Construction method of leachate collecting, guiding and discharging system

Through on-site hot melt welding and pipe sleeve connection, the connection unstable and construction difficulty of the leachate collection and drainage system in the landfill is solved, and the stable connection and efficient drainage effect are achieved, adapting to the garbage pile body Settlement deformation improves construction efficiency and economy.

CN118880989APending Publication Date: 2024-11-01EVERBRIGHT ECOLOGICAL RESTORATION (JIANGSU) CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411055765.5
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-02
Publication Date
2024-11-01

AI Technical Summary

Technical Problem

The construction method of the existing landfill leachate collection and drainage system has the problem of unstable connection of HDPE flower pipes, long construction time and high cost, and the connection between the leachate extraction well and the inspection well is difficult, which affects the impact of Construction progress and effect.

Method used

On-site butt hot melt welding is used to weld the flower pipes and the guide pipes are penetrated into the shaft. The overall structure is formed by single-rail welding. The inspection wells and extraction wells are connected with pipe sleeves to simplify the bottom sealing process and improve connection stability and construction efficiency.

Benefits of technology

The stable connection of the leachate collection and drainage system is achieved, the construction cycle is shortened, the drainage effect is improved, and the uneven settlement of the garbage pile is adapted to the impact and fracture resistance of the pipeline is enhanced.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure HDA0004976353840000011
    Figure HDA0004976353840000011
  • Figure HDA0004976353840000012
    Figure HDA0004976353840000012
  • Figure HDA0004976353840000021
    Figure HDA0004976353840000021
Patent Text Reader

Abstract

The invention relates to the technical field of waste landfill sewage treatment, in particular to the technical field of waste landfill leachate system construction. According to the construction method of the leachate collecting, guiding and discharging system, manufacturing and laying methods of the leachate inspection well and the leachate extraction well are improved, so that the overall stability of a leachate collecting, guiding and discharging pipeline is high, and the seepage discharging effect is good. The construction method that the pipes are connected through the sleeves can adapt to differential settlement of the garbage heap, bending deformation of a certain degree can be counteracted, serious dislocation and breakage caused by uneven stress of the pipes can be avoided, and it can be ensured that leachate can still be smoothly guided after deformation adjustment caused by local adaptation to heap settlement of the guide and discharge pipe is achieved. The construction method has the advantages of being good in economical efficiency, flexible in operation, short in construction period, resistant to impact and fracture after construction, resistant to bending and tensile deformation and the like.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of landfill sewage treatment, and in particular to the technical field of landfill leachate system construction. Background Art

[0002] In order to ensure the safe operation of the landfill and the stability of the pile after closure, it is necessary to control the liquid level height and water flow path position of the leachate seeping from the foot of the pile slope, so as to facilitate the timely discharge of the leachate from the foot of the slope and prevent the leachate from overflowing and polluting the surrounding environment.

[0003] Usually, the construction of leachate collection and drainage system in landfill includes the layout of leachate extraction wells and inspection wells, the connection between the flower pipes used to drain the leachate from the blind ditch at the foot of the pile slope, the connection between the collection and drainage pipes and the leachate extraction wells and inspection wells, and the connection between the drainage flower pipes and the drainage pipes at the ends of the leachate extraction wells and inspection wells.

[0004] The construction method of the landfill leachate collection and drainage system used in the prior art mainly includes the following steps:

[0005] (1) Excavation of blind trench;

[0006] (2) Collection and drainage pipe connection and laying:

[0007] Wrap the flower pipe with HDPE anti-seepage film and then tie it with plastic buckle soft joints to connect it, or clamp the two flower pipes with a hoop to connect them, or wrap the flower pipes with geotextiles or other geotextile materials and place them directly; weld the tees of the vertical shafts of the extraction well and the inspection well, and then connect them with the leachate drainage flower pipe through the tee branch pipe, or drill a hole at the position where the drainage pipe is to be installed at the end of the vertical shaft, and then insert the drainage pipe into the vertical shaft for further welding and sealing;

[0008] (3) Backfill the trench with garbage and compact it.

[0009] The construction method of the prior art mainly has the following shortcomings:

[0010] 1. There are shortcomings in the use of soft joints or simple wrapping of geotechnical materials for HDPE drainage pipes: if uneven settlement occurs in the pile, the soft joints may be torn off, the drainage pipes may be seriously misaligned, and the gravel filled in the blind ditch may enter the drainage pipes, affecting the drainage effect of the leachate and resulting in a reduction in the water conduction capacity of the pipe cross section.

[0011] 2. The shortcomings of the HDPE drainage pipe clamp elastic connection method: This method integrates rigid connection and flexible connection, the inner layer is sealed, and the outer layer uses stainless steel clamps or HDPE clamps to increase the strength of the interface. This type of connection method is greatly affected by the water level of the drainage blind ditch of the leachate at the construction site, has high requirements for the consistency of the horizontal axis of the pipes at both ends, takes a long time to construct, is difficult, and has relatively high costs.

[0012] 3. The leachate extraction well and inspection well adopt the segmented hot-melt welding tee, and the connection method between the tee branch pipe and the drainage pipe is insufficient: because the extraction well and inspection well are generally designed for φ630-φ1000 HDPE pipes, the position of the tee needs to be determined according to the actual site in addition to the reference design drawings. If it is welded in advance, it may not be connected to the drainage pipe on site. At the same time, the thicker the pipe diameter, the heavier the pipe weight. When the large-diameter pipe is hot-melt connected, the interface has a large heating area, the preheating time is long, and it is inconvenient to move. The more difficult it is to weld on site, the more difficult it is, which will affect the progress of on-site construction. Or, in order to save trouble, after the hole is opened at the end of the shaft where the drainage pipe is to be installed, the drainage pipe socket is inserted into the shaft. Because it is not further welded and sealed, some garbage and debris will enter the shaft along the gap between the horizontal drainage pipe and the shaft. Summary of the invention

[0013] In view of the shortcomings of the prior art, the present invention mainly improves the connection method between the flower pipe and the leachate extraction well and the leachate inspection well, and provides a construction method for a leachate collection and drainage system with flexible operation, short construction period, stable connection, impact resistance and fracture resistance.

[0014] The construction method of the leachate collection and drainage system provided by the present invention mainly comprises the following steps:

[0015] (1) Excavation of blind trench;

[0016] (2) Collection and drainage pipe connection and laying:

[0017] The flower pipes are butt-jointed and hot-melt welded on site before laying, and then the geotextile or geotextile is wrapped and sewn around the pipes according to the design drawings to prevent gravel and debris from entering the pipes;

[0018] Production and laying of leachate inspection well: Cut HDPE pipes as the main body of the vertical shaft, and locate and open through holes on the wall of the vertical shaft according to the elevations of the two ends of the drainage pipe in the blind ditch for drainage of leachate. Pass the leachate drainage flower pipe through the through hole of the vertical shaft. The through flower pipe is located at the middle upper end of the internal section of the vertical shaft. After positioning according to the design requirements, a rectangular groove section is cut out to serve as the inspection port for subsequent inspection of whether the drainage pipe is blocked. The outer wall of the vertical shaft pipe is polished by a grinder and then welded multiple times on a single track, so that the through drainage flower pipe and the outer wall of the vertical shaft form a whole leachate inspection well; install after sealing the bottom of the vertical shaft; connect the flower pipes between the leachate inspection wells;

[0019] Leachate extraction well fabrication and laying: After the leachate extraction well is fabricated and installed, the flower pipes between the extraction wells are connected;

[0020] (3) Backfill the trench with garbage and compact it.

[0021] Furthermore, the following method is adopted for laying the leachate extraction well in the step (2): HDPE pipe is cut as a vertical well, the position of the water outlet opening of the vertical well is determined according to the design requirements, the socket-shaped guide pipe is inserted into the opening of the vertical well, the outer wall of the opening of the vertical well is grinded by a grinder and then subjected to multiple single-track welding, so that the socket-shaped guide pipe and the vertical well form a leachate extraction well as a whole; the bottom of the vertical well is sealed and then installed; and the pipes between the leachate inspection wells are connected.

[0022] Furthermore, in step (2), when sealing the bottom of the shaft, a smaller HDPE baffle with a thickness of 1-2 cm is selected according to the specifications of the shaft. This method is simpler and cheaper than the conventional welding end sealing method.

[0023] Furthermore, in the step (2), the flower pipes between the leachate inspection well / leachate extraction well are connected by a pipe sleeve, and a HDPE pipe that is two sizes larger than the leachate drain flower pipe and has a length of 30cm-40cm is used as a sleeve to connect the two flower pipes. During installation, the sleeve is first installed on one side of the drain flower pipe on the leachate inspection well / leachate extraction well and then placed in a designated installation point, and the axis between the drain flower pipe and the drain flower pipe of the leachate inspection well / leachate extraction well is adjusted to be in the same straight line. During installation, the control elevation is adjusted by manually stepping on the pipe, and the sleeve is pushed forward with a tool until the sleeve is installed between the drain flower pipe and the drain flower pipe of the leachate inspection well / leachate extraction well; the gap between the sleeve and the drain flower pipe is adjusted by wrapping the HDPE film.

[0024] Specifically, when the leachate inspection well is manufactured in step (2), the leachate drainage pipe is passed through the through hole of the vertical well, so that the length of the drainage pipe extending out of the vertical well is greater than 50 cm.

[0025] Preferably, when the leachate inspection well is manufactured in step (2), the leachate drainage pipe is passed through the through hole of the vertical well, so that the length of the drainage pipe extending out of the vertical well is 50cm-100cm.

[0026] Specifically, when the leachate extraction well is prepared in step (2), the socket-and-spigot guide pipe is inserted into the vertical well opening by 5 cm-15 cm.

[0027] Beneficial Effects

[0028] The connection construction method of the leachate collection and drainage system provided by the present invention improves the manufacturing and laying methods of the leachate inspection well and the leachate extraction well, so that the leachate collection and drainage pipeline has strong overall stability and good drainage effect. The construction method of connecting the pipes through the casing can adapt to the uneven settlement of the garbage pile, offset a certain degree of bending and stretching deformation, and will not cause serious local dislocation and fracture due to uneven force on the pipes. It can ensure that the drainage pipes can still guide the leachate smoothly after deformation adjustment caused by local adaptation to the settlement of the pile. The construction method has good economy, flexible operation, short construction period, and the pipelines after construction are impact-resistant and fracture-resistant, and have the advantages of bending and stretching deformation resistance. BRIEF DESCRIPTION OF THE DRAWINGS

[0029] Figure 1 This is a schematic diagram of the structure of a leachate extraction well manufactured in a specific embodiment of the present invention;

[0030] Figure 2 This is a schematic diagram of the structure of a leachate inspection well manufactured in a specific embodiment of the present invention;

[0031] Figure 3 It is a schematic diagram of the pipe sleeve connection in a specific embodiment of the present invention.

[0032] In the figure: 1. vertical shaft; 2. drainage pipe connected to the vertical shaft; 3. opening; 4. inspection port; 5. pipe sleeve; 6. drainage pipe. DETAILED DESCRIPTION

[0033] In order to make the purpose, features and advantages of the present invention more obvious and easy to understand, the specific embodiments of the present invention are described in detail below in conjunction with the accompanying drawings. Specific details are set forth in the following description to facilitate a full understanding of the present invention, and those skilled in the art can make similar improvements without violating the concept of the present invention. Therefore, the protection scope of the present invention is not limited by the specific embodiments disclosed below.

[0034] Embodiment 1

[0035] In a specific embodiment of the present invention, the construction method of the leachate collection and drainage system mainly includes the following steps:

[0036] (1) Excavation of blind ditch trenches; 1. According to the coordinates shown in the design drawings, measure and lay out the blind ditch for drainage of leachate, and use an excavator to excavate the blind ditch trenches.

[0037] (2) Collection and drainage pipe connection and laying:

[0038] The flower pipes are butt-jointed and hot-melt welded on site and then laid. Then, geofilters or geotextiles are wrapped and sewn around the pipes according to the design drawings to prevent crushed stone and debris from entering the pipes. Usually, HDPE pipes are 6m or 9m long, and the diameter of the drainage pipes is generally 200mm-250mm. According to the design drawings, the manufacturer directly drills holes or drills holes on site, and then the welding length of each section of the flower pipe between the wells is determined in combination with the locations of the leachate extraction well and the leachate inspection well at the foot of the pile slope (generally, the distance between the two inspection wells is between 35m and 60m). After the flower pipes are butt-jointed and hot-melt welded on site, geofilters or geotextiles and other geotechnical materials are wrapped and sewn around the pipes according to the drawings to prevent crushed stone and debris from entering the pipes.

[0039] Production and laying of leachate inspection well: Cut the HDPE pipe as the main body of the vertical shaft, and locate and open a through hole on the wall of the vertical shaft according to the elevations of the two ends of the drainage pipe in the blind ditch of the leachate drainage. Pass the leachate drainage flower pipe through the through hole of the vertical shaft. This section of the drainage flower pipe extends out of the outer wall of the vertical shaft pipe by ≥50cm. The optimal distance is 50cm-100cm. This distance can be determined according to the length of the drainage flower pipe to be connected at the other end. The through flower pipe is located at the middle upper opening of the internal section of the vertical shaft. After positioning according to the design requirements, a rectangular groove section is cut out to serve as a subsequent inspection port for checking whether the drainage pipe is blocked, and then flushing and dredging the pipe. The perforated outer wall of the vertical shaft pipe is polished by a grinder and then welded multiple times on a single track so that the through drainage flower pipe and the outer wall of the vertical shaft form a leachate inspection well as a whole. The structure after welding is as follows Figure 2 As shown; install after sealing the bottom of the shaft; connect the flower pipes between the leachate inspection wells; the diameter of the HDPE pipes for the inspection wells is generally 630mm-1000mm. According to the design drawings and the actual well height required on site, cut the HDPE pipes as the shaft body, and locate and open holes on the shaft wall according to the elevations of the two ends of the drainage pipe in the leachate drainage blind ditch. Electric drills can be used on site with the aid of grinders to open holes.

[0040] Leachate extraction well fabrication and laying: After the leachate extraction well is fabricated and installed, the flower pipes between the extraction wells are connected;

[0041] (3) Backfill the trench with garbage and compact it. After the pipes are connected, backfill the blind ditch with gravel to the designed elevation, and then sew the geotechnical materials wrapped around the outer layer of the blind ditch. Use an excavator to backfill the garbage and compact it, and then carry out the subsequent garbage pile shaping construction.

[0042] Embodiment 2

[0043] In another specific embodiment of the present invention, the following method is used for laying the leachate extraction well in step (2) of the previous embodiment: HDPE pipes are cut as vertical wells, the position of the opening of the water outlet of the vertical well is determined according to the design requirements, the socket-shaped guide pipe is inserted into the opening of the vertical well by 5 cm-15 cm, the outer wall of the opening of the vertical well is polished by a grinder, and then single-track welding is performed for multiple times, so that the socket-shaped guide pipe and the vertical well form a leachate extraction well as a whole, and the structure after welding is as shown in FIG. Figure 1 As shown; install after sealing the bottom of the shaft; connect the flower pipes between the leachate inspection wells.

[0044] In a specific embodiment, when sealing the bottom of the shaft in step (2), a smaller HDPE baffle with a thickness of 1-2 cm is selected according to the specifications of the shaft to seal the bottom of the shaft. This method is simpler and cheaper than conventional welding end sealing.

[0045] Embodiment 3

[0046] In another specific embodiment of the present invention, the flower pipes between the leachate inspection well and the leachate extraction well in step (2) are connected by a pipe sleeve, and a HDPE pipe two sizes larger than the leachate drainage flower pipe and 30cm-40cm in length is used as a sleeve to connect the two flower pipes. The effect after the sleeve connection is as follows: Figure 3 As shown. During installation, first install the casing on one side of the drainage pipe on the leachate inspection well / leachate extraction well and then put it into the designated installation point. Adjust the axis between the drainage pipe and the drainage pipe of the leachate inspection well / leachate extraction well so that they are in the same straight line. During installation, manually step on the pipe to adjust the control elevation, and use tools to push the casing forward until the casing is installed between the drainage pipe and the drainage pipe of the leachate inspection well / leachate extraction well; the gap between the casing and the drainage pipe is adjusted by wrapping the HDPE film. During implementation, the appropriate HDPE casing can be selected according to the wall thickness and model of the drainage pipe. The HDPE casing is a 6m or 9m long pipe cut in sections on site. The casing generally uses an HDPE pipe that is two sizes larger than the leachate drainage pipe, and the length of the casing is between 30cm and 40cm. If the casing is too short, the horizontal axis of the drainage pipes at both ends will deviate to a certain extent, and the force of the drainage pipes at both ends cannot be effectively controlled. Later, the pipes may be misaligned with the gravel, garbage, and soil backfilled on the top of the pipes. If the casing is too long, it is difficult to construct the casing between the drainage pipes at both ends, and the casing pipe is also wasted.

[0047] In the specific implementation, before installing the drainage pipes and the leachate inspection well / leachate extraction well, the leachate seeping out of the excavated blind ditch should be drained first for subsequent construction. According to the design structure diagram of the leachate drainage blind ditch, geotextiles and other geotechnical materials are first laid in the ditch, and then a layer of gravel is laid. The ditch bottom elevation is measured with measuring equipment to ensure that the water flow elevation of the drainage pipe to be installed at the bottom of the ditch meets the design requirements, and then the welded leachate drainage pipe is installed, and the leachate inspection well and extraction well are installed. The drainage pipes are connected to the drainage pipes at both ends or one end of the leachate extraction well and inspection well with HDPE casing. After the drainage pipes are installed, the ditch top elevation needs to be measured again with measuring equipment. The local drainage pipe elevation can be adjusted with gravel to ensure smooth subsequent leachate flow.

Claims

1. A construction method for a leachate collection and drainage system, characterized in that: The main steps include: (1) Excavation of blind trench; (2) Collection and drainage pipe connection and laying: The flower pipes are butt-jointed and hot-melt welded on site before laying, and then the geotextile or geotextile is wrapped and sewn around the pipes according to the design drawings to prevent gravel and debris from entering the pipes; Production and laying of leachate inspection well: Cut HDPE pipes as the main body of the vertical shaft, and locate and open through holes on the wall of the vertical shaft according to the elevations of the two ends of the drainage pipe in the blind ditch for drainage of leachate. Pass the leachate drainage flower pipe through the through hole of the vertical shaft. The through flower pipe is located at the middle upper end of the internal section of the vertical shaft. After positioning according to the design requirements, a rectangular groove section is cut out to serve as the inspection port for subsequent inspection of whether the drainage pipe is blocked. The outer wall of the vertical shaft pipe is polished by a grinder and then welded multiple times on a single track, so that the through drainage flower pipe and the outer wall of the vertical shaft form a whole leachate inspection well; install after sealing the bottom of the vertical shaft; connect the flower pipes between the leachate inspection wells; Leachate extraction well fabrication and laying: After the leachate extraction well is fabricated and installed, the flower pipes between the extraction wells are connected; (3) Backfill the trench with garbage and compact it.

2. The construction method of the leachate collection and drainage system according to claim 1, characterized in that: The following method is used for making and laying the leachate extraction well in step (2): HDPE pipes are cut as vertical wells, the position of the water outlet opening of the vertical well is determined according to the design requirements, the socket-shaped guide pipe is inserted into the opening of the vertical well, the outer wall of the opening of the vertical well is grinded by a grinder and then subjected to multiple single-track welding, so that the socket-shaped guide pipe and the vertical well form a leachate extraction well as a whole; the bottom of the vertical well is sealed and then installed; and the pipes between the leachate inspection wells are connected.

3. The construction method of the leachate collection and drainage system according to claim 2, characterized in that: When sealing the bottom of the shaft in step (2), a smaller HDPE baffle with a thickness of 1-2 cm is selected according to the specifications of the shaft to seal the bottom of the shaft.

4. The construction method of the leachate collection and drainage system according to claim 3, characterized in that: In the step (2), the flower pipes between the leachate inspection well / leachate extraction well are connected by a pipe sleeve, and a HDPE pipe that is two sizes larger than the leachate drainage flower pipe and has a length of 30cm-40cm is used as a sleeve to connect the two flower pipes. During installation, the sleeve is first installed on one side of the drainage flower pipe on the leachate inspection well / leachate extraction well and then placed in a designated installation point, and the axis between the drainage flower pipe and the drainage flower pipe of the leachate inspection well / leachate extraction well is adjusted to be in the same straight line. During installation, the control elevation is adjusted by manually stepping on the pipe, and the sleeve is pushed forward with a tool until the sleeve is installed between the drainage flower pipe and the drainage flower pipe of the leachate inspection well / leachate extraction well; the gap between the sleeve and the drainage flower pipe is adjusted by wrapping the HDPE film.

5. The construction method of the leachate collection and drainage system according to claim 1, characterized in that: When the leachate inspection well is manufactured in step (2), the leachate drainage pipe is passed through the through hole of the vertical well, so that the length of the drainage pipe extending out of the vertical well is greater than 50 cm.

6. The construction method of the leachate collection and drainage system according to claim 1, characterized in that: When the leachate inspection well is prepared in step (2), the leachate drainage pipe is passed through the through hole of the vertical well, so that the length of the drainage pipe extending out of the vertical well is 50cm-100cm.

7. The construction method of the leachate collection and drainage system according to claim 2, characterized in that: When the leachate extraction well is prepared in step (2), the socket-and-spigot guide pipe is inserted into the vertical well opening by 5 cm-15 cm.