Reusable safety belt suspension device for building construction and construction method

CN118892629APending Publication Date: 2024-11-05CHINA CONSTR EIGHTH ENG BUREAU (GANSU) CONSTR CO LTD
View PDF 5 Cites 0 Cited by

Patent Information

Application Number
CN202411270890.8
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-09-11
Publication Date
2024-11-05

AI Technical Summary

Technical Problem

The installation of steel wire ropes for safety belts in existing construction work involving high-altitude and edge-prone operations is time-consuming, labor-intensive, wastes a lot of materials, and has high repair costs, making it difficult to improve construction efficiency and reduce costs while ensuring construction safety.

Method used

A reusable safety belt suspension device is adopted, which involves threading ropes through bolt holes inside the shear wall and securing them with limiting and hanging mechanisms, including components such as steel pipe sleeves, rope clips, and moving rings, to ensure stable installation and safety for multiple workers.

Benefits of technology

It achieves stable installation of seat belt suspension, reduces material waste, improves construction efficiency, supports multiple people working simultaneously, and reduces construction costs and subsequent repair expenses.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118892629A_ABST
    Figure CN118892629A_ABST
Patent Text Reader

Abstract

The invention discloses a reusable safety belt hanging device for building construction and a construction method, and relates to the technical field of building construction.The reusable safety belt hanging device comprises two shear walls, screw holes are formed in the inner sides of the two shear walls, ropes penetrate through the inner sides of the two screw holes, and the reusable safety belt hanging device further comprises a limiting mechanism and a plurality of hanging mechanisms; the limiting mechanisms are arranged at the two ends of the rope; one end of the rope penetrates through the interior of the first steel pipe sleeve and is firstly fixed in a factory through the aluminum pressing sleeve and the first rope clamp, the length of the rope is controlled according to the distance between the screw holes between the two shear walls on site, the other end of the rope penetrates through the inner sides of the two screw holes correspondingly, and the other end of the rope penetrates through the interior of the second steel pipe sleeve; the multiple second rope clamps are used for fixing, the overall mounting and fixing effect is ensured, the screw holes in the inner sides of the two shear walls are used for replacing embedded steel pipes, waste of embedded steel pipe materials is reduced, and meanwhile mounting and turnover use are facilitated.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of building construction, and in particular to a reusable safety belt hanging device for building construction and a construction method. Background Art

[0002] With the development of the country's infrastructure and construction industry, the requirements of government departments and companies for safe production are becoming increasingly stringent, and the requirements for construction safety management are constantly increasing. However, according to data released by the National Bureau of Statistics, the incidence rate of fall accidents from heights still ranks first among the "five major injuries" in construction projects. The probability of fall accidents from heights is extremely high, accounting for about half or more of the total number of accidents of all types, and the risk of casualties is extremely high.

[0003] The traditional installation methods of hanging wire ropes for safety belts for high-altitude and edge operations are basically divided into two methods: fixing the wire ropes through pre-buried steel pipes during construction of the main structure and directly fixing them with wire rope clips on the main structure. Fixing the wire ropes through pre-buried steel pipes during construction of the main structure has the disadvantages of serious waste of steel pipe materials, high repair costs after cutting off the pre-buried steel pipes, and loose fixation; while directly fixing the wire ropes with wire rope clips on the main structure has the disadvantages of serious waste of wire ropes and time-consuming and laborious construction. Therefore, how to effectively carry out high-altitude and edge operations under the premise of ensuring construction safety, achieve the purpose of ensuring construction quality and progress, ensuring construction safety, and at the same time reduce construction costs and improve construction efficiency is an important issue.

[0004] In order to effectively avoid safety accidents caused by inadequate protection during construction work at heights or on the edges, and to solve a series of problems such as the time-consuming and labor-intensive installation of safety belt suspension wire ropes for construction work at heights or on the edges, serious material waste, and high subsequent repair costs, the present invention proposes a reusable safety belt suspension device and construction method for construction work. Summary of the invention

[0005] The object of the present invention is to provide a reusable safety belt hanging device and a construction method for building construction to solve the problems raised in the above-mentioned background technology.

[0006] The technical solution of the present invention is: a reusable safety belt hanging device and construction method for construction, including two shear walls, the inner sides of the two shear walls are provided with screw holes, the inner sides of the two screw holes are penetrated by ropes, and also include: a limiting mechanism and a plurality of hanging mechanisms, the limiting mechanism is arranged at both ends of the rope; the plurality of hanging mechanisms are respectively arranged on the outside of the rope; the limiting mechanism includes a steel pipe sleeve 1 sleeved on one end of the rope, and a steel pipe sleeve 2 sleeved on the other end of the rope, one end of the rope is penetrated through the interior of the steel pipe sleeve 1 and is fixed by an aluminum pressing sleeve and a rope clamp 1, and the other end of the rope is penetrated through the interior of the steel pipe sleeve 2 and is fixed by a plurality of rope clamps 2.

[0007] Preferably, one of the hanging mechanisms includes a moving ring slidably arranged on the outside of the rope, a connecting rod is fixed to the lower end of the moving ring, a hanging ring is fixed to the lower end of the connecting rod, a sliding rod is slidably arranged through the inner side of the moving ring, a limiting ring is fixed to the lower end of the sliding rod, and a handle is fixed to the upper end of the sliding rod, a spring is sleeved on the outer side of the sliding rod, one end of the spring is fixed to the outside of the limiting ring, and the other end of the spring is fixed to the inside of the moving ring.

[0008] Preferably, PVC tubes are provided on the inner sides of the two screw holes.

[0009] Preferably, a safety bend is provided at one end of the rope fixed by a plurality of rope clips.

[0010] Preferably, wooden squares are fitted on the outer sides of the two shear walls, and the other sides of the two wooden squares are fitted with the first steel pipe sleeve and the second steel pipe sleeve respectively, and the ropes are passed through the inner sides of the two wooden squares.

[0011] Preferably, the diameter of the rope is 10 mm, and the diameters of the steel pipe sleeve one and the steel pipe sleeve two are both 50 mm.

[0012] Preferably, the inner wall of the limiting ring is coated with a polytetrafluoroethylene coating.

[0013] The present invention also discloses a construction method of a reusable safety belt suspension device for building construction, comprising the following steps:

[0014] Step 1: Customize the fixed end connection node according to the drawing. The length of the rope can be adjusted according to the actual situation on site;

[0015] Step 2: Purchase two steel pipe sleeves and two rope clamps required for connecting and fixing the movable end of the rope as needed;

[0016] Step 3: Set multiple movable rings on the outside of the rope as needed, install the rope in the edge and high-altitude working areas according to the positions of the two screw holes of the main structure on site, and pass the movable end of the rope through the inside of the second steel pipe sleeve, fix it with multiple rope clamps, and complete the overall limit;

[0017] Step 4: Inspection and acceptance, fix the safety belt on multiple lifting rings to carry out the operation.

[0018] The present invention provides a reusable safety belt suspension device and construction method for construction by improvement, which has the following improvements and advantages compared with the prior art:

[0019] Firstly, the present invention passes one end of the rope through the inside of a steel pipe sleeve and fixes it in the factory by means of an aluminum compression sleeve and a rope clamp. The length of the rope is controlled according to the distance between the screw holes between the two shear walls on site. The other end of the rope is passed through the inside of the two screw holes respectively, and the other end of the rope is passed through the inside of a steel pipe sleeve and fixed by means of a plurality of rope clamps, thereby ensuring the overall installation and fixing effect. The screw holes on the inner sides of the two shear walls are used to replace the embedded steel pipes, thereby reducing the waste of the embedded steel pipe materials and facilitating installation and turnover.

[0020] Secondly, the present invention provides a plurality of movable rings on the outside of the rope. Before completing the installation between the rope and the screw hole, the plurality of handles are respectively grasped and pulled to engage the plurality of movable rings to the outside of the rope. Then the plurality of handles are loosened, and under the elastic potential energy of the plurality of springs, the plurality of limit rings are reset to squeeze the outside of the rope to ensure that a certain distance is maintained between the plurality of movable rings. The buckle of the safety belt is engaged with the plurality of lifting rings, which can support multiple workers to work at the same time and avoid safety belts being entangled when multiple people are working, thereby causing safety hazards. BRIEF DESCRIPTION OF THE DRAWINGS

[0021] In order to more clearly illustrate the specific implementation methods of the present invention or the technical solutions in the prior art, the drawings required for use in the specific implementation methods or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are some implementation methods of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.

[0022] Figure 1 It is a schematic diagram of the overall structure of the present invention;

[0023] Figure 2 It is a schematic diagram of the rope fixed end structure in the present invention;

[0024] Figure 3 It is a schematic diagram of the structure of the movable end of the rope in the present invention;

[0025] Figure 4 It is a separate structural diagram of one of the hanging mechanisms in the present invention.

[0026] Reference numerals:

[0027] 1. Shear wall; 2. Screw hole; 3. Rope; 4. Steel pipe sleeve 1; 5. Aluminum pressure sleeve; 6. Rope clamp 1; 7. Steel pipe sleeve 2; 8. Rope clamp 2; 9. Moving ring; 10. Connecting rod; 11. Lifting ring; 12. Sliding rod; 13. Limiting ring; 14. Spring; 15. Handle; 16. PVC pipe; 17. Safety bend; 18. Wooden square. DETAILED DESCRIPTION

[0028] The present invention is described in detail below, and the technical solutions in the embodiments of the present invention are clearly and completely described. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0029] The present invention provides a reusable safety belt suspension device and a construction method for construction through improvement. The technical solution of the present invention is:

[0030] Embodiment 1:

[0031] like Figures 1 to 4 As shown, the embodiment of the present invention provides a reusable safety belt hanging device for construction and a construction method, comprising two shear walls 1, the inner sides of the two shear walls 1 are both provided with screw holes 2, the inner sides of the two screw holes 2 are penetrated with ropes 3, and further comprising: a limiting mechanism and a plurality of hanging mechanisms, the limiting mechanisms are arranged at both ends of the rope 3; the plurality of hanging mechanisms are respectively arranged on the outside of the rope 3; the limiting mechanism comprises a steel pipe sleeve 1 4 sleeved on one end of the rope 3, a steel pipe sleeve 2 7 sleeved on the other end of the rope 3, one end of the rope 3 is penetrated and penetrated inside the steel pipe sleeve 1 4 It is fixed by an aluminum pressing sleeve 5 and a rope clamp 6. The other end of the rope 3 passes through the inside of the steel pipe sleeve 7 and is fixed by multiple rope clamps 8. One end of the rope 3 passes through the inside of the steel pipe sleeve 4 and is pre-fixed in the factory by an aluminum pressing sleeve 5 and a rope clamp 6. The length of the rope 3 is selected according to the distance between the two screw holes 2 at the work site. The other end of the rope 3 passes through the inside of the steel pipe sleeve 7 and is fixed by multiple rope clamps 8 to complete the overall installation. The fixation by multiple rope clamps 8 ensures the stability of the overall installation.

[0032] Furthermore, PVC tubes 16 are provided on the inner sides of the two screw holes 2. By providing two PVC tubes 16, the wear between the rope 3 and the main structure can be reduced.

[0033] Furthermore, a safety bend 17 is provided at one end of the rope 3 fixed by a plurality of rope clips 8 .

[0034] Furthermore, wooden planks 18 are fitted on the outer sides of the two shear walls 1, and the other sides of the two wooden planks 18 are fitted with the steel pipe sleeve 1 4 and the steel pipe sleeve 2 7 respectively. The rope 3 passes through the inner sides of the two wooden planks 18. By padding the two wooden planks 18, structural wear can be reduced.

[0035] Furthermore, the diameter of the rope 3 is 10 mm, and the diameters of the steel pipe sleeve 1 4 and the steel pipe sleeve 2 7 are both 50 mm, ensuring that the rope 3 can be passed through the steel pipe sleeve 1 4 and the steel pipe sleeve 2 7 .

[0036] Embodiment 2:

[0037] Further, one of the hanging mechanisms includes a moving ring 9 slidably arranged on the outside of the rope 3, a connecting rod 10 is fixed to the lower end of the moving ring 9, a hanging ring 11 is fixed to the lower end of the connecting rod 10, a sliding rod 12 is slidably arranged on the inner side of the moving ring 9, a limiting ring 13 is fixed to the lower end of the sliding rod 12, and a handle 15 is fixed to the upper end of the sliding rod 12, a spring 14 is sleeved on the outer side of the sliding rod 12, one end of the spring 14 is fixed to the outer side of the limiting ring 13, and the other end of the spring 14 is fixed to the inner side of the moving ring 9;

[0038] During operation, hold the multiple handles 15 and pull upwards respectively. After moving the movable ring 9 to a suitable position, release the multiple handles 15 respectively. Under the elastic potential energy of the multiple springs 14, the multiple limit rings 13 abut against the outside of the rope 3 to complete the installation. By providing multiple movable rings 9, when the safety belt is subsequently fixed, the safety belt buckle can be clamped and fixed between the multiple lifting rings 11 respectively, which can support multiple people to work at the same time and avoid the safety belts from being entangled with each other during operation, affecting construction safety.

[0039] Furthermore, the inner wall of the limiting ring 13 is coated with a polytetrafluoroethylene coating, and the polytetrafluoroethylene coating can reduce the friction coefficient and reduce the wear between the rope 3 and the limiting ring 13.

[0040] Embodiment three:

[0041] The present invention also discloses a construction method of a reusable safety belt suspension device for building construction, comprising the following steps:

[0042] Step 1: Customize the fixed end connection node from the manufacturer according to the drawing. The length of the rope 3 can be adjusted according to the actual situation on site;

[0043] Step 2: Purchase the steel pipe sleeve 2 7 and rope clamp 2 8 required for connecting and fixing the movable end of the rope 3 as needed;

[0044] Step 3: A plurality of movable rings 9 are set on the outside of the rope 3 as needed, and the rope 3 is installed in the edge and high-altitude working areas according to the positions of the two screw holes 2 of the on-site main structure, and the movable end of the rope 3 is passed through the inner side of the steel pipe sleeve 7, and fixed by a plurality of rope clamps 8 to complete the overall limit;

[0045] Step 4: Inspection and acceptance, fix the safety belts on multiple lifting rings 11 to carry out the operation.

[0046] Specific implementation steps: when in use, one end of the rope 3 is passed through the steel pipe sleeve 4 and pre-formed in the factory through the aluminum pressure sleeve 5 and the rope clamp 6. The steel pipe sleeve 2 7 and the rope clamp 2 8 required for connecting and fixing the movable end of the rope 3 are purchased as needed. A plurality of movable rings 9 are sleeved on the outside of the rope 3 as needed. The rope 3 is installed in the edge and high-altitude working areas according to the positions of the two screw holes 2 of the on-site main structure. When sleeved on the plurality of movable rings 9, the plurality of grips 15 are respectively held and pulled upward. After the movable rings 9 are moved to the appropriate position, the plurality of grips 15 are respectively released. Under the elastic potential energy of the plurality of springs 14, the plurality of limit rings 13 abut against the outside of the rope 3 to complete the installation. By setting There are multiple movable rings 9. When the safety belt is fixed later, the safety belt buckle can be clamped and fixed between multiple lifting rings 11 respectively, which can support multiple people working at the same time and avoid the safety belts from being entangled with each other during operation, affecting construction safety. The movable end of the rope 3 is passed through the inner side of the steel pipe sleeve 7 and fixed by multiple rope clamps 8 to complete the overall limiting, inspection and acceptance. The safety belt is fixed on multiple lifting rings 11 for operation. The screw holes 2 on the inner sides of the two shear walls 1 are used to replace the embedded steel pipes, which reduces the waste of embedded steel pipe materials and facilitates the installation and the overall turnover of the device. The two PVC pipes 16 can reduce the wear between the rope 3 and the main structure.

[0047] The above description enables those skilled in the art to implement or use the present invention. Various modifications to these embodiments will be apparent to those skilled in the art, and the general principles defined herein may be implemented in other embodiments without departing from the spirit or scope of the present invention. Therefore, the present invention will not be limited to the embodiments shown herein, but will conform to the widest scope consistent with the principles and novel features disclosed herein.

Claims

1. A reusable safety belt hanging device for construction, comprising two shear walls (1), the inner sides of the two shear walls (1) are both provided with screw holes (2), the inner sides of the two screw holes (2) are penetrated by ropes (3), characterized in that: Also includes: A limiting mechanism, wherein the limiting mechanism is arranged at both ends of the rope (3); A plurality of hanging mechanisms, wherein the plurality of hanging mechanisms are respectively arranged on the outside of the rope (3); The limiting mechanism comprises a steel pipe sleeve 1 (4) sleeved on one end of the rope (3) and a steel pipe sleeve 2 (7) sleeved on the other end of the rope (3); one end of the rope (3) passes through the interior of the steel pipe sleeve 1 (4) and is fixed by an aluminum pressing sleeve (5) and a rope clamp 1 (6); the other end of the rope (3) passes through the interior of the steel pipe sleeve 2 (7) and is fixed by a plurality of rope clamps 2 (8).

2. A reusable safety belt suspension device for construction according to claim 1, characterized in that: One of the hanging mechanisms comprises a moving ring (9) slidably arranged on the outside of the rope (3), a connecting rod (10) is fixed at the lower end of the moving ring (9), a hanging ring (11) is fixed at the lower end of the connecting rod (10), a sliding rod (12) is slidably arranged through the inner side of the moving ring (9), a limiting ring (13) is fixed at the lower end of the sliding rod (12), and a handle (15) is fixed at the upper end of the sliding rod (12), a spring (14) is sleeved on the outer side of the sliding rod (12), one end of the spring (14) is fixed to the outer side of the limiting ring (13), and the other end of the spring (14) is fixed to the inner side of the moving ring (9).

3. The reusable safety belt suspension device for construction according to claim 1, characterized in that: PVC tubes (16) are arranged on the inner sides of the two screw holes (2).

4. The reusable safety belt suspension device for construction according to claim 1, characterized in that: One end of the rope (3) fixed by a plurality of rope clamps (8) is provided with a safety bend (17).

5. The reusable safety belt suspension device for construction according to claim 1, characterized in that: The outer sides of the two shear walls (1) are both fitted with wooden planks (18), the other sides of the two wooden planks (18) are respectively fitted with the first steel pipe sleeve (4) and the second steel pipe sleeve (7), and the rope (3) is passed through the inner sides of the two wooden planks (18).

6. The reusable safety belt suspension device for construction according to claim 1, characterized in that: The diameter of the rope (3) is 10 mm, and the diameters of the first steel pipe sleeve (4) and the second steel pipe sleeve (7) are both 50 mm.

7. The reusable safety belt suspension device for construction according to claim 2, characterized in that: The inner wall of the limiting ring (13) is coated with a polytetrafluoroethylene coating.

8. A construction method for a reusable safety belt suspension device for construction according to any one of claims 1 to 7, characterized in that: The following steps are involved: Step 1: Customize the fixed end connection node from the manufacturer according to the drawing. The length of the rope (3) can be adjusted according to the actual situation on site; Step 2: Purchase the rope (3) as needed, and connect and fix the movable end of the rope to the steel pipe sleeve (7) and rope clamp (8) required; Step 3: A plurality of movable rings (9) are sleeved on the outside of the rope (3) as required, and the rope (3) is installed in the edge and high-altitude operation area according to the positions of the two screw holes (2) of the on-site main structure, and the movable end of the rope (3) is passed through the inner side of the second steel pipe sleeve (7) and fixed by a plurality of rope clamps (8) to complete the overall positioning; Step 4: Inspection and acceptance, fix the safety belts on the multiple lifting rings (11) to carry out the operation.

Citation Information

Patent Citations

  • Safety belt hanger used for high-place operation

    CN109939384A

  • Special safety belt suspending device for overhauling of switch cabinets

    CN110681085A

  • Power line repair frame convenient to use

    CN112054428A

  • Safety belt suspension device for substation maintenance

    CN217567198U

  • Safety rope hanging cableway device for subway station supporting structure construction

    CN219638459U