Power grid supply chain abnormity monitoring method and system

By building a core business indicator system and monitoring instructions, the problem of incomplete statistical analysis of data in power grid supply chain operations has been solved, risk prevention capabilities and operational efficiency have been improved, and the compliance of the supply chain and the comprehensiveness of data analysis have been ensured.

CN118780654AInactive Publication Date: 2024-10-15STATE GRID SHANGHAI MUNICIPAL ELECTRIC POWER CO +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202310369739.9
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2023-04-07
Publication Date
2024-10-15
Estimated Expiration
Not applicable · inactive patent

AI Technical Summary

Technical Problem

There are incomplete statistical analysis of data and insufficient compliance analysis in the operation of the power grid supply chain. In particular, there are statistical analysis shortcomings in waste, settlement, quality and other links, resulting in insufficient statistics of risk points and affecting operational efficiency and risk prevention capabilities.

Method used

Build a core business indicator system, including business compliance, bidding business compliance, contract business compliance, warehousing business compliance and waste business compliance indicators, and build multiple monitoring instructions based on these indicators, which will be executed after triggering The corresponding disposal strategy ensures the comprehensiveness and timeliness of data analysis through indicator value monitoring, trend monitoring and business scenario monitoring.

Benefits of technology

By quantifying the core business of the supply chain and clarifying key node disposal strategies, the risk prevention capabilities of supply chain operations and the depth of data analysis are improved to ensure the efficiency and compliance of supply chain operations.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118780654A_ABST
    Figure CN118780654A_ABST
Patent Text Reader

Abstract

The invention relates to a power grid supply chain abnormity monitoring method and system, and the method comprises the steps: constructing a core business index system which comprises a business compliance index, a bidding business compliance index, a contract business compliance index, a storage business compliance index, and a waste business compliance index; constructing a plurality of monitoring instructions based on the core business index system; and when any monitoring instruction is triggered, executing the processing strategy corresponding to the monitoring instruction. Compared with the prior art, the index system is constructed, so that the supply chain core business is quantified, the supply chain business and key node processing strategy is clarified by combing the key indexes of the core business, the supply chain core business abnormity monitoring is enhanced, and the supply chain operation risk prevention capability is improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of power grid supply chain management, and in particular to a power grid supply chain abnormality monitoring method and system. Background Art

[0002] Building a modern smart supply chain system with power grid characteristics can fully integrate upstream and downstream resources and promote changes in supply chain quality and efficiency. With the practical operation and continuous iteration and update of the modern smart supply chain, the Shanghai Supply Chain Operation Center ESC has gradually entered the stage of normalized operation and in-depth application. Power grid companies have formed a set of ESC supply chain operation platforms based on the data base of the entire supply chain and multi-scenario collaborative linkage, which has achieved coverage of five major sectors, nine professional business scenarios and key operation data, including intelligent procurement, digital logistics, panoramic quality control, collaborative management and control, and operation supervision, providing a strong platform guarantee for the deepening of supply chain operations.

[0003] However, with the continuous development of business, the following problems still exist in the supply chain operation of power grid enterprises: in terms of statistical analysis of business operation data, the compliance control analysis of key business nodes is not comprehensive enough, and there are still shortcomings in statistical analysis of waste, settlement, quality and other links. In terms of compliance analysis, there are only statistics on two funds and one model, overlong orders, overdue warnings for inventory turnover materials, and 54 risk points at the headquarters. In general, the operation analysis and monitoring of the power grid supply chain are still incomplete and inadequate. Summary of the invention

[0004] The purpose of the present invention is to provide a method and system for monitoring power supply chain abnormalities in order to overcome the defects of the above-mentioned prior art.

[0005] The purpose of the present invention can be achieved by the following technical solutions:

[0006] According to a first aspect of the present invention, a method for monitoring abnormality in a power grid supply chain is provided, comprising:

[0007] Constructing a core business indicator system, which includes business compliance indicators, bidding business compliance indicators, contract business compliance indicators, warehousing business compliance indicators and waste business compliance indicators;

[0008] Based on the core business indicator system, multiple monitoring instructions are constructed;

[0009] When any monitoring instruction is triggered, the handling strategy corresponding to the monitoring instruction is executed.

[0010] Furthermore, the business compliance index includes two secondary indicators: the accuracy of two-level catalog procurement execution and the accuracy of material plan submission. The calculation formula is as follows:

[0011] The execution accuracy rate of the two-level procurement catalogue = 1-(the number of items in the two-level procurement catalogue that are not fully executed / the number of items in the two-level procurement catalogue that should be executed);

[0012] Accuracy rate of material plan submission = (actual quantity received - quantity of project returned materials) / quantity of material requirements reported in the purchase requisition.

[0013] Furthermore, the bidding compliance index includes four secondary indicators: bidding execution standardization rate, contract signing standardization rate, bid winning amount accuracy rate, and bid cancellation execution standardization rate. The calculation formula is as follows:

[0014] Bidding execution standardization rate = 1-(∑The number of non-bidding procurement contracts obtained by splitting contracts with a total amount exceeding the bidding line + the number of non-bidding procurement contracts with a contract amount exceeding the bidding line + the number of contracts with a contract amount exceeding the bidding line after changes without justifiable reasons) / the total number of contracts signed;

[0015] Contract signing standardization rate = 1-(number of items where the bid winning time is later than the contract signing time + number of items in the contract where payment is made in advance) / total number of contracts signed;

[0016] Winning bid amount accuracy rate = number of items with the same winning bid amount and bid amount during the statistical period / number of winning bid items during the statistical period;

[0017] The compliance rate of bid cancellation = 1-number of items that should be cancelled but were not / total number of winning bids.

[0018] Furthermore, the contract business compliance index includes two secondary indicators: the timeliness rate of e-commerce settlement and the accuracy rate of contract signing suppliers. The calculation formula is as follows:

[0019] Timely settlement rate of e-commerce = total amount of timely payments for e-commerce orders / total amount of payables for e-commerce orders;

[0020] Accuracy rate of contracted suppliers = number of items that are consistent between contracted suppliers and winning bidders during the statistical period / number of winning bid items during the statistical period.

[0021] Furthermore, the compliance indicators of the warehousing business include 8 secondary indicators: non-registered warehouse inventory turnover rate, empty warehouse rate, online regular inventory timeliness rate, inventory situation difference rate, false balance inventory rate, overdue rate of deposited materials transferred to own materials, professional warehouse inventory turnover rate, overdue rate of overdue unutilized inventory, and the calculation formula is as follows:

[0022] Non-registered warehouse inventory turnover rate = non-registered warehouse annual outbound amount / non-registered warehouse average inventory amount;

[0023] Empty warehouse ratio = actual number of warehouses used / total number of warehouses;

[0024] Timely rate of online regular inventory counting = number of warehouses counted in time / total number of warehouses;

[0025] Inventory situation difference rate = difference amount in inventory result / total amount of all materials counted;

[0026] False balance profit rate = number of false balance profit items / total number of items;

[0027] Overdue rate of deposited materials converted to owned materials = number of items of deposited materials that have been in stock for more than P days / total number of items of deposited materials in stock, where P is the set overdue time threshold;

[0028] Professional warehouse inventory turnover rate = professional warehouse annual outbound amount / professional warehouse average inventory amount;

[0029] The overdue rate of unprofitable pool = the number of entries that exceed the profit pool maintenance time K days / the total number of profit pool entries, where K is the set control cycle.

[0030] Furthermore, the compliance index of the waste business includes one secondary index: the execution rate of the demolition and recycling plan, and the calculation formula is:

[0031] Execution rate of demolition and recycling plan = actual warehousing quantity / approved initial demolition quantity.

[0032] Furthermore, the monitoring instructions include:

[0033] Indicator numerical monitoring: set multiple numerical intervals for each indicator under the core business indicator system, set interval handling strategies for each indicator in each numerical interval, monitor the numerical intervals in which the indicator values ​​under the core business indicator system are located, and execute the interval handling strategies corresponding to the numerical intervals.

[0034] Furthermore, the monitoring instructions include:

[0035] Indicator trend monitoring: set a monitoring period and fluctuation range for each indicator under the core business indicator system, set a fluctuation handling strategy for each indicator, detect whether the numerical fluctuation of the indicators under the core business indicator system in the continuous monitoring period exceeds the fluctuation range, and if so, execute the fluctuation handling strategy of the indicator.

[0036] Furthermore, the monitoring instructions include:

[0037] Business scenario monitoring, setting multiple business scenarios, each business scenario is associated with at least one indicator under the core business indicator system, trigger conditions are set for each business scenario, and scenario handling strategies are set for each business scenario. Monitor whether multiple indicators associated with the business scenario meet the preset trigger conditions, and execute the scenario handling strategy of the business scenario when they are met.

[0038] According to a second aspect of the present invention, there is provided a power grid supply chain abnormality monitoring system, comprising:

[0039] An indicator system construction module is used to construct a core business indicator system, wherein the core business indicator system includes business compliance indicators, bidding business compliance indicators, contract business compliance indicators, warehousing business compliance indicators and waste business compliance indicators;

[0040] An instruction construction module, which constructs multiple monitoring instructions based on the core business indicator system;

[0041] The execution module executes the disposal strategy corresponding to any monitoring instruction when any monitoring instruction is triggered.

[0042] Compared with the prior art, the present invention has the following beneficial effects:

[0043] Build an indicator system to quantify the core business of the supply chain. By sorting out the key indicators of the core business, clarify the supply chain business and key node handling strategies, strengthen the monitoring of abnormalities in the core business of the supply chain, and enhance the risk prevention capabilities of supply chain operations. BRIEF DESCRIPTION OF THE DRAWINGS

[0044] Figure 1 This is a schematic diagram of the core business indicator system. DETAILED DESCRIPTION

[0045] The present invention is described in detail below in conjunction with the accompanying drawings and specific embodiments. This embodiment is implemented on the premise of the technical solution of the present invention, and a detailed implementation method and a specific operation process are given. Obviously, the described embodiment is only an embodiment of a part of the present invention, not all embodiments, and the protection scope of the present invention is not limited to the following embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without making creative work should fall within the scope of protection of the present invention.

[0046] "One embodiment" or "embodiment" referred to herein refers to a specific feature, structure or characteristic that may be included in at least one implementation of the present invention. In the description of the present invention, it should be understood that the terms "first", "second" and "third" in the specification and claims of the present invention and the above-mentioned drawings are used to distinguish different objects, rather than to describe a specific order. In addition, the terms "including" and "having" and any variations thereof are intended to cover non-exclusive inclusions. For example, a process, method, system, product or device that includes a series of steps or units is not limited to the listed steps or units, but optionally includes steps or units that are not listed, or optionally includes other steps or units that are inherent to these processes, methods, products or devices.

[0047] This specification provides method operation steps such as embodiments or flowcharts, but more or fewer operation steps may be included based on conventional or non-creative labor. The order of steps listed in the embodiments is only one way of executing the order of many steps and does not represent the only execution order. When the actual system or server product is executed, it can be executed in sequence or in parallel (for example, in a parallel processor or multi-threaded processing environment) according to the method shown in the embodiments or the drawings, or the execution order of steps without timing restrictions can be adjusted.

[0048] The present invention provides a method for monitoring abnormality of a power grid supply chain, comprising:

[0049] (1) Build a core business indicator system, such as Figure 1 As shown, the core business indicator system includes business compliance indicators, bidding business compliance indicators, contract business compliance indicators, warehousing business compliance indicators and waste business compliance indicators;

[0050] 1) Business compliance indicators include two secondary indicators: two-level catalog procurement execution accuracy and material plan submission accuracy:

[0051] ① Definition of the indicator for the execution accuracy of the two-level procurement catalog: Based on the two-level procurement catalog list, compare the procurement methods and ECP bidding results, and statistically analyze the items that have not been uniformly tendered in the State Grid in accordance with the centralized procurement requirements. Based on this indicator, the implementation of the centralized procurement catalog can be judged, and then the items that have not been tendered and purchased in accordance with the requirements of the two-level procurement catalog can be identified. The execution accuracy of Shanghai Company's centralized procurement, the number of items that have not been fully implemented, and the amount within a specified time period are statistically analyzed.

[0052] The execution accuracy rate of the two-level procurement catalogue = 1-(the number of items in the two-level procurement catalogue that are not fully executed / the number of items in the two-level procurement catalogue that should be executed);

[0053] ② Definition of indicators for the accuracy of material plan submission: compare the order receipt quantity and the project return material quantity, identify the deviation between the planned value and the actual material quantity used, calculate the accuracy of material plan submission based on material application as the benchmark data, and count the overall material plan submission accuracy of Shanghai Company within the specified time period, the number and amount of material deviations.

[0054] Accuracy rate of material plan submission = (actual quantity received - quantity of project returned materials) / quantity of material requirements reported in the purchase requisition.

[0055] 2) The compliance index of bidding business includes 4 secondary indicators: bidding execution standardization rate, contract signing standardization rate, bid winning amount accuracy rate, and bid cancellation execution standardization rate. The calculation formula is as follows:

[0056] ① Definition of the indicator of the bidding execution standardization rate: This indicator conducts post-analysis on situations such as circumventing bidding activities by splitting the number of times the same material is purchased in the project", "circumventing bidding activities by non-public bidding", and "changing the contract amount for improper reasons to exceed the bidding line". Different types of projects are monitored differently, and projects that conduct "non-public bidding" activities are paid special attention to, and items where the contract signing amount exceeds the project bidding line are identified. In addition, for contracts that are changed for improper reasons, whether the amount after the change exceeds the project bidding line, contracts that exceed the bidding line are marked and warned.

[0057] Bidding execution standardization rate = 1-(∑The number of non-bidding procurement contracts obtained by splitting contracts with a total amount exceeding the bidding line + the number of non-bidding procurement contracts with a contract amount exceeding the bidding line + the number of contracts with a contract amount exceeding the bidding line after changes without justifiable reasons) / the total number of contracts signed;

[0058] ② Definition of the indicator for the contract signing standardization rate: This indicator focuses on monitoring and analyzing the behaviors of "signing the contract before winning the bid" and "paying before the payment period stipulated in the contract". It uses the bid winning time and the payment time stipulated in the contract as the benchmark time nodes, compares the contract signing date and the actual payment date, and identifies behaviors that are not implemented correctly.

[0059] Contract signing standardization rate = 1-(number of items where the bid winning time is later than the contract signing time + number of items in the contract where payment is made in advance) / total number of contracts signed;

[0060] ③ Definition of the indicator for the accuracy of the winning bid amount: This indicator uses the supplier’s bid quotation amount as the benchmark value, compares it with the winning bid amount and identifies the deviation between the two, and conducts post-analysis on items where the quoted amount is inconsistent with the winning amount.

[0061] Winning bid amount accuracy rate = number of items with the same winning bid amount and bid amount during the statistical period / number of winning bid items during the statistical period;

[0062] ④ Definition of the indicator for the standard execution rate of bid cancellation: This indicator is based on the execution requirements of bidding activities, focuses on the implementation of the behavior of canceling invalid bids, identifies the behaviors that should be cancelled but are not, and conducts monitoring and analysis.

[0063] The compliance rate of bid cancellation = 1-number of items that should be cancelled but were not / total number of winning bids.

[0064] 3) The contract business compliance index includes two secondary indicators: the timeliness of e-commerce settlement and the accuracy of contract signing suppliers. The calculation formula is as follows:

[0065] ① Definition of the indicator of e-commerce settlement timeliness rate: This indicator reflects the timeliness of e-commerce settlement within the statistical period. Specifically, guided by the monitoring requirements for order settlement timeliness in 45 and 47, the timeliness of e-commerce order settlement is uniformly controlled, with the invoice verification date as the benchmark node, and attention is paid to order items that have not completed payment within 60 days.

[0066] Timely settlement rate of e-commerce = total amount of timely payments for e-commerce orders / total amount of payables for e-commerce orders;

[0067] ② Definition of the indicator for the accuracy rate of contracted suppliers: This indicator reflects the consistency between the contracted suppliers and the successful bidders of each project unit during the statistical period.

[0068] Accuracy rate of contracted suppliers = number of items that are consistent between contracted suppliers and winning bidders during the statistical period / number of winning bid items during the statistical period.

[0069] 4) The compliance indicators of warehousing business include 8 secondary indicators: inventory turnover rate of non-registered warehouses, empty warehouse rate, timely rate of online regular inventory, inventory difference rate, false balance inventory rate, overdue rate of consigned materials transferred to own materials, inventory turnover rate of professional warehouses, and overdue rate of overdue unutilized warehouses. The calculation formula is as follows:

[0070] ① Definition of the indicator of inventory turnover rate of non-registered warehouses: Combined with the inventory distribution analysis of non-registered warehouses and the warehousing warning scenario of non-registered warehouses, the visualization scenario of all physical resources of the ESC operation center is improved. By adding the identification of State Grid registered warehouses and non-State Grid registered warehouses, the inventory amount, inventory composition, inventory age, material category and other analyses of non-State Grid registered warehouses can be screened out to show the current inventory level and usage of materials in non-State Grid registered warehouses.

[0071] Non-registered warehouse inventory turnover rate = non-registered warehouse annual outbound amount / non-registered warehouse average inventory amount;

[0072] ②Indicator definition of empty warehouse rate: This indicator is used to display the distribution of vacant warehouse positions, assisting business personnel to make full use of each warehouse and reduce empty warehouse situations.

[0073] Empty warehouse ratio = actual number of warehouses used / total number of warehouses;

[0074] ③Indicator definition of online regular inventory timeliness rate: This indicator records the time of online regular inventory counting, compares the difference between the last regular inventory counting time and the current time, and then conducts inventory counting at regular intervals. It will give early warning information to warehouses that have not conducted inventory counting for more than a certain threshold.

[0075] Timely rate of online regular inventory counting = number of warehouses counted in time / total number of warehouses;

[0076] ④ Definition of the indicator of inventory situation difference rate: This indicator combines the authenticity analysis of material in-and-out information, inventory situation analysis and false receipt analysis. Based on the differences in the inventory list, it can be designed in two parts: multi-dimensional analysis and detailed query. It provides data support to ensure the consistency between accounts and actuals, and assists business personnel to quickly understand the authenticity of the accounts.

[0077] Inventory situation difference rate = difference amount in inventory result / total amount of all materials counted;

[0078] ⑤ Definition of the indicator of false balance inventory profit rate: This indicator combines the false balance inventory profit monitoring with the monitoring and analysis of false receipt and return of materials. Through this indicator, early warning information can be given for the frequent transfer of inventory based on the same batch of materials / physical ID and the whole-in and whole-out of the same batch of materials. By adding labels, it can distinguish whether the warning reason is frequent inventory transfer or whole-in and whole-out. According to the labels, the corresponding analysis content can be filtered out.

[0079] False balance profit rate = number of false balance profit items / total number of items;

[0080] ⑥Indicator definition of the overdue rate of deposited materials transferred to owned materials: Improve the comprehensive operation analysis of warehouse management in the ESC operation center - inventory turnover material overdue warning scenario, distinguish between deposited and non-deposited materials, add monitoring and early warning analysis for deposits, and issue early warnings for storage exceeding a certain threshold.

[0081] Overdue rate of deposited materials converted to owned materials = number of items of deposited materials that have been in stock for more than P days / total number of items of deposited materials in stock, where P is the set overdue time threshold, such as 180 days;

[0082] ⑦ Definition of indicators for inventory turnover rate of professional warehouses: Improve the visualization scenario of all physical resources in the ESC operation center, realize the sharing of multi-source data of professional warehouses and information of material warehouses, realize multi-dimensional analysis and detailed query of professional warehouse resources, supplemented by graphic analysis, data penetration and other means.

[0083] Professional warehouse inventory turnover rate = professional warehouse annual outbound amount / professional warehouse average inventory amount;

[0084] ⑧ Definition of the overdue rate of overdue unutilized materials: within a certain statistical period, according to the State Grid regulations, daily early warning statistics are conducted on the materials in the ERP system. Taking the query date as the time point, the overdue unutilized materials are analyzed and graded early warnings are issued.

[0085] The overdue rate of unprofitable items = the number of items that have exceeded the profit pool maintenance time by K days / the total number of items in the profit pool, where K is the set control period, such as 360 days.

[0086] 5) The compliance index of waste business includes 1 secondary index: the implementation rate of the demolition and recycling plan, which is calculated as follows:

[0087] ① Definition of the indicator for the execution rate of the dismantling and recycling plan: Set the indicator of "monitoring of waste materials that should be dismantled but have not been dismantled" to reflect whether the waste materials are fully recycled. Add monitoring and early warning analysis to the execution of the dismantling and recycling plan, and provide early warning information prompts if the set threshold is not reached.

[0088] Execution rate of demolition and recycling plan = actual warehousing quantity / approved initial demolition quantity.

[0089] (2) Based on the core business indicator system, multiple monitoring instructions are constructed. When any monitoring instruction is triggered, the disposal strategy corresponding to the monitoring instruction is executed.

[0090] 1) Monitoring instructions include:

[0091] Indicator numerical monitoring: set multiple numerical intervals for each indicator under the core business indicator system, set interval handling strategies for each indicator in each numerical interval, monitor the numerical intervals of indicator values ​​under the core business indicator system, and execute the interval handling strategies corresponding to the numerical intervals.

[0092] As in the embodiment of the present application, the timeliness rate of e-commerce settlement is monitored. When the timeliness rate of e-commerce settlement is less than or equal to 95%, a business reminder is issued. When the timeliness rate of e-commerce settlement is less than or equal to 90%, an urging process is carried out. When the timeliness rate of e-commerce settlement is less than or equal to 85%, a work order is issued.

[0093] Different interval handling strategies can be alarm reminders for different risk levels. Specifically, multiple risk levels (numerical intervals) and corresponding alarm reminders (interval handling strategies) can be set according to the specific definition of the indicator and its importance to supply chain operations. For example, the risk levels include normal (continuous monitoring), early warning (reminder), abnormal (attention), and serious (key attention).

[0094] 2) Monitoring instructions include:

[0095] Indicator trend monitoring sets the monitoring period and fluctuation range for each indicator under the core business indicator system, sets the fluctuation handling strategy for each indicator, and detects whether the numerical fluctuation of the indicators under the core business indicator system in the continuous monitoring period exceeds the fluctuation range. If so, the fluctuation handling strategy of the indicator is executed.

[0096] The fluctuation here can be that the difference between the indicator and the previous monitoring period exceeds the threshold, or that the difference between the indicator and the average of multiple historical monitoring period values ​​exceeds the threshold, or that the difference between the indicator and the historical average is greater than or less than 2 times the standard deviation, 3 times the standard deviation, etc., which can be analyzed using statistical methods, which will not be elaborated here.

[0097] If the value fluctuation of an indicator is abnormal, you need to pay attention to the relevant data of the indicator. The fluctuation handling strategy can be an alarm reminder or other configurable handling strategies.

[0098] 3) Monitoring instructions include:

[0099] Business scenario monitoring, set up multiple business scenarios, associate each business scenario with at least one indicator under the core business indicator system, set the trigger conditions for each business scenario separately, set the scenario handling strategy for each business scenario separately, monitor whether the multiple indicators associated with the business scenario meet the preset trigger conditions, and execute the scenario handling strategy of the business scenario when they are met.

[0100] The above-mentioned indicator value monitoring and indicator trend monitoring are to monitor whether there are abnormalities in the changes of a single indicator. Considering that the changes of a single indicator may not reflect the abnormality of a certain business scenario, the business scenario is associated with indicators, and the numerical monitoring or trend monitoring of multiple indicators is used to reflect whether the business scenario is abnormal. Specifically, it can be set by business personnel themselves, such as combining the bidding business compliance indicators with the contract business compliance indicators to analyze whether there are abnormalities in the material supply business scenario of bidding and contract settlement. The scenario disposal strategy can be an alarm reminder or other configurable disposal strategies.

[0101] In addition, indicators can be classified, and different types of indicators can be matched with different disposal strategies. For example, according to the characteristics of monitoring indicators, they can be classified into timeliness, status, and content. Among them, timeliness indicators monitor the timeliness of the entire supply chain process from demand planning to contract settlement, and issue early warning reminders for the risk of overdue material supply at the node, such as whether each link is handled in a timely manner and whether the materials can be delivered on time. Therefore, abnormal timeliness indicators will affect the advancement of each link of the supply chain, such as the e-commerce settlement rate. Status indicators record special states that affect the timeliness of the completion of the monitoring node for specific business links, and push them to relevant personnel, such as whether there are special abnormalities in the state, etc. Therefore, abnormal status indicators will affect the business of the supply chain link. Content indicators monitor the content of events that are prone to cause supply risks and compliance updates, and issue early warning reminders for risk items, such as whether the content is reasonable and whether the time content has the possibility of causing supply risks.

[0102] On the one hand, this application realizes business statistics based on the characteristics of power grid materials, analyzes and sorts out various businesses, accurately classifies them, defines corresponding indicators, clarifies the statistical rules of each indicator, ensures the rationality and feasibility of the set indicators, and ensures the efficient operation of the power grid enterprise supply chain. On the other hand, it provides an indicator monitoring method for abnormal supply chain business, improves the supply chain business and key node disposal strategies by sorting out the key indicators of the core business, strengthens the monitoring of abnormal core business of the supply chain, and improves the risk prevention ability of supply chain operation performance.

[0103] A power grid supply chain abnormality monitoring system, comprising:

[0104] The indicator system construction module is used to construct the core business indicator system, which includes business compliance indicators, bidding business compliance indicators, contract business compliance indicators, warehousing business compliance indicators and waste business compliance indicators;

[0105] The instruction building module builds multiple monitoring instructions based on the core business indicator system;

[0106] The execution module executes the disposal strategy corresponding to any monitoring instruction when any monitoring instruction is triggered.

[0107] Those skilled in the art can clearly understand that, for the convenience and brevity of description, the specific working process of the described module can refer to the corresponding process in the aforementioned method embodiment, and will not be repeated here.

[0108] The preferred specific embodiments of the present invention are described in detail above. It should be understood that a person skilled in the art can make many modifications and changes based on the concept of the present invention without creative work. Therefore, any technical solution that can be obtained by a person skilled in the art through logical analysis, reasoning or limited experiments based on the concept of the present invention on the basis of the prior art should be within the scope of protection determined by the claims.

Claims

1. A method for monitoring abnormality in a power supply chain, characterized in that: include: Constructing a core business indicator system, which includes business compliance indicators, bidding business compliance indicators, contract business compliance indicators, warehousing business compliance indicators and waste business compliance indicators; Based on the core business indicator system, multiple monitoring instructions are constructed; When any monitoring instruction is triggered, the handling strategy corresponding to the monitoring instruction is executed.

2. A method for monitoring abnormality of a power supply chain according to claim 1, characterized in that: The business compliance indicators include two secondary indicators: the accuracy of two-level catalog procurement execution and the accuracy of material plan submission. The calculation formula is as follows: The execution accuracy rate of the two-level procurement catalogue = 1-(the number of items in the two-level procurement catalogue that are not fully executed / the number of items in the two-level procurement catalogue that should be executed); Accuracy rate of material plan submission = (actual quantity received - quantity of project returned materials) / quantity of material requirements reported in the purchase requisition.

3. A method for monitoring power supply chain anomalies according to claim 1, characterized in that: The bidding compliance index includes four secondary indicators: bidding execution standardization rate, contract signing standardization rate, bid winning amount accuracy rate, and bid cancellation execution standardization rate. The calculation formula is as follows: Bidding execution standardization rate = 1-(∑The number of non-bidding procurement contracts obtained by splitting contracts with a total amount exceeding the bidding line + the number of non-bidding procurement contracts with a contract amount exceeding the bidding line + the number of contracts with a contract amount exceeding the bidding line after changes without justifiable reasons) / the total number of contracts signed; Contract signing standardization rate = 1-(number of items where the bid winning time is later than the contract signing time + number of items in the contract where payment is made in advance) / total number of contracts signed; Winning bid amount accuracy rate = number of items with the same winning bid amount and bid amount during the statistical period / number of winning bid items during the statistical period; The compliance rate of bid cancellation = 1-number of items that should be cancelled but were not / total number of winning bids.

4. A method for monitoring power supply chain anomalies according to claim 1, characterized in that: The contract business compliance index includes two secondary indicators: the timeliness of e-commerce settlement and the accuracy of contract signing suppliers. The calculation formula is as follows: Timely settlement rate of e-commerce = total amount of timely payments for e-commerce orders / total amount of payables for e-commerce orders; Accuracy rate of contracted suppliers = number of items that are consistent between contracted suppliers and winning bidders during the statistical period / number of winning bid items during the statistical period.

5. A method for monitoring power supply chain anomalies according to claim 1, characterized in that: The compliance indicators of warehousing business include 8 secondary indicators: non-registered warehouse inventory turnover rate, empty warehouse rate, online regular inventory timeliness rate, inventory situation difference rate, false balance inventory rate, overdue rate of deposited materials transferred to own materials, professional warehouse inventory turnover rate, overdue rate of overdue unutilized materials, and the calculation formula is as follows: Non-registered warehouse inventory turnover rate = non-registered warehouse annual outbound amount / non-registered warehouse average inventory amount; Empty warehouse ratio = actual number of warehouses used / total number of warehouses; Timely rate of online regular inventory counting = number of warehouses counted in time / total number of warehouses; Inventory situation difference rate = difference amount in inventory result / total amount of all materials counted; False balance profit rate = number of false balance profit items / total number of items; Overdue rate of deposited materials converted to owned materials = number of items of deposited materials that have been in stock for more than P days / total number of items of deposited materials in stock, where P is the set overdue time threshold; Professional warehouse inventory turnover rate = professional warehouse annual outbound amount / professional warehouse average inventory amount; The overdue rate of unprofitable pool = the number of entries that exceed the profit pool maintenance time K days / the total number of profit pool entries, where K is the set control cycle.

6. A method for monitoring power supply chain anomalies according to claim 1, characterized in that: The compliance indicators of the waste business include one secondary indicator: the implementation rate of the demolition and recycling plan, and the calculation formula is: Execution rate of demolition and recycling plan = actual warehousing quantity / approved initial demolition quantity.

7. A method for monitoring power supply chain anomalies according to claim 1, characterized in that: The monitoring instructions include: Indicator numerical monitoring: set multiple numerical intervals for each indicator under the core business indicator system, set interval handling strategies for each indicator in each numerical interval, monitor the numerical intervals in which the indicator values ​​under the core business indicator system are located, and execute the interval handling strategies corresponding to the numerical intervals.

8. A method for monitoring power supply chain anomalies according to claim 1, characterized in that: The monitoring instructions include: Indicator trend monitoring: set a monitoring period and fluctuation range for each indicator under the core business indicator system, set a fluctuation handling strategy for each indicator, detect whether the numerical fluctuation of the indicators under the core business indicator system in the continuous monitoring period exceeds the fluctuation range, and if so, execute the fluctuation handling strategy of the indicator.

9. A method for monitoring abnormality in a power supply chain according to claim 1, characterized in that: The monitoring instructions include: Business scenario monitoring, setting multiple business scenarios, each business scenario is associated with at least one indicator under the core business indicator system, trigger conditions are set for each business scenario, and scenario handling strategies are set for each business scenario. Monitor whether multiple indicators associated with the business scenario meet the preset trigger conditions, and execute the scenario handling strategy of the business scenario when they are met.

10. A power grid supply chain abnormality monitoring system, characterized in that: include: An indicator system construction module is used to construct a core business indicator system, wherein the core business indicator system includes business compliance indicators, bidding business compliance indicators, contract business compliance indicators, warehousing business compliance indicators and waste business compliance indicators; An instruction construction module, which constructs multiple monitoring instructions based on the core business indicator system; The execution module executes the disposal strategy corresponding to any monitoring instruction when any monitoring instruction is triggered.