Virtual power plant aggregation optimization method based on generalized demand side resource differentiation adjustment

By establishing a generalized demand-side resource adjustment capability evaluation model and an objective function model in the virtual power plant, the resource scheduling strategy of the virtual power plant is optimized, which solves the problem of traditional virtual power plants failing to dispatch internal resources in a differentiated manner and improves the supply and demand balance capability of the power system. and resource utilization efficiency.

CN118798560APending Publication Date: 2024-10-18ANSHAN POWER SUPPLY COMPANY OF STATE GRID LIAONING ELECTRIC POWER COMPANY +2
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202410898119.9
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-07-05
Publication Date
2024-10-18

AI Technical Summary

Technical Problem

Traditional virtual power plants fail to effectively differentiate and dispatch internal multi-agent frequency modulation auxiliary service resources, and fail to fully utilize the spatiotemporal differences of generalized demand-side resources, resulting in insufficient power system supply and demand balance capabilities.

Method used

A virtual power plant aggregation optimization method based on differentiated regulation of generalized demand-side resources is proposed. By collecting distributed power generation, adjustable load and energy storage resource data, the resource subject adjustment capability evaluation model and objective function model are established, and virtual power plant operators and resources are designed. Resource aggregation method between agents, optimizing scheduling strategies to improve resource utilization efficiency.

Benefits of technology

It realizes the differentiated adjustment capability assessment and optimized dispatch of resource entities within the virtual power plant, improves the economics of resource aggregation and optimized dispatch of the virtual power plant, encourages resource entities to participate in frequency regulation auxiliary services, and enhances the response capability and supply-demand balance of the power system.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118798560A_ABST
    Figure CN118798560A_ABST
Patent Text Reader

Abstract

The invention relates to a virtual power plant aggregation optimization method based on generalized demand side resource differentiation adjustment, which belongs to the technical field of power system resource optimization, and comprises the following steps: firstly, collecting power data of a generalized demand side resource main body, including power generation power data of a distributed power supply, power utilization power data of a flexible load and baseline data of the flexible load; and the resource price of the frequency modulation auxiliary service. And then, the adjustment capability of each demand side resource main body is extracted from historical data, and each main body provides frequency modulation auxiliary service resources after being aggregated by a virtual power plant. And finally, based on the differentiated generalized demand side resource main body adjustment capability, establishing a virtual power plant aggregation optimization model, and solving the optimization model through a concave-convex process algorithm to obtain a resource aggregation method between the virtual power plant and each internal main body, including an adjustment amount and an adjustment income, thereby achieving the purpose of improving the aggregation income of the virtual power plant.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention belongs to the technical field of power system resource optimization, and in particular relates to a virtual power plant aggregation optimization method based on the differentiated regulation capability of generalized demand-side resources. Background Art

[0002] In recent years, with the increase in the number of distributed power generation units such as photovoltaic power generation units, distributed energy storage units such as battery groups and electric vehicles in the distribution system, virtual power plants have gradually shifted from traditional demand-side load resource aggregation to generalized demand-side resources, which not only include load resources, but also distributed power sources, energy storage resources, etc. In this context, virtual power plants that consider generalized demand-side resources have more flexible and scalable power regulation capabilities because they have both power generation resources and power consumption resources. Therefore, studying the aggregation optimization scheduling strategy of virtual power plants that consider generalized demand-side resources can improve the response capability of the power demand side and ensure the balance of supply and demand in the power system.

[0003] Traditional virtual power plants mainly concentrate on aggregating controllable resources to participate in electricity trading, focusing on the external benefits after internal resource aggregation, but fail to take into account the temporal and spatial differences in the regulation capabilities of internal broad demand-side resource entities, and thus fail to differentiate the frequency regulation auxiliary service resources of multiple entities within the virtual power plant.

[0004] Therefore, a new technical solution is urgently needed in the prior art to solve the above problems. Summary of the invention

[0005] The technical problem to be solved by the present invention is: to provide a virtual power plant aggregation optimization method based on differentiated regulation of generalized demand-side resources, to propose an evaluation index for the regulation capability of generalized demand-side resource entities, to establish a virtual power plant aggregation optimization model, and to design a resource aggregation method between virtual power plant operators and internal entities, including regulation quantity and regulation benefits, so as to achieve the purpose of improving the economic efficiency of virtual power plant resource aggregation optimization scheduling.

[0006] The virtual power plant aggregation optimization method based on the differentiated regulation of generalized demand-side resources includes the following steps:

[0007] Step 1: Collect power data of generalized demand-side resource entities, including distributed generation resource data, adjustable load resource data, energy storage resource data, and resource price data of each generalized demand-side resource entity when participating in frequency regulation auxiliary services;

[0008] Step 2: Establish a generalized demand-side resource subject regulation capacity assessment model, including a resource regulation speed assessment model per unit time and a resource regulation capacity model per unit electricity price;

[0009] Step 3: Establish a virtual power plant aggregation optimization objective function model based on the differentiated regulation capability of generalized demand-side resources, and establish constraint conditions for the objective function model;

[0010] Step 4: Solve the virtual power plant aggregation optimization objective function model based on the differentiated regulation capability of generalized demand-side resources established in step 3 through the concave-convex process algorithm. The solved model is converted into a convex programming problem for power plant aggregation optimization scheduling.

[0011] The distributed power generation resource data in step 1 includes real-time power generation curve data of distributed photovoltaic and distributed wind power; the adjustable load resource data includes real-time power consumption curve data of load and baseline load curve data; the energy storage resource data includes real-time charge / discharge power curve data and planned charge / discharge power curve data.

[0012] Step 2: Generalized demand-side resource subject regulation capability assessment model

[0013] θ k =D k *C k

[0014] In the formula, θ k is the adjustment capability of the resource subject, which is the adjustment performance indicator D k With holding regulation capacity C k The product of .

[0015] The constraints of the objective function model in step three include the profit constraints of each generalized demand side resource entity, the selection constraints of each generalized demand side resource entity for the virtual power plant dispatching instructions, the content constraints of the dispatching instructions of each generalized demand side resource entity, and the dispatching capacity limit constraints of the resource entity.

[0016] The virtual power plant aggregation optimization objective function model in step 3 takes the maximization of virtual power plant revenue as the objective function.

[0017]

[0018] Where U A For revenue, T k is the dispatch capacity, I k Compensation for scheduling.

[0019] Through the above design scheme, the present invention can bring the following beneficial effects: based on the virtual power plant aggregation optimization method of differentiated regulation of generalized demand-side resources, on the one hand, the construction of the generalized demand-side resource regulation capacity evaluation model fully considers the resource regulation speed per unit time, the resource regulation capacity per unit electricity price, and the influence of the participating regulation capacity on the resource regulation capacity;

[0020] On the other hand, considering the differentiated regulation capabilities of multiple entities on the broad demand side, the virtual power plant can aggregate and optimize the frequency regulation resources of internal resource entities, which can effectively incentivize internal resource entities to participate in providing frequency regulation auxiliary services and increase the benefits of frequency regulation auxiliary services provided by internal resource entities of the virtual power plant. BRIEF DESCRIPTION OF THE DRAWINGS

[0021] The present invention is further described below with reference to the accompanying drawings and specific embodiments:

[0022] Figure 1 It is a schematic flow chart of the virtual power plant aggregation optimization method based on the differentiated regulation of generalized demand-side resources of the present invention.

[0023] Figure 2 It is a schematic diagram of the scheduling structure of the virtual power plant aggregation optimization method based on the differentiated regulation of generalized demand-side resources of the present invention. DETAILED DESCRIPTION

[0024] Virtual power plant aggregation optimization method based on differentiated regulation of generalized demand-side resources, such as Figure 1 and Figure 2 As shown, the following steps are included:

[0025] Step 1: Collect power data of general demand-side resource entities.

[0026] Broad demand-side resources include three categories: distributed generation resources, adjustable load resources, and energy storage resources. In order to achieve the aggregate optimization of broad demand-side resources in the virtual power plant, first of all, the power data of each broad demand-side resource entity is collected. For distributed generation resources, the real-time power curve data of distributed photovoltaic / distributed wind power is collected. For adjustable load resources, the real-time power consumption curve data and baseline load curve data of flexible loads are collected. For energy storage resources, the real-time charging / discharging power curve data and planned charging / discharging power curve data are collected. Subsequently, the resource price data of each broad demand-side resource entity when participating in the frequency regulation auxiliary service is collected.

[0027] Step 2: Establish a regulatory capacity assessment model for broad demand-side resource entities.

[0028] The regulation capacity of resource entities on the broad demand side includes two aspects: the resource regulation speed per unit time and the resource regulation capacity per unit electricity price.

[0029] Step 2.1: Establish a resource adjustment speed evaluation model per unit time:

[0030] Step 2.1.1: Calculate the resource adjustment speed evaluation model between two adjacent sampling points (15 minutes apart) using formula (1):

[0031]

[0032] Where η 1,i is the response speed of the active power of the subject between the i-th sampling point and the i+1-th sampling point, P i , P i+1 is the power value of the i-th and i+1-th sampling points, t i ,t i+1 It represents the time corresponding to the i-th and i+1-th sampling points, and N is the total number of sampling points of the distributed generation power curve / adjustable load power curve / energy storage resource discharge / charging power curve (the interval between two sampling points is 15 minutes, with a total of 96 sampling points).

[0033] Step 2.1.2: Consider that the collection cycle of the power generation / consumption curve is one day, the sampling interval is 15 minutes, and the sampling points are 96. Since the power generation / consumption values ​​of different generalized demand resource entities vary greatly, the resource adjustment speed value within one cycle of the power generation / consumption curve in formula (1) is normalized and dimensionless:

[0034]

[0035] In the formula, ξ 1,i For η 1,i After normalization and dimensionless processing, η 1,min is the minimum value of the active power regulation rate corresponding to adjacent sampling points in all collected data of the subject, η 1,max It is the maximum value of the active power regulation rate corresponding to adjacent sampling points in all collected data of the subject.

[0036] Step 2.1.3: Calculate the maximum resource adjustment speed per hour in one cycle of the power generation / consumption curve by formula (2), which is used as the unit time response capacity of the subject:

[0037] ξ 1,w =max{ξ 1,i ,i=1,…,4},w=1,…,24 (3)

[0038] In the formula, ξ 1,w It is the maximum value of the normalized active power regulation rate between adjacent sampling points of the subject in the wth hour.

[0039] Step 2.2: Establish a resource regulation capacity evaluation model under unit electricity price:

[0040] Step 2.2.1: Calculate the resource regulation capacity evaluation model between two adjacent sampling points (15 minutes apart) under the influence of the frequency regulation auxiliary service resource price through formula (4):

[0041]

[0042] Where η 2,j It represents the response capability of the subject to the unit electricity price at the jth sampling point, P j is the power corresponding to the jth sampling point, P 0,j is the active power of the benchmark load curve at the jth sampling point, q j is the frequency modulation auxiliary service resource price corresponding to the jth sampling point.

[0043] Step 2.2.2: Since the power generation / consumption values ​​of different generalized demand resource entities vary greatly, the resource regulation capacity values ​​under the unit electricity price of different entities are normalized and dimensionless, as shown in formula (5):

[0044]

[0045] In the formula, ξ 2,j For η 2,j After normalization and dimensionless processing, η 2,min is the minimum unit price response ability of the subject in all collected data, η 2,max It is the maximum value of the subject’s unit price responsiveness in all collected data.

[0046] Step 2.2.3: Calculate the maximum resource regulation capacity per hour within the power generation / consumption curve cycle using formula (6), which is used as the unit price regulation capacity of the resource entity:

[0047] ξ 2,w =max{ξ 2,j ,j=1,…,4},w=1,…24 (6)

[0048] In the formula, ξ 2,w It is the maximum value of the data after normalization of the response capacity of the active power between adjacent sampling points to the price level of frequency regulation resources of the subject in the wth hour.

[0049] Step 2.3: Establish a regulatory capacity assessment model for generalized demand-side resource entities through formula (8):

[0050] D k =(ξ 1,w +ξ 2,w ) / 2 (7)

[0051] Where D k is the adjustment performance index of the resource subject, which is the resource adjustment speed per unit time ξ 1,w and resource regulation capacity under unit electricity priceξ 2,w The average value of .

[0052] θ k=D k *C k (8)

[0053] In the formula, θ k is the adjustment capability of the resource subject, which is the adjustment performance indicator D k With holding regulation capacity C k The product of .

[0054] Step 3: Establish a virtual power plant aggregation optimization model based on the differentiated regulation capabilities of generalized demand-side resources.

[0055] Step 3.1: Based on the evaluation of the differentiated regulation capability of generalized demand-side resources calculated in step 2, establish the virtual power plant aggregation optimization objective function for frequency regulation auxiliary services.

[0056] Step 3.1.1: The virtual power plant contains K types of generalized demand-side resource entities, which are arranged in ascending order according to their resource adjustment capabilities, as shown in formula (9).

[0057] θ={θ1,…,θ k ,…,θ K}, k = 1, ... K (9)

[0058] Among them, θ k represents the adjustment capability of the k-th resource subject, satisfying θ1<…<θ k <…<θ K .

[0059] Step 3.1.2: Establish the virtual power plant aggregation optimization objective function based on the differentiated regulation capability of generalized demand-side resources. Type θ k The scheduling requirement corresponding to the resource subject is (T k , I k ), T k is the dispatch capacity, I k is the dispatch compensation. The virtual power plant control strategy containing the generalized demand-side resource subject is shown in formula (10).

[0060]

[0061] In the process of virtual power plant aggregation optimization scheduling, for resource subject k, the regulation capacity is θ k , execute scheduling requirements (T k , I k ), and its benefits are shown in formula (11).

[0062]

[0063] In the formula, γ P is the unit adjustment cost of resources, θ k m(I k) is the value function of scheduling compensation, and k is a monotonically increasing concave function of .

[0064] After aggregating the internal generalized demand-side resources, the benefits of the virtual power plant participating in providing frequency regulation ancillary services are shown in formula (12).

[0065]

[0066] In the formula, p cap and p mil are the frequency regulation capacity price and frequency regulation mileage price respectively; α rat is the frequency regulation mileage ratio of the virtual power plant.

[0067] Taking the maximization of virtual power plant revenue as the objective function, an aggregate optimization scheduling model for generalized demand-side resources is constructed. The objective function model is established through formula (13):

[0068]

[0069] Step 3.2: Establish virtual power plant aggregation optimization constraints based on the differentiated regulation capabilities of generalized demand-side resources.

[0070] Step 3.2.1: Establish the income constraints of various entities on the generalized demand-side resources:

[0071] As shown in formula (14), all resource entities participating in the virtual power plant dispatch will obtain effective benefits.

[0072] θ k m(I k )-γ P T k ≥0,k=1,…K (14)

[0073] Through formula (15), resource entities with higher regulation capabilities will obtain higher benefits.

[0074] θ k m(I k )-γ P T k ≥θ k-1 m(I k-1 )-γ P T k-1 , k = 2, ... K (15)

[0075] Formula (15) can be further simplified to formula (16):

[0076] θ1m(I1)-γ P T1≥0 (16)

[0077] Step 3.2.2: Establish the selection constraints of various generalized demand-side resource entities for virtual power plant dispatch instructions:

[0078] As shown in formula (17), resource entities participating in the virtual power plant dispatch should select dispatch instructions that are suitable for their own regulation capabilities:

[0079] θ k m(I k )-γ P T k ≥θ k′ m(I k′ )-γ P T k′ ,k,k′=1,…K, (17)

[0080] Formula (17) can be further simplified to formula (18):

[0081] θ k m(I k )-γ P T k ≥θ k m(I k-1 )-γ P T k-1 , k = 2, ... K (18)

[0082] Step 3.2.3: Establish the dispatch instruction content constraints for each subject of generalized demand-side resources:

[0083] As shown in formula (19), the higher the regulation capability of the resource subject, the higher the scheduling return obtained.

[0084] 0≤…<I k <…<I K , k = 1, ... K (19)

[0085] Step 3.2.4: Use formula (20) to establish the scheduling capacity constraint of the resource subject:

[0086] T k ≤C k , k = 1, ... K (20)

[0087] Step 4: Solve the virtual power plant aggregation optimization model based on the differentiated regulation capability of generalized demand-side resources through the concave-convex process algorithm. Since equation (18) is the difference between two concave functions, the proposed virtual power plant optimization model cannot directly apply convex programming. Therefore, the original optimization model is transformed into a convex programming problem through the concave-convex process algorithm.

[0088] Define the function f k (I k )=θ k m(Ik ), perform a first-order Taylor expansion:

[0089]

[0090] In the formula, I k,0 [σ] is the initial value of the σth iteration.

[0091] On this basis, equation (18) can be transformed into the difference between a concave function and an affine function:

[0092]

[0093] The optimal solution of each iteration is used as the initial value of the next iteration, that is,

[0094] When the difference between the virtual power plant revenues in two consecutive iterations satisfies the convergence condition δ, the iteration terminates, as shown in the formula:

[0095]

[0096] Finally, using formula (13) as the objective function and formulas (16), (19), (20), and (22) as constraints, a virtual power plant aggregation optimization model is formed. Since this optimization problem is a typical convex programming problem, Matlab software and solver CVX are used to solve it, and a virtual power plant aggregation optimization strategy based on the differentiated regulation capability of generalized demand-side resources is obtained.

Claims

1. A virtual power plant aggregation optimization method based on differentiated regulation of generalized demand-side resources is characterized by: The following steps are included: Step 1: Collect power data of generalized demand-side resource entities, including distributed generation resource data, adjustable load resource data, energy storage resource data, and resource price data of each generalized demand-side resource entity when participating in frequency regulation auxiliary services; Step 2: Establish a generalized demand-side resource subject regulation capacity assessment model, including a resource regulation speed assessment model per unit time and a resource regulation capacity model per unit electricity price; Step 3: Establish a virtual power plant aggregation optimization objective function model based on the differentiated regulation capability of generalized demand-side resources, and establish constraint conditions for the objective function model; Step 4: Solve the virtual power plant aggregation optimization objective function model based on the differentiated regulation capability of generalized demand-side resources established in step 3 through the concave-convex process algorithm. The solved model is converted into a convex programming problem for power plant aggregation optimization scheduling.

2. The virtual power plant aggregation optimization method based on differentiated regulation of generalized demand-side resources according to claim 1 is characterized by: The distributed power generation resource data in step 1 includes real-time power generation curve data of distributed photovoltaic and distributed wind power; the adjustable load resource data includes real-time power consumption curve data of load and baseline load curve data; the energy storage resource data includes real-time charge / discharge power curve data and planned charge / discharge power curve data.

3. The virtual power plant aggregation optimization method based on generalized demand-side resource differentiated regulation according to claim 1 is characterized by: Step 2: Generalized demand-side resource subject regulation capability assessment model i k =D k *C k In the formula, θ k is the adjustment capability of the resource subject, which is the adjustment performance indicator D k With holding regulation capacity C k The product of .

4. The virtual power plant aggregation optimization method based on generalized demand-side resource differentiated regulation according to claim 1 is characterized by: The constraints of the objective function model in step three include the profit constraints of each generalized demand side resource entity, the selection constraints of each generalized demand side resource entity for the virtual power plant dispatching instructions, the content constraints of the dispatching instructions of each generalized demand side resource entity, and the dispatching capacity limit constraints of the resource entity.

5. The virtual power plant aggregation optimization method based on generalized demand-side resource differentiated regulation according to claim 1 is characterized by: The virtual power plant aggregation optimization objective function model in step 3 takes the maximization of virtual power plant revenue as the objective function. Where U A For revenue, T k is the dispatch capacity, I k Compensation for scheduling.