Dewatering construction method for confined water depth foundation pit

Through the dewatering construction method of deep foundation pits under pressure, including the steps of measuring and setting out, burying casings, drilling holes, and filling filter materials, the problems of low efficiency and large environmental impact of traditional foundation pit dewatering methods are solved, and construction safety is improved. performance and stability, achieving effective control and utilization of pressurized water.

CN118774155APending Publication Date: 2024-10-15SINOHYDRO BUREAU 6 CO LTD
View PDF 0 Cites 1 Cited by

Patent Information

Application Number
CN202410982362.9
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-07-22
Publication Date
2024-10-15

AI Technical Summary

Technical Problem

Traditional foundation pit dewatering methods have problems such as low efficiency, poor results, and a large impact on the surrounding environment. Especially in the construction of deep foundation pits, the soil conditions are complex, resulting in increased construction difficulty and safety threats.

Method used

The dewatering construction method for deep foundation pits under pressure is adopted, including the steps of measuring and setting out, burying casings, drilling holes, hanging casings, filling filter materials, cleaning wells, installing pumping equipment, and plugging well pipes. Through precise control and Use pressurized water to ensure construction safety and stability and reduce the impact on the surrounding environment.

Benefits of technology

It improves the safety and stability of foundation pit construction, reduces construction difficulty, achieves effective control and utilization of pressurized water, and ensures construction quality and environmental protection.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118774155A_ABST
    Figure CN118774155A_ABST
Patent Text Reader

Abstract

The invention provides a dewatering construction method for a confined water depth foundation pit, and belongs to the technical field of foundation pit construction.According to the dewatering construction method, a casing pipe is hoisted after hole forming, well wall collapse can be prevented, safety in a well can be guaranteed, after the filter material filling procedure is completed, the casing pipe part is pulled out, part of the casing pipe is reserved to form an upper section and a lower section, and the casing pipe part is taken out; the upper section and the lower section do not affect normal underground water overflow, the stability of the confined water depth foundation pit can be guaranteed, in the construction process of the deep foundation pit, the construction difficulty can be lowered, well washing and water pumping equipment installation and water pumping test steps can be reduced, the working state of a well pipe can be monitored in real time, problems can be found and solved in time, and the construction quality is guaranteed; through well casing plugging, construction monitoring and emergency measures, quick response can be achieved when abnormal conditions occur, and possible risks can be effectively handled. Through a series of construction steps and technical means, the stability and reliability of precipitation construction are ensured, and the engineering safety is improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of foundation pit construction, in particular to a construction method for dewatering a pressurized deep foundation pit. Background Art

[0002] Foundation pit dewatering technology is of great significance in current engineering construction, especially in the period of rapid development of urban construction. With the continuous development and utilization of underground space, the problem of pressurized water faced by foundation pit construction has gradually become prominent. Pressurized water has a high water pressure and may cause disasters such as water and sand gushing in the foundation pit, which seriously threatens the safety of construction and the surrounding environment.

[0003] Traditional foundation pit dewatering methods may have problems such as low efficiency, poor results, and great impact on the surrounding environment. For example, some methods may cause the groundwater level to drop too much, affecting the safety of surrounding buildings; or the dewatering effect is unstable and cannot meet construction requirements; for deep foundation pits, due to their large depth and complex soil conditions, the difficulty of dewatering construction is also increased accordingly.

[0004] To this end, the present invention proposes a dewatering construction method for a pressurized deep foundation pit, which improves the safety and stability of the foundation pit construction and also minimizes the impact on the surrounding environment. Summary of the invention

[0005] In order to solve the problems of low efficiency, poor effect and great impact on the surrounding environment of traditional foundation pit dewatering methods, the present invention provides a construction method for dewatering deep foundation pits in pressurized water, which can effectively control and utilize pressurized water, improve the safety and stability of construction, and reduce the impact on the surrounding environment. It has the characteristics of accuracy, safety and stability, and can be widely used in construction in the field of foundation pit dewatering technology.

[0006] In order to achieve the above object, the present invention adopts the following technical solutions:

[0007] The construction method for dewatering a deep foundation pit with pressurized water comprises the following steps:

[0008] S1. Measure and lay out to determine the location of the foundation pit;

[0009] S2. Bury casing to prevent the influx of groundwater;

[0010] S3, using drilling equipment to take soil and form holes;

[0011] S4, hanging and lowering the casing;

[0012] S5, hanging and lowering the well pipe;

[0013] S6. Remove debris and sediment from the hole to ensure that the well is unobstructed;

[0014] S7, filling filter material;

[0015] S8, pull out part of the casing, and the part of the casing remaining in the hole forms upper and lower sections; specifically,

[0016] The buried casing in step S4 includes: a short section and a long section, the bottom end of the long section is aligned with the top end of the short section, and a plurality of welded inner strips are commonly connected between the short section and the long section, and the top end of the long section has a flange portion;

[0017] During the process of pulling out part of the casing, the welded inner strip between the short section and the long section is broken, so that the short section is completely left at the bottom of the hole. After the long section is raised to a suitable height, the long section is cut off at 2m below the ground elevation. The upper part of the cut long section is raised out of the hole or 0.5-1m is reserved at the hole mouth;

[0018] S9, wash the well, install pumping equipment, inspect and test the well pipe;

[0019] S10. Well pipe sealing, construction monitoring and emergency measures.

[0020] Preferably, the surveying and laying out in S1 specifically includes: according to the designed well pipe position, in combination with the reference points provided on site, a control network is established within the scope of the project by combining the guide wire and triangulation, and the control points are re-surveyed and used after approval; the well pipe positioning is carried out by the total station polar coordinate method, and marked and identified in the form of "gantry piles".

[0021] Preferably, the casing burying in S2 specifically includes:

[0022] The location of casing burial should coincide with the determined well pipe position, and a 450 drilling and pulling machine should be used to lower the casing.

[0023] Preferably, the use of a 450 pulling machine for lowering the casing specifically includes: the casing is buried by manually digging a pit directly on the ground, filling the bottom of the pit with 0.5m thick clay, and then burying the casing; the casing is not less than 30cm above the ground, and a cross line is used to check whether the center of the casing coincides with the center of the pile to ensure that the plane position deviation of the casing after burial is <5cm.

[0024] Preferably, the use of drilling equipment to drill holes in S3 specifically includes: after the drilling rig is in place horizontally and the pile position is verified to be correct, drilling construction can be carried out, and a 360 rotary drilling rig is used to start drilling. The drilling should be slow at first and then fast, with an initial penetration of 0.4-0.5m / min, to confirm whether there is an unfavorable stratum underground. After the penetration reaches the clay layer, if the drilling is normal, the penetration can be increased.

[0025] Preferably, the hanging and placing of the well pipe in S5 specifically includes: slowly lowering the well pipe with a 75t truck crane, welding each section of the steel pipe at the hole mouth, hanging and placing the well pipe vertically, and keeping the well pipe corresponding to the hole center to prevent rainwater, mud, sand or foreign matter from flowing into the well, the well pipe must be at least 20cm above the ground, and the well mouth must be covered;

[0026] The well pipe comprises: an upper seamless steel pipe, a middle bridge filter pipe and a lower sedimentation pipe.

[0027] Preferably, the filter filling material in S7 specifically includes: after the well pipe reaches the designed depth, the mud in the well is appropriately diluted, and then gravel is immediately filled around the well pipe, and the gravel is successively from the bottom layer to the top layer: medium coarse sand and melon seed slices, medium coarse sand, yellow pure fine sand, and clay balls.

[0028] Preferably, the well washing and installation of pumping equipment to inspect and test the well pipe in S9 specifically includes:

[0029] Step 1: Within 8 hours after the well is completed, place the sludge pump into the bottom of the well to repeatedly pump and wash to ensure the water seepage effect. During the well washing process, observe the changes in water level and water output;

[0030] Step 2: Install pumping equipment:

[0031] ① The pumping test should be carried out after the well washing quality meets the requirements, and the maximum drawdown pumping should be performed. The water output should be calculated using the steady flow principle, and the static water level and drawdown should be measured;

[0032] ②Install submersible pump and piping system;

[0033] ③When lowering the water pump, use steel rope or wire to fasten it, tie the water pipe mouth firmly, and install a cover plate at the wellhead after the water pump is installed to prevent foreign objects from falling into the well;

[0034] Step 3: Lock pumping test:

[0035] The lock foundation pit is set as one zone, and the pressure relief well is constructed in three sequences;

[0036] ① Before constructing the pressure relief well, complete the construction of the observation well; before the pressure relief well is completed, in order to prevent the overflow of pressurized water, the observation well can be used to pump out water when necessary; the test ensures the effectiveness of the observation well, and if the water output from the observation well is normal, proceed to step ②, otherwise, the design decision will be made on site according to the situation;

[0037] ②Construct a first-order pressure relief well and test to ensure the effectiveness of the pressure relief well. If the water output is normal, continue to step ③. Otherwise, the design decision will be made on site according to the situation;

[0038] ③ Pump water from the completed pressure relief wells in ② and observe all observation wells within the sluice foundation pit. If the water level of all observation wells meets the design requirements and can be stable for three days, the design scheme of the water level relief wells shall be optimized; if the water level of only some observation wells meets the design requirements or all observation wells do not meet the design requirements, the water level relief test shall be continued according to ④, and the water level relief wells in ② shall not be interrupted;

[0039] ④Construct the second-order pressure relief well and test to ensure the effectiveness of the pressure relief well. If the water output is normal, continue to step ⑤. Otherwise, the design decision will be made on site according to the situation;

[0040] ⑤ Pump water from the completed pressure relief wells in ②④, and observe all observation wells within the sluice foundation pit. If the precipitation of all observation wells meets the design requirements and can be stable for three days, the design plan of the precipitation wells needs to be optimized; otherwise, three-sequence pressure relief wells should be added according to the situation.

[0041] Preferably, the well pipe plugging in S10 specifically includes: cleaning the well pipe and draining the water to avoid affecting the subsequent construction, unplugging the water pump, inserting a 40mm grouting pipe into the pipe, the bottom of the grouting pipe enters the well pipe, and the well pipe is initially filled with melon seed slices, and the melon seed slices should be backfilled to more than 9.0m above the grouting pipe mouth. Before the formal grouting, the grouting pipe position should be fixed at the well pipe mouth, and the cement slurry should be pre-mixed according to the size of the well, with a water-cement ratio of 0.6 to 0.7, and then grouting is started. After grouting about 0.5 to 1.0m of slurry, the grouting pipe is lifted up by 0.5 to 1.0m to continue grouting; after the grouting pipe is lifted up by 3.0m, a section of the grouting pipe is pulled out, and the process is repeated until the plugging is completed.

[0042] The beneficial effects of the present invention are as follows: the casing is suspended after the hole is formed, which can prevent the well wall from collapsing and ensure the safety of the well. After the filter material filling process is completed, the casing is partially pulled out, and part of the casing is reserved to form upper and lower sections. The upper and lower sections will not affect the normal overflow of groundwater, and can also ensure the stability of the deep foundation pit under pressure. During the construction of the deep foundation pit, the difficulty of construction can be reduced. The well washing and installation of pumping equipment and the pumping test steps can monitor the working status of the well pipe in real time, discover and solve problems in time, and ensure the construction quality. Through the well pipe plugging, construction monitoring and emergency measures, it is possible to respond quickly when abnormal situations occur and effectively deal with possible risks. Through the above series of construction steps and technical means, the stability and reliability of the precipitation construction are ensured, and the safety of the project is improved. BRIEF DESCRIPTION OF THE DRAWINGS

[0043] In order to more clearly illustrate the construction method of dewatering a deep foundation pit under pressure, the following drawings are shown;

[0044] Figure 1 It is a schematic diagram of a pressure relief well / observation well in a foundation pit of the present invention;

[0045] Figure 2It is a schematic diagram of the plan layout of the observation well and the pressure relief well of the present invention;

[0046] Figure 3 It is a schematic diagram of the casing of the present invention.

[0047] The reference numerals in the accompanying drawings:

[0048] 1. Well pipe; 101. Lower sedimentation pipe; 102. Middle bridge filter pipe; 103. Upper seamless steel pipe; 2. Medium-coarse sand and melon seed slices; 3. Medium-coarse sand; 4. Yellow pure fine sand; 5. Clay balls; 6. Mortar; 7. Casing; 701. Short section; 702. Long section; 702a. Flange; 703. Welded inner strip; a. First-order pressure relief well; b. Second-order pressure relief well; c. Third-order pressure relief well; d. Observation well. DETAILED DESCRIPTION

[0049] Taking a sluice and ship lock project as an example, the construction method of pressurized water deep foundation pit dewatering is explained. In the deep foundation pit construction, how to effectively control and utilize pressurized water, improve the safety and stability of construction, and reduce the impact on the surrounding environment, and it has the characteristics of accuracy, safety and stability.

[0050] Please refer to the attached Figure 1-Figure 3 This embodiment provides a construction method for dewatering a deep foundation pit under pressure, comprising the following steps:

[0051] Step 1: Measure and lay out to ensure the accuracy of construction, as follows:

[0052] According to the location of the well pipe Figure 2 Based on the benchmarks provided by the owner, a control network is established within the scope of the project using a combination of traverse and triangulation. The control points can only be used after re-survey and approval. The well pipe positioning is carried out using the total station polar coordinate method and marked with "gantry piles".

[0053] Step 2: The drilling rig is in place to facilitate subsequent construction, as follows;

[0054] To ensure that the well pipe can be smoothly lowered to the predetermined depth, before the drilling rig is placed, the ground around the pile hole is cleaned and leveled and the foundation is compacted to ensure that the drilling rig body is placed stably. When the drilling rig is in place, the center of the drill bit and the center of the pile position are ensured to be on the same plumb line, and the centering error is less than 10mm. After the drilling rig is in place, adjust the level, keep the borehole vertical, measure the floor elevation, and fill in the inspection form. Drilling can only be carried out after the supervision engineer has inspected and accepted the centering of the drilling rig and the verticality of the drill rod. Before formal drilling, the drilling rig must first be tested for operation to check the stability and condition of the drilling rig to ensure that the subsequent hole construction can be continuous.

[0055] Step 3: bury the casing to protect the wellhead and prevent the influx of groundwater, as follows;

[0056] The location of the casing should be consistent with the pile position. The pile position is located by the total station polar coordinate method, and the cross line is used to check the "gantry pile" to determine the location of the casing. The casing is placed down by a 450 puller. The casing is made of 14mm thick steel plate, 11.5m long, and has a slurry discharge port at the top.

[0057] To ensure the quality of the borehole, the casing should meet the following requirements: Onshore casing is buried by manually digging a pit directly on the ground, filling the bottom of the pit with 0.5m thick clay, and then burying the casing; the casing is not less than 30cm above the ground; when there is pressurized water in the borehole, it should be 1.5 to 2.0m higher than the stabilized pressurized water level; after the casing is sunk into the stratum, use a cross line to check whether the center of the casing coincides with the center of the pile to ensure that the plane position deviation of the casing after burial is <5cm; to increase rigidity and prevent deformation, a stiffening rib is welded on the outer side of the upper and lower ends and the middle of the casing.

[0058] Step 4: Preparation and use of mud, in order to ensure stability during drilling and reduce pollution to the environment, as follows;

[0059] The mud wall of the well pipe is mainly made of purchased bentonite. The mud specific gravity, viscosity and sand content should be measured frequently during the hole making process. The mud specific gravity should be 1.05-1.10. The on-site test personnel are responsible for making original records of the quality inspection of the hole making mud and the hole cleaning mud, and notify the relevant personnel of the inspection results for timely adjustment.

[0060] Step 5: Soil excavation and hole formation is to use drilling equipment to dig out the soil to form a hole in preparation for the subsequent well pipe installation, as follows;

[0061] After the drilling rig is in place horizontally and the pile position is verified, drilling construction can be carried out. The 360 ​​rotary drilling rig starts drilling. The drilling should be slow at first and then fast. The initial footage is 0.4-0.5m / min. Confirm whether there is an unfavorable stratum underground. After the footage reaches the clay layer, if the drilling is normal, the footage can be appropriately increased. The drop hammer grab grabs the soil in the casing out of the hole and unloads it on the ground. The loader loads it into the dump truck and transports it out of the drying area. After the drying is completed, it is transported to the designated waste dump. When taking soil to form a hole, the elevation of the water-proof layer and the pebble layer should be recorded in detail, and a hole column chart should be formed to control the backfill elevation of filter materials, clay balls, etc. After the hole reaches the designed elevation, the hole depth, hole diameter, and hole wall verticality are checked. Before the inspection, the inspection tools, measuring ropes and other tools are prepared. During the drilling process, attention should be paid to the drilling rig instrument at all times. If the instrument shows that the verticality has changed, it should be adjusted in time, and drilling should be carried out after adjustment.

[0062] Step 6: Hanging and lowering the casing. The purpose of hanging and lowering the casing is to prevent the well wall from collapsing and ensure the safety of the well. The details are as follows;

[0063] After the soil is taken, a 75t crawler crane is used to lower the full casing. The full casing is made of φ610 seamless steel pipe with a wall thickness of 14mm. The overall length of the casing is the same as the hole depth, and the hole mouth uses a pre-made flange.

[0064] The sleeve includes: a short section 701 and a long section 702. The bottom end of the long section 702 is aligned with the top end of the short section 701. A plurality of welded inner strips 703 are commonly connected between the short section 701 and the long section 702. The top end of the long section 702 has a flange portion 702a.

[0065] The multiple welded inner strips 703 connect the short section 701 and the long section 702 into a whole, so that the casing can be hoisted and lowered smoothly.

[0066] Step 7: Hole cleaning: Hole cleaning is to remove debris and sediment in the hole to ensure that the well is unobstructed. The details are as follows;

[0067] The hole is cleaned before the well pipe is lowered into the well. The hole is cleaned by injecting clean water for displacement, using a mud pump to pump out the sediment, and measuring the hole depth.

[0068] Step 8: Hanging the well pipe is to hang the pre-prepared well pipe into the hole for installation, as follows;

[0069] The well pipe is divided into three parts, the upper seamless steel pipe 103, the middle bridge filter pipe (10m) 102, and the lower sedimentation pipe (1m) 101. It is slowly lowered by a 75t truck crane. Each section of the steel pipe is welded at the hole mouth, and the welding quality meets the specifications and design requirements. In order to prevent the upper and lower sections from being misaligned, the well pipe should be straightened in the direction before lowering the pipe. The well pipe should be suspended vertically and kept in the center of the wellbore to prevent rainwater, mud, sand or foreign matter from flowing into the well. The well pipe should be at least 20cm above the ground, and the wellhead should be covered. When lowering the well pipe, it cannot be rotated or moved up and down to prevent the filter from being damaged, causing mud and sand to flow into the precipitation well.

[0070] Step nine, filling filter material, filling filter material and clay is to filter out impurities and suspended matter in the water, as follows;

[0071] S1: Filter filling: After the well pipe reaches the designed depth, the mud in the well is appropriately diluted, and then gravel is immediately filled around the well pipe. The gravel is: medium-coarse sand + 10% melon seed slices. The gravel is filled into a pebble layer. The 1m connecting area between the pebble layer and the impermeable layer is backfilled with clay balls, and the rest is backfilled with clay.

[0072] You can also use the method where the layers from bottom to top are: medium coarse sand and melon seed slices, medium coarse sand, yellow pure fine sand, and clay balls.

[0073] S2: When backfilling the filter material, it should be filled evenly around the well pipe to make the filter layer thickness uniform. The backfill amount of the filter material should meet the requirements of the specification. After the well pipe sinks, the water seepage performance of the well pipe should be checked in time. When the sand filter material is poured into the well hole around the well pipe, muddy water should emerge from the well pipe, or clean water is injected into the well pipe. If the water can seep in quickly, the well pipe can be considered to be good. If the water does not seep in, it should be handled immediately. After a set of well pipes are buried, the well should be pumped and washed in time.

[0074] S3: The filter material outside the well pipe is graded gravel and medium-coarse sand, which should be evenly placed to prevent the separation of coarse and fine aggregates, and the filter material should be densely filled. After the filter material is filled, clay balls are filled. When clay balls are filled, they should be filled evenly around, and the filling height should not be less than 1m. After the filling is completed, clay filling is carried out.

[0075] Step 10: Pull out part of the casing, and the part of the casing remaining in the hole forms upper and lower sections.

[0076] Specifically, during the process of pulling out part of the casing, the welded inner strip 703 at the short section 701 and the long section 702 is broken, so that the short section 701 is completely left at the bottom of the hole. After the long section 702 is raised to a suitable height, the long section 702 is cut off at 2m below the ground elevation, and the upper part of the cut long section 702 is raised out of the hole or 0.5-1m is reserved at the hole mouth.

[0077] Step 11: Well washing, installation of pumping equipment and pumping test is to inspect and test the well pipe to ensure its normal operation, as follows;

[0078] S1: Well washing: After the backfill filling is completed, the well shall be washed according to the regulations. The well washing shall be sufficient and timely. Within 8 hours after the well is completed, the sludge pump shall be placed in the bottom of the well for repeated pumping and washing to ensure the water seepage effect. During the well washing process, the water level and water output changes shall be observed.

[0079] S2: Install pumping equipment:

[0080] ① The pumping test should be carried out after the well washing quality meets the requirements. The maximum drawdown should be performed, the water output should be calculated using the steady flow principle, and the static water level and drawdown should be measured.

[0081] ②Install the submersible pump and piping system: Check the motor and pump body before installation. The pump type should be P=7.5KW, H=50m, and flow rate 50m3 / h. The equipment can be installed only after inspection. The insulation of the submersible motor, cables and connectors is safe and reliable, and is equipped with a protective switch control to ensure safe operation. During the installation process, ensure that each connection part is sealed reliably and leak-proof.

[0082] ③ When lowering the water pump, it should be tied firmly with steel rope or wire, and the water pipe mouth should be tied firmly. After the water pump is installed, a cover plate should be installed at the wellhead to prevent foreign objects from falling into the well.

[0083] S3: Lock pumping test:

[0084] The ship lock foundation pit is set as one area, and the pressure relief well is constructed in three sequences.

[0085] ① Before constructing the pressure relief well, complete the construction of the observation well. Before the pressure relief well is completed, in order to prevent the overflow of pressurized water, the observation well can be used to pump out water when necessary. The test ensures the effectiveness of the observation well. If the water output from the observation well is normal, continue to step ②. Otherwise, the design decision will be made on site according to the situation.

[0086] ②Construct a first-order pressure relief well and test to ensure the effectiveness of the pressure relief well. If the water output is normal, continue to step ③. Otherwise, the design decision will be made on site based on the situation.

[0087] ③ Pump water from the completed pressure relief wells in ② and observe all observation wells within the sluice foundation pit: if the dewatering of all observation wells meets the design requirements and can be stable for three days, the dewatering well design plan needs to be optimized; if the dewatering of only some observation wells meets the design requirements or all observation wells do not meet the design dewatering requirements, continue the dewatering test according to ④ and the dewatering of the pressure relief wells in ② will not be interrupted.

[0088] ④Construct the second-order pressure relief well and test to ensure the effectiveness of the pressure relief well. If the water output is normal, continue to step ⑤. Otherwise, the design decision will be made on site based on the situation.

[0089] ⑤ Pump water from the completed pressure relief wells in ②④, and observe all observation wells within the sluice foundation pit: if the precipitation of all observation wells meets the design requirements and can be stable for three days, the design plan of the precipitation wells needs to be optimized; otherwise, three-sequence pressure relief wells are added according to the situation.

[0090] Step 12: Well plugging, construction monitoring and emergency measures to prevent groundwater from gushing out again and ensure the safety of construction, as follows:

[0091] S1: Well pipe plugging: Before sealing the well after the dewatering operation is completed, the well pipe should be cleaned to remove the garbage and gravel, etc. After cleaning the debris, the well pipe should be cleaned and the water should be drained to avoid affecting the subsequent construction, and the pump should be pulled out. A 40mm grouting pipe is lowered into the pipe, and the bottom of the grouting pipe enters the bottom of the well pipe. Melon seeds are initially filled into the well pipe, and the melon seeds should be backfilled to more than 9.0m above the grouting pipe mouth. Before the formal grouting, the position of the grouting pipe should be fixed at the well pipe mouth, and the cement slurry should be pre-mixed according to the size of the well, with a water-cement ratio of 0.6 to 0.7. Then start grouting. After grouting about 50cm to 100cm of slurry, lift the grouting pipe up 0.5 to 1.0m to continue grouting; after the grouting pipe is lifted up 3.0m, pull out a section of the grouting pipe, and continue in sequence until the plugging is completed.

[0092] S2: Construction monitoring:

[0093] ① Surrounding environment monitoring: including monitoring of settlement, tilt, crack generation and development of surrounding buildings and roads, generally one every 10m;

[0094] ②Monitor the settlement, inclination, crack generation and development of surrounding pipelines (gas pipes, water pipes, rainwater pipes, sewage pipes, fire pipes, power pipes, etc.), generally one crack every 10 meters. Excavate and expose the pipeline joints for monitoring;

[0095] ③ Lateral displacement of deep soil layer on the foundation pit slope;

[0096] ④ Groundwater level observation hole;

[0097] ⑤Foundation settlement detection.

[0098] S3: Emergency measures:

[0099] ① The retaining works are extremely complex, and there are many factors that affect safety. A certain number of emergency equipment and materials should be available on site, such as sand bags, channel steels or steel pipes, grouting machines, etc. The equipment and materials must be in place before excavation; the construction unit must take corresponding emergency measures in a timely manner to ensure safety. When the displacement of the foundation pit is too large, additional supports can be added to the parts with conditions, or soil nails can be driven in, soil can be unloaded from the top of the slope, and bagged soil can be used for counter pressure at the foot of the slope; when the foundation pit leaks, emergency measures such as compaction grouting or rotary jet piles can be taken; when the situation is critical, the excavation of the earth should be stopped immediately, and the earth should be backfilled if necessary, and emergency measures such as unloading the earth outside the pit should be taken. When the situation is critical, the pit should be backfilled.

[0100] Type ② mechanical construction should ensure that the ground has sufficient bearing capacity, and measures should be taken to ensure the stability of the machinery to avoid overturning and slope instability during operation.

[0101] ③ During the excavation of the foundation pit, pay close attention to the changes in the groundwater level outside the pit. If water seepage or sand flow is found, the designer should be notified in time and plugging measures should be taken.

[0102] ④ The treatment of waste soil, slag and waste mud during the construction process should comply with the regulations of relevant departments and pay attention to environmental protection.

[0103] ⑤ During the foundation pit excavation process, excavation should be carried out in layers according to the design requirements. Excavation can only be continued after each support construction reaches the design strength. "Big pot bottom" excavation is strictly prohibited, and drainage work in the foundation pit must be done well. If construction is carried out during the rainy season, sufficient pumping equipment must be prepared to ensure that the base is not soaked for a long time.

[0104] ⑥ After the foundation pit is excavated to the designed depth, drainage ditches and collection wells should be built at the bottom of the foundation pit, and the accumulated water in the collection wells should be removed in time.

[0105] ⑦ When cracks appear on the ground surface, grouting is used to seal the cracks to prevent surface water from seeping in.

[0106] Those skilled in the art will readily appreciate other embodiments of the present invention after considering the specification and practicing the disclosure of the invention herein. This application is intended to cover any variations, uses or adaptations of the present invention that follow the general principles of the present invention and include common knowledge or customary techniques in the art that are not disclosed by the present invention. The specification and examples are to be considered exemplary only, and the true scope and spirit of the present invention are indicated by the following claims.

[0107] It should be understood that relational terms such as "first" and "second" are used only to distinguish one entity or operation from another entity or operation, and do not necessarily require or imply any such actual relationship or order between these entities or operations. The present invention is not limited to the precise structure described above and shown in the accompanying drawings, and various modifications and changes can be made without departing from the scope thereof. The scope of the present invention is limited only by the appended claims.

Claims

1. Construction method of dewatering deep foundation pit under pressure water, It is characterized in that The following steps are involved: S1. Measure and lay out to determine the location of the foundation pit; S2. Bury casing to prevent the influx of groundwater; S3, using drilling equipment to take soil and form holes; S4, hanging and lowering the casing (7); S5, hanging and lowering the well pipe; S6. Remove debris and sediment from the hole to ensure that the well is unobstructed; S7, filling filter material; S8, pull out part of the casing, and the part of the casing remaining in the hole forms upper and lower sections; specifically, The buried casing in step S4 includes: a short section (701) and a long section (702), wherein the bottom end of the long section (702) is aligned with the top end of the short section (701), and a plurality of welded inner strips (703) are commonly connected between the short section (701) and the long section (702), and the top end of the long section (702) has a flange portion (702a); During the process of pulling out part of the casing, the welded inner strip (703) at the short section (701) and the long section (702) is broken, so that the short section (701) is completely left at the bottom of the hole. After the long section (702) is lifted to a suitable height, the long section (702) is cut off at a height 2 m below the ground level. The upper part of the cut long section (702) is lifted out of the hole or reserved 0.5-1 m at the hole mouth. S9, wash the well, install pumping equipment, inspect and test the well pipe; S10. Well pipe sealing, construction monitoring and emergency measures.

2. The method for dewatering a deep foundation pit under pressure according to claim 1, It is characterized in that The surveying and laying out in S1 specifically includes: according to the designed well pipe position, combined with the reference points provided on site, a control network is established within the scope of the project by combining the guide wire and triangulation, and the control points are re-surveyed and used after approval; the well pipe positioning is carried out by the polar coordinate method of the total station, and marked and identified in the form of "gantry piles".

3. The dewatering construction method for a deep foundation pit under pressure water according to claim 2, It is characterized in that The casing embedding in S2 specifically includes: The location of casing burial should coincide with the determined well pipe position, and a 450 drilling and pulling machine should be used to lower the casing.

4. The method for dewatering a deep foundation pit under pressure according to claim 3, Features: The use of a 450 pulling machine for placing the casing specifically includes: the casing is buried by manually digging a pit directly on the ground, filling the bottom of the pit with 0.5m thick clay, and then burying the casing; the casing is not less than 30cm above the ground, and a cross line is used to check whether the center of the casing coincides with the center of the pile to ensure that the plane position deviation of the casing after burial is <5cm.

5. The method for dewatering a deep foundation pit under pressure according to claim 1, Features: The use of drilling equipment to drill holes in S3 specifically includes: after the drilling rig is in place horizontally and the pile position is verified to be correct, drilling construction can be carried out, and a 360 rotary drilling rig is used to start drilling. The drilling should be slow at first and then fast, with an initial penetration of 0.4-0.5m / min. Confirm whether there is an unfavorable stratum underground. After the penetration reaches the clay layer, if the drilling is normal, the penetration can be increased.

6. The method for dewatering a deep foundation pit under pressure according to claim 1, It is characterized in that The hanging and placing of the well pipe in S5 specifically includes: slowly lowering it with a 75t truck crane, welding each section of the steel pipe at the hole mouth, hanging and placing the well pipe vertically, and keeping the well pipe corresponding to the center of the hole to prevent rainwater, mud, sand or foreign matter from flowing into the well, the well pipe must be at least 20cm above the ground, and the well mouth must be covered; The well pipe comprises: an upper seamless steel pipe (103), a middle bridge filter pipe (102), and a lower sedimentation pipe (103).

7. The method for dewatering a deep foundation pit under pressure water according to claim 1, It is characterized in that The filter filling material in S7 specifically includes: after the well pipe reaches the designed depth, the mud in the well is appropriately diluted, and then gravel is immediately filled around the well pipe, and the gravel is successively: medium coarse sand and melon seed slices, medium coarse sand, yellow pure fine sand, and clay balls from the bottom to the top.

8. The method for dewatering a deep foundation pit under pressure water according to claim 1, It is characterized in that The well washing and installation of pumping equipment to inspect and test the well pipe in S9 specifically includes: Step 1: Within 8 hours after the well is completed, place the sludge pump into the bottom of the well for repeated pumping and washing to ensure the water seepage effect. During the well washing process, observe the changes in water level and water output; Step 2: Install pumping equipment: ① The pumping test should be carried out after the well washing quality meets the requirements, and the maximum drawdown pumping should be performed. The water output should be calculated using the steady flow principle, and the static water level and drawdown should be measured; ②Install submersible pump and piping system; ③When lowering the water pump, use steel rope or wire to fasten it, tie the water pipe mouth firmly, and install a cover plate at the wellhead after the water pump is installed to prevent foreign objects from falling into the well; Step 3: Lock pumping test: The lock foundation pit is set as one zone, and the pressure relief well is constructed in three sequences; ① Before constructing the pressure relief well, complete the construction of the observation well; before the pressure relief well is completed, in order to prevent the overflow of pressurized water, the observation well can be used to pump out water when necessary; the test ensures the effectiveness of the observation well, and if the water output from the observation well is normal, proceed to step ②, otherwise, the design decision will be made on site according to the situation; ②Construct a first-order pressure relief well and test to ensure the effectiveness of the pressure relief well. If the water output is normal, continue to step ③. Otherwise, the design decision will be made on site according to the situation; ③ Pump water from the completed pressure relief wells in ② and observe all observation wells within the sluice foundation pit. If the water level of all observation wells meets the design requirements and can be stable for three days, the design scheme of the water level relief wells shall be optimized; if the water level of only some observation wells meets the design requirements or all observation wells do not meet the design requirements, the water level relief test shall be continued according to ④, and the water level relief wells in ② shall not be interrupted; ④Construct the second-order pressure relief well and test to ensure the effectiveness of the pressure relief well. If the water output is normal, continue to step ⑤. Otherwise, the design decision will be made on site according to the situation; ⑤ Pump water from the completed pressure relief wells in ②④, and observe all observation wells within the sluice foundation pit. If the precipitation of all observation wells meets the design requirements and can be stable for three days, the design plan of the precipitation wells needs to be optimized; otherwise, three-sequence pressure relief wells should be added according to the situation.

9. The method for dewatering a deep foundation pit under pressure water according to claim 1, It is characterized in that The well pipe plugging in S10 specifically includes: cleaning the well pipe and draining the water to avoid affecting the subsequent construction, unplugging the water pump, inserting a 40mm grouting pipe into the pipe, the bottom of the grouting pipe enters the well pipe, and the well pipe is initially filled with melon seed slices, which should be backfilled to more than 9.0m above the grouting pipe mouth. Before the formal grouting, the grouting pipe position should be fixed at the well pipe mouth, and the cement slurry should be pre-mixed according to the size of the well, with a water-cement ratio of 0.6 to 0.7, and then grouting is started. After grouting about 0.5 to 1.0m of slurry, the grouting pipe is lifted up by 0.5 to 1.0m to continue grouting; after the grouting pipe is lifted up by 3.0m, a section of the grouting pipe is pulled out, and the process is repeated until the plugging is completed.