Power plant safety emergency management system

Through the combination of real-time monitoring and data system early warning and prediction modules, the power plant safety emergency management system achieves rapid diagnosis and emergency response, solves the problem of inefficiency in regional sector data processing in the existing technology, and improves the accuracy and response speed of emergency processing. , reducing the risk loss of the power plant.

CN118759907APending Publication Date: 2024-10-11GUONENG (HUIZHOU) THERMAL POWER CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202410815551.7
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-06-21
Publication Date
2024-10-11

AI Technical Summary

Technical Problem

The existing power plant safety emergency management system cannot effectively divide regional sections for data processing, resulting in a busy system, affecting emergency response efficiency, and failing to quickly diagnose risks, resulting in losses to the power plant.

Method used

The real-time monitoring module is combined with sensors for all-round monitoring, the data system early warning prediction module performs fast and accurate data processing, the risk intelligent diagnosis module automatically selects emergency response plans through abnormal analysis and intelligent algorithm simulation technology, and the remote monitoring and control module performs flexible adjustments. The data analysis and reporting module generates security reports to optimize management.

Benefits of technology

It improves the response speed and accuracy of the power plant's emergency response, reduces losses, ensures the safety and production stability of the power plant, and reduces potential risks.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118759907A_ABST
    Figure CN118759907A_ABST
Patent Text Reader

Abstract

The invention provides a power plant safety emergency management system. Comprising the steps of S1, real-time monitoring module establishment, S2, data system early warning and prediction, S3, risk intelligent diagnosis, S4, emergency response processing, S5, remote monitoring and control, and S6, data analysis and reporting. Safety accidents caused by negligence can be avoided, intelligent data analysis and decision support are performed by means of big data and a system algorithm, remote monitoring and emergency response can be performed anytime and anywhere, a scientific decision basis can be provided for managers, loss caused by the safety accidents can be reduced to the maximum extent, and the system can automatically start an emergency response process. Meanwhile, the method has a self-learning capability, provides an optimization scheme for safety management of corresponding region plates of the power plant, prevents similar conditions from occurring repeatedly, and reduces loss.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of power plant safety management, and in particular to a power plant safety emergency management system. Background Art

[0002] A power plant is a power plant that converts some form of raw energy into electrical energy for fixed facilities or transportation, such as thermal, hydro, steam, diesel or nuclear power plants. Power plant safety management refers to the management process of effectively identifying, evaluating and controlling various safety risks in the operation of a power plant to ensure the safety of power plant equipment, personnel and the environment. As an important base for energy production, power plants may involve dangerous factors such as high-voltage electricity, gas, and chemicals during operation, so safety management is crucial.

[0003] At present, some power plant safety emergency management systems have certain safety hazards. There is no corresponding regional division for the safety management of the entire power plant. The system is prone to being busy during unified data processing, which in turn affects the power plant's emergency response efficiency. At the same time, the system cannot quickly diagnose risks, and power plant safety management personnel cannot coordinate with the safety emergency management system to make the best and effective emergency response plan, missing the golden emergency time and causing losses to the power plant enterprise. Summary of the invention

[0004] The invention discloses a power plant safety emergency management system, aiming to solve the technical problems mentioned above.

[0005] In order to achieve the above object, the present invention adopts the following technical solutions:

[0006] A power plant safety emergency management system includes the following specific steps:

[0007] S1. Establish a real-time monitoring module to conduct all-round electronic video monitoring of the power plant's risk areas, emergency response routes and risk equipment, and use temperature sensors, humidity sensors and noise sensors to conduct real-time monitoring of the equipment in various parts of the power plant and the surrounding areas of the equipment areas. The monitoring equipment and monitoring sensors are inspected regularly at the prescribed time to ensure the validity of the monitoring data;

[0008] S2. Data system early warning prediction, which includes data collection module, data extraction and analysis module, risk data interception module, data classification transmission module, and data classification storage module. The power plant plans the block number by department, and the corresponding department is responsible for the data processing work of the corresponding regional block, so as to quickly and accurately process the data;

[0009] S3, intelligent risk diagnosis, which conducts rapid intelligent diagnosis of risk data in the early warning forecast of the S2 data system, uses abnormal analysis algorithms and quantitative analysis algorithms to conduct intelligent diagnosis of risk data, and combines intelligent algorithm simulation technology to automatically select the optimal solution for emergency response, improve response speed and accuracy, and at the same time, emergency response personnel should be well prepared;

[0010] S4, emergency response processing. According to the emergency processing plan generated in S3 risk intelligent diagnosis, the system automatically shuts down the equipment in the corresponding area of ​​the power plant, isolates the equipment, and opens the emergency channel for personnel evacuation to minimize losses;

[0011] S5. Remote monitoring and control. Through remote monitoring, the safety administrator of the corresponding area of ​​the power plant can provide on-site guidance through the mobile remote monitoring system. The safety administrator's authority is greater than the system response authority, so the emergency response plan can be flexibly adjusted.

[0012] S6. Data analysis and reporting. After the power plant safety emergency response is completed, the system will organize the monitoring data and emergency response data, conduct statistical analysis on the entire emergency response process through intelligent statistical analysis algorithms, and automatically generate safety reports to provide data support for managers. According to the actual analysis data, corresponding adjustments and improvements can be made to the equipment and safety specifications of each area of ​​the power plant to prevent potential risks, thereby ensuring the safety of the entire power plant in the actual production process and reducing the risk of losses in the power plant.

[0013] Preferably, the S2 data system early warning forecast specifically includes the following:

[0014] S2.1. Data collection module

[0015] Collect and transmit the electronic video monitoring data, temperature sensor, humidity sensor and noise sensor data collected by the real-time monitoring module established by S1 in a unified manner, and mark the corresponding power plant area block number;

[0016] S2.2. Data extraction and analysis module

[0017] Conduct systematic data analysis based on the data collected in the corresponding area to ensure data validity. Use data analysis algorithms and machine learning algorithms to conduct real-time analysis and prediction of collected data to identify potential safety hazards in advance. Analyze the abnormal data and classify them as risk data. Label the risk data to avoid data congestion and delay in subsequent unified diagnosis, which may lead to data diagnosis errors.

[0018] S2.3, Risk data interception module

[0019] Identify the data analyzed in the data extraction and analysis module and intercept the marked risk data in real time;

[0020] S2.4, data classification transmission module

[0021] The risk data and normal data intercepted in real time by the risk data interception module are classified and transmitted to avoid data confusion leading to risk diagnosis errors. The risk data has the first-level priority transmission authority, thereby reducing the entire risk data diagnosis process and ensuring the safety emergency efficiency of the power plant;

[0022] S2.5, data classification storage module

[0023] The risk-free data extracted and analyzed are classified and stored, that is, the electronic video monitoring data of the equipment area, the temperature data of the equipment area, the humidity data of the equipment area and the noise of the equipment area are classified and stored to avoid confusion between the data. At the same time, the risk data completed by emergency handling is refluxed and stored.

[0024] Preferably, the data analysis algorithm formula is as follows:

[0025] [f(X)=text{sign}(sum_{i=1}^{n}alpha_iy_iK(X_i,X)+b)]

[0026] Among them, (X) is the input sample, (alpha_i) is the coefficient of the support vector machine, (y_i) is the sample label, (K(cdot, cdot)) is the kernel function, and (b) is the bias term.

[0027] Preferably, the data analysis algorithm helps the extraction system collect data patterns, trends and associations, thereby analyzing the laws and information in the data, and then quickly and accurately analyzing large amounts of data, providing a scientific basis for emergency response plans, helping safety managers to formulate corresponding emergency response plans, improving the safety management efficiency of power plants, reducing risks and losses, and protecting the interests of power plant enterprises.

[0028] Preferably, the machine learning algorithm formula is as follows:

[0029] Model: y=w_1x_1+w_2x_2+...+w_nx_n+b

[0030] Loss function (mean square error): J(w,b)=frac{1}{2m}sum_{i=1}^{m}(h_w(x^{(i)})-y^{(i)})^2.

[0031] Preferably, the machine learning algorithm can self-adjust according to changes in system data and new situations, continuously improve the accuracy and generalization ability of system book analysis and judgment, conduct in-depth analysis and insight, extract useful information therefrom, and produce reliable risk predictions.

[0032] Preferably, the intelligent algorithm simulation technology is specifically:

[0033] Monte Carlo simulation: I = frac{V}{N}sum_{i=1}^{N}f(x_i)

[0034] Used to estimate the probability distribution or numerical solution of a complex system. Where (I) is the estimated value, (V) is the volume of the integration interval, (N) is the number of sampling points, (x_i) is a random sample point, and (f(x_i)) is the function value at point (x_i);

[0035] Arrange the events in the system in chronological order and process them one by one;

[0036] The process of continuous evolution of system status over time is discretized for simulation, and ultimately the best emergency response plan is obtained.

[0037] Preferably, the remote monitoring and control of the corresponding power plant area section can only be remotely controlled by the safety administrator of the corresponding area section to prevent irrelevant personnel from modifying the emergency plan and causing losses. At the same time, the system records the operation process of the safety administrator during the entire emergency handling process, which serves as a reference for subsequent data analysis and reporting, thereby reducing the safety risks of the power plant.

[0038] Preferably, the intelligent statistical analysis algorithm formula is as follows:

[0039] Covariance matrix: C = frac{1}{m}sum_{i=1}^{m}(x^{(i)})(x^{(i)})^T

[0040] Eigenvalue decomposition: C = W Lambda W^T

[0041] Keep the first k principal components: X_{text{reduce}}=XW_{text{reduce}}.

[0042] Preferably, the intelligent statistical analysis algorithm reflects the relationship between key parameters and variables in the system data, helps safety management personnel to adjust parameters and make improvements, and optimizes the power plant safety emergency management plan. BRIEF DESCRIPTION OF THE DRAWINGS

[0043] Figure 1 It is a schematic diagram of the overall process of the present invention. DETAILED DESCRIPTION

[0044] Example: See Figure 1 , in a power plant safety emergency management system;

[0045] A power plant safety emergency management system comprises the following steps;

[0046] S1. Establish a real-time monitoring module to conduct all-round electronic video monitoring of the power plant's risk areas, emergency response routes and risk equipment, and use temperature sensors, humidity sensors and noise sensors to conduct real-time monitoring of the equipment in various parts of the power plant and the surrounding areas of the equipment areas. The monitoring equipment and monitoring sensors are inspected regularly at the prescribed time to ensure the validity of the monitoring data;

[0047] S2. Data system early warning and prediction. The data system early warning and prediction includes data collection module, data extraction and analysis module, risk data interception module, data classification transmission module, and data classification storage module. The power plant plans the block number according to the department, and the corresponding department is responsible for the data processing work of the corresponding regional block, so as to quickly and accurately process the data;

[0048] S3, intelligent risk diagnosis, which conducts rapid intelligent diagnosis of risk data in the early warning forecast of the S2 data system, uses abnormal analysis algorithms and quantitative analysis algorithms to conduct intelligent diagnosis of risk data, and combines intelligent algorithm simulation technology to automatically select the optimal solution for emergency response, improve response speed and accuracy, and at the same time, emergency response personnel should be well prepared;

[0049] S4, emergency response processing. According to the emergency processing plan generated in S3 risk intelligent diagnosis, the system automatically shuts down the equipment in the corresponding area of ​​the power plant, isolates the equipment, and opens the emergency channel for personnel evacuation to minimize losses;

[0050] S5. Remote monitoring and control. Through remote monitoring, the safety administrator of the corresponding area of ​​the power plant can provide on-site guidance through the mobile remote monitoring system. The safety administrator's authority is greater than the system response authority, so the emergency response plan can be flexibly adjusted.

[0051] S6. Data analysis and reporting. After the power plant safety emergency response is completed, the system will organize the monitoring data and emergency response data, conduct statistical analysis on the entire emergency response process through intelligent statistical analysis algorithms, and automatically generate safety reports to provide data support for managers. According to the actual analysis data, corresponding adjustments and improvements can be made to the equipment and safety specifications of each area of ​​the power plant to prevent potential risks, thereby ensuring the safety of the entire power plant in the actual production process and reducing the risk of losses in the power plant.

[0052] The S2 data system early warning forecast specifically includes the following:

[0053] S2.1. Data collection module

[0054] Collect and transmit the electronic video monitoring data, temperature sensor, humidity sensor and noise sensor data collected by the real-time monitoring module established by S1 in a unified manner, and mark the corresponding power plant area block number;

[0055] S2.2. Data extraction and analysis module

[0056] Conduct systematic data analysis based on the data collected in the corresponding area to ensure data validity. Use data analysis algorithms and machine learning algorithms to conduct real-time analysis and prediction of collected data to identify potential safety hazards in advance. Analyze the abnormal data and classify them as risk data. Label the risk data to avoid data congestion and delay in subsequent unified diagnosis, which may lead to data diagnosis errors.

[0057] S2.3, Risk data interception module

[0058] Identify the data analyzed in the data extraction and analysis module and intercept the marked risk data in real time;

[0059] S2.4, data classification transmission module

[0060] The risk data and normal data intercepted in real time by the risk data interception module are classified and transmitted to avoid data confusion leading to risk diagnosis errors. The risk data has the first-level priority transmission authority, thereby reducing the entire risk data diagnosis process and ensuring the safety emergency efficiency of the power plant;

[0061] S2.5, data classification storage module

[0062] The risk-free data extracted and analyzed are classified and stored, that is, the electronic video monitoring data of the equipment area, the temperature data of the equipment area, the humidity data of the equipment area and the noise of the equipment area are classified and stored to avoid confusion between the data. At the same time, the risk data completed by emergency handling is refluxed and stored.

[0063] The data analysis algorithm formula is as follows;

[0064] [f(X)=text{sign}(sum_{i=1}^{n}alpha_iy_iK(X_i,X)+b)]

[0065] Among them, (X) is the input sample, (alpha_i) is the coefficient of the support vector machine, (y_i) is the sample label, (K(cdot, cdot)) is the kernel function, and (b) is the bias term.

[0066] Data analysis algorithms help the extraction system collect data patterns, trends and associations, so as to analyze the laws and information in the data, and then quickly and accurately analyze large amounts of data, provide a scientific basis for emergency response plans, help safety managers formulate corresponding emergency response plans, improve the safety management efficiency of power plants, reduce risks and losses, and protect the interests of power plant enterprises.

[0067] The machine learning algorithm formula is as follows;

[0068] Model: y=w_1x_1+w_2x_2+...+w_nx_n+b

[0069] Loss function (mean square error): J(w,b)=frac{1}{2m}sum_{i=1}^{m}(h_w(x^{(i)})-y^{(i)})^2.

[0070] Machine learning algorithms can adjust themselves according to changes in system data and new situations, continuously improve the accuracy and generalization ability of system book analysis and judgment, conduct in-depth analysis and insights, extract useful information from them, and produce reliable risk forecasts.

[0071] Intelligent algorithm simulation technology is specifically:

[0072] Monte Carlo simulation: I = frac{V}{N}Sum__{i=1}^{N}f(x_i)

[0073] Used to estimate the probability distribution or numerical solution of a complex system. Where (I) is the estimated value, (V) is the volume of the integration interval, (N) is the number of sampling points, (x_i) is a random sample point, and (f(x_i)) is the function value at point (x_i);

[0074] Arrange the events in the system in chronological order and process them one by one;

[0075] The process of continuous evolution of system status over time is discretized for simulation; ultimately the best emergency response plan is obtained.

[0076] Remote monitoring and control: The corresponding power plant area can only be remotely controlled by the safety administrator of the corresponding area to prevent irrelevant personnel from modifying the emergency plan and causing losses. At the same time, the system records the operation process of the safety administrator during the entire emergency handling process, which serves as a reference for subsequent data analysis and reporting, reducing the safety risks of the power plant.

[0077] The formula of intelligent statistical analysis algorithm is as follows;

[0078] Covariance matrix: C = frac{1}{m}sum_{i=1}^{m}(x^{(i)})(x^{(i)})^T

[0079] Eigenvalue decomposition: C = W Lambda W^T

[0080] Keep the first k principal components: X_{text{reduce}}=XW_{text{reduce}}.

[0081] Through intelligent statistical analysis algorithms, the relationship between key parameters and variables in system data is reflected, helping safety managers to adjust parameters and make improvements, and optimize power plant safety emergency management plans;

[0082] This power plant safety emergency management system uses sensors to monitor the status of power plant equipment and environmental parameters in real time, can quickly discover abnormal situations, and can avoid safety accidents caused by negligence. It uses big data and system algorithms to perform intelligent data analysis and decision support. It can remotely monitor and respond to emergencies anytime and anywhere, and can provide managers with a scientific decision-making basis to minimize the losses caused by safety accidents. The system can automatically start the emergency response process, reduce human intervention time, and reduce accident losses. At the same time, it has self-learning capabilities and provides optimization solutions for the safety management of corresponding regional sectors of the power plant, preventing similar situations from occurring multiple times, protecting the interests of power plant enterprises, and reducing losses.

[0083] The above shows and describes the basic principles, main features and advantages of the present invention. Those skilled in the art should understand that the present invention is not limited by the above embodiments. The above embodiments and descriptions are only preferred examples of the present invention and are not intended to limit the present invention. Without departing from the spirit and scope of the present invention, the present invention may have various changes and improvements, which fall within the scope of the present invention to be protected. The scope of protection of the present invention is defined by the attached claims and their equivalents.

Claims

1. A power plant safety emergency management system, characterized in that: A power plant safety emergency management system comprises the following steps; S1. Establish a real-time monitoring module to conduct all-round electronic video monitoring of the power plant's risk areas, emergency response routes and risk equipment, and use temperature sensors, humidity sensors and noise sensors to conduct real-time monitoring of the equipment in various parts of the power plant and the surrounding areas of the equipment areas. The monitoring equipment and monitoring sensors are inspected regularly at the prescribed time to ensure the validity of the monitoring data; S2. Data system early warning prediction, which includes data collection module, data extraction and analysis module, risk data interception module, data classification transmission module, and data classification storage module. The power plant plans the block number by department, and the corresponding department is responsible for the data processing work of the corresponding regional block, so as to quickly and accurately process the data; S3, intelligent risk diagnosis, which conducts rapid intelligent diagnosis of risk data in the early warning forecast of the S2 data system, uses abnormal analysis algorithms and quantitative analysis algorithms to conduct intelligent diagnosis of risk data, and combines intelligent algorithm simulation technology to automatically select the optimal solution for emergency response, improve response speed and accuracy, and at the same time, emergency response personnel should be well prepared; S4, emergency response processing. According to the emergency processing plan generated in S3 risk intelligent diagnosis, the system automatically shuts down the equipment in the corresponding area of ​​the power plant, isolates the equipment, and opens the emergency channel for personnel evacuation to minimize losses; S5. Remote monitoring and control. Through remote monitoring, the safety administrator of the corresponding area of ​​the power plant can provide on-site guidance through the mobile remote monitoring system. The safety administrator's authority is greater than the system response authority, so the emergency response plan can be flexibly adjusted. S6. Data analysis and reporting. After the power plant safety emergency response is completed, the system will organize the monitoring data and emergency response data, conduct statistical analysis on the entire emergency response process through intelligent statistical analysis algorithms, and automatically generate safety reports to provide data support for managers. According to the actual analysis data, corresponding adjustments and improvements can be made to the equipment and safety specifications of each area of ​​the power plant to prevent potential risks, thereby ensuring the safety of the entire power plant in the actual production process and reducing the risk of losses in the power plant.

2. A power plant safety emergency management system according to claim 1, characterized in that: The S2 data system early warning forecast specifically includes the following: S2.

1. Data collection module Collect and transmit the electronic video monitoring data, temperature sensor, humidity sensor and noise sensor data collected by the real-time monitoring module established by S1 in a unified manner, and mark the corresponding power plant area block number; S2.

2. Data extraction and analysis module Conduct systematic data analysis based on the data collected in the corresponding area to ensure data validity. Use data analysis algorithms and machine learning algorithms to conduct real-time analysis and prediction of collected data to identify potential safety hazards in advance. Analyze the abnormal data and classify them as risk data. Label the risk data to avoid data congestion and delay in subsequent unified diagnosis, which may lead to data diagnosis errors. S2.3, Risk data interception module Identify the data analyzed in the data extraction and analysis module and intercept the marked risk data in real time; S2.4, data classification transmission module The risk data and normal data intercepted in real time by the risk data interception module are classified and transmitted to avoid data confusion leading to risk diagnosis errors. The risk data has the first-level priority transmission authority, thereby reducing the entire risk data diagnosis process and ensuring the safety emergency efficiency of the power plant; S2.5, data classification storage module The risk-free data extracted and analyzed are classified and stored, that is, the electronic video monitoring data of the equipment area, the temperature data of the equipment area, the humidity data of the equipment area and the noise of the equipment area are classified and stored to avoid confusion between the data. At the same time, the risk data completed by emergency handling is refluxed and stored.

3. A power plant safety emergency management system according to claim 2, characterized in that: The data analysis algorithm formula is as follows: [f(X)=text{sign}(sum_{i=1}^{n}alpha_iy_iK(X_i,X)+b)] Among them, (X) is the input sample, (alpha_i) is the coefficient of the support vector machine, (y_i) is the sample label, (K(cdot, cdot)) is the kernel function, and (b) is the bias term.

4. A power plant safety emergency management system according to claim 3, characterized in that: The data analysis algorithm helps the extraction system collect data patterns, trends and associations, thereby analyzing the laws and information in the data, and then quickly and accurately analyzing large amounts of data, providing a scientific basis for emergency response plans, helping safety managers to formulate corresponding emergency response plans, improving the safety management efficiency of power plants, reducing risks and losses, and protecting the interests of power plant enterprises.

5. A power plant safety emergency management system according to claim 2, characterized in that: The machine learning algorithm formula is as follows; Model: y=w_1x_1+w_2x_2+...+w_nx_n+b Loss function (mean square error): J(w,b)=frac{1}{2m}sum_{i=1}^{m}(h_w(x^{(i)})-y^{(i)})^2.

6. A power plant safety emergency management system according to claim 5, characterized in that: The machine learning algorithm can adjust itself according to changes in system data and new situations, continuously improve the accuracy and generalization ability of system book analysis and judgment, conduct in-depth analysis and insights, extract useful information from it, and produce reliable risk predictions.

7. A power plant safety emergency management system according to claim 1, characterized in that: The intelligent algorithm simulation technology is specifically: Monte Carlo simulation: I = frac{V}{N}Sum__{i=1}^{N}f(x_i) Used to estimate the probability distribution or numerical solution of a complex system. Where (I) is the estimated value, (V) is the volume of the integration interval, (N) is the number of sampling points, (x_i) is a random sample point, and (f(x_i)) is the function value at point (x_i); Arrange the events in the system in chronological order and process them one by one; The process of continuous evolution of system status over time is discretized for simulation; ultimately the best emergency response plan is obtained.

8. A power plant safety emergency management system according to claim 1, characterized in that: The remote monitoring and control can only be performed by the security administrator of the corresponding area section of the power plant to prevent irrelevant personnel from modifying the emergency plan and causing losses. At the same time, the system records the operation process of the security administrator during the entire emergency handling process, which serves as a reference for subsequent data analysis and reporting, thereby reducing the safety risks of the power plant.

9. A power plant safety emergency management system according to claim 1, characterized in that: The intelligent statistical analysis algorithm formula is as follows: Covariance matrix: C = frac{1}{m}sum_{i=1}^{m}(x^{(i)})(x^{(i)})^T Eigenvalue decomposition: C = W Lambda W^T Keep the first k principal components: X_{text{reduce}}=XW_{text{reduce}}.

10. A power plant safety emergency management system according to claim 9, characterized in that: The intelligent statistical analysis algorithm reflects the relationship between key parameters and variables in the system data, helps safety management personnel to adjust parameters and make improvements, and optimizes the power plant safety emergency management plan.