Split structure tension leg fan platform installation method
By adopting a combination technology of split structure and threaded rod mechanism in the tension leg fan platform, the problems of long ballast time and installation risks in the deep sea areas are solved, and rapid and accurate pretension force adjustment of tension tendons is achieved. Improves installation efficiency and safety.
Patent Information
- Application Number
- CN202411249886.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-06
- Publication Date
- 2024-11-01
AI Technical Summary
In the installation of tension leg fan platforms in deep sea areas, the floating body ballast time is long, the installation efficiency is low, and the installation risk is high. Especially in water depths of 60 meters or more, it is difficult for the existing technology to quickly adjust the pretension force of the tension tendons. , resulting in reduced installation efficiency and increased risk.
The split structure is used as the auxiliary ballast draft device. Through the split structure's threaded rod mechanism and threaded rod locking assembly mechanism, the pretension force of the tension tendon can be achieved quickly and accurately controlled, reducing the main scale of the floating body system. The split structure of multiple sets of tension tendon support devices and mooring anchoring systems simplifies the installation process and reduces construction risks.
It significantly reduces the operating time of floating ballast, improves installation efficiency, reduces installation risks, can accurately adjust the pretension force of the tension tendon, reduces the cost of offshore construction and operation and maintenance, and ensures the operation safety of the tension leg platform.
Smart Images

Figure CN118877152A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to deep sea floating platform installation technology, and in particular to a method for installing a split structure tension leg wind turbine platform. Background Art
[0002] At present, with the substantial reduction of offshore wind power resources, offshore wind power projects are gradually developing in the direction of deep sea. Floating wind power platforms have become the mainstream equipment for deep sea wind power development. With the increase in the wind turbine capacity and power generation efficiency of floating wind power platforms in the industry, and the substantial reduction in the weight requirements of steel structures per megawatt, tension leg wind power platforms have gradually become a better choice after semi-submersible floating wind power platforms with their better motion performance, shallow draft, small scale, light and stable structure. Tension leg wind turbine platforms are generally composed of wind turbine systems, floating structures, tension tendons and mooring anchor systems. The tension leg platform uses its own displacement volume that is much larger than the buoyancy, and uses the excess part as the pre-tension of the mooring chain (cable) and acts on the tension tendon to ensure that the tension tendon is in a tensioned state, and always keeps the wind turbine platform connected to the seabed anchor foundation to maintain the stability of the tension leg wind turbine platform.
[0003] The installation and commissioning of the tension leg wind turbine platform is crucial to the stability and safety of the platform operation, and is also related to the cost of the entire offshore construction. When installing the tension tendons at the bottom of a general tension leg platform, the seabed anchoring device is first installed, and then the seabed mooring cable or mooring chain is installed and the buoyancy ball is used to assist in floating on the sea surface for positioning. After that, the wind turbine system and the floating structure are towed to the mooring point to complete the connection between the mooring chain and the floating structure. Then, the connection and installation of the tension tendons are achieved by adjusting the ballast water volume in the floating ballast tank. Finally, by leveling the overall ballast, the tension of the tension tendons is gradually adjusted. Through tension monitoring, the platform reaches the working waterline and the tension tendons reach the pre-tensioning force. Due to the large scale of the general floating structure, the ballast is large, the ballast operation time is too long, and it is difficult to adjust the pre-tensioning force of the tension tendons through ballast water, the accuracy is difficult to control, the adjustment operation process is long, the installation efficiency is reduced, and the installation risk is increased. Summary of the invention
[0004] The technical problem to be solved by the present invention is to address the shortcomings of long floating body ballasting time, low installation efficiency and high installation risk during the installation of a tension leg wind platform in deep sea areas with a water depth of 60 meters or more. The present invention provides a split-structure tension leg wind platform installation method which can reduce the floating body ballasting operation time, improve installation efficiency and reduce installation risk.
[0005] In order to solve the above technical problems, the present invention adopts the following technical solutions:
[0006] A method for installing a split-structure tension leg wind turbine platform, characterized in that the tension leg wind turbine platform includes a wind turbine system, a floating body system, multiple groups of tension tendon support devices, and multiple groups of mooring anchoring systems, each tension tendon support device includes a split structure as an auxiliary ballast draft device, an assembly locking mechanism is arranged on the top of the split structure, and a top mooring connection mechanism is arranged on the bottom, the assembly locking mechanism includes a threaded rod mechanism and a threaded rod locking assembly mechanism, the threaded rod locking assembly mechanism is installed on the threaded rod mechanism, the top mooring connection mechanism includes a top universal joint shackle, a top anchor chain segment and a main mooring cable connected in sequence from top to bottom; each mooring anchoring system includes a bottom anchor chain segment, a bottom shackle and a seabed anchor pile connected in sequence from top to bottom; each group of tension tendon support devices includes multiple tension tendon support devices, each group of mooring anchoring systems includes multiple mooring anchoring systems, the tension tendon support devices correspond to the mooring anchoring systems one by one, and the method for installing the tension leg wind turbine platform includes:
[0007] Step 1: Complete the hoisting and docking installation of the wind turbine system and the floating body system at the dock to form a wind turbine floating body. After the commissioning is completed, it will be towed to the working sea area to prepare for assembly and connection with the tension tendon support device;
[0008] Step 2: Before the first step is completed, the seabed anchor piles of the mooring anchor system are positioned to the seabed surface through seabed piling operations to prepare for the cable reconnection of the tension tendon support device;
[0009] The third step: tie each group of tendon support devices together with steel wire ropes, transport them to the work site by engineering ship, and after lifting them to the sea surface by the ship crane, tie the tendon support devices to the mooring piles of the engineering ship with auxiliary mooring cables to prevent the tendon support devices from drifting away. Next, ballast the cabins in the split structure to make the tendon support devices dive to the lowest end of the working draft position of the floating system. Use underwater robots to combine underwater operations to assemble the main mooring cables of the tendon support devices with the bottom anchor chain segments of the mooring anchoring system, complete the connection between the tension tendons on the tendon support devices and the bottom anchor chain segments on the seabed, and then unload the ballast in the ballast tanks in the split structure to make the split structure begin to float, gradually tighten the main mooring cables to the stretched state, and complete the first pre-tensioning of the tendons.
[0010] Step 4: Drag the wind turbine buoy formed by the first step to the work site, then quickly ballast the buoy system until it is near the working draft. According to the position of the tension tendon support device, use the auxiliary mooring cable to pass through the threaded assembly hole on the wind turbine buoy, preliminarily position the various component structures corresponding to the installation position of the wind turbine buoy, remove the auxiliary mooring cable, and use underwater auxiliary operations to connect the threaded rod mechanism on the tension tendon support device and insert it into the threaded assembly hole on the wind turbine buoy, and use the threaded rod locking assembly mechanism to perform preliminary thread locking assembly, and then assemble the tension tendon support devices at other positions similarly. After the tension tendons of all tension tendon support devices are assembled with the wind turbine buoy, gradually release the ballast in the ballast tank of the buoy system until the tension tendons are pre-tightened for the second time and stop near the final pre-tensioning force, thus completing the tension key installation and connection of the entire tension leg platform.
[0011] The present invention adopts a split structure as an auxiliary ballast draft device, so that the main scale of the floating system is small, it is easy to quickly dive with ballasted water, and the ballasting operation time of the floating system is reduced; when the present invention is specifically installed, the split structure itself serves as an auxiliary buoyancy device, firstly dives with the top anchor chain segment and the main mooring cable under ballasting, and is connected to the pre-installed bottom anchor chain segment and the seabed anchor pile through a connecting buckle, and the split structure replaces the original auxiliary buoyancy ball to directly empty the ballast in the split structure to achieve the first pre-tensioning state of the tension tendon, and then the floating system of the ballasted wind turbine float dives and is connected and installed with the split structure, and then the ballast in the floating system is adjusted to reach a state close to the pre-tensioning state of the tension tendon, and finally the threaded adjustment in the threaded rod mechanism in the upper assembly locking mechanism of the split structure and the threaded rod locking assembly mechanism is controlled to achieve precise control of the state of the tension tendon pre-tensioning force. This installation method has shorter ballast adjustment time than traditional methods and lower construction and installation risks. In particular, it can more accurately adjust the pre-tensioning force of the tension tendon, reducing offshore construction time and construction costs as well as the subsequent operation and maintenance costs of the tension leg platform after operation, ultimately ensuring the safe operation of the tension leg platform.
[0012] Preferably, the first step, the second step and the third step are performed substantially simultaneously, and after the third step is completed, the wind turbine buoy is towed to its place. To improve work efficiency and save offshore installation costs, the interval between the completion time of the first step and the completion time of the third step is less than 1 day.
[0013] Preferably, the wharf is selected to be as close as possible to the wind turbine platform operation site to facilitate the integrated towing of the wind turbine pontoon.
[0014] Preferably, both the upper and lower ends of the main mooring rope are connected to the anchor chain buckles at both ends by connecting buckles.
[0015] Preferably, the main mooring cable is connected to the split structure via a top anchor chain segment and a top universal joint shackle.
[0016] Preferably, each set of tension key support devices is transported to the work site with the assistance of an engineering vessel and hoisted into the water, and then tied to the mooring pile of the engineering vessel with an auxiliary mooring cable to prevent the split structure from drifting away.
[0017] Preferably, in the third step, the ballast tank in the split structure is ballasted and dived with the assistance of an engineering vessel, dives to the working water depth, and is tied to the engineering vessel by an auxiliary cable to prevent it from drifting away.
[0018] Preferably, in the third step, after the main mooring rope of the tension key supporting device is connected, the entire ballast in the split structure is removed by using an engineering vessel to achieve the first pre-tensioning state of the tension key.
[0019] Preferably, in the fourth step, the floating system is ballasted to a very small height range above or below the working waterline, and the height range is smaller than the height at which the pipe threads of the threaded rod mechanism pass through the floating system, so as to facilitate the initial positioning of the threaded rod mechanism of the locking mechanism assembled on the split structure and the assembly with the fixed threaded holes on the floating system.
[0020] Preferably, in the fourth step, when the floating body ballast system is unloaded to near the working draft height, the tensioning force of the tension tendon is precisely adjusted by locally adjusting the pipe thread to achieve the final tension state of the tension tendon.
[0021] Preferably, both upper and lower ends of the main mooring rope are connected to the top anchor chain segment and the bottom anchor chain segment at both ends by connecting buckles, which facilitates underwater operation and improves connection efficiency.
[0022] Preferably, the upper end of the main mooring line is connected to the top universal joint shackle through the top anchor chain segment, which has good wear resistance, prevents the main mooring line from being directly connected to the top universal joint shackle, and reduces the risk of the main mooring line being worn.
[0023] Preferably, the auxiliary cables on the split structures pass through the threaded holes of the wind turbine float upward to assist in the initial positioning of each group of split structures and the wind turbine float. After each group of split structures approaches the platform float, the auxiliary cables are released and the underwater working pipe threads are aligned and assembled with the float foundation and the upper thread locking mechanism of the split structure is assembled.
[0024] Preferably, after the integrated fan is reconnected to the split structure tension key, the tension tendon is adjusted to a second tensioning state by continuing to release the ballast in the float, which is basically close to the final pre-tensioning state. Finally, the top thread depth of each group of split structures is fine-tuned to accurately control the final pre-tensioning state of the tension key.
[0025] Compared with the prior art, the present invention has the following beneficial effects:
[0026] (1) The split structure of the present invention can be used as an auxiliary ballast draft device, which makes the main scale of the floating body foundation small, facilitates rapid ballast water diving, and reduces the ballast operation time of the floating body system;
[0027] (2) The split structure of the present invention can be used as an auxiliary buoyancy device. First, the ballast is applied and the device is connected to the bottom anchor pile, and then the auxiliary buoyancy ball is replaced and the ballast is emptied to reach the first pre-tensioning state of the tension tendon. After that, the wind turbine platform is ballasted and the split structure is installed. The ballast in the buoy is adjusted to reach a state close to the pre-tensioning state of the tension tendon. The two ballast applications and installations are beneficial to the process adjustment of the pre-tension of the tension key and the final state adjustment.
[0028] (3) The present invention achieves precise control of the state of the pre-tensioning force of the tension tendon by controlling the adjustment of the threads in the threaded assembly locking mechanism on the upper part of the split structure, which is easy to operate and easy to implement;
[0029] (4) The ballast adjustment time of the present invention is shorter than that of the traditional method, and the construction and installation risk is lower. In particular, it can more accurately adjust the pre-tensioning force of the tension tendon, reduce the offshore construction time and construction cost, and the subsequent operation and maintenance cost of the tension leg platform after operation, and ultimately ensure the safe operation of the tension leg platform.
[0030] (5) The present invention can be used to carry out installation operations on tension leg wind turbine platforms in deep sea areas with a water depth of 60 meters or more, and can be widely used in the installation of tension leg wind power platforms in deep sea areas such as the South China Sea and the East China Sea. BRIEF DESCRIPTION OF THE DRAWINGS
[0031] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.
[0032] Figure 1 It is a structural schematic diagram of the split-structure tension leg wind turbine platform system involved in the present invention.
[0033] Figure 2 This is a schematic diagram of the installation of the wind turbine float.
[0034] Figure 3 It is a schematic diagram of the connection between a single set of tension key support device and the mooring anchor system.
[0035] Figure 4 Schematic diagram of the installation of tension key support devices and mooring anchor systems for all groups.
[0036] Figure 5 This is a schematic diagram showing the installation of the entire tension leg fan platform system.
[0037] In the figure: 1--wind turbine system; 2--floating system; 3--tension tendon support device, 3-1--threaded rod mechanism, 3-2--split structure; 3-3--main mooring cable, 3-4--top anchor chain segment, 3-5--top universal joint shackle, 3-6--wire rope; 3-7--threaded rod locking assembly mechanism; 4--mooring anchoring system, 4-1--bottom anchor chain segment, 4-2--bottom shackle, 4-3--seabed anchor pile, 4-4--seabed surface. DETAILED DESCRIPTION
[0038] The present invention is further described below in conjunction with specific preferred embodiments, but the protection scope of the present invention is not limited thereby.
[0039] For the convenience of description, the relative position relationship of each component, such as up, down, left, right, etc., is described according to the layout direction of the drawings in the specification, and does not limit the structure of this patent.
[0040] See also Figure 1 The present invention relates to a split structure tension leg wind turbine platform, which comprises a wind turbine system 1 at the top, a floating body system 2 at the middle, a plurality of tension tendon support devices 3 connected to the floating body system 2, and a plurality of mooring anchor systems 4 at the bottom, a total of four parts. Each tension tendon support device 3 comprises a split structure 3-2 as an auxiliary ballast draft device, an assembly locking mechanism is arranged at the top of the split structure 3-2, and a top mooring connection mechanism is arranged at the bottom, the assembly locking mechanism comprises a threaded rod mechanism 3-1 and a threaded rod locking assembly mechanism 3-7, the threaded rod locking assembly mechanism 3-7 is installed on the threaded rod mechanism 3-1, and the top mooring connection mechanism comprises a top universal joint shackle 3-5, a top anchor chain segment 3-4 and a main mooring cable 3-3 connected in sequence from top to bottom. Each mooring anchor system 4 comprises a bottom anchor chain segment 4-1, a bottom shackle 4-2 and a seabed anchor pile 4-3 connected in sequence from top to bottom. Each group of tension tendon support devices includes a plurality of tension tendon support devices 3, and each group of mooring anchor systems includes a plurality of mooring anchor systems 4, and the tension tendon support devices 3 are connected one-to-one with the mooring anchor systems 4. In this embodiment, the tension leg wind turbine platform adopts a 3x2 mooring scheme, that is, three groups of tension tendon support devices, a total of six tension tendon support devices 3, are tied together in groups of two.
[0041] See also Figure 2-Figure 5 The specific installation method of the split structure tension leg fan platform of the present invention includes:
[0042] The first step is to fold and tow the wind turbine platform: Figure 2As shown, the upper wind turbine system 1 and the middle triangular floating body system 2 are hoisted and docked at the dock to form a wind turbine floating body. After debugging, it is towed to the working sea area to be assembled and connected with the tension tendon support device 3;
[0043] The second step is the installation of the mooring anchor system 4: Figure 3 As shown, before the first step is completed, an anchor pile 4-3 with a shackle 4-2 and a section of metal anchor chain 4-1 is positioned to the seabed surface 4-4 through a seabed piling operation, so as to prepare for the main mooring cable 3-3 of the tension tendon support device 3 to be connected back;
[0044] The third step is to connect the anchor chain of the tension tendon support device 3 and the mooring anchor system 4: Figure 3 , Figure 4 As shown, generally, a tension leg platform will involve several sets of main mooring cable positioning, which requires several sets of tension tendon support devices 3 to be connected to the floating system 2. During the specific connection, each set of tension tendon support devices 3 is tied together with steel wire ropes 3-6, transported to the work site by an engineering ship, and lowered to the sea surface by a ship crane. One end of the auxiliary mooring cable is tied to the tension tendon support device 3, and the other end of the auxiliary mooring cable is connected to the mooring pile of the engineering ship to prevent the tension tendon support device 3 from drifting away. Next, the inner cabin of the split structure 3-2 is ballasted to make the tension tendon support device 3 dive to the lowest working draft position of the floating system 2. At the end, an underwater robot is used in combination with underwater operations to assemble the bottom connecting buckle of the main mooring cable 3-3 with the bottom anchor chain segment 4-1 attached to the seabed anchor pile 4-3 of the mooring anchoring system 4, and the tension tendon on the tension tendon support device 3 is connected back to the bottom anchor chain segment 4-1 located on the seabed. After that, the ballast tank in the split structure 3-2 is unloaded, and the split structure 3-2 begins to float up, gradually tightening the main mooring cable 3-3 to a stretched state, completing the first pre-tensioning of the tension tendon; similar to the above-mentioned process of connecting the tension tendon on the tension tendon support device 3 with the bottom anchor chain segment 4-1, the connection of other groups of tension tendon support devices 3 is completed;
[0045] The fourth step is to connect the integrally connected fan system 1 and floating system 2 with the tension key support device 3, that is, the first step is completed a short time after the third step is completed, and then the assembly connection of the assembly locking mechanism of the fan floating body and the tension tendon support device 3 and the precise control of the tension tendon preload force are started: Figure 5As shown, the wind turbine buoy integrated body closed in the first step is towed to the in-place working site, and then the buoy system 2 is quickly ballasted until it is near the working draft, and the position of the tension tendon support device 3 is gradually adjusted. The auxiliary mooring cable used when the engineering vessel is lowered in the first step is passed through the threaded assembly hole on the buoy system 2, so that each group of tension tendon support devices 3 and the corresponding installation position of the buoy system 2 can be initially positioned, and the auxiliary mooring cable is removed. The threaded rod mechanism 3-1 is docked and inserted into the threaded assembly hole on the buoy system 2 through underwater auxiliary operations, and the threaded locking mechanism 3-7 is used for preliminary threaded locking assembly. Then, the tension tendon support devices 3 at other positions are assembled similarly. After the tension tendons of all tension tendon support devices 3 are assembled with the buoy system 2, the ballast in the ballast tank of the buoy system 2 is gradually released until the tension tendons are pre-tightened for the second time to a point close to the final pre-tensioning force and stop. Finally, the pre-tightening force of the final tension tendon is accurately controlled by locally adjusting the threaded rod mechanism 3-1 and the threaded rod locking assembly mechanism 3-7 to complete the tension key installation connection of the entire tension leg platform.
[0046] The split structure 3-2 in the installation method of the split-structure tension leg wind turbine platform of the present invention can be used as an auxiliary ballast draft device. The split structure 3-2 itself is first ballasted and dived and then the ballast is released to reach the first pre-tensioning state of the tension tendon. Combined with the ballasted diving of the wind turbine float and the partial release of the ballast to reach a state close to the pre-tensioning state of the tension tendon, the thread adjustment in the threaded locking mechanism on the upper part of the split structure is controlled to achieve precise control of the pre-tensioning state of the tension tendon.
[0047] The main scale of the floating system in the installation method of the split-structure tension leg wind turbine platform of the present invention is small, and it is easy to quickly dive with ballast water. The ballast adjustment time is shorter than that of the traditional method, and the construction and installation risk is low. In particular, it can more accurately adjust the pre-tensioning force of the tension tendon, reduce the offshore construction time and construction cost, and the operation and maintenance cost of the tension leg platform after the later operation, and ultimately ensure the safe operation of the tension leg platform. Installation operations can be carried out for tension leg wind turbine platforms in deep sea areas with a water depth of 60 meters or more and deep sea areas, and can be widely used in the installation of tension leg wind power platforms in deep sea areas such as the South China Sea and the East China Sea.
[0048] The above is only a specific implementation scheme of the present invention, but the protection scope of the present invention is not limited thereto. Any technician familiar with the art can make many possible changes and modifications to the technical scheme of the present invention by using the technical content disclosed above without departing from the scope of the technical scheme of the present invention, or modify it into an equivalent embodiment of equivalent changes. Therefore, any simple modification, equivalent change and modification made to the above embodiments according to the technical essence of the present invention without departing from the content of the technical scheme of the present invention should fall within the protection scope of the technical scheme of the present invention.
Claims
1. A method for installing a split structure tension leg wind turbine platform, characterized in that: The tension leg wind turbine platform comprises a wind turbine system, a floating body system, a plurality of tension tendon support devices, and a plurality of mooring anchor systems. Each tension tendon support device comprises a split structure as an auxiliary ballast draft device. An assembly locking mechanism is arranged at the top of the split structure, and a top mooring connection mechanism is arranged at the bottom. The assembly locking mechanism comprises a threaded rod mechanism and a threaded rod locking assembly mechanism. The threaded rod locking assembly mechanism is installed on the threaded rod mechanism. The top mooring connection mechanism comprises a top universal joint shackle, a top anchor chain segment, and a main mooring cable connected in sequence from top to bottom. Each mooring anchor system comprises a bottom anchor chain segment, a bottom shackle, and a seabed anchor pile connected in sequence from top to bottom. Each group of tension tendon support devices includes a plurality of tension tendon support devices, each group of mooring anchor systems includes a plurality of mooring anchor systems, the tension tendon support devices correspond to the mooring anchor systems one by one, and the tension leg wind turbine platform installation method includes: Step 1: Complete the hoisting and docking installation of the wind turbine system and the floating body system at the dock to form a wind turbine floating body. After the commissioning is completed, it will be towed to the working sea area to prepare for assembly and connection with the tension tendon support device; Step 2: Before the first step is completed, the seabed anchor piles of the mooring anchor system are positioned to the seabed surface through seabed piling operations to prepare for the cable reconnection of the tension tendon support device; The third step: tie each group of tendon support devices together with steel wire ropes, transport them to the work site by engineering ship, and after lifting them to the sea surface by the ship crane, tie the tendon support devices to the mooring piles of the engineering ship with auxiliary mooring cables to prevent the tendon support devices from drifting away. Next, ballast the cabins in the split structure to make the tendon support devices dive to the lowest end of the working draft position of the floating system. Use underwater robots to combine underwater operations to assemble the main mooring cables of the tendon support devices with the bottom anchor chain segments of the mooring anchoring system, complete the connection between the tension tendons on the tendon support devices and the bottom anchor chain segments on the seabed, and then unload the ballast in the ballast tanks in the split structure to make the split structure begin to float, gradually tighten the main mooring cables to the stretched state, and complete the first pre-tensioning of the tendons. Step 4: Drag the wind turbine buoy formed by the first step to the work site, then quickly ballast the buoy system until it is near the working draft. According to the position of the tension tendon support device, use the auxiliary mooring cable to pass through the threaded assembly hole on the wind turbine buoy, preliminarily position the various component structures corresponding to the installation position of the wind turbine buoy, remove the auxiliary mooring cable, and use underwater auxiliary operations to connect the threaded rod mechanism on the tension tendon support device and insert it into the threaded assembly hole on the wind turbine buoy, and use the threaded rod locking assembly mechanism to perform preliminary thread locking assembly, and then assemble the tension tendon support devices at other positions similarly. After the tension tendons of all tension tendon support devices are assembled with the wind turbine buoy, gradually release the ballast in the ballast tank of the buoy system until the tension tendons are pre-tightened for the second time and stop near the final pre-tensioning force, thus completing the tension key installation and connection of the entire tension leg platform.
2. The installation method of the split structure tension leg wind turbine platform according to claim 1 is characterized in that: The first step, the second step and the third step are performed substantially simultaneously, and after the third step is completed, the wind turbine float is towed into position.
3. The method for installing a split structure tension leg wind turbine platform according to claim 1, characterized in that: The location of the wharf should be as close as possible to the wind turbine platform operation site.
4. The installation method of the split structure tension leg wind turbine platform according to claim 1 is characterized in that: The upper and lower ends of the main mooring rope are connected to the anchor chain buckles at both ends by connecting buckles.
5. The method for installing a split structure tension leg wind turbine platform according to claim 1, characterized in that: The main mooring cable is connected to the split structure via a top anchor chain segment and a top universal joint shackle.
6. The method for installing a split structure tension leg wind turbine platform according to claim 1, characterized in that: Each set of tension key support devices is transported to the work site with the assistance of an engineering vessel and hoisted into the water, and then tied to the mooring pile of the engineering vessel with an auxiliary mooring cable.
7. The method for installing a split structure tension leg wind turbine platform according to claim 1, characterized in that: In the third step, the ballast tank in the split structure is ballasted and dived with the assistance of the engineering vessel, dives to the working water depth, and is bound to the engineering vessel through an auxiliary cable.
8. The method for installing a split structure tension leg wind turbine platform according to claim 1, characterized in that: In the third step, after the main mooring rope of the tension key support device is connected, the entire ballast in the split structure is removed by using an engineering vessel to achieve the first pre-tensioning state of the tension key.
9. The method for installing a split structure tension leg wind turbine platform according to claim 1, characterized in that: In the fourth step, the floating body system is ballasted to a very small height range above or below the working waterline, wherein the height range is smaller than the height at which the pipe threads of the threaded rod mechanism pass through the floating body system.
10. The method for installing a split structure tension leg wind turbine platform according to claim 1, characterized in that: In the fourth step, when the floating body ballast system is unloaded to near the working draft height, the tensioning force of the tension tendon is precisely adjusted by locally adjusting the pipe thread to achieve the final tension state of the tension tendon.