulating pump, without changing the installation position of the circulating pump; and the durability performance test of multiple circulating pumps can be carried out simultaneously, which greatly reduces the layout space of the test platform, and can quickly calculate whether the attenuation rate of the suction performance of the circulating pump before and after the durability test under different water channel length simulation conditions is qualified, effectively improving the test efficiency of the circulating pump.
[0025] In order to make the above-mentioned objects, features and advantages of the present invention more obvious and understandable, preferred embodiments are given below and described in detail with reference to the accompanying drawings. BRIEF DESCRIPTION OF THE DRAWINGS
[0026] The above and / or additional aspects and advantages of the present invention will become apparent and easily understood from the description of the embodiments in conjunction with the following drawings, in which:
[0027] Figure 1 A schematic structural diagram of a circulating pump test system of the present invention;
[0028] Figure 2 for Figure 1 A schematic diagram of the structure of the switchable water channel device;
[0029] Figure 3 for Figure 1A top view of the switchable waterway device;
[0030] Figure 4 for Figure 1 Front view of the switchable waterway device.
[0031] Description of main component symbols:
[0032] 100, switchable water channel device; 10, base frame; 11, vertical frame; 20, first test water channel; 21, water inlet interface; 22, first bypass pipe; 23, first control valve; 30, second test water channel; 31, second bypass pipe; 32, second control valve; 40, third test water channel; 41, third control valve; 50, output pipe; 51, water outlet interface; 60, vertical water pipe; 61, horizontal water pipe; 62, first arc elbow; 63, second arc elbow; 64, first interval; 65, second interval;
[0033] 200. Test bench; 210. Suction test station; 220. Durability test station; 230. Control center; 300. Main water tank; 400. Cache auxiliary water tank; 410. Cache control valve. DETAILED DESCRIPTION
[0034] This section will describe in detail the specific embodiments of the present invention. The preferred embodiments of the present invention are shown in the accompanying drawings. The purpose of the accompanying drawings is to supplement the description of the text part of the specification with graphics, so that people can intuitively and vividly understand each technical feature and the overall technical solution of the present invention, but it cannot be understood as a limitation on the scope of protection of the present invention.
[0035] In the description of the present invention, the meaning of "above", "below", "exceed", etc. is not inclusive of the number itself, and the meaning of "above", "below", "within", etc. is inclusive of the number itself. If there is a description of "first" or "second", it is only used to distinguish the technical features, and cannot be understood as indicating or implying the relative importance or implicitly indicating the number of the indicated technical features or implicitly indicating the order of the indicated technical features.
[0036] In the description of the present invention, it should be understood that descriptions involving orientations, such as up, down, front, back, left, right, etc., and orientations or positional relationships indicated are based on the orientations or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore should not be understood as a limitation on the present invention.
[0037] In the present invention, unless otherwise clearly defined, the words "set", "install", "connect" and the like should be understood in a broad sense, for example, they can be directly connected or indirectly connected through an intermediate medium; they can be fixedly connected or detachably connected or integrally formed; they can be mechanically connected; they can be the internal connection of two elements or the interaction relationship between two elements. Those skilled in the art can reasonably determine the specific meanings of the above words in the present invention in combination with the specific content of the technical solution.
[0038] Example
[0039] Reference Figures 1 to 4 , a circulating pump testing method provided by the present invention is characterized by comprising: a switchable water channel device 100, a testing table 200 and a main water tank 300;
[0040] The switchable water channel device 100 includes a water inlet interface 21, a water outlet interface 51, a plurality of control valves and a test water channel arranged in a serpentine coil structure; by changing the on / off of the control valve, the water channel length of the test water channel can be changed;
[0041] The test bench 200 includes a suction test station 210, a durability test station 220 and a control center 230; the suction test station 210, the switchable water channel device and the main water tank 300 are connected through pipelines; the durability test station 220 is connected to the main water tank 300 through pipelines; the circulation pump can be installed at the suction test station 210 or the durability test station 220, and is electrically connected to the control center 230;
[0042] The test method includes the following steps:
[0043] S1, place the circulating pump at the suction test station 210, and measure the water flow rate U of the circulating pump at full load under the water path length of each test water path. 1 toU N ; Where N is the number of switchable lengths of the waterway;
[0044] S2, placing the circulation pump at the durability test station 220, and performing a start-stop durability test T times;
[0045] S3, put the circulating pump after the endurance test again in the suction test station, and measure the water flow rate K of the circulating pump at full load under the water path length of each test water path. 1 To K N ;
[0046] S4, calculate the full load water flow K of the circulating pump after the durability test under various water channel length conditions N Before the endurance test, the circulating pump has a full load flow rate U N The ratio of the circulating pump after the durability test is obtained.N (F N =1-K N / U N );
[0047] S5, determine and calculate the attenuation rate F under various waterway length conditions N Whether qualified.
[0048] In the present invention, the switchable water channel device 100 is provided with a test water channel arranged in a serpentine winding coil structure. By changing the on-off of the control valve, the water channel length of the test water channel can be changed. Without changing the installation position of the circulating pump, a variety of water channel length simulation conditions can be quickly performed, so that the suction performance under different water channel length simulation conditions can be measured at the suction test station 210; and the durability test station 220 of the test bench 200 can also perform the start-stop durability test of other circulating pumps at the same time. The present invention integrates the suction test under different water channel length simulation conditions on a test system of a circulating pump, without changing the installation position of the circulating pump; and the durability performance test of multiple circulating pumps can be carried out simultaneously, which greatly reduces the layout space of the test platform, and can quickly calculate whether the attenuation rate of the suction performance of the circulating pump before and after the durability test under different water channel length simulation conditions is qualified, effectively improving the test efficiency of the circulating pump.
[0049] In this embodiment, the switchable water channel device 100 includes a base frame 10, and a first test water channel 20, a second test water channel 30, a third test water channel 40 and an output pipe 50 disposed on the base frame 10;
[0050] The first test water channel 20, the second test water channel 30, the third test water channel 40 and the output pipe 50 are connected in sequence; the first test water channel 20 is provided with a water inlet interface 21, and the output pipe 50 is provided with a water outlet interface 51; the first test water channel 20, the second test water channel 30 and the third test water channel 40 are arranged in a serpentine winding coil structure;
[0051] A first bypass pipe 22 and a first control valve 23 are provided between the end of the first test water circuit 20 and the output pipe 50 ; a second bypass pipe 31 and a second control valve 32 are provided between the second test water circuit 30 and the output pipe 50 ; a third control valve 41 is provided between the end of the third test water circuit 40 and the output pipe 50 .
[0052] The circuitous serpentine coil arrangement of the first test water circuit 20, the second test water circuit 30, and the third test water circuit 40 can simulate the actual circuitous piping conditions of the water heater connecting pipes; and by controlling the conduction state of the test water circuit and the output pipe 50 through the first control valve 23, the second control valve 32 or the third control valve 41, the water circuit length of the actual water circuit of the test water circuit can be changed; multiple test states such as the state in which only the first test water circuit 20 is conductive, or the state in which the first test water circuit 20 and the second test water circuit 30 are conductive, or the state in which the three test water circuits are connected in sequence can be achieved. There is no need to change the installation position of the circulating pump. Only by switching the conduction state of the control valve on the water circuit test frame, the suction test under various water circuit length simulation conditions can be quickly performed, which greatly reduces the layout space of the test platform and effectively improves the test efficiency.
[0053] In this embodiment, the first test water channel 20, the second test water channel 30 and the third test water channel 40 are composed of a plurality of vertical water pipes 60 and a horizontal water pipe 61 arranged side by side; the horizontal water pipe 61 is connected to the vertical water pipe 60 through an arc-shaped bend pipe. By means of the vertical water pipe 60, the horizontal water pipe 61 and the arc-shaped bend pipe, the water test water channel arrangement of the serpentine winding coil structure can be realized on the base frame 10; and the vertical water pipe 60 can be arranged with water pipes of the same standard length, such as a 1-meter or 2-meter water pipe arrangement, which is convenient for arrangement.
[0054] In this embodiment, the arc-shaped bend pipe is provided with a first arc-shaped bend pipe 62 and a second arc-shaped bend pipe 63 with different radii. The first arc-shaped bend pipe 62 and the second arc-shaped bend pipe 63 with different pipe diameters can simulate the waterway conditions of large corners and small corners in actual waterway laying, which is closer to the use scenario of the water heater circulation pump.
[0055] Specifically, two adjacent vertical water pipes 60 are arranged periodically at two intervals, namely, a first interval 64 and a second interval 65; the upper parts of a plurality of vertical water pipes 60 are connected to the horizontal water pipe 61 via a first arc-shaped elbow 62, and the lower parts are connected to the horizontal water pipe 61 via a second arc-shaped elbow 63. In this arrangement, the vertical water pipes 60 are arranged periodically at intervals of the first interval 64 and the second interval 65, so that the water measurement waterway arrangement of the serpentine winding coil structure can be completed through the vertical water pipes 60, the horizontal water pipes 61, the first arc-shaped elbow 62 and the second arc-shaped elbow 63 of the same specifications, and the waterway working conditions of large corners and small corners in actual waterway laying can be simulated.
[0056] In this embodiment, the base frame 10 includes a vertical frame 11; the first test water channel 20 and the second test water channel 30 are arranged on one side of the vertical frame 11, and the third test water channel 40 is arranged on the other side of the vertical frame 11. By arranging the test water channels on both sides of the vertical frame 11, the span space of the vertical frame 11 is further reduced in space.
[0057] Furthermore, a plurality of vertical frames 11 may be arranged at intervals to further reduce the span space of the base frame 10 .
[0058] In some embodiments, the lengths of the first test water channel 20 and the second test water channel 30 are the same, which is half the length of the third test water channel 40. In this arrangement, the total length of the first test water channel 20 and the second test water channel 30 is the same as that of the third test water channel, and the two opposite sides of the vertical frame 11 can be arranged with a similar horizontal span, making full use of the space on both sides of the vertical frame 11 for arranging the test water channels.
[0059] For example, the length of the third water measuring waterway is between 20 meters and 40 meters; and the length of the first water measuring waterway and the second water measuring waterway is between 10 meters and 20 meters.
[0060] After multiple tests, it is preferred that the length of the first test waterway 20 and the second test waterway 30 are both 15 meters; the length of the third test waterway 40 is 30 meters. It can better simulate the use conditions of small rooms, ordinary rooms, multi-storey duplexes or large flats, and can be easily arranged through vertical water pipes 60, horizontal water pipes 61, first arc-shaped elbows 62 and second arc-shaped elbows 63 of the same specifications; wherein the first bypass pipe 22 and the second bypass pipe 31 are centrally arranged in the vertical water pipe 60.
[0061] The specific switching conditions of the test waterway are as follows:
[0062] 1. Simulate the test condition of a small room, close the second control valve 32 and the third control valve 41, open the first control valve 23, and then the test water flows along the first test water channel 20 and the first bypass pipe 22 toward the output pipe 50, which is a test water channel condition with a water channel length of 15 meters.
[0063] 2. Simulate the test conditions of an ordinary room, close the first control valve 23 and the third control valve 41, open the second control valve 32, and the test water flows along the first test water channel 20, the second test water channel 30, and the second bypass pipe 31 toward the output pipe 50, which is a test water channel condition with a water channel length of 30 meters.
[0064] 3. To simulate the test condition of a multi-story duplex or large flat, close the first control valve 23 and the second control valve 32, and open the third control valve 41; at this time, the test waterway flows along the first test waterway 20, the second test waterway 30, and the third test waterway 40 toward the output pipe 50, which is a test waterway condition with a waterway length of 60 meters.
[0065] In the above arrangement, the number N of switchable lengths of the waterway is 3;
[0066] In this method, the decay rate F NThe qualified index can be adjusted according to the product positioning, such as 90%, 88%, 85% or 80%.
[0067] It can also be adjusted according to different waterway length conditions. For example, for a 15-meter waterway test condition, F N The qualified rate index is 90%; in the test waterway condition with a length of 30 meters, F N The qualified rate index is 85%; in the test waterway condition with a length of 60 meters, F N The pass rate target is 80%.
[0068] In this embodiment, a buffer sub-tank 400 is further provided between the endurance test station 220 and the main water tank 300; a buffer control valve 410 is provided between the buffer sub-tank 400 and the main water tank 300. The buffer sub-tank 400 can store a certain amount of water and is directly connected to the milk wine test station. When the circulation pump of the endurance test station 220 repeatedly starts to pump water, a chaotic water flow will be formed. The end of the water flow is transferred to the buffer sub-tank 400 and terminated, and will not be directly transferred to the main water tank 300. The main water tank 300 can maintain a relatively stable water level state, ensuring the stability of the water flow of the switchable water channel device 100 and the stability of the test water pressure of the suction test station 210.
[0069] In this embodiment, in order to improve the efficiency of the durability test, a plurality of durability test stations 220 are provided, and the plurality of durability test stations 220 are connected to the buffer auxiliary water tank 400 through a pipeline. The durability test of multiple circulating pump samples can be carried out at the same time. The durability test process is generally a large number of start-stop durability tests with a certain period of pumping and a certain period of shutdown. For example, a cycle test process of 100,000 times of pumping for 3 seconds and shutting down for 5 seconds.
[0070] In order to facilitate intuitive feedback of test status and data, as well as adjustment of test parameters, the control center 230 is provided with control buttons and a display screen.
[0071] Of course, the present invention is not limited to the above-mentioned embodiments, and those skilled in the art may make equivalent modifications or substitutions without violating the spirit of the present invention. These equivalent modifications and substitutions are all included in the scope defined by the claims of this application.
Claims
1. A circulating pump testing method, characterized in that: include: A switchable water channel device (100), a test bench (200) and a main water tank (300); The switchable water channel device (100) comprises a water inlet interface (21), a water outlet interface (51), a plurality of control valves and a test water channel arranged in a serpentine coil structure; the water channel length of the test water channel can be changed by changing the on / off of the control valve; The test bench (200) comprises a suction test station (210), a durability test station (220) and a control center (230); the suction test station (210), the switchable water channel device and the main water tank (300) are connected via a pipeline; the durability test station (220) is connected to the main water tank (300) via a pipeline; a circulating pump can be installed at the suction test station (210) or the durability test station (220), and is electrically connected to the control center (230); The test method includes the following steps: S1, placing the circulating pump at the suction test station (210), measuring the water flow rate U1 to U2 of the circulating pump at full load at each test water channel length. N ; Where N is the number of switchable lengths of the waterway; S2, placing the circulation pump at a durability test station (220) and performing a start-stop durability test T times; S3, put the circulating pump after the endurance test again in the suction test station, and measure the water flow rate of the circulating pump at full load K1 to K2 at the water path length of each test water path. N ; S4, calculate the full load water flow K of the circulating pump after the durability test under various water channel length conditions N Before the endurance test, the circulating pump has a full load flow rate U N The ratio of the circulating pump after the durability test is obtained. N (F N =1-K N / U N ); S5, determine and calculate the attenuation rate F under various waterway length conditions N Whether qualified.
2. The circulating pump testing method according to claim 1, characterized in that: The switchable water channel device (100) comprises a base frame (10), and a first test water channel (20), a second test water channel (30), a third test water channel (40) and an output pipe (50) arranged on the base frame (10); The first test water channel (20), the second test water channel (30), the third test water channel (40) and the output pipe (50) are connected in sequence; the first test water channel (20) is provided with a water inlet interface (21), and the output pipe (50) is provided with a water outlet interface (51); the first test water channel (20), the second test water channel (30) and the third test water channel (40) are arranged in a serpentine winding coil structure; A first bypass pipe (22) and a first control valve (23) are provided between the end of the first test water circuit (20) and the output pipe (50); a second bypass pipe (31) and a second control valve (32) are provided between the second test water circuit (30) and the output pipe (50); and a third control valve (41) is provided between the end of the third test water circuit (40) and the output pipe (50).
3. The circulating pump testing method according to claim 2, characterized in that: The first test water channel (20), the second test water channel (30) and the third test water channel (40) are composed of a plurality of vertical water pipes (60) and transverse water pipes (61) arranged side by side; the transverse water pipes (61) are connected to the vertical water pipes (60) via arc-shaped elbows.
4. The circulating pump testing method according to claim 3, characterized in that: The arc-shaped curved pipe is provided with a first arc-shaped curved pipe (62) and a second arc-shaped curved pipe (63) having different radii.
5. The circulating pump testing method according to claim 4, characterized in that: Two adjacent vertical water pipes (60) are periodically arranged at two intervals, namely, a first interval (64) and a second interval (65); the upper parts of a plurality of the vertical water pipes (60) are connected to the horizontal water pipe (61) via a first arc-shaped curved pipe (62), and the lower parts are connected to the horizontal water pipe (61) via a second arc-shaped curved pipe (63).
6. The circulating pump testing method according to claim 3, characterized in that: The base frame (10) comprises a vertical frame (11); the first test water channel (20) and the second test water channel (30) are arranged on one side of the vertical frame (11), and the third test water channel (40) is arranged on the other side of the vertical frame (11).
7. The circulating pump testing method according to claim 2, characterized in that: The water channel lengths of the first test water channel (20) and the second test water channel (30) are both 15 meters; and the water channel length of the third test water channel (40) is 30 meters.
8. The circulating pump testing method according to claim 1, characterized in that: A cache auxiliary water tank (400) is also provided between the endurance test station (220) and the main water tank (300); and a cache control valve (410) is provided between the cache auxiliary water tank (400) and the main water tank (300).
9. The circulating pump testing method according to claim 8, characterized in that: A plurality of the endurance test stations (220) are provided, and the plurality of the endurance test stations (220) are all connected to the cache auxiliary water tank (400) via pipelines.
10. The circulating pump testing method according to claim 1, characterized in that: The control center (230) is provided with control buttons and a display screen.
Citation Information
Patent Citations
Test system, durability test method and performance test method
CN107781155A
High-temperature and high-rotating-speed hydraulic pump testing equipment
CN118008779A
Simulated waterway detection equipment for gas water heater
CN209247377U
Water pump operation test system
CN220539832U
Circulating pump test switchable waterway structure
CN222963015U