Auxiliary decision-making system and method for rapid in-place hoisting of precast beam of crane ship
The status of the crane ship is obtained through GPS monitoring and sensors, and a dynamic mathematical relationship between the real-time position of the precast girder and the position of the crane ship is established, which solves the problem of accurate positioning of precast beams during the hoisting of long-span bridges, improves construction efficiency and avoids collisions .
Patent Information
- Application Number
- CN202410759281.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-06-13
- Publication Date
- 2024-10-15
AI Technical Summary
During the hoisting process of precast beams on long-span bridges, due to environmental factors such as inertia and wind, it is difficult for the crane ship controller to quickly and accurately determine the distance between the hoisted objects and the target position, leading to problems such as low construction efficiency, lag in information transmission, and collisions in the installation of precast beams.
The ship's coordinates, lifting height and luffing angle are obtained through GPS monitoring on the ship, and the real-time coordinates of the precast beam are calculated. Compared with the theoretical target coordinates, the movement instructions of the ship and crane are given to achieve the rapid placement of large-segment precast beams. Auxiliary operations.
It achieves precise hoisting of prefabricated beams, avoids collisions, greatly saves construction personnel time, and improves construction efficiency.
Smart Images

Figure CN118771201A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of prefabricated beam installation, and in particular to an auxiliary decision system and method for the rapid positioning of prefabricated beams hoisted by a crane ship. Background Art
[0002] With the advancement of bridge technology, many new bridge types have emerged in the design of cross-river and cross-sea bridges. Among them, concrete beam bridges, steel box beam bridges, and steel-concrete composite beam bridges are widely used.
[0003] In order to improve the construction period and reduce the construction cost, large-span bridges generally use large-segment prefabricated beams. The beams are prefabricated in the prefabrication yard or construction site in advance, and then transported to the installation location in the river during construction and installed by a large crane ship. The prefabricated beams are controlled by the operator in the control room of the crane ship during the lifting and docking. The prefabricated segment beams hoisted by the crane ship are generally large, and the hoisted objects will shake to a certain extent during the hoisting process due to environmental factors such as inertia and wind. It is not easy to quickly judge the distance between the hoisted objects and the target installation location by naked eye observation, and the controller cannot obtain the specific situation of the hoisting and docking. Another method is to use walkie-talkies to guide the route through multiple commanders on the installed prefabricated beams and the operators in the control room of the crane ship. Although this method is feasible, it also has problems such as time-consuming and labor-intensive, low construction efficiency, and information transmission lag, and it is easy to cause collisions in the installation of prefabricated beams. Therefore, in view of the above situation, a quick placement auxiliary decision-making system and method for the hoisting of large segment prefabricated beams by crane ships is proposed. Summary of the invention
[0004] The purpose of the present invention is to address the defects of the prior art and to provide a crane ship prefabricated beam rapid lifting and positioning auxiliary decision-making system and method. The real-time coordinates of the center point of the top surface of the prefabricated beam are obtained by converting the ship coordinates, lifting height and amplitude angle monitored by the GPS on the ship using spatial deviation. By comparing the real-time coordinates of the point with the theoretical target coordinates, the movement of the ship and the crane are indicated, thereby realizing auxiliary operation guidance for the lifting of large-section prefabricated beams.
[0005] In order to solve the above technical problems, the present invention provides a method for assisting decision-making in the rapid installation of prefabricated beams by a crane ship, comprising:
[0006] S1. Calculate the coordinates (X5, Y5, Z5) of the target point O2 of the precast beam, which is the coordinates of the center point of the precast beam after installation. Calculate the azimuth angle θ2 of the ship when installing the precast beam.
[0007] S2. After the ship approaches the installation position of the prefabricated beam and drops anchor, calculate the current position coordinates O1 (X, Y, Z) of the center point of the prefabricated beam;
[0008] S3, calculate the plane deviation and elevation deviation of O1 and O2;
[0009] S4, judging whether the elevation deviation meets the requirement, if so, executing step S5;
[0010] S5. Adjust the position of the ship according to the plane deviation so that the plane deviation meets the requirements;
[0011] S6, calculate the current position θ1 of the ship, and determine whether θ1 is equal to θ2. If so, execute step S7;
[0012] S7, calculating the plane deviation of O1 and O2, and judging whether the plane deviation is equal to zero, if so, the ship controls the precast beam to descend vertically to the precast beam target point O2.
[0013] Further, in step S1, the method for calculating the azimuth angle θ2 of the ship during the installation of the prefabricated beam is:
[0014] Two positioning points of the same height are set on the ship. The theoretical position coordinates of the two positioning points when the ship is installing the prefabricated beam are calculated. The line connecting the two positioning points is parallel to the prefabricated beam. The azimuth
[0015] Further, step S2 includes:
[0016] Calculate the horizontal distance between the midpoint of the line connecting the two positioning points on the ship and the center point of the precast beam, L = L1 + Mcosα, where L1 is the distance between the hinge point between the boom and the ship and the line connecting the two positioning points along the longitudinal direction of the ship, M is the length of the boom, and α is the boom amplitude angle;
[0017] When the ship approaches the installation position of the prefabricated beam and drops anchor, obtain the current position coordinates of the two positioning points on the ship A(X1, Y1, Z1) and B(X2, Y2, Z2), and calculate the current position coordinates of the center point of the prefabricated beam O1(X, Y, Z), where: H2 is the vertical distance between the center point of the precast beam and the deck, H1 is the vertical distance between the positioning point on the ship and the deck, and θ is the angle between the perpendicular bisector of the line connecting the two positioning points and the X-axis.
[0018] Further, step S3 includes: the plane deviation and elevation deviation of O1 and O2 are respectively:
[0019] Elevation deviation = Z-Z5.
[0020] Further, step S4 includes:
[0021] Determine whether the elevation deviation meets the safety height requirement. If the elevation deviation is less than the safety height requirement, control the crane to lift the precast beam until the elevation deviation is greater than the safety height requirement.
[0022] Further, step S5 includes:
[0023] It is determined whether the plane deviation is greater than the amplitude variation of the boom. If so, the ship is moved by retracting and releasing the cable until the plane deviation is less than the amplitude variation of the boom; otherwise, step S6 is executed.
[0024] Further, step S6 includes: calculating the current position θ1 of the ship according to the two positioning points on the ship, judging whether θ1 is equal to θ2, if not, adjusting the position of the ship by retracting and releasing the cable until θ1=θ2, otherwise, executing step S7.
[0025] Further, step S7 includes: calculating the plane deviation of O1 and O2, judging whether the plane deviation is equal to zero, and if not, controlling the boom to vary the amplitude until the plane deviation is equal to zero.
[0026] In a second aspect, the present invention provides a crane ship prefabricated beam lifting rapid positioning auxiliary decision system, including a control system, a positioning winch, a crane and two positioning devices;
[0027] The crane comprises an encoder, and the encoder is used to detect the luffing angle and lifting height of the crane;
[0028] The positioning winches are symmetrically arranged at the four corners of the ship, and cables are arranged on the positioning winches. The positioning winches adjust the position of the ship through the cables and anchors connected to the cables;
[0029] The two positioning devices have the same height, and the perpendicular bisector of the line connecting the two positioning devices passes through the longitudinal axis of the ship. The two positioning devices are used to detect the position of the ship;
[0030] The control system is respectively connected to the positioning device, the crane, and the positioning winch. The control system calculates the current position and orientation of the ship and the current position coordinates of the center point of the precast beam by receiving the ship position information detected by the positioning device. The control system controls the positioning winch to adjust the position and orientation of the ship according to the current position and orientation of the ship. The control system controls the operation of the crane according to the adjustment results of the position and orientation of the ship, so that the precast beam is accurately moved to the target point.
[0031] Furthermore, it includes a control room, and a space truss is arranged on the top of the control room. The space truss includes a bracket, a vertical pole, an oblique brace, and a horizontal brace. The bottom end of the vertical pole is fixed to the top of the control room, and two oblique braces are symmetrically arranged and tilted. One end of the two oblique braces is connected to the vertical pole, and the other end of the two oblique braces is connected to the top of the control room to form a spatial triangular prism shape. The two ends of the horizontal brace connect the two oblique braces. The bracket is installed on the top of the vertical pole, and it is connected to the vertical pole in a T shape.
[0032] The beneficial effects of the present invention are:
[0033] 1. The present invention obtains the state of the crane vessel through satellite positioning technology, obtains the state of the crane of the crane vessel through sensors, and then establishes a dynamic mathematical relationship between the real-time position of the precast beam and the position of the crane vessel and the state of the boom. The three-way deviation between the real-time position of the precast beam and the set target position can be displayed on the operation room interface to avoid collisions during the hoisting of large-segment precast beams.
[0034] 2. The present invention can make auxiliary decisions on the lifting of large-section precast beams according to the deviation between the real-time position of the precast beams and the set target position, and give operational suggestions. Through the crane ship anchor shifting system, the crane boom lengthening, lifting and other operation guidance adjustments, the lifting of large-section precast beams can be quickly guided, which greatly saves construction personnel and improves construction efficiency. BRIEF DESCRIPTION OF THE DRAWINGS
[0035] Figure 1 It is the overall construction composition diagram of the present invention;
[0036] Figure 2 Positioning winch distribution map for the present invention;
[0037] Figure 3 This is a layout diagram of the space truss of the present invention on the top of the control room;
[0038] Figure 4 It is a front view of the space truss of the present invention;
[0039] Figure 5 This is a dimension diagram of the ship structure of the present invention;
[0040] Figure 6 A diagram showing the relative position relationship between the positioning device of the present invention and the prefabricated beam;
[0041] Figure 7 This is a schematic diagram of ship position deviation adjustment according to the present invention;
[0042] Figure 8 The figure is an overall flow chart of the hoisting of prefabricated beams of the present invention.
[0043] Reference numerals: lifting winch 1; luffing winch 2; boom 3; hook 4; control room 5; prefabricated beam 6; positioning winch 7; bracket 8; positioning device 9; vertical pole 10; diagonal brace 11; transverse brace 12. DETAILED DESCRIPTION
[0044] In order to make the technical problems, technical solutions and beneficial effects to be solved by the present application more clearly understood, the present application is further described in detail below in conjunction with the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are only used to explain the present application and are not used to limit the present application.
[0045] like Figure 1 As shown, this embodiment provides a crane ship prefabricated beam lifting rapid positioning auxiliary decision system, including a control system, a positioning winch 7, a crane and two positioning devices 9.
[0046] The crane includes a boom 3, a luffing winch 2, a lifting winch 1, a control room 5, and an encoder. The luffing winch 2 controls the luffing of the boom 3, and the lifting winch 1 controls the lifting height. The luffing angle and the lifting height are detected by encoders installed on the respective winches. The prefabricated beam 6 to be installed is connected to the hook 4 of the crane by a steel wire rope. There are four steel wire ropes. The steel wire rope and the hook 4 are connected by a shackle. When hoisting, the center point of the top surface of the prefabricated beam 6 to be installed is used as the control point.
[0047] like Figure 2 As shown, the positioning winches 7 are symmetrically arranged at the four corners of the ship, and cables are set on the positioning winches 7. The positioning winches 7 adjust the position of the ship through the cables and the anchors connected to the cables. In this embodiment, eight positioning winches 7 are arranged. During the installation of the prefabricated beam 6, the position and orientation of the ship body are measured by two positioning devices 9, compared with the target ship position, and the positioning winches 7 are operated to retract and release the cables, shift multiple times, and gradually converge, so that the ship reaches the target position. The number of positioning winches 7 used is generally determined according to the specific working conditions. When the water flow is large, 8 anchors are cast, and when the water flow is small, 6 anchors can be cast;
[0048] like Figure 3 , 4 As shown, the two positioning devices 9 have the same height, and the perpendicular bisector of the line connecting the two positioning devices 9 passes through the longitudinal axis of the ship. The two positioning devices 9 are used to detect the position of the ship; a space truss is arranged on the top of the control room 5, and the space truss includes a bracket 8, a vertical pole 10, a diagonal brace 11, and a horizontal brace 12. Two diagonal braces 11 are arranged symmetrically and tilted, and one end of the two diagonal braces 11 is connected to the vertical pole 10, and the other end of the two diagonal braces 11 is connected to the top of the control room 5 to form a spatial triangular prism shape. The two ends of the horizontal brace 12 connect the two diagonal braces 11 to strengthen the overall truss structure strength. The bracket 8 is installed on the top of the vertical pole 10, and it is connected to the vertical pole 10 in a T shape. In this embodiment, the positioning device 9 uses GPS.
[0049] The control room 5 includes a controller, a computer display, and a winch console. The encoder of the crane is electrically connected to the controller, and the detected amplitude change angle and lifting height are transmitted to the controller via RS485. The two GPSs are also electrically connected to the controller via RS485 to transmit the collected ship position and orientation to the controller.
[0050] like Figure 2 As shown, a tension sensor and an encoder are installed on each positioning winch 7. The tension sensor is used to monitor the tension of the electric winch cable, and the encoder is used to monitor the retracted length of the electric winch cable. The retracted and extended of each positioning winch 7 is controlled by a corresponding winch control handle on the winch console to achieve the winch cable movement of the ship.
[0051] The computer display screen includes a precast beam 6 lifting rapid positioning auxiliary decision page, which includes a ship position display area, a crane status display area, and a precast beam 6 status display area. The ship position display area includes the current coordinates measured by two GPSs, the ship target position that can be input, and the spatial deviation between the current ship position and the ship target position; the crane status display area includes the amplitude change angle and lifting height of all crane booms 3; the precast beam 6 status display area includes the real-time coordinate value of the precast beam 6 control point, the target coordinate value of the precast beam 6 control point, and the spatial deviation between the real-time position of the precast beam 6 control point and the target position.
[0052] The method for hoisting the prefabricated beam 6 by using the crane ship prefabricated beam hoisting rapid positioning auxiliary decision system includes:
[0053] S1, such as Figure 1 As shown, the coordinates (X5, Y5, Z5) of the target point O2 of the precast beam are calculated. The target point O2 of the precast beam is the coordinates of the center point of the top surface of the precast beam 6 after installation. The theoretical position coordinates C (X3, Y3, Z3) and D (X4, Y4, Z4) measured by the two positioning devices 9 when the ship is installing the precast beam 6 are calculated, and the azimuth angle of the ship when the precast beam 6 is installed is calculated.
[0054] S2. Calculate the horizontal distance between the midpoint of the line connecting the two positioning points on the ship and the center point of the precast beam L = L1 + Mcosα, where Figure 5 As shown, L1 is the distance between the hinge point between the boom 3 and the ship and the connecting line of the two positioning points along the longitudinal direction of the ship, M is the length of the boom 3, and α is the amplitude change angle of the boom 3.
[0055] After the ship approaches the installation position of the prefabricated beam 6 and drops anchor, the bow of the ship basically points to the installation position of the prefabricated beam 6, and the current position coordinates A (X1, Y1, Z1) and B (X2, Y2, Z2) measured by the two positioning devices 9 on the ship are obtained, and the current position coordinates O1 (X, Y, Z) of the center point of the prefabricated beam are calculated, where: like Figure 5 As shown, H2 is the vertical distance between the center point of the precast beam and the deck, H1 is the vertical distance between the positioning point on the ship and the deck, and θ is the angle between the perpendicular bisector of the line connecting the two positioning points and the X-axis.
[0056] S3. Calculate the plane deviation and elevation deviation of O1 and O2: Elevation deviation = Z-Z5.
[0057] S4. Determine whether the elevation deviation meets the requirement (elevation deviation>5m). If so, execute step S5; otherwise, control the crane to lift the precast beam 6 until the elevation deviation is greater than the safety height requirement.
[0058] S5. Adjust the position of the ship according to the plane deviation so that the plane deviation meets the requirements.
[0059] It should be noted that the ship deviation includes plane position deviation and rotation deviation. Any deviation of the ship may appear in the form of plane position deviation and rotation deviation alone or in a combined form. Figure 7 As shown, according to the positions of the anchor points F1, F2, F3, F4, F5, F6, F7, and F8 of the ship, as well as the ship positions monitored by two GPSs and the target installation position of the precast beam 6, the real-time position of the ship, the target position of the precast beam 6 and the relative position relationship of the anchor points of the ship can be determined in the ship position display area of the computer display screen. The ship is to move from the first real-time position to the target position. When the ship deviation is adjusted, the plane position deviation is first adjusted to prevent rotation deviation from occurring after the plane movement. When the plane deviation is greater than 5m (this value can be set, specifically determined by the amplitude variation degree of the crane boom 3, to ensure that the plane position of the precast beam 6 to be installed can be coincident with the plane position of the target point by amplitude variation), there is a plane deviation. At this time, the computer display gives an operation instruction, prompting "F1, F2, F7, and F8 release the cable, and F3, F4, F5, and F6 collect it", until 0m≦plane deviation≦5m is monitored, so that the ship reaches the second real-time position.
[0060] S6. Calculate the current position of the ship Determine whether θ1 and θ2 are greater than zero. If θ1 is less than zero, set θ1 = π-θ1. If θ2 is less than zero, set θ2 = π-θ2. Determine whether θ1 is equal to θ2. If so, execute step S7.
[0061] It should be noted that after the ship reaches the second real-time position, the plane position deviation adjustment is completed. At this time, the ship's orientation θ1 and θ2 should be compared. If θ1>θ2, the computer display gives an operation instruction, prompting "F1, F2, F5, F6 to reel in the cable, F3, F4, F7, F8 to release the cable", until θ1=θ2; if θ1<θ2, the computer display gives an operation instruction, prompting "F1, F2, F5, F6 to release the cable, F3, F4, F7, F8 to reel in the cable", until θ1=θ2. After the rotation deviation adjustment is completed, enter S7.
[0062] S7, calculate the plane deviation of O1 and O2, and determine whether the plane deviation is equal to zero. If so, the ship controls the precast beam 6 to vertically descend to the precast beam target point O2; if not, the boom 3 is controlled to change its amplitude until the plane deviation is equal to zero, and then the precast beam 6 is controlled to vertically descend to the precast beam target point O2.
[0063] The present invention obtains the state of the crane ship through satellite positioning technology, obtains the state of the crane of the crane ship through sensors, and then establishes a dynamic mathematical relationship between the real-time position of the precast beam 6 and the position of the crane ship and the state of the boom 3. The three-way deviation between the real-time position of the precast beam 6 and the set target position can be displayed on the operation room interface to avoid collisions in the hoisting of large-section precast beams 6. In addition, the system can make auxiliary decisions for the hoisting of large-section precast beams 6 according to the deviation between the real-time position of the precast beam 6 and the set target position, and give operation suggestions. Through the crane ship anchor shifting system, the crane amplitude change, lifting and other operation guidance adjustments, the rapid guidance of the hoisting of large-section precast beams 6 is achieved, which greatly saves construction personnel and improves construction efficiency.
[0064] The embodiments described above are only used to illustrate the technical solutions of the present application, rather than to limit them. Although the present application has been described in detail with reference to the aforementioned embodiments, a person skilled in the art should understand that the technical solutions described in the aforementioned embodiments may still be modified, or some of the technical features may be replaced by equivalents. Such modifications or replacements do not deviate the essence of the corresponding technical solutions from the spirit and scope of the technical solutions of the embodiments of the present application, and should all be included in the protection scope of the present application.
Claims
1. A method for assisting decision-making in the rapid installation of prefabricated beams on a crane ship, characterized in that: include: S1, calculate the coordinates (X5, Y5, Z5) of the precast beam target point O2, where the precast beam target point O2 is the coordinates of the center point of the precast beam (6) after installation; calculate the azimuth angle θ2 of the ship when installing the precast beam (6); S2, after the ship approaches the installation position of the prefabricated beam (6) and drops anchor, calculate the current position coordinates O1 (X, Y, Z) of the center point of the prefabricated beam; S3, calculate the plane deviation and elevation deviation of O1 and O2; S4, judging whether the elevation deviation meets the requirement, if so, executing step S5; S5. Adjust the position of the ship according to the plane deviation so that the plane deviation meets the requirements; S6, calculate the current position θ1 of the ship, and determine whether θ1 is equal to θ2. If so, execute step S7; S7, calculating the plane deviation of O1 and O2, and judging whether the plane deviation is equal to zero. If so, the ship controls the precast beam (6) to descend vertically to the precast beam target point O2.
2. The method for assisting decision-making in the rapid installation of prefabricated beams on a crane vessel according to claim 1 is characterized in that: In step S1, the method for calculating the azimuth angle θ2 when the ship is installing the prefabricated beam (6) is: Two positioning points of the same height are set on the ship. The theoretical position coordinates C (X3, Y3, Z3) and D (X4, Y4, Z4) of the two positioning points when the ship is installing the prefabricated beam (6) are calculated. The line connecting the two positioning points is parallel to the prefabricated beam (6). Then the azimuth 3. The method for assisting decision-making in the rapid installation of prefabricated beams on a crane vessel according to claim 2 is characterized in that: Step S2 includes: Calculate the horizontal distance L=L1+Mcosα between the midpoint of the line connecting the two positioning points on the ship and the center point of the precast beam, where L1 is the distance between the hinge point between the boom (3) and the ship and the line connecting the two positioning points along the longitudinal direction of the ship, M is the length of the boom (3), and α is the amplitude angle of the boom (3); After the ship approaches the installation position of the precast beam (6) and drops anchor, the current position coordinates A(X1, Y1, Z1) and B(X2, Y2, Z2) of the two positioning points on the ship are obtained, and the current position coordinates O1(X, Y, Z) of the center point of the precast beam are calculated, where: H2 is the vertical distance between the center point of the precast beam and the deck, H1 is the vertical distance between the positioning point on the ship and the deck, and θ is the angle between the perpendicular bisector of the line connecting the two positioning points and the X-axis.
4. The method for assisting decision-making in the rapid installation of prefabricated beams on a crane vessel according to any one of claims 1 to 3, characterized in that: Step S3 includes: the plane deviation and elevation deviation of O1 and O2 are respectively: Elevation deviation = Z-Z5.
5. The method for assisting decision-making in the rapid installation of prefabricated beams on a crane vessel according to claim 4 is characterized in that: Step S4 includes: It is judged whether the elevation deviation meets the safety height requirement. If the elevation deviation is less than the safety height requirement, the crane is controlled to lift the precast beam (6) until the elevation deviation is greater than the safety height requirement.
6. The method for assisting decision-making in the rapid installation of prefabricated beams on a crane vessel according to claim 5, characterized in that: Step S5 includes: It is determined whether the plane deviation is greater than the amplitude variation of the boom (3); if so, the ship is moved by retracting and releasing the cable until the plane deviation is less than the amplitude variation of the boom (3); otherwise, step S6 is executed.
7. The method for assisting decision-making in the rapid installation of prefabricated beams on a crane vessel according to claim 6, characterized in that: Step S6 includes: calculating the current position θ1 of the ship according to the two positioning points on the ship, judging whether θ1 is equal to θ2, if not, adjusting the position of the ship by retracting and releasing the cable until θ1=θ2, otherwise, executing step S7.
8. The method for assisting decision-making in the rapid installation of prefabricated beams on a crane vessel according to claim 6, characterized in that: Step S7 comprises: calculating the plane deviation of O1 and O2, judging whether the plane deviation is equal to zero, and if not, controlling the boom (3) to change the amplitude until the plane deviation is equal to zero.
9. A crane ship prefabricated beam lifting rapid positioning auxiliary decision system, characterized by: It comprises a control system, a positioning winch (7), a crane and two positioning devices (9); The crane comprises an encoder, and the encoder is used to detect the luffing angle and lifting height of the crane; The positioning winches (7) are symmetrically arranged at the four corners of the ship, and cables are arranged on the positioning winches (7). The positioning winches (7) adjust the position of the ship through the cables and anchors connected to the cables. The two positioning devices (9) have the same height, a perpendicular bisector of a line connecting the two positioning devices (9) passes through the longitudinal axis of the ship, and the two positioning devices (9) are used to detect the position of the ship; The control system is respectively connected to the positioning device (9), the crane, and the positioning winch (7). The control system receives the ship position information detected by the positioning device (9), calculates the current position and orientation of the ship and the current position coordinates of the center point of the precast beam (6), and controls the positioning winch (7) to adjust the position and orientation of the ship according to the current position and orientation of the ship. The control system controls the crane to operate according to the adjustment result of the position and orientation of the ship, so that the precast beam (6) is accurately moved to the target point.
10. The quick-positioning auxiliary decision-making system for lifting prefabricated beams of a crane vessel according to claim 9 is characterized in that: The invention comprises a control room (5), wherein a space truss is arranged on the top of the control room (5), wherein the space truss comprises a bracket (8), a vertical pole (10), an oblique support rod (11), and a horizontal support rod (12), wherein the bottom end of the vertical pole (10) is fixed on the top of the control room (5), and two oblique support rods (11) are symmetrically arranged and tilted, wherein one end of the two oblique support rods (11) is connected to the vertical pole (10), and the other end of the two oblique support rods (11) is connected to the top of the control room (5) to form a spatial triangular prism shape, and the two ends of the horizontal support rod (12) connect the two oblique support rods (11), and the bracket (8) is installed on the top of the vertical pole (10), and is connected to the vertical pole (10) in a T-shape.