Storage tank failure prediction method and device, electronic equipment and storage medium

Through the combination of Bayesian network and fuzzy language, the problem of low prediction accuracy of tank leakage accidents is solved, the accuracy and analysis efficiency of tank failure prediction are improved, and effective prevention and control measures are provided.

CN118898025APending Publication Date: 2024-11-05CHINA PETROLEUM & CHEMICAL CORP +1
View PDF 3 Cites 0 Cited by

Patent Information

Application Number
CN202310501363.2
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2023-05-05
Publication Date
2024-11-05

AI Technical Summary

Technical Problem

In the prior art, the failure prediction accuracy of storage tank leakage accidents is low, making it difficult to accurately analyze dynamic processes, and the lack of historical data leads to the failure probability of basic events is difficult to express with accurate numerical values.

Method used

The Bayesian network is used to combine the fuzzy language and risk assessment in the expert database to construct a tank failure prediction model. By determining risk factors, constructing Bayesian networks, and obtaining prior probability and conditional probability, the failure probability of the tank is calculated.

Benefits of technology

It improves the accuracy of tank failure prediction, can express the complex logical relationship between risk factors more scientifically, simplifies the analysis process, and provides effective prevention and control guidance.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118898025A_ABST
    Figure CN118898025A_ABST
Patent Text Reader

Abstract

The invention provides a storage tank failure prediction method and device, electronic equipment and a storage medium. The method comprises the steps that risk factors of storage tank failure are determined; on the basis of the qualitative relationship among the risk factors, constructing a Bayesian network for carrying out storage tank failure prediction; obtaining at least one risk evaluation fuzzy language corresponding to each root node in the Bayesian network from a preset expert database, and determining a prior probability of each root node based on each risk evaluation fuzzy language; and determining the failure probability of the storage tank based on the prior probability of each root node and the conditional probability table of the Bayesian network. According to the method, the complex logic relationship among the risk factors can be more scientifically expressed, so that the constructed Bayesian model better conforms to the actual condition of the storage tank. Meanwhile, the problem that the prior probability of the basic event corresponding to each root node is difficult to represent by an accurate numerical value due to lack and incompleteness of historical data is solved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of storage tanks, and in particular to a storage tank failure prediction method, device, electronic equipment and storage medium. Background Art

[0002] Storage tanks are important production facilities in the petrochemical industry. They can store a large amount of toxic, harmful, flammable, explosive and other important energy materials. At the same time, because storage tanks have the characteristics of saving investment costs, strong operability and convenient management, they are being used more and more widely, and their development prospects are very broad. Once a storage tank leaks and encounters a fire source, it will cause a fire and explosion accident, and even a multi-level domino effect, resulting in catastrophic consequences.

[0003] In order to reduce the occurrence of tank leakage accidents, it is necessary to evaluate the tank leakage risk in the early stage and identify key events. At present, qualitative and quantitative risk assessment methods are mostly used, such as brainstorming, Delphi method, safety checklist, fault tree analysis, event tree analysis, etc. However, these methods are only applicable to static analysis and it is difficult to analyze the dynamic process of tank leakage accidents. In addition, due to the lack of historical data and incomplete failure cause statistics, the failure probability of basic events is difficult to express with accurate numerical values, which leads to low accuracy in tank failure prediction. Summary of the invention

[0004] The present invention provides a storage tank failure prediction method, device, electronic equipment and storage medium, which are used to solve the defect of low storage tank failure prediction accuracy in the prior art.

[0005] The present invention provides a method for predicting failure of a storage tank, comprising:

[0006] Identify risk factors for tank failure;

[0007] Based on the qualitative relationship between risk factors, a Bayesian network for tank failure prediction is constructed.

[0008] Obtaining at least one risk assessment fuzzy language corresponding to each root node in the Bayesian network from a preset expert database, and determining a priori probability of each root node based on each risk assessment fuzzy language;

[0009] Based on the prior probability of each root node and the conditional probability table of the Bayesian network, the failure probability of the storage tank is determined.

[0010] According to a method for predicting storage tank failure provided by the present invention, the prior probability of each root node is determined based on each risk assessment fuzzy language, including:

[0011] Based on each risk assessment fuzzy language, the trapezoidal fuzzy number corresponding to each risk assessment fuzzy language is determined;

[0012] Based on the trapezoidal fuzzy numbers corresponding to each risk assessment fuzzy language, the aggregate fuzzy number of each root node is determined;

[0013] The aggregated fuzzy numbers of each root node are defuzzified to obtain the prior probability of each root node.

[0014] According to a method for predicting storage tank failure provided by the present invention, the aggregated fuzzy number of each root node is determined based on the trapezoidal fuzzy number corresponding to each risk assessment fuzzy language, including:

[0015] Based on the expert scores corresponding to the fuzzy languages ​​of each risk assessment, the expert weights corresponding to the fuzzy languages ​​of each risk assessment are determined;

[0016] Based on the expert weights corresponding to each risk assessment fuzzy language, each trapezoidal fuzzy number is aggregated to obtain the aggregated fuzzy number of each root node.

[0017] According to a storage tank failure prediction method provided by the present invention, the aggregated fuzzy number is determined based on the following formula:

[0018]

[0019] in, is the aggregate fuzzy number of root node i, C ij =(a ij ,b ij ,c ij ,d ij ) is the trapezoidal fuzzy number of expert j for root node i, W e C ij The expert weight.

[0020] According to a method for predicting storage tank failure provided by the present invention, the aggregated fuzzy numbers of each root node are defuzzified to obtain the prior probability of each root node, including:

[0021] Based on the aggregated fuzzy numbers of each root node, the fuzzy probability of each root node is determined;

[0022] Based on the fuzzy probability of each root node, the prior probability of each root node is determined.

[0023] A method for predicting storage tank failure according to the present invention further includes:

[0024] In the event of a storage tank failure, the posterior probability of each root node is determined based on the conditional probability table of the Bayesian network.

[0025] According to a storage tank failure prediction method provided by the present invention, the risk factors include damage to the tank body and accessories, human factors, management factors, operation factors, natural disasters, foundation damage, tank bottom damage, tank wall damage, tank top damage, accessory damage, floating plate damage, sealing failure, operational errors, design defects, poor material corrosion resistance, foundation leakage, foundation settlement, floating roof panel corrosion, floating roof weld corrosion, floating roof seal perforation, outer wall anti-corrosion layer shedding, outer wall corrosion, wall plate weld corrosion, tank bottom corrosion, large angle weld corrosion, bottom plate weld cracks, bolts, flanges and other corrosion Corrosion, failure of detection instruments, corrosion of tank wall pipes, corrosion of guide pipes and oil measuring pipes, damage to the float, damage to the seal, corrosion of the float, water or oil accumulation on the float, corrosion of pillars, damage to the wind ring, damage to the sealing pressure plate, corrosion of the sealing belt, poor wax scraping effect, improper operation of the oil tank, improper welding, overfilling, improper inspection and maintenance, failure to conduct regular inspections, illegal use of mechanical equipment, incomplete process safety information, unreasonable operation process, improper process hazard analysis, high pressure and temperature, poor soil properties, strong stray current, high salt content of the oil, lightning strikes, heavy rains, strong winds and earthquakes.

[0026] The present invention also provides a storage tank failure prediction device, comprising:

[0027] A determination unit for determining risk factors for tank failure;

[0028] A construction unit for constructing a Bayesian network for tank failure prediction based on the qualitative relationship between various risk factors;

[0029] A computing unit, used to obtain at least one risk assessment fuzzy language corresponding to each root node in the Bayesian network from a preset expert database, and determine the prior probability of each root node based on each risk assessment fuzzy language;

[0030] The prediction unit is used to determine the failure probability of the storage tank based on the prior probability of each root node and the conditional probability table of the Bayesian network.

[0031] The present invention also provides an electronic device, comprising a memory, a processor, and a computer program stored in the memory and executable on the processor, wherein when the processor executes the program, any of the above-mentioned methods for predicting storage tank failure is implemented.

[0032] The present invention also provides a non-transitory computer-readable storage medium having a computer program stored thereon, and when the computer program is executed by a processor, the method for predicting failure of a storage tank as described above is implemented.

[0033] The present invention also provides a computer program product, comprising a computer program, wherein when the computer program is executed by a processor, the computer program implements any of the above-mentioned methods for predicting storage tank failure.

[0034] The tank failure prediction method, device, electronic device and storage medium provided by the present invention can more scientifically express the complex logical relationship between the risk factors based on the Bayesian network constructed by each risk factor, so that the constructed Bayesian model is more in line with the actual situation of the tank. At the same time, the prior probability of each root node is determined based on the risk assessment fuzzy language in the preset expert library, which solves the problem that the prior probability of the basic event corresponding to each root node is difficult to express with an accurate numerical value due to the lack and incompleteness of historical data, thereby improving the prediction accuracy of the tank failure probability. In addition, the analysis process of the present invention for predicting tank failure is simple and efficient, and can quickly provide effective guidance for the prevention and control of tank leakage accidents. BRIEF DESCRIPTION OF THE DRAWINGS

[0035] In order to more clearly illustrate the technical solutions in the present invention or the prior art, the following briefly introduces the drawings required for use in the embodiments or the description of the prior art. Obviously, the drawings described below are some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.

[0036] Figure 1 It is a schematic diagram of the flow of the storage tank failure prediction method provided by the present invention;

[0037] Figure 2 It is a schematic diagram of the Bayesian network structure provided by the present invention;

[0038] Figure 3 It is a schematic diagram of the prior probability and the posterior probability of each root node provided by the present invention;

[0039] Figure 4 It is a flow chart of another storage tank failure prediction method provided by the present invention;

[0040] Figure 5 It is a structural schematic diagram of a storage tank failure prediction device provided by the present invention;

[0041] Figure 6 It is a structural schematic diagram of the electronic device provided by the present invention. DETAILED DESCRIPTION

[0042] In order to make the purpose, technical solution and advantages of the present invention clearer, the technical solution of the present invention will be clearly and completely described below in conjunction with the drawings of the present invention. Obviously, the described embodiments are part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0043] In order to reduce the occurrence of tank leakage accidents, it is necessary to evaluate the tank leakage risk in the early stage and identify key events. At present, qualitative and quantitative risk assessment methods are mostly used, such as brainstorming, Delphi method, safety checklist, fault tree analysis, event tree analysis, etc. However, these methods are only applicable to static analysis and it is difficult to analyze the dynamic process of tank leakage accidents. In addition, due to the lack of historical data and incomplete failure cause statistics, the failure probability of basic events is difficult to express with accurate numerical values, which leads to low accuracy in tank failure prediction.

[0044] To this end, the present invention provides a storage tank failure prediction method. Figure 1 It is a schematic diagram of the flow of the method for predicting storage tank failure provided by the present invention, such as Figure 1 As shown, the method comprises the following steps:

[0045] Step 110: Determine risk factors for tank failure.

[0046] Here, risk factors refer to factors that cause leakage accidents in storage tanks and thus lead to failure of storage tanks. In some specific implementations, the causes of storage tank leakage accidents can be analyzed and risk factors can be determined based on relevant laws, regulations, standards, specifications, and expert or field experience.

[0047] For example, damage to the tank and its accessories may lead to leakage accidents in the tank, and thus damage to the tank and its accessories may serve as a risk factor for tank failure.

[0048] Step 120: Based on the qualitative relationship between the risk factors, a Bayesian network for predicting storage tank failure is constructed.

[0049] Specifically, the qualitative relationship between the risk factors can be understood as the influence relationship between the risk factors. After determining the qualitative relationship between the risk factors, the parent node and child node corresponding to each risk factor can be determined, and then the corresponding fault tree can be constructed and converted into a Bayesian network topology structure.

[0050] like Figure 2As shown, tank leakage is caused by damage to the tank body and accessories, human factors, management factors, operational factors or natural disasters. Damage to the tank body and accessories is caused by foundation damage, tank bottom damage, tank wall damage, tank top damage, accessory damage, design defects or poor material corrosion resistance; human errors are caused by improper inspection and maintenance, illegal use of mechanical equipment or operational errors; improper management is caused by failure to conduct regular inspections, incomplete process safety information, unreasonable operating procedures or improper process hazard analysis; poor operating quality is caused by high pressure and temperature, poor soil properties, strong stray current or high salt content of oil; natural disasters are caused by lightning strikes, heavy rains, strong winds, and earthquakes; foundation damage is caused by foundation leakage or foundation settlement; tank top damage It is caused by corrosion of the floating roof panel, corrosion of the floating roof weld or perforation of the floating roof seal; tank wall damage is caused by the shedding of the outer wall anti-corrosion layer, corrosion of the outer wall or corrosion of the wall plate weld; tank bottom damage is caused by corrosion of the tank bottom, corrosion of large angle welds or cracks in the bottom plate weld; accessory damage is caused by corrosion of bolts, flanges, etc., failure of detection instruments, corrosion of tank wall pipes or corrosion of guide pipes and oil measuring pipes, floating plate damage or seal damage; floating plate damage is caused by corrosion of the floating plate, water or oil accumulation on the floating plate, corrosion of the pillars or damage to the windproof ring; seal damage is caused by damage to the sealing pressure plate, corrosion of the sealing belt or poor wax scraping effect. Therefore, a fault tree for tank leakage accidents can be established, and the fault tree can be converted into a Bayesian network topology for tank failure prediction. Among them, the fault tree corresponding to the Bayesian network used for tank failure prediction is as follows Figure 2 shown.

[0051] Step 130: Obtain at least one risk assessment fuzzy language corresponding to each root node in the Bayesian network from a preset expert database, and determine the prior probability of each root node based on each risk assessment fuzzy language.

[0052] Specifically, the preset expert database can store the risk assessment fuzzy language of each root node by different experts, and then the risk assessment fuzzy language of each root node can be aggregated to determine the aggregated fuzzy number of each root node, and the prior probability of each root node can be determined according to the aggregated fuzzy number. The prior probability refers to the probability of the corresponding root node event occurring according to the past experience analysis.

[0053] Step 140: Determine the failure probability of the storage tank based on the prior probability of each root node and the conditional probability table of the Bayesian network.

[0054] Usually, the conditional probability of the Bayesian network topology is determined by the "AND / OR" logic gate in the fault tree, that is, the "0 or 1" method. However, the conditional probability of tank leakage caused by damage to the tank body and accessories, operation factors, human factors, management factors and natural disasters using the "AND / OR" logic gate in the fault tree does not conform to the actual situation. For example, human error does not necessarily lead to tank leakage. Therefore, the embodiment of the present invention can use the "AND / OR" logic gate in the fault tree combined with expert evaluation to obtain a conditional probability table.

[0055] When the prior probability of each root node and the conditional probability table of the Bayesian network are known, the probability of a tank leak, that is, the failure probability of the tank, can be calculated using Bayesian forward reasoning.

[0056] It can be seen that the Bayesian network constructed based on various risk factors in the embodiment of the present invention can more scientifically express the complex logical relationship between various risk factors, so that the constructed Bayesian model is more in line with the actual situation of the storage tank. At the same time, the prior probability of each root node is determined based on the risk assessment fuzzy language in the preset expert library, which solves the problem that the prior probability of the basic event corresponding to each root node is difficult to express with an accurate numerical value due to the lack and incompleteness of historical data, thereby improving the prediction accuracy of the failure probability of the storage tank. In addition, the analysis process of the embodiment of the present invention for predicting storage tank failure is simple and efficient, and can quickly provide effective guidance for the prevention and control of storage tank leakage accidents.

[0057] Based on the above embodiment, the prior probability of each root node is determined based on each risk assessment fuzzy language, including:

[0058] Based on each risk assessment fuzzy language, the trapezoidal fuzzy number corresponding to each risk assessment fuzzy language is determined;

[0059] Based on the trapezoidal fuzzy numbers corresponding to each risk assessment fuzzy language, the aggregate fuzzy number of each root node is determined;

[0060] The aggregated fuzzy numbers of each root node are defuzzified to obtain the prior probability of each root node.

[0061] In some specific implementations, 9-level trapezoidal fuzzy numbers can be used to describe the linguistic terms and corresponding trapezoidal fuzzy numbers of the corresponding levels of risk factors, where Table 1 is a comparison table of fuzzy language and trapezoidal fuzzy numbers. The risk assessment fuzzy language stored in the preset expert library can be the linguistic terms in Table 1. The linguistic terms are compared in Table 1, and the corresponding trapezoidal fuzzy numbers are determined by the test.

[0062] Table 1

[0063]

[0064] In addition, each root node may correspond to multiple risk assessment fuzzy languages, and then each root node may correspond to multiple trapezoidal fuzzy numbers. On this basis, the multiple trapezoidal fuzzy numbers corresponding to each root node are aggregated to determine the aggregated fuzzy number of each root node, and the aggregated fuzzy number is defuzzified to obtain the failure probability of each root node, that is, the prior probability of each root node, where the prior probability of each node is as follows: Figure 3 shown.

[0065] It can be seen that the embodiments of the present invention solve the problem that the failure probability of each root node is difficult to represent with an accurate numerical value due to the lack of historical data and incomplete failure cause statistics.

[0066] Based on any of the above embodiments, based on the trapezoidal fuzzy numbers corresponding to each risk assessment fuzzy language, determining the aggregate fuzzy number of each root node includes:

[0067] Based on the expert scores corresponding to the fuzzy languages ​​of each risk assessment, the expert weights corresponding to the fuzzy languages ​​of each risk assessment are determined;

[0068] Based on the expert weights corresponding to each risk assessment fuzzy language, each trapezoidal fuzzy number is aggregated to obtain the aggregated fuzzy number of each root node.

[0069] Specifically, the expert score is used to characterize the confidence of the corresponding risk assessment fuzzy language. The higher the expert score, the stronger the professional ability of the corresponding expert, and thus the higher the confidence of the risk assessment fuzzy language given by the corresponding expert.

[0070] In some specific implementations, experts can be scored according to their positions, years of work, education level and age to obtain expert scores. Table 2 is a comparison table of expert sub-item scores. As shown in Table 2, the higher the position, the longer the years of work, the higher the education level and the older the age, the higher the corresponding sub-item score. The sum of all sub-item scores is the expert score. Table 3 is a comparison table of the scores of three experts and the expert weights. As shown in Table 3, according to the position, years of work, education level and age of expert 1, it can be determined from Table 2 that the corresponding sub-item scores are 4, 2, 6 and 2, respectively, and the corresponding expert score is 4+2+6+2=14.

[0071] Table 2

[0072]

[0073]

[0074] Table 3

[0075]

[0076] According to the expert scores corresponding to each risk assessment fuzzy language, the expert weights corresponding to each risk assessment fuzzy language can be calculated using the following formula:

[0077]

[0078] In the formula, S e represents the score of expert e, W e represents the expert weight of expert e, as shown in Table 3, the expert weight corresponding to expert 1

[0079] After obtaining the expert weights corresponding to each risk assessment fuzzy language, each trapezoidal fuzzy number is aggregated to obtain the aggregated fuzzy number of each root node.

[0080] It can be seen that the embodiment of the present invention converts the expert's linguistic terms into reliable probability data by combining trapezoidal fuzzy numbers with expert evaluation, and makes the result more reasonable by considering the expert's cognitive certainty, so as to accurately determine the prior probability of each root node.

[0081] Based on any of the above embodiments, the aggregate fuzzy number is determined based on the following formula:

[0082]

[0083] in, is the aggregate fuzzy number of root node i, C ij =(a ij ,b ij ,c ij ,d ij ) is the trapezoidal fuzzy number of expert j for root node i, W e C ij The expert weight.

[0084] Based on any of the above embodiments, the aggregated fuzzy numbers of each root node are defuzzified to obtain the prior probability of each root node, including:

[0085] Based on the aggregated fuzzy numbers of each root node, the fuzzy probability of each root node is determined;

[0086] Based on the fuzzy probability of each root node, the prior probability of each root node is determined.

[0087] Specifically, after aggregating the trapezoidal fuzzy numbers corresponding to each risk assessment fuzzy language, the aggregated fuzzy numbers need to be defuzzified to obtain a relatively reliable failure probability of each root node, that is, a priori probability of each root node.

[0088] In some specific implementations, the regional center method can be used to defuzzify the aggregated fuzzy number to obtain the fuzzy probability FPS of each root node:

[0089]

[0090] Next, the fuzzy probability FPS of each root node is converted into the prior probability FFP of each root node, where Table 4 is the prior probability table of each root node:

[0091]

[0092]

[0093] Table 4

[0094]

[0095]

[0096] Based on any of the above embodiments, the method further includes:

[0097] In the case of tank failure, the posterior probability of each root node is determined based on the conditional probability table of the Bayesian network.

[0098] Specifically, in the Bayesian network reverse reasoning, the posterior probability reflects the key risk factors that lead to tank leakage accidents. In the case of tank failure, the tank failure probability can be set to 1, that is, P(Z=YSE)=1, and then the posterior probability P(X i =YES︱Z=YES), the posterior probability value is Figure 3 shown.

[0099] Among them, the posterior probability of the i-th root node can be expressed as P(X i |Z), the specific formula is:

[0100]

[0101] In the formula, P(X i ) represents the joint probability of risk factors at each node, P(z|X i ) represents the conditional probability derived from the Bayesian network of the tank leakage.

[0102] In addition, the embodiment of the present invention can also calculate the sensitivity value of each root node, determine the degree of influence of the leaf node input on the root node output, and thus identify the key risk factors causing the tank accident, wherein Table 5 is a list of key risk factors.

[0103] Table 5

[0104] Root Node Prior probability Posterior probability Sensitivity value X11 1.13E-02 7.21E-02 5.3806 X25 5.14E-03 3.92E-02 6.6196 X29 8.98E-03 4.90E-02 4.46 X32 6.06E-03 3.31E-02 4.46 X34 3.23E-03 4.29E-02 12.29 X35 2.59E-03 3.44E-02 12.29

[0105] Through the Bayesian network reverse reasoning technology, it can be known that when a storage tank leakage accident occurs, the posterior probability of tank bottom corrosion (X11), high temperature, high pressure (X25), improper welding (X29), illegal use of mechanical equipment (X32), no regular inspection (X34) and incomplete process safety information (X35) in the root node is relatively large, which is the most likely cause of the tank accident.

[0106] According to the results of sensitivity analysis, failure to conduct regular inspections (X34) and incomplete process safety information (X35) are areas that managers need to focus on in daily management. Regular inspections and improvement of process safety information are very important for the corrosion, operation, and maintenance of storage tanks. In actual safety management, the purpose of risk control by managers is to find out the key risk factors that have a greater impact on accidents, focus on these areas in daily management, take effective risk control measures, and reduce the probability of accidents as much as possible.

[0107] Furthermore, the conditional probability of the Bayesian network topology is determined by the “AND / OR” logic gate in the fault tree, that is, “0 or 1”. For example, severe foundation settlement and foundation leakage will definitely lead to foundation damage. The conditional probability of tank leakage caused by damage to the tank body and accessories, operational factors, human factors, management factors, and natural disasters does not conform to the actual situation by the “AND / OR” logic gate in the fault tree. For example, human error does not necessarily lead to tank leakage. Therefore, the combination of expert evaluation and fuzzy set theory is used to obtain the conditional probability table. Table 6 is a conditional probability table, where “Y” represents the occurrence of an event and “N” represents the non-occurrence of an event.

[0108] Table 6

[0109]

[0110]

[0111] Based on any of the above embodiments, risk factors include damage to the tank body and accessories, human factors, management factors, operation factors, natural disasters, foundation damage, tank bottom damage, tank wall damage, tank top damage, accessory damage, floating plate damage, seal failure, operational errors, design defects, poor material corrosion resistance, foundation leakage, foundation settlement, floating roof panel corrosion, floating roof weld corrosion, floating roof seal perforation, outer wall anti-corrosion layer shedding, outer wall corrosion, wall plate weld corrosion, tank bottom corrosion, large angle weld corrosion, bottom plate weld cracks, bolts, flanges, etc. Corrosion, detectors At least one of the following: meter failure, corrosion of tank wall pipe, guide pipe, oil measuring pipe, float damage, seal damage, float corrosion, water or oil accumulation on the float, pillar corrosion, wind ring damage, sealing pressure plate damage, sealing belt corrosion, poor wax scraping effect, improper oil tank operation, improper welding, overfilling, improper inspection and maintenance, failure to conduct regular inspections, illegal use of mechanical equipment, incomplete process safety information, unreasonable operation process, improper process hazard analysis, high pressure and temperature, poor soil properties, strong stray current, high salt content of oil, lightning strike, heavy rain, strong wind and earthquake.

[0112] Based on any of the above embodiments, the present invention also provides a method for predicting tank failure, such as Figure 4 As shown, the method includes:

[0113] Firstly, the causes of tank failure (tank leakage accident) are analyzed to determine the risk factors, and based on the qualitative relationship between the risk factors, a fault tree is constructed and converted into a Bayesian network.

[0114] Next, each expert is evaluated according to their ability, and the expert score is obtained, and the expert weight is determined according to the expert score. Then, based on the fuzzy set theory, trapezoidal fuzzy numbers are used to represent the probability of the event corresponding to each root node, and the expert weight is used to realize the aggregation of the trapezoidal fuzzy numbers of different experts for each root node, and it is converted into a priori probability through defuzzification to obtain the priori probability of each root node.

[0115] Then, the conditional probability table of the Bayesian network is constructed by using the "AND / OR" logic gates in the fault tree and expert evaluation.

[0116] Finally, the probability of tank leakage, i.e., the tank failure probability, is calculated using Bayesian forward reasoning technology. In addition, the embodiment of the present invention can also assume that the tank has failed (i.e., the tank has leaked), and use Bayesian network reverse reasoning technology to diagnose and identify the key risk factors that lead to tank leakage, so as to achieve sensitivity analysis.

[0117] The storage tank failure prediction device provided by the present invention is described below. The storage tank failure prediction device described below and the storage tank failure prediction method described above can be referenced to each other.

[0118] Based on any of the above embodiments, the present invention also provides a tank failure prediction device, such as Figure 5 As shown, the device comprises:

[0119] A determination unit 510, for determining risk factors of storage tank failure;

[0120] A construction unit 520, for constructing a Bayesian network for predicting storage tank failure based on the qualitative relationship between the risk factors;

[0121] The calculation unit 530 is used to obtain at least one risk assessment fuzzy language corresponding to each root node in the Bayesian network from a preset expert database, and determine the prior probability of each root node based on each risk assessment fuzzy language;

[0122] The prediction unit 540 is used to determine the failure probability of the storage tank based on the prior probability of each root node and the conditional probability table of the Bayesian network.

[0123] Figure 6 is a schematic diagram of the structure of the electronic device provided by the present invention, such as Figure 6 As shown, the electronic device may include: a processor 610, a memory 620, a communications interface 630 and a communications bus 640, wherein the processor 610, the memory 620 and the communications interface 630 communicate with each other through the communications bus 640. The processor 610 may call the logic instructions in the memory 620 to execute the tank failure prediction method, which includes: determining the risk factors of tank failure; constructing a Bayesian network for tank failure prediction based on the qualitative relationship between the risk factors; obtaining at least one risk assessment fuzzy language corresponding to each root node in the Bayesian network from a preset expert library, and determining the prior probability of each root node based on each risk assessment fuzzy language; determining the failure probability of the tank based on the prior probability of each root node and the conditional probability table of the Bayesian network.

[0124] In addition, the logic instructions in the above-mentioned memory 620 can be implemented in the form of software functional units and can be stored in a computer-readable storage medium when sold or used as an independent product. Based on such an understanding, the technical solution of the present invention can be essentially or partly embodied in the form of a software product that contributes to the prior art. The computer software product is stored in a storage medium, including several instructions for a computer device (which can be a personal computer, a server, or a network device, etc.) to perform all or part of the steps of the method described in each embodiment of the present invention. The aforementioned storage medium includes: U disk, mobile hard disk, read-only memory (ROM, Read-Only Memory), random access memory (RAM, Random Access Memory), disk or optical disk, etc. Various media that can store program codes.

[0125] On the other hand, the present invention also provides a computer program product, which includes a computer program stored on a non-transitory computer-readable storage medium, and the computer program includes program instructions. When the program instructions are executed by a computer, the computer can execute the tank failure prediction method provided by the above methods, and the method includes: determining the risk factors of tank failure; constructing a Bayesian network for tank failure prediction based on the qualitative relationship between the risk factors; obtaining at least one risk assessment fuzzy language corresponding to each root node in the Bayesian network from a preset expert library, and determining the prior probability of each root node based on each risk assessment fuzzy language; determining the failure probability of the tank based on the prior probability of each root node and the conditional probability table of the Bayesian network.

[0126] On the other hand, the present invention also provides a non-transitory computer-readable storage medium having a computer program stored thereon, which, when executed by a processor, is implemented to execute the above-mentioned tank failure prediction methods, the methods comprising: determining risk factors for tank failure; constructing a Bayesian network for tank failure prediction based on the qualitative relationship between the risk factors; obtaining at least one risk assessment fuzzy language corresponding to each root node in the Bayesian network from a preset expert library, and determining the prior probability of each root node based on each risk assessment fuzzy language; determining the failure probability of the tank based on the prior probability of each root node and the conditional probability table of the Bayesian network.

[0127] The device embodiments described above are merely illustrative, wherein the units described as separate components may or may not be physically separated, and the components displayed as units may or may not be physical units, that is, they may be located in one place, or they may be distributed on multiple network units. Some or all of the modules may be selected according to actual needs to achieve the purpose of the scheme of this embodiment. Ordinary technicians in this field can understand and implement it without paying creative labor.

[0128] Through the description of the above implementation methods, those skilled in the art can clearly understand that each implementation method can be implemented by means of software plus a necessary general hardware platform, and of course, it can also be implemented by hardware. Based on this understanding, the above technical solution is essentially or the part that contributes to the prior art can be embodied in the form of a software product, and the computer software product can be stored in a computer-readable storage medium, such as ROM / RAM, a disk, an optical disk, etc., including a number of instructions for a computer device (which can be a personal computer, a server, or a network device, etc.) to execute the methods described in each embodiment or some parts of the embodiments.

[0129] Finally, it should be noted that the above embodiments are only used to illustrate the technical solutions of the present invention, rather than to limit it. Although the present invention has been described in detail with reference to the aforementioned embodiments, those skilled in the art should understand that they can still modify the technical solutions described in the aforementioned embodiments, or make equivalent replacements for some of the technical features therein. However, these modifications or replacements do not deviate the essence of the corresponding technical solutions from the spirit and scope of the technical solutions of the embodiments of the present invention.

Claims

1. A method for predicting storage tank failure, characterized in that: include: Identify risk factors for tank failure; Based on the qualitative relationship between risk factors, a Bayesian network for tank failure prediction is constructed. Obtaining at least one risk assessment fuzzy language corresponding to each root node in the Bayesian network from a preset expert database, and determining a priori probability of each root node based on each risk assessment fuzzy language; Based on the prior probability of each root node and the conditional probability table of the Bayesian network, the failure probability of the storage tank is determined.

2. The method for predicting storage tank failure according to claim 1, characterized in that: The prior probability of each root node is determined based on each risk assessment fuzzy language, including: Based on each risk assessment fuzzy language, the trapezoidal fuzzy number corresponding to each risk assessment fuzzy language is determined; Based on the trapezoidal fuzzy numbers corresponding to each risk assessment fuzzy language, the aggregate fuzzy number of each root node is determined; The aggregated fuzzy numbers of each root node are defuzzified to obtain the prior probability of each root node.

3. The method for predicting storage tank failure according to claim 2, characterized in that: The step of determining the aggregate fuzzy number of each root node based on the trapezoidal fuzzy number corresponding to each risk assessment fuzzy language includes: Based on the expert scores corresponding to the fuzzy languages ​​of each risk assessment, the expert weights corresponding to the fuzzy languages ​​of each risk assessment are determined; Based on the expert weights corresponding to each risk assessment fuzzy language, each trapezoidal fuzzy number is aggregated to obtain the aggregated fuzzy number of each root node.

4. The method for predicting storage tank failure according to claim 3, characterized in that: The aggregate fuzzy number is determined based on the following formula: in, is the aggregate fuzzy number of root node i, C ij =(a ij ,b ij ,c ij ,d ij ) is the trapezoidal fuzzy number of expert j for root node i, W e C ij The expert weight.

5. The method for predicting storage tank failure according to claim 2, characterized in that: The defuzzification of the aggregated fuzzy numbers of each root node to obtain the prior probability of each root node includes: Based on the aggregated fuzzy numbers of each root node, the fuzzy probability of each root node is determined; Based on the fuzzy probability of each root node, the prior probability of each root node is determined.

6. The method for predicting storage tank failure according to any one of claims 1 to 5, characterized in that: Also includes: In the event of a storage tank failure, the posterior probability of each root node is determined based on the conditional probability table of the Bayesian network.

7. The method for predicting storage tank failure according to any one of claims 1 to 5, characterized in that: The risk factors include damage to the tank and its accessories, human factors, management factors, operational factors, natural disasters, foundation damage, tank bottom damage, tank wall damage, tank top damage, accessory damage, floating plate damage, seal failure, operational errors, design defects, poor material corrosion resistance, foundation leakage, foundation settlement, floating roof panel corrosion, floating roof weld corrosion, floating roof seal perforation, outer wall anti-corrosion layer shedding, outer wall corrosion, wall plate weld corrosion, tank bottom corrosion, large angle weld corrosion, bottom plate weld cracks, bolt, flange and other corrosion, detection instrument failure, At least one of the following: corrosion of the tank wall pipe, guide pipe, oil measuring pipe, float damage, seal damage, float corrosion, water or oil accumulation on the float, pillar corrosion, wind ring damage, sealing pressure plate damage, sealing belt corrosion, poor wax scraping effect, improper tank operation, improper welding, overfilling, improper inspection and maintenance, failure to conduct regular inspections, illegal use of mechanical equipment, incomplete process safety information, unreasonable operation process, improper process hazard analysis, high pressure and temperature, poor soil properties, strong stray current, high salt content of oil, lightning strikes, heavy rain, strong winds and earthquakes.

8. A storage tank failure prediction device, characterized in that: include: A determination unit for determining risk factors for tank failure; A construction unit for constructing a Bayesian network for tank failure prediction based on the qualitative relationship between various risk factors; A computing unit, used to obtain at least one risk assessment fuzzy language corresponding to each root node in the Bayesian network from a preset expert database, and determine the prior probability of each root node based on each risk assessment fuzzy language; The prediction unit is used to determine the failure probability of the storage tank based on the prior probability of each root node and the conditional probability table of the Bayesian network.

9. An electronic device comprising a memory, a processor, and a computer program stored in the memory and executable on the processor, wherein: When the processor executes the program, the tank failure prediction method according to any one of claims 1 to 7 is implemented.

10. A non-transitory computer-readable storage medium having a computer program stored thereon, characterized in that: When the computer program is executed by a processor, the method for predicting storage tank failure according to any one of claims 1 to 7 is implemented.

Citation Information

Patent Citations

  • Submarine pipeline reliability evaluation method based on neutrosophic fuzzy Bayesian network

    CN114580150A

  • Oil storage tank failure assessment method and related device

    CN114648211A

  • Adaptive Bayes Network data mining modeling

    US6973459B1