Mechanical complete equipment and method for installing spacing rod of power transmission line
By designing the mechanized set of equipment for installation of spacer rods in transmission lines, including lifting devices and spacer rod installation trolleys, the problems of large labor investment in installation of spacer rods in multi-split wires and high construction risks are solved, and efficient and safe spacer rod installation is achieved, and construction is improved. Efficiency and mechanization level.
Patent Information
- Application Number
- CN202411063283.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-05
- Publication Date
- 2024-11-01
AI Technical Summary
In the prior art, the installation of multi-split conductor spacer rods in transmission lines requires a lot of manpower, resulting in high-altitude work labor intensity and high construction risks, and poses a major safety accident hazard.
A complete set of equipment for mechanized installation of spacer rods in transmission lines is designed, including lifting devices, spacer rod hangers and spacer rod installation trolleys. The vertical lifting, online transportation and rapid installation of spacer rods are achieved by using lifting ropes and walking devices, and the distance measurement is carried out. The device ensures accurate spacing of the spacing rods.
It reduces manpower investment, reduces the labor intensity and construction risks of spacer rod installation, improves construction efficiency, and improves the level of mechanized equipment for high-altitude operations, making construction safer and more efficient.
Smart Images

Figure CN118889260A_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to the technical field of spacer installation in power transmission line construction, and in particular relates to a complete set of mechanized equipment for installing spacer bars in power transmission line and an installation method. Background Art
[0002] Although the spacer bars used in the installation of multi-split conductors are a kind of accessory hardware, they are related to the operating safety and service life of the multi-split conductors. Since a large number of spacer bars need to be installed between the spans of multi-split conductors of transmission lines, and they are heavy, it is labor-intensive to drag the spacer bars at high altitudes by manpower, and the climbing and descending processes rely entirely on manual dragging and braking. The process poses a great safety hazard and the construction risk is high.
[0003] Therefore, it is urgent to develop a complete set of transmission line spacer installation equipment that can realize vertical lifting of spacer bars, online transportation, online measurement, and rapid installation of spacer bars. Summary of the invention
[0004] In order to solve the problems in the prior art, the present invention provides a complete set of mechanized equipment for installing spacer bars of power transmission lines and an installation method.
[0005] In order to solve the above technical problems, the present invention adopts the following technical solutions: A complete set of mechanized equipment for installing spacer bars of power transmission lines, including a lifting device, a lifting rope, a spacer bar hanger and a spacer bar installation trolley, wherein: The lifting device has two installation positions, including the tower installation position and the spacer bar installation trolley installation position; when the lifting device is installed at the tower position, the lifting device cooperates with the lifting rope to lift the spacer bar installation trolley to a predetermined position and place it on the conductor; when the lifting device is installed at the spacer bar installation trolley installation position, the lifting device cooperates with the lifting rope to lift the spacer bar hanger to a predetermined position; A spacer rod hanger, used for hanging the spacer rods on the spacer rod hanger; The spacer bar installation trolley comprises a frame, a running device and a distance measuring device. The running device is used for running on the conductor, and the distance measuring device is used for determining the distance between the spacer bars.
[0006] Furthermore, the running device is symmetrically arranged on the left and right sides of the frame, and the running device on each side includes two wheel hub motors distributed front and back, and the wheel hub motors are integrated with running wheels; the two wheel hub motors are installed on the wheel hub motor mounting frame, and the wheel hub motor mounting frame is connected to the frame; An electric push rod extending toward the conducting wire is installed in the middle of the wheel hub motor mounting frame, and a brake pad is installed at the lower part of the electric push rod.
[0007] Furthermore, a horizontally extending square tube is fixed on the hub motor mounting frame, a sleeve is fixed at a corresponding position on the frame, and the square tube and the sleeve are plug-fitted and fixed by a pin to form a telescopic sleeve structure with adjustable length.
[0008] Furthermore, a tensioning device is provided in cooperation with the traveling device, and the tensioning device includes a lifting cross arm extending left and right, and both ends of the lifting cross arm are respectively connected to a T-shaped adjustment frame, and the front and rear ends of the T-shaped adjustment frame are respectively provided with a tensioning wheel assembly, and the tensioning wheel assembly corresponds to the traveling wheel up and down; The lifting cross arm is connected with a lifting drive mechanism for driving the lifting cross arm to move up and down.
[0009] Furthermore, the lifting drive mechanism includes a screw, a stepper motor, a nut, a screw stabilizing frame, a screw support seat and a guide column, wherein: the screw is arranged vertically, the lower end of the screw is transmission-connected to the stepper motor, and the stepper motor is fixed to the frame through a motor mounting frame; a nut cooperating with the screw is provided on the screw, and the nut is connected to the lifting cross arm; The screw stabilizer frame is located above the lifting cross arm and is fixedly connected to the frame. A screw support seat is fixedly provided on the screw stabilizer frame, and the upper end of the screw is rotatably connected to the screw support seat. At the same time, a guide column extending downward is fixed on the screw stabilizer frame, and the guide column passes through the lifting cross arm and slides with it.
[0010] Furthermore, the frame of the spacer bar installation trolley is a box-type structure, and a suspension sleeve for installing a lifting device is provided above the frame; The bottom of the frame is a base plate, which is provided with a guide sleeve for fixing the lower end of the guide post; An electronic control box is also integrated at the rear end of the frame.
[0011] Furthermore, a guide pulley block is provided at the lower part of the frame, and the lifting rope passes through the guide pulley block.
[0012] Furthermore, the spacer rod rack is a T-shaped structure.
[0013] Furthermore, the distance measuring device is installed at the front end of the frame, and the mounting surface on the frame for mounting the distance measuring device is an inclined surface; The distance measuring device comprises two fixed plates and a slide rail connected between the two fixed plates, a slider is mounted on the slide rail and can move along the slide rail; a slider top screw is provided on the slider for fixing the position of the slider; The slider is provided with a slider slot, and the rangefinder is installed in the slider slot and is fixed by pressing the rangefinder top screw; The front end of the frame is also provided with an opening for emitting the measuring light emitted by the rangefinder.
[0014] The present invention also discloses a method for installing a transmission line spacer, based on the transmission line spacer installation mechanized complete set of equipment, which is characterized by comprising the following steps: (1) After the operator carries the lifting device and one end of the lifting rope to the designated position, he / she installs the lifting device at the installation position on the tower and fixes the rope end. The ground staff fixes the other end of the rope end to the hanging point of the spacer bar installation trolley. The operator on the tower drives the lifting device to lift the spacer bar installation trolley onto the tower, then places the running device of the spacer bar installation trolley on the conductor and presses the tensioning device. (2) Remove the lifting device and install it on the installation position of the spacer bar installation trolley. The ground staff installs the spacer bar bracket on the ground end of the lifting rope and hangs the spacer bar on the spacer bar bracket. The operator on the tower drives the lifting device again to lift the spacer bar to the lower part of the conductor; (3) Set the spacing of the spacer bars on the distance measuring device, and start the walking device to drive the spacer bar installation trolley to move; When the spacer bar installation trolley reaches the first installation position, the distance measuring device sends a signal, stops the car, takes out the next spacer bar and completes the installation manually; When the spacer bar installation trolley reaches the second installation position, the distance measuring device sends a signal, stops the car, takes out the next spacer bar and completes the installation manually; Repeat the above steps to complete the installation of all spacers.
[0015] Beneficial effects of the present invention: The present invention conducts key technical research on a complete set of equipment for installing spacer bars for power transmission lines, effectively solving the construction problem of a large number of spacer bars for multiple split conductors in power transmission lines and heavy installation tasks, reduces the manpower input in installing spacer bars for high-altitude operations on power transmission lines, reduces the labor intensity and construction risks of the spacer bar installation process, improves the construction efficiency of installing spacer bars for power transmission lines, improves the level of mechanized equipment for high-altitude operations on power transmission lines, and further advances the comprehensive mechanization of power transmission line construction. BRIEF DESCRIPTION OF THE DRAWINGS
[0016] Figure 1 It is a schematic diagram of the connection between the lifting device and the spacer rod mounting trolley in the present invention; Figure 2 It is a schematic diagram of the connection between the lifting device and the spacer rod bracket in the present invention; Figure 3 A schematic diagram of a mechanized complete set of equipment for installing spacer bars on power transmission lines according to the present invention; Figure 4 for Figure 3 Side view of Figure 5 It is a schematic diagram of the spacer bar installation trolley of the present invention; Figure 6 for Figure 5 Side view of Figure 7 for Figure 5 Rear view of Figure 8 It is a schematic diagram of the walking device in the present invention; Fig. 9 is a schematic diagram of the tensioning device in the present invention; Fig.10 is a schematic diagram of a distance measuring device in the present invention; Fig.11 is a schematic diagram of a frame of the present invention; Fig.12 for Fig.11 The middle section of .
[0017] The drawings are only used for illustrative purposes and should not be construed as limitations on this patent. In order to better illustrate this embodiment, some parts of the drawings may be omitted, enlarged, or reduced, and do not represent the size of the actual product. For those skilled in the art, it is understandable that some well-known structures and their descriptions in the drawings may be omitted. DETAILED DESCRIPTION
[0018] The technical solutions in the embodiments of the present invention will be described clearly and completely below in conjunction with the accompanying drawings in the embodiments of the present invention.
[0019] like Figures 1 to 12 As shown, this embodiment provides a complete set of mechanized equipment for installing spacer bars in power transmission lines, including a lifting device, a lifting rope 2, a spacer bar hanger 4 and a spacer bar installation trolley 3, wherein the lifting device is a rope climbing machine 1.
[0020] The rope climbing machine 1 has two installation positions, including an installation position on a tower and an installation position of a spacer rod installation trolley.
[0021] When the rope climbing machine 1 is installed on the tower, the rope climbing machine 1 is installed at a suitable position on the tower, the rope end is fixed, and the ground staff connects the other end of the rope end to the hanging point of the spacer bar installation trolley through the U-shaped ring 7, so that the spacer bar installation trolley can be lifted to the predetermined position and placed on the conductor 6.
[0022] When the rope climbing machine 1 is installed at the installation position of the spacer bar installation trolley, one end of the lifting rope 2 is wrapped around the pulley of the rope climbing machine 1, and the safety cover is buckled. The hanging hole of the rope climbing machine 1 passes through the upper pin shaft 8, and the upper pin shaft is fastened to the suspension sleeve on the upper part of the frame through nuts and washers. The other end of the lifting rope 2 is installed with the spacer bar hanger 4. The spacer bar hanger 4 is a T-shaped structure, and the spacer bars 5 are evenly placed on both sides. The operator on the tower drives the rope climbing machine 1, lifts the spacer bar 5 to the lower part of the conductor 6, sets the spacer bar spacing, follows the trolley, and removes the spacer bar for installation according to the signal prompt from the distance measuring device.
[0023] Since the mechanized equipment for installing spacers on power lines is mainly for four-split conductors, the spacer installation trolley 3 travels on the multi-split conductors of the transmission line, which involves the reliability and stability of the trolley's travel on the line. Considering that the number of spacers mounted on the online spacer installation trolley is large and the load is heavy, the single-line side-hanging scheme has unstable factors such as unbalanced load and overload, it is planned to adopt a double-hanging drive scheme, that is, the walking device is suspended on two multi-split sub-conductors and travels. Considering the semi-rigid characteristics of the conductors, a four-wheel drive structure is made to optimize the driving performance.
[0024] Specifically, the spacer bar installation trolley 3 includes a traveling device 10 , a tensioning device 20 , a frame 30 , a distance measuring device 40 , a guide pulley block 50 and an electric control box 60 .
[0025] The running device 10 is symmetrically arranged on the left and right sides of the frame. The running device 10 on each side includes two wheel hub motors 11 distributed front and rear, and the wheel hub motors 11 are integrated with running wheels; the two wheel hub motors 11 are installed on the wheel hub motor mounting frame 12, and the wheel hub motor mounting frame 12 is connected to the frame 30 to form a single-side drive unit. The running devices 10 on both sides form four wheel hub motors that are independently driven, and the installation and control are simple.
[0026] The middle part of the hub motor mounting frame 12 is provided with an electric push rod 13 extending toward the wire, and the lower part of the electric push rod 13 is provided with a brake pad 14. In this way, a double-side parking brake is formed to ensure the reliability and safety of the large-slope parking brake.
[0027] Two horizontally extending square tubes 15 are welded on the hub motor mounting frame 12, and two sleeves 36 are fixed at corresponding positions on the frame 30. The square tubes 15 are plugged into the sleeves 36 and fixed by pins 37 to form a telescopic sleeve structure with adjustable length. The telescopic sleeve structure can adjust the lateral wheelbase of the left and right walking devices to adapt to different wire spacings.
[0028] In order to increase the walking friction and improve the climbing ability, a tensioning device 20 is designed. The tensioning device 20 includes a lifting cross arm 26 extending left and right, and the two ends of the lifting cross arm 26 are connected to a T-shaped adjustment frame 28 through a pin shaft 37. When the T-shaped adjustment frame 28 is rotated to a horizontal position, it forms a contact limit with the lifting cross arm 26. The front and rear ends of the T-shaped adjustment frame 28 are respectively provided with a tensioning wheel assembly 29, and the tensioning wheel assembly 29 corresponds to the hub motor 11 one by one; The lifting cross arm 26 is connected to a lifting drive mechanism to drive it to move up and down. The lifting drive mechanism includes a screw 23, a stepping motor 22, a nut 24, a screw stabilizing frame 210, a screw support seat 211 and a guide column 212, wherein: the screw 23 is vertically arranged, the lower end of the screw 23 is drivingly connected to the stepping motor 22, and the stepping motor 22 is fixed to the anchor plate 310 of the frame through the motor mounting frame 21; the screw 23 is provided with a nut 24 that cooperates with it, and the nut 24 is fixedly connected to the lifting cross arm 26 through a screw 25.
[0029] The screw rod 23 has a large stroke. In order to enhance the stability of the screw rod, a screw rod support seat 211 is arranged on the top for guidance. The screw rod support seat 211 is installed on the screw rod stabilizing frame 210. The vertical surface of the screw rod stabilizing frame 210 is connected to the fixed cross brace 39 of the spacer rod mounting trolley by bolts.
[0030] The screw stabilizer 210 is provided with a guide post 212 extending downward, the top of the guide post 212 passes through the through hole on the screw stabilizer 210, and is limited by the shaft clamp spring. The middle of the guide post 212 passes through the lifting cross arm 26 and slides with it. The bottom of the guide post 212 is stuck in the guide sleeve 311 of the anchor plate 310.
[0031] During operation, the stepper motor 22 drives the nut 24 to drive the lifting cross arm 26 and the T-shaped adjustment frame 28 and the tensioning wheel assembly 29 installed on the cross arm to move up and down along the guide column 212 to achieve the tensioning and retracting of the tensioning device.
[0032] The frame body panel 8 is a cold-rolled plate bending and welding structure, which is a box-type structure as a whole, with high strength and light weight. A suspension sleeve 31 for installing a lifting device is provided above the frame 30. The suspension sleeve 31 is fixedly connected to the upper end of the suspension column 32, and the lower end of the suspension column 32 is fixedly connected to the suspension cross brace 33 fixed in the frame and a foot rib plate 35 is added at the connection. At the same time, a suspension diagonal brace 34 is also provided between the suspension column 32 and the frame 30.
[0033] A sleeve 36 is welded to the upper part of the frame 30. A fixed cross brace 39 is welded to the middle part of the frame 30 for fixed connection with the screw stabilizer frame 210. The bottom of the frame 30 is a base plate 310, and guide sleeves 311 are welded to the left and right sides of the base plate 310 to fix the lower end of the guide column 212. The rear end of the frame 30 is also integrated with an electric control box 312, which is a closed chamber for installing electrical components such as battery packs and controllers, and is designed with an electric control box door 313. Hinged handles 314 are installed on the upper part of both ends of the frame 30 to facilitate transfer and transportation.
[0034] A guide pulley block 50 is also provided at the lower part of the frame 30, and the lifting rope 2 passes through the guide pulley block 50, so that the guide pulley block 50 can limit the lifting rope 2. When the trolley climbs a slope or there is a height difference between the front and rear wires, the body is inclined, and a spacer bar is hung under the rope. If there is no guide pulley block, the swing amplitude of the lifting rope 2 is large, and the box will wear the rope.
[0035] The distance measuring device 40 is installed at the front end of the frame 30, and the mounting surface of the frame for mounting the distance measuring device is an inclined surface. The distance measuring device 40 includes two fixing plates 41, and a cylindrical slide rail 42 connected between the two fixing plates 41. A slider 43 is installed on the slide rail 42 and can move along the slide rail; a slider top screw 44 is provided on the slider 43 to fix the position of the slider 43. The slider 43 is provided with a slider slot, and the rangefinder 45 is installed in the slider slot and is pressed and fixed by the rangefinder top screw 46. The front end of the frame 30 is also provided with an opening for the measurement light emitted by the rangefinder to be emitted.
[0036] When the rangefinder 45 moves along the inclined plane with the slider 43, there must be an intersection between the track and the box inside the spacer bar. By adjusting the slider 43 so that the measuring light emitted by the rangefinder 45 is projected onto a certain point inside the box, the distance between the rangefinder and the spacer bar can be accurately measured.
[0037] This embodiment also discloses a method for installing a transmission line spacer, based on a complete set of mechanized equipment for installing a transmission line spacer, comprising the following steps: (1) After the operator carries the rope climbing machine and one end of the lifting rope to the designated position, the rope climbing machine 1 is installed at a suitable position on the tower and the rope end is fixed. The ground staff fixes the other end of the rope end to the hanging point of the installation trolley. The operator on the tower drives the rope climbing machine 1 to lift the spacer bar installation trolley 3 onto the tower, and then places the hub motor 11 and the running wheel of the spacer bar installation trolley on the conductor 6, and compresses the tensioning wheel assembly 29.
[0038] (1) Remove the rope climbing machine 1 and install it on the corresponding position of the spacer installation trolley. The ground staff installs the spacer hanger 4 on the ground end of the lifting rope 2 and hangs the spacer 5 on the spacer hanger 4. The operator on the tower drives the rope climbing machine 1 again to lift the spacer 5 to the lower part of the conductor.
[0039] (3) Adjust the distance meter 45 on the distance measuring device, set the spacing of the spacer bars, and start the traveling device; When the spacer bar installation trolley reaches the next installation position, the distance meter will sound and light alarm, stop the car, remove the first spacer bar and complete the installation; When the spacer bar installation trolley reaches the second installation position, the distance meter will sound and light alarm, stop the car, remove the second spacer bar and complete the installation manually; Repeat the above steps to complete the installation of all spacers.
[0040] The present invention effectively solves the difficult construction problems of a large number of spacer bars for multiple split conductors of a transmission line and heavy tasks, reduces the manpower input in the installation of spacer bars for high-altitude operations on transmission lines, reduces the labor intensity and construction risks of the spacer bar installation process, improves the construction efficiency of the installation of spacer bars for transmission lines, improves the level of mechanized equipment for high-altitude operations on transmission lines, and further improves the comprehensive mechanized construction of transmission lines, with low labor intensity and high installation efficiency.
[0041] The above embodiments are only used to illustrate rather than limit the technical solutions of the present invention. Although the present invention is described in detail with reference to the above embodiments, those skilled in the art should understand that the present invention can still be modified or replaced by equivalents. Any modification or partial replacement that does not depart from the spirit and scope of the present invention should be included in the scope of the claims of the present invention.
[0042] If the words "first", "second", etc. are used in this document to limit components, those skilled in the art should know that the use of "first" and "second" is only to facilitate the description of the present invention and simplify the description. Unless otherwise stated, the above words have no special meaning.
[0043] In the description of the present invention, it is to be understood that the terms “center”, “longitudinal”, “lateral”, “length”, “width”, “thickness”, “up”, “down”, “front”, “back”, “left”, “right”, “vertical”, “horizontal”, “top”, “bottom”, “inside”, “outside”, “clockwise”, “counterclockwise”, “axial”, “radial”, “circumferential”, etc., indicating orientations or positional relationships based on the orientations or positional relationships shown in the accompanying drawings, are only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply that the referred device or element must have a specific orientation, be constructed and operated in a specific orientation, and therefore should not be understood as limiting the present invention.
[0044] In the description of the present invention, it should be noted that, unless otherwise clearly specified and limited, the terms "installed", "connected", and "connected" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or it can be indirectly connected through an intermediate medium, or it can be the internal communication of two components. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.
Claims
1. A complete set of mechanized equipment for installing spacer bars on power transmission lines, characterized by: It includes a lifting device, a lifting rope, a spacer rod bracket and a spacer rod installation trolley, wherein: The lifting device has two installation positions, including the tower installation position and the spacer bar installation trolley installation position; when the lifting device is installed at the tower position, the lifting device cooperates with the lifting rope to lift the spacer bar installation trolley to a predetermined position and place it on the conductor; when the lifting device is installed at the spacer bar installation trolley installation position, the lifting device cooperates with the lifting rope to lift the spacer bar hanger to a predetermined position; A spacer rod hanger, used for hanging the spacer rods on the spacer rod hanger; The spacer bar installation trolley comprises a frame, a running device and a distance measuring device. The running device is used for running on the conductor, and the distance measuring device is used for determining the distance between the spacer bars.
2. The complete set of mechanized equipment for installing transmission line spacers according to claim 1 is characterized in that: The running device is symmetrically arranged on the left and right sides of the frame, and the running device on each side includes two wheel hub motors distributed front and back, and the wheel hub motors are integrated with running wheels; the two wheel hub motors are installed on the wheel hub motor mounting frame, and the wheel hub motor mounting frame is connected to the frame; An electric push rod extending toward the conducting wire is installed in the middle of the wheel hub motor mounting frame, and a brake pad is installed at the lower part of the electric push rod.
3. The mechanized complete set of equipment for installing transmission line spacers according to claim 2 is characterized in that: A horizontally extending square tube is fixed on the hub motor mounting frame, a sleeve is fixed at a corresponding position on the vehicle frame, and the square tube and the sleeve are plug-fitted and fixed by a pin to form a telescopic sleeve structure with adjustable length.
4. The complete set of mechanized equipment for installing transmission line spacers according to claim 2 is characterized in that: A tensioning device is provided in conjunction with the traveling device, and the tensioning device includes a lifting cross arm extending left and right, and both ends of the lifting cross arm are respectively connected to a T-shaped adjustment frame, and the front and rear ends of the T-shaped adjustment frame are respectively provided with a tensioning wheel assembly, and the tensioning wheel assembly corresponds to the traveling wheel up and down; The lifting cross arm is connected with a lifting drive mechanism for driving the lifting cross arm to move up and down.
5. The complete set of mechanized equipment for installing transmission line spacers according to claim 4 is characterized in that: The lifting drive mechanism includes a screw, a stepper motor, a nut, a screw stabilizing frame, a screw support seat and a guide column, wherein: the screw is arranged vertically, the lower end of the screw is connected to the stepper motor by transmission, and the stepper motor is fixed to the frame through the motor mounting frame; the screw is provided with a nut matched with it, and the nut is connected to the lifting cross arm; The screw stabilizer frame is located above the lifting cross arm and is fixedly connected to the frame. A screw support seat is fixedly provided on the screw stabilizer frame, and the upper end of the screw is rotatably connected to the screw support seat. At the same time, a guide column extending downward is fixed on the screw stabilizer frame, and the guide column passes through the lifting cross arm and slides with it.
6. The complete set of mechanized equipment for installing spacer bars of power transmission lines according to claim 5 is characterized in that: The frame of the spacer bar installation trolley is a box-type structure, and a suspension sleeve for installing a lifting device is provided above the frame; The bottom of the frame is a base plate, which is provided with a guide sleeve for fixing the lower end of the guide post; An electronic control box is also integrated at the rear end of the frame.
7. The complete set of mechanized equipment for installing spacer bars of power transmission lines according to claim 1 is characterized in that: A guide pulley block is also provided at the lower part of the frame, and the lifting rope passes through the guide pulley block.
8. The complete set of mechanized equipment for installing spacer bars of power transmission lines according to claim 1 is characterized in that: The spacer rod rack is a T-shaped structure.
9. The complete set of mechanized equipment for installing spacer bars of power transmission lines according to claim 1 is characterized in that: The distance measuring device is installed at the front end of the frame, and the mounting surface on the frame for mounting the distance measuring device is an inclined surface; The distance measuring device comprises two fixed plates and a slide rail connected between the two fixed plates, a slider is mounted on the slide rail and can move along the slide rail; a slider top screw is provided on the slider for fixing the position of the slider; The slider is provided with a slider slot, and the rangefinder is installed in the slider slot and is fixed by pressing the rangefinder top screw; The front end of the frame is also provided with an opening for emitting the measuring light emitted by the rangefinder.
10. A method for installing a transmission line spacer, based on the mechanized complete set of equipment for installing a transmission line spacer according to any one of claims 1 to 9, characterized in that The following steps are involved: (1) After the operator carries the lifting device and one end of the lifting rope to the designated position, he / she installs the lifting device at the installation position on the tower and fixes the rope end. The ground staff fixes the other end of the rope end to the hanging point of the spacer bar installation trolley. The operator on the tower drives the lifting device to lift the spacer bar installation trolley onto the tower, then places the running device of the spacer bar installation trolley on the conductor and presses the tensioning device. (2) Remove the lifting device and install it on the installation position of the spacer bar installation trolley. The ground staff installs the spacer bar bracket on the ground end of the lifting rope and hangs the spacer bar on the spacer bar bracket. The operator on the tower drives the lifting device again to lift the spacer bar to the lower part of the conductor; (3) Set the spacing of the spacer bars on the distance measuring device, and start the walking device to drive the spacer bar installation trolley to move; When the spacer bar installation trolley reaches the first installation position, the distance measuring device sends a signal, stops the car, takes out the next spacer bar and completes the installation manually; When the spacer bar installation trolley reaches the second installation position, the distance measuring device sends a signal, stops the car, takes out the next spacer bar and completes the installation manually; Repeat the above steps to complete the installation of all spacers.