Pipeline hanging device

By designing a detachable pipeline hanging device, the problem of heavy fixed weight of pipelines and poor space utilization in ships is solved, achieving lightweight and improved stability, and adapting to the installation needs of small spaces.

CN118775631APending Publication Date: 2024-10-15CSSC HUANGPU WENCHONG SHIPBUILDING CO LTD
View PDF 8 Cites 0 Cited by

Patent Information

Application Number
CN202411153414.8
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-21
Publication Date
2024-10-15

AI Technical Summary

Technical Problem

In the field of ships, the fixation of pipes, air ducts, cables and other components needs to be easy to disassemble, and it is necessary to reduce the weight of the ship and make reasonable use of space, especially in small spaces to adapt to different installation conditions.

Method used

A pipeline hanging device is designed, which includes a detachable hanger, ceiling component and pipe clamp component. It is connected through fasteners and through holes to realize the lightweight and shape adjustment of the connecting rod to adapt to the installation needs of different spaces.

Benefits of technology

It achieves convenient disassembly and weight reduction of pipelines, improves the stability of the hanger, and can flexibly fix pipelines in small spaces to meet the needs of different installation spaces.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118775631A_ABST
    Figure CN118775631A_ABST
Patent Text Reader

Abstract

The invention belongs to the technical field of ship pipelines, and discloses a pipeline hanging device. The pipeline hanging device comprises a hanging bracket, a suspended ceiling assembly and a pipe clamp assembly. The hanging bracket comprises a plurality of connecting rods and a plurality of first fastening pieces, the connecting rods are detachably connected into the whole hanging bracket through the first fastening pieces, a plurality of through holes are formed in the connecting rods, and the first fastening pieces are arranged in the through holes in a penetrating mode respectively. The suspended ceiling assembly comprises a plurality of suspended ceiling connecting pieces, the suspended ceiling connecting pieces are detachably connected to the top of the hanging bracket through second fastening pieces, and the second fastening pieces are arranged in the through holes in a penetrating mode. The pipe clamp assembly is detachably connected to the bottom of the hanging bracket, the pipe clamp assembly comprises a first fastener and a second fastener, the first fastener and the second fastener are sequentially connected end to end, a constraint space is defined by the first fastener and the second fastener, and the first fastener and the second fastener are detachably connected.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of ship pipelines, and in particular to a pipeline hanging device. Background Art

[0002] In the shipbuilding field, pipes, ducts, cables and other components need to be fixed on the ship.

[0003] Because these components need to be maintained or replaced, devices that fix the components are needed to facilitate disassembly; at the same time, ship weight control is one of the key points of ship construction. Reducing the weight of ship outfitting can reduce ship energy consumption, so it is necessary to use lightweight devices to reduce ship weight; in addition, the layout of these components requires rational use of space and reduced space occupancy, so the devices need to adapt to different spaces, especially small spaces.

[0004] To this end, a pipeline hanging device is provided to solve the above problems. Summary of the invention

[0005] The object of the present invention is to provide a pipeline hanging device which is easy to disassemble, lightens the weight, and can adjust the shape according to the installation space to adapt to the installation space.

[0006] To achieve this object, the present invention adopts the following technical solutions:

[0007] Pipeline hanging device, including:

[0008] A hanger, the hanger comprising a plurality of connecting rods and a plurality of first fasteners, the connecting rods being detachably connected to form the hanger as a whole through the first fasteners, the connecting rods being provided with a plurality of through holes, the first fasteners being respectively passed through the through holes;

[0009] A ceiling assembly, comprising a plurality of ceiling connectors, each of which is detachably connected to the top of the hanger via a second fastener, and the second fastener is inserted through the through hole;

[0010] A pipe clamp assembly is detachably connected to the bottom of the hanger, and comprises a first fastener and a second fastener, wherein the first fastener and the second fastener are connected end to end in sequence and enclose a constraint space, and the first fastener and the second fastener are detachably connected.

[0011] Optionally, the first fastener includes a fastening bolt, and / or the second fastener includes a fastening bolt.

[0012] Optionally, each of the connecting rods includes a first vertical rod, a second vertical rod and a transverse rod, one end of the transverse rod is connected to the lower end of the first vertical rod via the first fastener, and the other end is connected to the lower end of the second vertical rod via the first fastener, the pipe clamp assembly is detachably connected to the transverse rod, and the top of the first vertical rod and the top of the second vertical rod are both connected to the ceiling connector.

[0013] Optionally, it also includes a connecting screw and a limiting nut, wherein the connecting screw is arranged on the upper part of the first fastener, the connecting screw passes through the through hole on the transverse rod from bottom to top, and the limiting nut is threadedly connected to the connecting screw and pressed against the side of the transverse rod away from the first fastener.

[0014] Optionally, the ceiling connector includes a flat iron clamp, which includes a first folding plate portion and a second folding plate portion connected to each other, the second folding plate portion extends in the same direction as the first vertical rod or the second vertical rod, and the first folding plate portion is horizontal.

[0015] Optionally, a riveted connector is provided on the first folding plate portion.

[0016] Optionally, the first vertical rod and the second vertical rod both extend in the vertical direction and are arranged side by side in the horizontal direction, and the transverse rod extends in the horizontal direction.

[0017] Optionally, the pipe clamp assembly further includes two locking bolts, one end of the first fastener and one end of the second fastener are connected via the locking bolts, and the other end of the first fastener and the other end of the second fastener are connected via the locking bolts.

[0018] Optionally, the pipe clamp assembly further includes a buffer sleeve, and the buffer sleeve is arranged on the first fastener and the second fastener.

[0019] Optionally, the through hole comprises a waisted round hole.

[0020] Beneficial effects of the present invention:

[0021] The pipeline hanging device provided by the present invention has a first fastener and a second fastener enclosing a restrained space, which is convenient for accommodating pipelines; the first fastener and the second fastener are detachably connected, which is convenient for installing or removing pipelines in the restrained space; the pipe clamp assembly is detachably connected to the bottom of the hanger, which is convenient for removing the pipe clamp assembly itself; connecting multiple ceiling connectors to the ship structure is beneficial to improving the stability of the hanger; multiple through holes on the connecting rod are beneficial to reducing the weight of the connecting rod itself, and the through holes provide connection positions for the first fastener and the second fastener, without the need to arrange additional connection points. The connecting rods are connected by the first fastener passing through the through hole, which is convenient for disassembly and assembly, and each connecting rod can be adaptively assembled into hangers of different shapes, that is, the adjustment of the hanger structure is achieved, which is beneficial to adapt to the installation space and fix the pipeline in a small space. BRIEF DESCRIPTION OF THE DRAWINGS

[0022] Figure 1 It is a structural schematic diagram of a pipeline hanging device provided by an embodiment of the present invention;

[0023] Figure 2 is an exploded view of a pipe clamp assembly, a connecting screw and a limiting nut provided in an embodiment of the present invention;

[0024] Figure 3 is a front view of a flat iron clamp provided by an embodiment of the present invention;

[0025] Figure 4 is a side view of a flat iron clamp provided by an embodiment of the present invention;

[0026] Figure 5 is a top view of a first fastener provided by an embodiment of the present invention;

[0027] Figure 6 It is a cross-sectional schematic diagram of a buffer sleeve provided in an embodiment of the present invention.

[0028] In the figure:

[0029] 1. Ship structure;

[0030] 100, hanger; 101, first vertical rod; 102, second vertical rod; 103, transverse rod; 104, through hole; 105, first fastener;

[0031] 200, ceiling assembly; 210, flat iron clip; 211, first folding plate portion; 212, second folding plate portion; 220, second fastener; 230, riveted connector;

[0032] 300, pipe clamp assembly; 301, first fastener; 302, second fastener; 303, locking bolt; 304, buffer sleeve; 305, perforation;

[0033] 400, connecting screw;

[0034] 500. Limit nut. DETAILED DESCRIPTION

[0035] The present invention will be further described in detail below in conjunction with the accompanying drawings and embodiments. It is to be understood that the specific embodiments described herein are only used to explain the present invention, rather than to limit the present invention. It should also be noted that, for ease of description, only parts related to the present invention, rather than all structures, are shown in the accompanying drawings.

[0036] In the description of the present invention, unless otherwise clearly specified and limited, the terms "connected", "connected", and "fixed" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection or an indirect connection through an intermediate medium, it can be the internal connection of two elements or the interaction relationship between two elements. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.

[0037] In the present invention, unless otherwise clearly specified and limited, a first feature being "above" or "below" a second feature may include that the first and second features are in direct contact, or may include that the first and second features are not in direct contact but are in contact through another feature between them. Moreover, a first feature being "above", "above" and "above" a second feature includes that the first feature is directly above and obliquely above the second feature, or simply indicates that the first feature is higher in level than the second feature. A first feature being "below", "below" and "below" a second feature includes that the first feature is directly below and obliquely below the second feature, or simply indicates that the first feature is lower in level than the second feature.

[0038] In the description of this embodiment, the terms "upper", "lower", "right", etc., directions or positional relationships are based on the directions or positional relationships shown in the drawings, and are only for the convenience of description and simplification of operation, rather than indicating or implying that the device or element referred to must have a specific direction, be constructed and operated in a specific direction, and therefore cannot be understood as limiting the present invention. In addition, the terms "first" and "second" are only used to distinguish in the description and have no special meaning.

[0039] like Figure 1 As shown, this embodiment provides a pipeline hanging device. Specifically, the pipeline hanging device includes a hanger 100, a ceiling assembly 200 and a pipe clamp assembly 300.

[0040] The hanger 100 includes a plurality of connecting rods and a plurality of first fasteners 105 . The connecting rods are detachably connected to form the whole hanger 100 through the first fasteners 105 . The connecting rods are provided with a plurality of through holes 104 , and the first fasteners 105 are respectively passed through the through holes 104 .

[0041] The ceiling assembly 200 includes a plurality of ceiling connectors, each of which is detachably connected to the top of the hanger 100 via a second fastener 220 , and the second fastener 220 is inserted into the through hole 104 .

[0042] The pipe clamp assembly 300 is detachably connected to the bottom of the hanger 100. The pipe clamp assembly 300 includes a first fastener 301 and a second fastener 302. The first fastener 301 and the second fastener 302 are connected end to end in sequence to form a restraining space. The first fastener 301 and the second fastener 302 are detachably connected.

[0043] The first fastener 301 and the second fastener 302 enclose a restraining space, which is convenient for accommodating and binding pipelines; the first fastener 301 and the second fastener 302 are detachably connected, which is convenient for installing or removing pipelines in the restraining space; the pipe clamp assembly 300 is detachably connected to the bottom of the hanger 100, which is convenient for removing the pipe clamp assembly 300 itself; connecting multiple ceiling connectors to the ship structure 1 is conducive to improving the stability of the hanger 100; multiple through holes 104 on the connecting rod are conducive to reducing the weight of the connecting rod itself, and the through holes 104 provide connection points for the first fastener 105 and the second fastener 220, without the need to arrange additional connection points. The first fastener 105 passes through the through hole 104 to connect the connecting rods, which is convenient for disassembly and assembly. By connecting different through holes 104 and adjusting the relative positions of the connecting rods, each connecting rod can be adaptively assembled into a hanger 100 of different shapes, that is, the structural form of the hanger 100 can be adjusted, which is conducive to adapting to the installation space and fixing pipelines in a small space. In this embodiment, the shipboard structure 1 is specifically a plate or a bulkhead.

[0044] The number of connecting rods included in the hanger 100 may be 2, 3 or more. The connecting rods can be assembled into hangers 100 of different shapes as required to adapt to different installation spaces.

[0045] The shape formed by the first fastener 301 and the second fastener 302 is not limited and depends on the cross-sectional form of the pipeline to be fixed. For example, it can be circular, square, irregular, etc.

[0046] The number of the pipe clamp assemblies 300 is not limited here, and can be one or more, and can be installed on the hanger 100 according to specific needs.

[0047] Optionally, the connecting rod is made of aluminum alloy, which has high strength and light weight, thus facilitating lightweighting.

[0048] Optionally, the first fastener 105 includes a fastening bolt. That is, the fastening bolt passes through the through holes 104 of the two connecting rods to connect the two connecting rods. The fastening bolt is used for connection, and the connection is reliable, which facilitates the disassembly and assembly of the hanger 100 itself, thereby facilitating the formation of hangers 100 of different shapes.

[0049] Similarly, the second fastener 220 includes a fastening bolt. That is, the fastening bolt connects the ceiling connector and the hanger 100. The fastening bolt is used for connection, and the connection is reliable, and it is convenient to disassemble and assemble the hanger 100 from the ceiling connector.

[0050] like Figure 1 As shown, optionally, each connecting rod includes a first vertical rod 101, a second vertical rod 102 and a transverse rod 103, one end of the transverse rod 103 is connected to the lower end of the first vertical rod 101 through a first fastener 105, and the other end is connected to the lower end of the second vertical rod 102 through the first fastener 105, the pipe clamp assembly 300 is detachably connected to the transverse rod 103, and the top of the first vertical rod 101 and the top of the second vertical rod 102 are both connected with a ceiling connector. In this embodiment, the hanger 100 is formed by connecting the first vertical rod 101, the second vertical rod 102 and the transverse rod 103 through two first fasteners 105. The structure of the hanger 100 is simple, and the first vertical rod 101 and the second vertical rod 102 are respectively connected to the ship structure 1 through the ceiling connector, and the stability is high.

[0051] like Figure 1 and Figure 2 As shown, in order to realize the detachable connection of the pipeline assembly on the transverse rod 103, optionally, the pipeline hanging device further includes a connecting screw 400 and a limiting nut 500, the connecting screw 400 is arranged on the upper part of the first fastener 301, the connecting screw 400 passes through the through hole 104 on the transverse rod 103 from bottom to top, and the limiting nut 500 is threadedly connected to the connecting screw 400 and pressed against the side of the transverse rod 103 away from the first fastener 301. Through the cooperation of the connecting screw 400, the limiting nut 500 and the transverse rod 103, the pipeline assembly is reliably connected and easy to disassemble, which is convenient for pipeline installation and maintenance.

[0052] like Figure 1 , Figure 3 and Figure 4As shown, optionally, the ceiling connector includes a flat iron clip 210, and the flat iron clip 210 includes a first folded plate portion 211 and a second folded plate portion 212 connected to each other, the second folded plate portion 212 extends in the same direction as the first vertical rod 101 or the second vertical rod 102, and the first folded plate portion 211 is horizontal. That is, the second folded plate portion 212 of the flat iron clip 210 connected to the first vertical rod 101 extends in the same direction as the first vertical rod 101, and fits each other in the horizontal direction, and is then fixed by the second fastener 220. Similarly, the second folded plate portion 212 of the flat iron clip 210 connected to the second vertical rod 102 extends in the same direction as the second vertical rod 102, and fits each other in the horizontal direction, and is then fixed by the second fastener 220. In this embodiment, the first folded plate portion 211 is perpendicular to the second folded plate portion 212. In this embodiment, the first folded plate portion 211 and the second folded plate portion 212 are integrally formed, and the structural strength is high.

[0053] Optionally, a riveted connector 230 is provided on the first folded plate portion 211. The flat iron clip 210 is fixed to the ship structure 1 through the riveted connector 230. In this embodiment, the riveted connector 230 includes a rivet, which is connected to the ship structure 1.

[0054] like Figure 1 As shown, optionally, the first vertical rod 101 and the second vertical rod 102 both extend in the vertical direction and are arranged side by side in the horizontal direction, and the transverse rod 103 extends in the horizontal direction. In other words, the extension direction of the first vertical rod 101 and the second vertical rod 102 is the same as the gravity direction, and the overall stability of the hanger 100 is good. In this embodiment, the pipe clamp assembly 300 is centrally arranged on the transverse rod 103 in the horizontal direction, so that the overall structure of the hanger 100 is stable.

[0055] like Figure 2 As shown, optionally, the pipe clamp assembly 300 further includes two locking bolts 303, one end of the first fastener 301 and one end of the second fastener 302 are connected by the locking bolts 303, and the other end of the first fastener 301 and the other end of the second fastener 302 are connected by the locking bolts 303. Specifically, the first fastener 301 and the second fastener 302 are both semi-annular fasteners, and two through holes 305 are respectively provided at both ends of the first fastener 301, and two through holes 305 are respectively provided at both ends of the second fastener 302. The locking bolts 303 pass through the through holes 305 to connect the first fastener 301 and the second fastener 302, so as to facilitate the disassembly and assembly of the pipeline. In this embodiment, the first fastener 301 and the second fastener 302 form a clamp structure as a whole.

[0056] like Figure 2 , Figure 5 and Figure 6As shown, optionally, the pipe clamp assembly 300 further includes a buffer sleeve 304, which is disposed on the first fastener 301 and the second fastener 302. Specifically, the buffer sleeve 304 is located inside the first fastener 301 and the second fastener 302, and the buffer sleeve 304 has a clamping groove on the edge in the axial direction, so as to clamp the edge of the first fastener 301 and the second fastener 302. The pipeline is directly connected to the buffer sleeve 304 to protect the pipeline. The buffer sleeve 304 can be a rubber sleeve.

[0057] like Figure 1 As shown, optionally, the through hole 104 includes a waist-shaped hole, which can further improve the lightness of the hanger 100, and the waist-shaped hole has a certain length, which further improves the flexibility of the setting position of the first fastener 105, and is convenient for adjusting the shape of the hanger 100. Specifically, a plurality of waist-shaped holes are opened along the length direction of the connecting rod, and the length direction of the waist-shaped holes is parallel to the length direction of the connecting rod.

[0058] Obviously, the above embodiments of the present invention are merely examples for clearly illustrating the present invention, and are not intended to limit the embodiments of the present invention. For those skilled in the art, various obvious changes, readjustments and substitutions can be made without departing from the protection scope of the present invention. It is not necessary and impossible to list all the embodiments here. Any modifications, equivalent substitutions and improvements made within the spirit and principles of the present invention should be included in the protection scope of the claims of the present invention.

Claims

1. Pipeline hanging device, It is characterized in that include: A hanger (100), the hanger (100) comprising a plurality of connecting rods and a plurality of first fasteners (105), the connecting rods being detachably connected to form the hanger (100) as a whole via the first fasteners (105), the connecting rods being provided with a plurality of through holes (104), and the first fasteners (105) being respectively inserted into the through holes (104); A ceiling assembly (200) comprising a plurality of ceiling connectors, each of the ceiling connectors being detachably connected to the top of the hanger (100) via a second fastener (220), wherein the second fastener (220) is disposed through the through hole (104); A pipe clamp assembly (300) is detachably connected to the bottom of the hanger (100), and the pipe clamp assembly (300) comprises a first fastener (301) and a second fastener (302), wherein the first fastener (301) and the second fastener (302) are connected end to end in sequence and enclose a constrained space, and the first fastener (301) and the second fastener (302) are detachably connected.

2. The pipeline hanging device according to claim 1, It is characterized in that The first fastener (105) includes a fastening bolt, and / or the second fastener (220) includes a fastening bolt.

3. The pipeline hanging device according to claim 1, It is characterized in that Each of the connecting rods comprises a first vertical rod (101), a second vertical rod (102) and a transverse rod (103); one end of the transverse rod (103) is connected to the lower end of the first vertical rod (101) via the first fastener (105), and the other end is connected to the lower end of the second vertical rod (102) via the first fastener (105); the pipe clamp assembly (300) is detachably connected to the transverse rod (103); the top of the first vertical rod (101) and the top of the second vertical rod (102) are both connected to the ceiling connector.

4. The pipeline hanging device according to claim 3, It is characterized in that It also includes a connecting screw (400) and a limiting nut (500), wherein the connecting screw (400) is arranged on the upper part of the first fastener (301), and the connecting screw (400) passes through the through hole (104) on the transverse rod (103) from bottom to top, and the limiting nut (500) is threadedly connected to the connecting screw (400) and pressed against the side of the transverse rod (103) away from the first fastener (301).

5. The pipeline hanging device according to claim 3, It is characterized in that The ceiling connecting piece comprises a flat iron clamp (210), wherein the flat iron clamp (210) comprises a first folding plate portion (211) and a second folding plate portion (212) which are connected to each other, wherein the second folding plate portion (212) extends in the same direction as the first vertical rod (101) or the second vertical rod (102), and the first folding plate portion (211) is horizontal.

6. The pipeline hanging device according to claim 5, It is characterized in that A riveted connection piece (230) is provided on the first folding plate portion (211).

7. The pipeline hanging device according to claim 3, It is characterized in that The first vertical rod (101) and the second vertical rod (102) both extend in the vertical direction and are arranged side by side in the horizontal direction, and the transverse rod (103) extends in the horizontal direction.

8. The pipeline hanging device according to claim 1, It is characterized in that The pipe clamp assembly (300) further comprises two locking bolts (303), one end of the first fastener (301) and one end of the second fastener (302) are connected via the locking bolts (303), and the other end of the first fastener (301) and the other end of the second fastener (302) are connected via the locking bolts (303).

9. The pipeline hanging device according to any one of claims 1 to 8, It is characterized in that The pipe clamp assembly (300) further comprises a buffer sleeve (304), wherein the buffer sleeve (304) is arranged on the first fastener (301) and the second fastener (302).

10. The pipeline hanging device according to any one of claims 1 to 8, It is characterized in that The through hole (104) comprises a waisted circular hole.

Citation Information

Patent Citations

  • Adjustable hanger for marine PE (polyethylene) pipes

    CN203131230U

  • Water pipe hanging bracket structure for ship

    CN204254033U

  • Mechanical and electrical installation synthesizes support

    CN206958399U

  • Connecting structure of heavy anti-sliding assembly type comprehensive pipeline support hanger

    CN213299035U

  • Assembled gantry support hanger

    CN215110933U