By designing a snap-type pipe extubation machine, combined with the hydraulic station system and dual oil pump working method, the problems of complicated construction of joint pipe method and difficult control of pipe extubation are solved, automatic and intelligent control are realized, and the reliability and efficiency of construction are improved. , suitable for alpine areas.
Patent Information
- Application Number
- CN202411010006.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-26
- Publication Date
- 2024-10-15
AI Technical Summary
The construction process of the existing jointed pipe method is complicated, and the pipe extrusion process of the pipe extrusion machine is difficult to control, which affects the construction efficiency and quality.
A key-type pipe extubation machine is designed, including a jacking cylinder, an upper frame, a lower frame, a holding ring and a key. It adopts a hydraulic station system and a dual oil pump working method to achieve automation and intelligent control to ensure construction reliability and Operational flexibility.
It simplifies the structure and control process of the pipe extrusion machine, improves the reliability and efficiency of construction, is suitable for special environments such as alpine areas, and ensures tight connection and high-quality construction of joint pipes.
Smart Images

Figure CN118774129A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of hydraulic equipment, in particular to a key-type pipe pulling machine used for pulling out joint pipes in the construction of connecting wall sections of underground continuous walls. Background Art
[0002] The anti-seepage wall is generally made up of various unit wall sections. The construction method without wall section is only available in the self-setting mortar anti-seepage wall. The joints between wall sections are the weak links of the anti-seepage wall; if the connection is not good, concentrated leakage may occur, reducing the anti-seepage effect. The basic requirements for the connection of wall sections are close contact, long seepage diameter and good integrity. According to different construction methods, the connection of wall sections can be divided into drilling method, joint pipe (plate) method, double reverse arc method, cutting (milling) method and other construction methods.
[0003] When using the joint pipe method, the pouring and pipe pulling process must be strictly controlled. When the hole is deep and the hole diameter is large, a hydraulic pipe pulling machine must be used to pull the pipe, and it needs to be poured and pulled at the same time. There are two ways of transmitting force between the pipe pulling machine and the joint pipe: jacking and clamping. The clamping method has a high degree of mechanization, is easy to operate, and is more advanced, but the pipe pulling machine needs to add a set of clamping devices. The construction process of the joint pipe method is more complicated, and the control of the pipe pulling machine and the pipe pulling process is also required to be high. Summary of the invention
[0004] In view of the problems that the existing joint pipe method has complex construction technology and the pipe pulling process of the pipe pulling machine is difficult to control, the present invention has studied and developed a key-type pipe pulling machine for pulling out joint pipes in underground wall section connection construction. The control system of the pipe pulling machine is automated and intelligent on the basis of meeting the construction reliability.
[0005] In order to achieve the above-mentioned purpose, the present invention adopts the following technical scheme: a key-type pipe pulling machine for pulling out joint pipes in underground wall section connection construction, comprising a lifting cylinder, an upper frame, a lower frame, a clamping ring and a key, wherein:
[0006] The lifting cylinder is arranged between the upper frame and the lower frame, and is used to realize the lifting of the upper frame;
[0007] The clamping ring is arranged on the upper frame and is used to clamp the joint pipe;
[0008] The clamping key is arranged on the clamping ring and is used for locking the clamping ring and the joint pipe when the clamping ring is clamped.
[0009] Specifically, in some embodiments, the clamping ring of the present invention is composed of two semicircular steel plate welded structural parts.
[0010] Preferably, a slot is provided at one opposite end of the two clamping rings, and a key is assembled in the slot.
[0011] Specifically, in some embodiments, the present invention further includes a hydraulic station system, which uses a large and a small oil pump to perform fast operation and slow operation respectively.
[0012] Preferably, when the large pump is working, the lifting speed of the clamping ring is 0.6-0.7m / min, and the lowering speed is 1.30m / min; when the small pump is working, the lifting speed of the clamping ring is 0.01m / min.
[0013] Preferably, the hydraulic station system is provided with a synchronous speed regulating valve so that the lifting cylinder is always in a synchronous working state.
[0014] Specifically, in some embodiments, the tube pulling machine of the present invention can independently operate with a small pump micro-pulling and a large pump fast pulling; or, in the state of small pump micro-pulling, it can enter the automatic pulling mode. In this state, when the pressure rises to a limit value, the system stops the operation of the small pump and automatically switches to the operation mode of the large pump.
[0015] Compared with the prior art, the present invention has the following beneficial effects:
[0016] The present invention provides a key-type pipe pulling machine for pulling out joint pipes in underground wall section connection construction. The structure and control process are simple, the operation is flexible, and the control system is automated and intelligent on the basis of meeting the construction reliability. At the same time, it can be used in special construction environments such as construction in high-cold areas.
[0017] Instruction Manual
[0018] Figure 1 The present invention provides a structural schematic diagram of a key-type pipe pulling machine for pulling out joint pipes in underground wall section connection construction;
[0019] Figure 2 The present invention provides a side view of a key-type pipe pulling machine for pulling out joint pipes in underground wall segment connection construction;
[0020] Figure 3 The present invention provides a top view of a key-type pipe pulling machine for pulling out joint pipes in underground wall section connection construction.
[0021] In the figure: 1- upper shelf; 2- lower shelf; 3- holding ring; 4- key; 5- baffle. DETAILED DESCRIPTION
[0022] In order to make the purpose, technical solution and advantages of the present invention clearer, embodiments of the present invention are described in detail below, and examples of the embodiments are shown in the accompanying drawings, wherein the same or similar reference numerals throughout represent the same or similar elements or elements with the same or similar functions. The embodiments described below with reference to the accompanying drawings are exemplary and are only used to explain the present invention, and cannot be understood as limiting the present invention.
[0023] The invention provides a key-type pipe pulling machine for pulling out joint pipes in underground wall section connection construction, which adopts a double oil pump working mode and realizes automation and intelligence on the basis of satisfying construction reliability.
[0024] This embodiment provides a key-type pipe pulling machine for pulling out joint pipes in underground wall section connection construction, combined with Figure 1-3 , including a lifting cylinder, an upper frame 1, a lower frame 2, a clamping ring 3 and a key 4, etc., wherein the lower frame 2 is a welded steel plate box structure, the upper frame 1 is an inverted box structure, welded by a steel plate and placed on the upper part of the lifting cylinder, the clamping ring 3 is arranged on the upper frame 1, and the key 4 is arranged on the clamping ring 3. During the working process, the lifting of the upper frame 1 drives the lifting of the clamping ring 3 and the key 4 to achieve the purpose of pulling out the joint pipe.
[0025] Specifically, refer to Figure 1 The upper frame 1 is a square box, which is connected to the lower frame 2 by four lifting cylinders on all sides. The clamping ring 3 is composed of two relatively semicircular steel plate welded structural parts, which are arranged on the slide rails of the upper frame and are controlled by the hydraulic cylinder to clamp the joint pipe in the middle. A clamping key 4 is fixedly provided in the middle part of the two clamping rings 3 relative to each other, and a clamping groove is correspondingly provided on the joint pipe body. When the clamping ring is clamped, the clamping key 4 is inserted into the clamping groove of the joint pipe and locked to ensure that the clamping ring 3 will not loosen. The clamping key 4 is fixed to the clamping ring 3 through a baffle. The above structure should meet the requirements of construction stiffness and strength. It is better to adopt a clamping key structure, so that the pulling force of the pipe pulling machine on the joint pipe acts completely on the joint pipe without loss.
[0026] In other embodiments of the present invention, the latch key 4 can be hydraulically driven. When the clamping ring 3 is clamped, the latch key 4 is inserted into the clamping slot by hydraulic driving to achieve locking.
[0027] In this embodiment, the lifting cylinder diameter is set to 250mm, the rated pulling force is 490t (25MPa), the maximum pulling force is 618t (31.5MPa), and the relevant parameters of the pipe pulling machine are set as follows:
[0028]
[0029] This embodiment also provides a hydraulic station system to achieve control of the lifting and lowering process.
[0030] 1) The system uses L-HM46 anti-wear hydraulic oil;
[0031] 2) The system is equipped with two large and small oil pumps, which respectively perform fast and slow operations. When the large pump is working with the matching motor, the lifting speed of the clamping ring is 0.6-0.7m / min and the lowering speed is 1.30m / min; when the small pump is working, the lifting speed of the clamping ring is 0.01m / min; the selection of the lifting speed is mainly based on the fact that the above two speeds take into account safety and construction efficiency as well as the cost performance of equipment manufacturing. If these two speeds are too high, it will affect the safety of on-site operators, and the cost of matching motors and oil pumps will also increase. If they are too low, it will not be conducive to ensuring a certain pipe pulling efficiency and will affect the construction progress.
[0032] 3) The system rated working pressure is 25MPa and the ultimate working pressure is 31.5MPa;
[0033] 4) Control valve: The manual operation of the cylinder is equipped with 3 sets of operating handles, which respectively control fast lifting, lowering and slow lifting.
[0034] 5) The hydraulic system adopts a dual oil pump working mode, which starts the large and small pump systems at different times, which can effectively control the excessive growth of the bonding force between concrete and the pipe wall. The hydraulic station is designed with a synchronous speed regulating valve to keep the four cylinders in a synchronous working state.
[0035] 6) For construction in high-altitude and cold areas, the hydraulic oil tank should be equipped with an electric heating device, and the heating function can be turned on or off as needed to ensure the normal operation of the system.
[0036] In this embodiment, the electrical and control system should meet the working requirements of the mechanical and hydraulic parts. The electrical system of this equipment adopts the relay contact system control mode. The main parameters are as follows:
[0037] In order to meet the cable theft prevention requirements of remote projects, the main cable connector should be set to plug-in type. When necessary, the main cable can be unplugged and put away, and plugged in again when installed.
[0038] Rated working voltage: AC220V;
[0039] Wiring requirements: four-wire system (L1, L2, L3, N);
[0040] Maximum motor power: 55kW; (reference value, to be selected according to user requirements)
[0041] Small motor power: 4kW; (for reference, to be selected according to user requirements)
[0042] Circuit control method: relay contact.
[0043] Extubation stand control strategy:
[0044] The hydraulic and electrical control system is equipped with large and small pump pulling modes according to the needs of the pipe pulling process. To ensure the flexibility of system operation, the small pump micro-movement pulling and the large pump rapid pulling can be operated independently; the automatic pulling mode can also be switched in the micro-movement pulling state of the small pump. In this state, when the pressure rises to the limit, the system stops the small pump and automatically switches to the large pump operation mode. The pouring construction and pipe pulling construction should be closely coordinated, and the pouring speed should not be too fast. Micro-movement begins 3 hours after the pouring. After that, the interval time of the movable joint pipe should not exceed 30 minutes, and each time it is lifted by 1 to 2 cm to break the bonding force of the concrete. The micro-movement time should not be too early or too frequent (less than 10-15 minutes of activity should be considered frequent), otherwise it will be detrimental to the coagulation of the concrete and the stability of the hole wall. When the age of the concrete at the bottom of the pipe reaches the determined age of pipe removal, the joint pipe can be gradually pulled out according to the pouring speed of the concrete.
[0045] In this embodiment, the control system realizes automation and intelligence on the basis of ensuring construction reliability.
[0046] The principles and implementation methods of the present invention are described in this article using specific examples. The description of the above embodiments is only used to help understand the method and core idea of the present invention. At the same time, for those skilled in the art, according to the idea of the present invention, there will be changes in the specific implementation methods and application scope. In summary, the content of this specification should not be understood as limiting the present invention.
[0047] The principles and implementation methods of the present invention are described in this article using specific examples. The description of the above embodiments is only used to help understand the method and core idea of the present invention. At the same time, for those skilled in the art, according to the idea of the present invention, there will be changes in the specific implementation methods and application scope. In summary, the content of this specification should not be understood as limiting the present invention.
Claims
1. A key-type pipe pulling machine for pulling out joint pipes in underground wall section connection construction, characterized in that: It includes lifting cylinder, upper frame, lower frame, clamping ring and key, among which: The lifting cylinder is arranged between the upper frame and the lower frame, and is used to realize the lifting of the upper frame; The clamping ring is arranged on the upper frame and is used to clamp the joint pipe; The clamping key is arranged on the clamping ring and is used for locking the clamping ring and the joint pipe when the clamping ring is clamped.
2. A key-type pipe pulling machine for pulling out joint pipes in underground wall section connection construction according to claim 1, characterized in that: The clamping ring is composed of two semicircular steel plate welded structural parts.
3. A key-type pipe pulling machine for pulling out joint pipes in underground wall section connection construction according to claim 1, characterized in that: A clamping groove is arranged at one end opposite to the two clamping rings, and the clamping key is assembled in the clamping groove.
4. A key-type pipe pulling machine for pulling out joint pipes in underground wall section connection construction according to claim 1, characterized in that: The utility model also comprises a hydraulic station system, wherein the hydraulic station system adopts a large oil pump and a small oil pump to respectively perform a fast operation and a slow operation.
5. A key-type pipe pulling machine for pulling out joint pipes in underground wall section connection construction according to claim 4, characterized in that: When a large pump is working, the lifting speed of the clamping ring is 0.6-0.7m / min, and the lowering speed is 1.30m / min; when a small pump is working, the lifting speed of the clamping ring is 0.01m / min.
6. A key-type pipe pulling machine for pulling out joint pipes in underground wall section connection construction according to claim 4, characterized in that: The hydraulic station system is provided with a synchronous speed regulating valve to keep the lifting cylinder in a synchronous working state all the time.
7. A key-type pipe pulling machine for pulling out joint pipes in underground wall section connection construction according to any one of claims 4 to 6, characterized in that: The small pump inching start and the large pump fast start operate independently; or, the small pump inching start state switches to the automatic start mode. In this state, when the pressure rises to the limit, the system stops the small pump operation and automatically switches to the large pump operation mode.