A rapid construction method for deep pits in soft soil
By using a construction method that combines double-pipe high-pressure jet grouting piles with steel pipe supports in deep pit construction in soft soil areas, the problems of pit bottom heave and lateral slippage in deep pit construction in soft soil areas have been solved, achieving rapid, safe and economical construction results.
Patent Information
- Application Number
- CN202611482287.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2026-09-22
- Publication Date
- 2026-11-17
AI Technical Summary
When constructing deep pits in soft soil areas, traditional methods are difficult to effectively prevent the pit bottom from heaving and lateral slippage. Furthermore, the construction period for reinforced concrete supports is long, and the demolition is noisy, affecting the surrounding environment and safety.
The construction method adopts a combination of double-pipe high-pressure jet grouting water-stop curtain and steel pipe support. This includes setting up a high-pressure jet grouting water-stop curtain in the pit-within-pit section, installing steel pipe support after the bottom slab is constructed, forming an overall force-bearing system through force transmission plates, and removing the concrete internal support by combining the static cutting method of wire saw.
It effectively prevents sudden surges at the bottom of the pit, improves the rigidity of the support system, shortens the construction period, reduces material costs, reduces noise pollution, and achieves a balance between safety and economy.
Smart Images

Figure CN123109178A_ABST
Abstract
Description
Technical Field
[0001] This invention relates to the field of deep pit construction technology in soft soil, and in particular to a rapid construction method for deep pits in soft soil. Background Technology
[0002] In modern urban construction, some buildings often adopt a structural layout of main building, podium, and pure basement. Other building requirements, such as the need for sunken plazas, deep equipment rooms, and sump pits, result in basement structures often exhibiting varying depths, meaning that the excavation depth in some areas is significantly greater than that of the surrounding basement areas. When such projects are located in soft soil areas, the following construction challenges arise: Soft soil is characterized by high compressibility, low permeability, high sensitivity, and strong rheological properties. During pit-within-a-pit excavation, the soil arching effect created by the difference in soil elevation between the inside and outside of the pit is prone to failure, leading to heave and surge at the bottom of the pit and lateral slippage of the pit walls. Traditional slope excavation or simple sheet pile support lacks sufficient rigidity to resist the lateral flow pressure of soft soil.
[0003] The adjacent light rail line is extremely sensitive to settlement and displacement. Conventional construction methods, such as excavating deep pits within pits, can cause secondary deformation of the main foundation pit support structure, which is then transmitted to the light rail tunnel through the soil. Once the deformation exceeds the alarm threshold, it will seriously threaten train safety.
[0004] Traditional deep foundation pit support often uses reinforced concrete internal bracing. While it offers high rigidity, the long curing period severely restricts the progress of earthwork excavation and structural reconstruction. Furthermore, the removal of reinforced concrete bracing often involves blasting or using hydraulic breakers, resulting in significant vibration and noise, which not only disturbs the surrounding environment but also poses safety hazards. Summary of the Invention
[0005] The purpose of this invention is to address the shortcomings of existing technologies by proposing a rapid construction method for deep pits in soft soil.
[0006] To achieve the above objectives, the present invention adopts the following technical solution: A rapid construction method for deep pits in soft soil includes the following steps: S1: Construction of the main foundation pit water-stop curtain and support piles, and before the excavation of the main foundation pit, an independent double-pipe high-pressure jet grouting pile water-stop curtain is constructed at the design position of the pit-in-pit. S2: Install manholes in the main foundation pit and the pit within the pit to dewater the groundwater level and lower it to 1.0m below the current excavation surface; S3: Excavate the main foundation pit to the top elevation of the support piles, break the pile heads of the support piles, and construct the reinforced concrete cap beam and the first layer of concrete internal support. S4: After the concrete internal support reaches 80% of the design strength, the pit is excavated in layers and sections. After manual cleaning, C20 plain concrete cushion layer and brick formwork are constructed. S5: Construct a waterproof layer on the cushion layer, tie reinforcing bars, pour concrete for the pit bottom slab, and pre-embed steel plate connectors in the bottom slab; S6: Backfill soil in the construction pit and 300mm thick C20 plain concrete force transfer plate strip, so that the bottom plate and the support pile form an integral force system. S7: After the strength of the force transmission plate belt reaches 80%, the spiral welded steel pipe support is welded and installed on the pre-embedded steel plate connector, and the prestress is applied to the steel pipe support using a hydraulic jack. S8: After the strength of the force transmission plate belt reaches 100%, the concrete internal support is removed by static cutting with a wire saw. S9: The vertical structure of the construction pit is filled with the entire trench after the main structure reaches the design strength, and finally the steel pipe support is removed.
[0007] Preferably, in step S1, the construction of the double-pipe high-pressure jet grouting pile water-stop curtain adopts the skip-driving method, that is, spraying every other hole, and the interval between spraying construction of adjacent pile holes is not less than 24 hours; the specific construction parameters are: high-pressure pump pressure 25MPa, flow rate 80L / min; compressed air pressure 0.7MPa, air volume 3m3 / min; nozzle lifting speed 10cm / min; pile diameter 800mm, pile overlap width 200mm; The main foundation pit support piles are bored cast-in-place piles, with mud slurry used for hole formation and the mud slurry specific gravity controlled between 1.15 and 1.25, and the verticality deviation of the hole formation is less than 1%; the main foundation pit water-stop curtain is a triaxial mixing pile with a cement content of 20%, a water-cement ratio of 1.5, a sinking speed of no more than 1 m / min, and a lifting speed of no more than 2 m / min.
[0008] Preferably, in step S2, the well casing is made of Φ800mm sand-free concrete, and the filter material is crushed stone with a particle size of 1-4mm; in the silty soil layer of soft soil area, the well spacing is 15m; during precipitation, the groundwater level change rate is controlled to not exceed 500mm / d, and the cumulative change amount does not exceed 1000mm.
[0009] Preferably, in step S3, the pile head of the support pile is removed by the circumferential cutting method. The specific steps are as follows: First, a toothless cutting machine is used to cut 30-40mm deep along the design elevation, and the cutting depth does not exceed the thickness of the concrete protective layer of the pile body; then, a pneumatic pick is used to peel off the steel reinforcement protective layer above the circumferential cutting line from top to bottom; finally, the pile head is lifted out and the reserved concrete is manually chiseled away to the design elevation.
[0010] Preferably, in step S4, during the excavation of the pit within the pit, a 20-30cm thick soil layer is reserved for manual cleaning during mechanical excavation; the brick formwork is constructed with 240mm thick solid shale bricks, and the edge of the formwork extends 340mm beyond the edge of the raft slab to protect the waterproof layer.
[0011] Preferably, in step S5, the waterproof layer uses pre-laid reverse-adhesive waterproof membrane, and cement-based penetrating crystalline waterproof coating is applied to the pile head, with water-swellable waterstop strips installed around the pile head; when the diameter of the bottom slab reinforcement is greater than or equal to 16mm, a straight threaded sleeve mechanical connection is used, and the joint grade is level II; the construction joint of the external wall is left 300mm above the bottom slab, and the guide wall is poured together with the bottom slab concrete.
[0012] Preferred method: The construction quality control method for backfill soil in step S6 is as follows: before backfilling, the optimal moisture content of the soil is determined and controlled within the range of 15%-17%; a frog-type rammer is used for layered compaction, with each layer having a loose thickness of 300mm; the compaction coefficient is not less than 0.94; silty soil, cultivated soil, frozen soil and construction waste are strictly prohibited from being used for backfilling.
[0013] Preferably, in step S7, the spiral welded steel pipe support includes a first steel pipe support with a diameter of 609mm and a wall thickness of 12mm, and a second steel pipe support with a diameter of 426mm and a wall thickness of 10mm, both made of Q235B material; the dimensions of the embedded steel plate connector are 700mm×700mm×12mm; the hydraulic jack used to apply prestress has a tonnage of 300t, and the pre-applied axial force is 70% of the design axial force.
[0014] Preferred: Before removing the concrete internal support by the wire saw static cutting method in step S8, a socket-type disc-lock steel pipe support frame needs to be erected first. The specific parameters are: longitudinal spacing of the uprights is 900mm, transverse spacing is 1500mm, step distance is 1500mm, and the foundation of the frame is a reinforced concrete slab. Before cutting, the support beams are first stress-released, the cut blocks are placed on the frame, and after disassembly, they are hoisted off the site. During the static wire saw cutting operation, the foundation pit support structure is monitored in real time to control the rate of change of horizontal displacement at the pile top to not exceed 4 mm / d, the rate of change of vertical displacement of the surrounding roads to not exceed 3 mm / d, and the rate of change of axial force of the support to not exceed 400 kN / d.
[0015] Preferably: Before the overall backfilling of the trench is completed in step S9, the steel pipe support is always kept under stress; after the overall backfilling of the trench is completed and the main structure reaches the design strength, the prestress of the steel pipe support is first released, then the steel pipe support is cut off by gas cutting, and finally the support pile is removed.
[0016] The beneficial effects of this invention are as follows: 1. This invention employs a dual-pipe high-pressure jet grouting pile local water-stopping and steel pipe support active prestressing control technology. By independently setting up a high-pressure jet grouting pile water-stopping curtain at the pit-within-pit location, the confined water at the bottom of the pit is effectively blocked, eliminating the risk of sudden surge. At the same time, the steel pipe support, which is installed and prestressed in a timely manner after the bottom slab construction, greatly improves the overall rigidity of the support system. Combined with the rigid-to-support technology of the C20 plain concrete force transfer plate strip between the bottom slab and the support piles, the cantilever length of the support piles is effectively shortened.
[0017] 2. This invention and construction method have good economic benefits. The steel pipes have a high material recycling rate after dismantling and can be reused in other projects, which greatly reduces the material purchase cost. Compared with traditional reinforced concrete supports, it can save material costs. By locally reinforcing the jet grouting pipe water-stop curtain in the pit-in-pit section, the high cost of deepening the main foundation pit water-stop curtain to below the bottom of the pit is avoided, thus achieving a balance between safety and economy.
[0018] 3. The reuse of steel pipe supports in this invention reduces the generation of construction waste and the consumption of concrete materials. In the process of dismantling the internal concrete supports, diamond wire saw static cutting technology is used to eliminate the huge noise and dust pollution caused by the construction of hydraulic breakers.
[0019] 4. This invention replaces some of the traditional reinforced concrete supports with quick-installing steel pipe supports. The steel pipe supports are factory-customized components, requiring only welding and installation on site, eliminating the need for the lengthy processes of reinforcement binding, formwork erection, and curing required for concrete supports. Attached Figure Description
[0020] The accompanying drawings, which form part of this application, are used to provide a further understanding of the application and to make other features, objects, and advantages of the application more apparent. The illustrative embodiments and descriptions of this application are used to explain the application and do not constitute an undue limitation of the application. In the drawings: Figure 1 This is a structural diagram of the support nodes for the cap beam and internal support template of the present invention; Figure 2 This is a schematic diagram of the construction of the base plate side mold of the present invention; Figure 3 This is a plan view of the formwork support for the pit bottom plate of the present invention; Figure 4 This is a cross-sectional view of the formwork support for the pit bottom plate of the present invention. Detailed Implementation
[0021] To enable those skilled in the art to better understand the present application, the technical solutions in the embodiments of the present application will be clearly and completely described below with reference to the accompanying drawings. Obviously, the described embodiments are only some embodiments of the present application, and not all embodiments. Based on the embodiments in the present application, all other embodiments obtained by those of ordinary skill in the art without creative effort should fall within the scope of protection of the present application.
[0022] It should be noted that the terms "first," "second," etc., in the specification, claims, and accompanying drawings of this application are used to distinguish similar objects and are not necessarily used to describe a specific order or sequence. It should be understood that such data can be interchanged where appropriate for the embodiments of this application described herein. Furthermore, the terms "comprising" and "having," and any variations thereof, are intended to cover non-exclusive inclusion; for example, a process, method, system, product, or apparatus that comprises a series of steps or units is not necessarily limited to those steps or units explicitly listed, but may include other steps or units not explicitly listed or inherent to such processes, methods, products, or apparatus.
[0023] In this application, the terms "upper," "lower," "left," "right," "front," "rear," "top," "bottom," "inner," "outer," "middle," "vertical," "horizontal," "lateral," and "longitudinal" indicate the orientation or positional relationship based on the orientation or positional relationship shown in the accompanying drawings. These terms are primarily for the purpose of better describing this application and its embodiments, and are not intended to limit the indicated device, element, or component to having a specific orientation, or to be constructed and operated in a specific orientation.
[0024] Furthermore, in addition to indicating location or positional relationship, some of the aforementioned terms may also have other meanings. For example, the term "above" may also be used in some cases to indicate a certain dependency or connection relationship. Those skilled in the art can understand the specific meaning of these terms in this application based on the specific circumstances.
[0025] In addition, the term "multiple" should mean two or more.
[0026] It should be noted that, unless otherwise specified, the embodiments and features described in this application can be combined with each other. This application will now be described in detail with reference to the accompanying drawings and embodiments. Example 1:
[0027] A rapid construction method for deep pits in soft soil is described below: 1. Construction of the main foundation pit, the water-stop curtain and support structure for the pit within the basement. (1) After the layout and positioning, the construction of the main foundation pit water-stop and support structure shall be carried out first. The main foundation pit water-stop and support structure can be in the form of triaxial mixing piles + bored cast-in-place piles, or other forms can be adopted according to design requirements or local experience. The construction of triaxial mixing piles should control the mixing sinking and lifting speed, and the cement content should meet the design requirements; the construction of bored cast-in-place piles generally uses mud slurry wall protection, and the hole depth, diameter and steel cage specifications should be strictly constructed according to the drawings.
[0028] (2) Internal supports are generally installed during the excavation of the main foundation pit. Therefore, the water-stop curtain for the pit within the pit should be constructed before the excavation of the main foundation pit. The water-stop curtain for the pit within the pit can be constructed using double-pipe high-pressure jet grouting piles, or other forms can be adopted according to design requirements or local experience. The purpose of using jet grouting piles for the pit within the pit is that the mixing piles around the main foundation pit have not completely and effectively isolated the confined water layer at the bottom of the pit within the pit. If the pit within the pit is excavated directly, there will be a risk of foundation pit heave. Furthermore, if the mixing piles around the main foundation pit completely isolate the confined water layer in the pit within the pit, it will greatly increase the construction cost. Considering both construction safety and economic factors, double-pipe jet grouting piles need to be constructed separately for the pit within the pit to reduce the risk of foundation pit heave during the excavation of the pit within the pit. The double-pipe high-pressure jet grouting piles are constructed using the skip-driving method for each row of holes, that is, spraying one hole every other hole. The interval between spraying adjacent pile holes should not be less than 24 hours. During the construction of the pit-within-pit water-stop curtain, key processes such as pile top elevation, drill rod verticality, grouting pressure and flow rate, air pressure and volume, and jetting lifting speed are strictly controlled.
[0029] 2. Dewatering construction of the foundation pit Wells are installed in the main foundation pit and sub-pits of the basement to drain groundwater. In soft soil areas with silty soil layers, the wells are typically spaced approximately 15 meters apart. The construction of dewatering wells generally follows a process of drilling, installing well casings, backfilling with filter material, washing the wells, and pumping water. The well casings are made of sand-free concrete. Before excavation, the groundwater level is lowered to 1 meter below the excavation surface to facilitate drying operations in the foundation pit.
[0030] 3. Layered excavation of the main foundation pit for the basement. After the construction of the basement main foundation pit retaining structure and pre-dewatering is completed, earthwork excavation will commence. For foundation pits exceeding 5 meters in depth, the construction plan must be reviewed by experts. The construction process must strictly adhere to the plan. Earthwork excavation will be carried out in layers and sections, over-excavation is strictly prohibited, and the soil load at the pit edge will be released symmetrically and evenly to avoid sudden release of local loads, which could cause excessive deformation of the retaining structure due to sudden changes in local load.
[0031] 4. Excavation of the main foundation pit of the basement down to the top of the support piles and breaking the pile heads. After the main foundation pit is excavated to the top of the support piles, the elevation lines of each pile top are marked. A toothless cutter is used to cut the concrete on the surface of the pile along the marked lines to a depth of 30-40mm. To avoid cutting the main reinforcement, the cutting depth should not exceed the thickness of the concrete cover of the pile. A pneumatic pick is used to peel off the concrete cover of the reinforcement above the circumferential cut line from top to bottom and from the outside to the inside, and the reinforcement is slightly bent to facilitate construction. After the pile head is broken off, a crane is used to lift the pile head out, and the reserved concrete strip is manually chiseled away to achieve the pile head elevation required by the design. The loose slag on the pile head is removed and it is washed clean with water.
[0032] 5. Construction of the main foundation pit of the basement, including the capping beam and internal concrete supports. After the pile heads of the retaining piles are removed, reinforced concrete capping beams are installed around the perimeter of the foundation pit, with internal support beams supported at both ends. These, together with the perimeter water-stop curtain and retaining piles, form the entire foundation pit support system. The concrete pouring formwork typically uses 12-15mm thick plywood; secondary back ribs can be 50mm×100mm timber at 300mm intervals, while the main back ribs use φ48mm double steel pipes. The number of vertical rows is determined based on the height of the support beams, generally 2-3 rows. Tie bolts are added to the beam side formwork for fixation, and the bolts are reused with PVC sleeves. After the capping beam and internal support are poured, timely water curing is carried out, with a curing period of no less than 7 days. The structural details of the capping beam and internal support formwork support are as follows: Figure 1 As shown.
[0033] 6. Excavation of pits within pits, breaking pile heads of engineering piles, trench cleaning, and construction of the foundation layer. Only after the capping beam and concrete internal support are completed and reach the design strength can the next step of earthwork excavation be carried out. Earthwork excavation should also follow the principles of layered, block-based, and symmetrical excavation, and over-excavation is strictly prohibited.
[0034] The pile head chiseling is carried out using the circumferential cutting method, with the construction method being the same as in Section 5.2.4. The foundation 20cm to 30cm is cleaned manually to avoid disturbing the foundation or damaging the pile head.
[0035] After manual trenching is completed, the brick formwork for the foundation and sump pit should be laid in a timely manner, along with the surrounding subgrade, to reduce the exposure time of the foundation soil.
[0036] 7. Waterproofing construction of pit-within-a-pit project The preparation of the substrate before waterproofing construction, the construction procedures of each waterproofing layer and the handover between procedures, the water retention after construction, and the construction of the protective layer must all meet the requirements of the design drawings, specifications, and relevant technical regulations. It is essential to understand the performance and technical indicators of the various waterproofing materials used (such as pre-laid reverse-adhesive waterproofing membranes, elastomeric modified bitumen waterproofing membranes, polymer-modified bitumen root-penetration resistant waterproofing membranes, self-adhesive polymer-modified bitumen waterproofing membranes, polyethylene polypropylene waterproofing membranes, cement-based penetrating crystallizers, etc.), identify the key points and difficulties in basement waterproofing construction, especially detailed nodes such as pile heads, high and low spans, internal and external corners, post-pouring strips, and wall sleeves, ensuring that key points are highlighted and controlled during construction.
[0037] 8. Construction of the pit bottom slab and replacement support structure ① Construction of the pit bottom slab: The specifications and grades of the reinforcing bars for the base slab and foundation cap shall be constructed according to the design drawings. Before arrival at the site, a quality and visual inspection and retesting of the raw materials shall be conducted. Mechanical connections shall be used when the diameter of the reinforcing bars is ≥16mm, and lap splices shall be used when d<16mm. The reinforcing bar joint grade shall be Class II, meaning that the tensile strength of the joint shall not be less than the standard value of the tensile strength of the connected reinforcing bars, and it shall possess high ductility and the ability to withstand repeated tension and compression.
[0038] The construction joint for the exterior wall on the base slab is located 300mm from the top of the base slab (500mm in civil defense areas). This 300mm (500mm) high guide wall concrete is poured together with the base slab concrete. The side formwork of the base slab uses a 240mm high brick formwork, and the guide wall is supported by single-sided formwork. To prevent damage to the waterproof membrane, the edge of the base slab bedding layer extends 340mm beyond the edge of the raft slab during construction. (Specific details are as follows...) Figure 2 As shown.
[0039] The side formwork at the sump pit is made of 15mm thick plywood, the secondary joists are made of 50×90mm timber, and the main joists are made of double steel pipes (A48*3.0mm) with back bracing. Figure 3 , Figure 4 As shown.
[0040] The bottom formwork is made of multi-layer plywood, and a wooden box is made according to the size of the pit. The box is placed into the pit, and steel bars are hoisted into the box to prevent the concrete at the bottom of the pit from floating.
[0041] Removal: The formwork for the sump pit can be removed once the concrete strength is sufficient to ensure that its surface and edges will not be damaged during formwork removal. First, remove the diagonal and horizontal braces, then remove the joists and side formwork. Do not use a sledgehammer during formwork removal to prevent the formwork from impacting the concrete and causing cracks. After formwork removal, promptly clean up any adhering materials, and collect and manage all removed components in a timely manner.
[0042] ② Construction of the pit-in-pit replacement support structure 1) The construction sequence of the pit-in-pit replacement support structure is as follows: after the foundation slab is completed, the trench is backfilled with soil according to the structural requirements, C20 plain concrete cushion layer is poured, steel pipe support is reserved and steel plate is embedded during the pouring of the foundation slab concrete, steel pipe support is installed, 300mm thick C20 plain concrete force transmission plate is poured, the concrete strength grade of the replacement support belt reaches 100%, the concrete internal support is removed, and after the overall trench is backfilled, the steel pipe support is removed.
[0043] 2) The pit-within-a-pit fertilizer trench should be backfilled according to structural requirements as follows: ① Trench bottom cleaning and soil testing Before laying the soil, test the soil quality, including the presence of impurities and whether the particle size meets requirements. Take soil samples and use a compaction test to determine if the moisture content of the fill soil is within the controlled range. For cohesive soil, a general test method is to check that it can be formed into a ball by hand and crumbles easily when touched. If the moisture content is too high, loosen it, dry it, or evenly mix in dry soil. If it is too low, pre-moisten it with water. The fill soil should be at its optimum moisture content; the optimum moisture content for plain fill soil should be controlled between 15% and 17%.
[0044] ②Surveying and setting out Before backfilling, make horizontal marks to control the height and thickness of the backfill. Use lines drawn on the exterior walls of the basement and vertical poles to control the backfill height in some areas.
[0045] ③Lay the soil in layers and rake it level. Backfill soil should be laid in layers. The thickness of each layer should be determined according to the soil type, compaction requirements, and equipment performance. Generally, the thickness of each layer is 300mm with a frog-type rammer, and the thickness of each layer should not exceed 250mm when compacted manually; after each layer is laid, it should be leveled.
[0046] ④ Layered compaction and rolling Mechanical compaction is used in this project: two people operate the machine, one holding the tamper and the other operating the power supply to guide the machine. The outer perimeter is compacted first, followed by the middle. The route should not be repeated, and no areas should be missed. The subsequent compaction route should closely follow the previous compaction route, and multiple compaction operations should be performed. Each layer of mechanical compaction is approximately 300mm thick, while each layer of manual compaction is approximately 250mm thick, with a compaction coefficient of 0.94. Silt, topsoil, frozen soil, and construction waste are not allowed for backfilling.
[0047] 3) Construction of steel pipe support for pit-in-pit The specific parameters of the steel pipe supports at the pit-within-a-pit location in this project are as follows: Steel pipe support 1: Spiral welded steel pipe, diameter 609mm, wall thickness 12mm, center elevation -6.200 / 2.350m (absolute elevation), material Q235B. Steel pipe support 2: Spiral welded steel pipe, diameter 426mm, wall thickness 10mm, center elevation -6.200 / 2.350m (absolute elevation), material Q235B.
[0048] Before pouring concrete for the bottom slab of the pit-within-a-pit structure, the pre-embedded parts for the steel support connections are positioned according to the plan. After the pre-embedding is completed, concrete pouring begins. After the concrete for the bottom slab support replacement strip is poured, the steel pipe supports are installed. The steel pipe supports and pre-embedded parts are installed using welding.
[0049] 9. Removal of supports within the pit The first layer of internal concrete support can only be removed after the construction of the pit floor slab and the replacement support structure is completed, and after the floor slab and plain concrete load-bearing strip have reached 80% of their design strength. To ensure the construction period and the safety of the foundation pit, the internal concrete support is removed using a wire saw static cutting method. This cutting operation is fast, low-noise, vibration-free, and produces no dust or exhaust pollution. Furthermore, the cut is straight and smooth, requiring no post-processing and facilitating subsequent treatment of the cut surface. After the concrete blocks are cut, they fall onto the support frame for transport or hoisting.
[0050] When dismantling the concrete internal support of the pit within a pit, a support frame must be erected to ensure on-site construction safety. The frame is erected using a socket-type disc-lock steel pipe support frame. The foundation of the frame is a reinforced concrete slab. The longitudinal spacing of the uprights is 900mm, the transverse spacing is 1500mm, and the step distance is 1500mm. The steps for erecting the support frame for dismantling the concrete internal support are as follows: measuring and setting out, erecting the support frame, placing U-shaped supports, and cutting the concrete internal support after the support frame is erected.
[0051] The above description is merely a preferred embodiment of this application and is not intended to limit this application. Various modifications and variations can be made to this application by those skilled in the art. Any modifications, equivalent substitutions, improvements, etc., made within the spirit and principles of this application should be included within the protection scope of this application.
Claims
1. A rapid construction method for deep pits in soft soil, characterized in that, Includes the following steps: S1: Construction of the main foundation pit water-stop curtain and support piles, and before the excavation of the main foundation pit, an independent double-pipe high-pressure jet grouting pile water-stop curtain is constructed at the design position of the pit-in-pit. S2: Install pipe wells in the main foundation pit and the pit within the pit to dewater the groundwater level and lower it to a set distance below the current excavation surface; S3: Excavate the main foundation pit to the top elevation of the support piles, break the pile heads of the support piles, and construct the reinforced concrete cap beam and the first layer of concrete internal support. S4: After the concrete internal support reaches the preset strength, the pit is excavated in layers and sections, and after manual cleaning, a C20 plain concrete cushion layer and brick formwork are constructed. S5: Construct a waterproof layer on the cushion layer, tie reinforcing bars, pour concrete for the pit bottom slab, and pre-embed steel plate connectors in the bottom slab; S6: Backfill soil in the construction pit and C20 plain concrete force transfer plate strip, so that the bottom slab and the support piles form an integral force-bearing system. S7: After the strength of the force transmission plate belt reaches the preset strength, the spiral welded steel pipe support is welded and installed on the pre-embedded steel plate connector, and the prestress is applied to the steel pipe support by hydraulic jack. S8: After the strength of the force transmission plate belt reaches 100%, the concrete internal support is removed by static cutting with a wire saw. S9: The vertical structure of the construction pit is filled with the entire trench after the main structure reaches the design strength, and finally the steel pipe support is removed.
2. The rapid construction method for deep pits in soft soil according to claim 1, characterized in that, In step S1, the construction of the double-tube high-pressure jet grouting pile water-stop curtain adopts the skip-driving method, that is, spraying one hole every other hole, and the interval between spraying construction of adjacent pile holes is not less than 24 hours. The main foundation pit support piles are bored cast-in-place piles, with mud slurry used for hole formation and the mud slurry specific gravity controlled between 1.15 and 1.25; the main foundation pit water-stop curtain is a triaxial mixing pile with a cement content of 20%, a water-cement ratio of 1.5, a sinking speed of no more than 1 m / min, and a lifting speed of no more than 2 m / min.
3. The rapid construction method for deep pits in soft soil according to claim 1, characterized in that, In step S2, the well casing is made of sand-free concrete and the filter material is crushed stone. In the silty soil layer of soft soil areas, the well spacing is 15m. During precipitation, the groundwater level change rate is controlled to not exceed 500mm / d and the cumulative change amount does not exceed 1000mm.
4. The rapid construction method for deep pits in soft soil according to claim 1, characterized in that, In step S3, the pile head of the support pile is removed by the ring cutting method. The specific steps are as follows: First, a toothless cutting machine is used to cut around the design elevation, and the cutting depth does not exceed the thickness of the concrete protective layer of the pile body; then, a pneumatic pick is used to peel off the steel reinforcement protective layer above the ring cutting line from top to bottom; finally, the pile head is lifted out and the reserved concrete is manually chiseled away to the design elevation.
5. A rapid construction method for deep pits in soft soil according to claim 1, characterized in that, During the excavation of the pit within the pit in step S4, a 20-30cm thick soil layer is left for manual cleaning during mechanical excavation; the brick formwork is constructed with solid shale bricks, and the edge of the bedding layer extends beyond the edge of the raft slab to protect the waterproof layer.
6. A rapid construction method for deep pits in soft soil according to claim 1, characterized in that, In step S5, the waterproof layer uses pre-laid reverse-adhesive waterproof membrane, and cement-based penetrating crystalline waterproof coating is applied to the pile head. Water-swellable waterstop strips are installed around the pile head. When the diameter of the bottom plate reinforcement is greater than or equal to the set specification, straight threaded sleeve mechanical connection is used, and the joint grade is level II. The construction joint of the external wall is left above the bottom plate, and the guide wall is poured together with the bottom plate concrete.
7. A rapid construction method for deep pits in soft soil according to claim 1, characterized in that, The construction quality control method for backfilling soil in step S6 is as follows: before backfilling, the optimal moisture content of the soil is determined and controlled within the range of 15%-17%; a frog-type rammer is used for layered compaction.
8. A rapid construction method for deep pits in soft soil according to claim 1, characterized in that, In step S7, the spiral welded steel pipe support includes a first steel pipe support with a wall thickness of 12mm and a second steel pipe support with a wall thickness of 10mm; the size of the embedded steel plate connector is 700mm×700mm×12mm; the prestress is applied by a hydraulic jack, and the pre-applied axial force is 70% of the design axial force.
9. A rapid construction method for deep pits in soft soil according to claim 1, characterized in that, Before removing the concrete internal support by the wire saw static cutting method in step S8, a socket-type disc-lock steel pipe support frame must be erected. The foundation of the frame is a reinforced concrete base plate. Before cutting, the support beam is first stress-released, and the cut blocks are placed on the frame. After being disassembled, they are hoisted off the site. During the static wire saw cutting operation, the foundation pit support structure is monitored in real time to control the rate of change of horizontal displacement at the pile top to not exceed 4 mm / d, the rate of change of vertical displacement of the surrounding roads to not exceed 3 mm / d, and the rate of change of axial force of the support to not exceed 400 kN / d.
10. A rapid construction method for deep pits in soft soil according to claim 1, characterized in that, Before the overall backfilling of the trench is completed in step S9, the steel pipe support is always kept under stress. After the overall backfilling of the trench is completed and the main structure reaches the design strength, the prestress of the steel pipe support is first released, then the steel pipe support is cut off, and finally the support pile is removed.