Method for predicting swing width of thalweg of continuous curve under influence of bank protection project

Through multiple regression analysis and remote sensing image processing, a method for predicting the swing width of the continuous curve deep pendant line was established, which solved the prediction problem of the impact of bank protection engineering on the deep pendant line, and achieved accurate reflection of the river evolution law and winding river deep pendant line Effective simulation of line swing.

CN118898201APending Publication Date: 2024-11-05XINJIANG AGRI UNIV
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202410945849.X
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-07-12
Publication Date
2024-11-05

AI Technical Summary

Technical Problem

The existing technology is difficult to effectively predict the impact of bank protection engineering on the swing width of continuous curved deep-burning lines, especially the lack of quantitative analysis of the dynamic changes of local river sections after the construction of river protection, resulting in river evolution laws and winding river deep-burning lines. The characteristics were not accurately reflected.

Method used

Multivariate regression analysis method is adopted to establish a function relationship of the swing width of the continuous curve deep-burning line by obtaining remote sensing images, establishing a curve coordinate system, fitting the initial unstopped length and the outbound straight line length, combining hydrological data and curve indicators. , verify the accuracy of the formula and compare it with the actual deep red line to predict the swing trend of the deep red line.

Benefits of technology

Quantitative analysis of continuous curve deep red line under bank protection engineering conditions is realized. The predicted value is close to actual changes, which can reflect the swing trend of deep red line, and provides an important reference for the swing of deep red line in similar rivers. The simulation range is 500m- Within the range of 600m and 150m-500m.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118898201A_ABST
    Figure CN118898201A_ABST
Patent Text Reader

Abstract

The invention discloses a continuous bend thalweg swing width prediction method under the influence of bank protection engineering, and relates to the technical field of river channel analysis. Comprising the steps of obtaining a riverway center line extracted by a remote sensing image; three curve thalweg lines are intercepted according to the coordinate system to fit a common line of the three curve thalweg lines; determining approximate in-shore length and initial non-in-shore length of the thalweg line, collecting hydrological data of the river reach, and fitting an empirical relational expression of the initial non-in-shore length in combination with each influence parameter index; fitting the length of a thalweg out-of-bank straight line according to the initial non-in-bank length, the hydrological data of the river reach and the indexes of all the bends; and taking the length of the out-of-bank straight line as an abscissa, fitting a function relational expression of the swing width of the continuous curve thalweg, verifying the accuracy of the formula, and comparing the formula with an actual thalweg. The method provides a reference value for the continuous curve thalweg swing rule.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of river channel analysis, and in particular to a method for predicting the swing width of a continuous bend channel line under the influence of a bank protection project. Background Art

[0002] The channel thalassemia line refers to the deepest part on both sides of the centerline of the river channel, that is, the line connecting the lowest points on the cross section of the river channel. The thalassemia swing is an important part of the lateral deformation of wandering rivers. Most of the relevant studies are on wandering rivers. For example, the upper reaches of the Tarim River are a typical wandering section. The increase in flow during the flood season makes the mainstream of the wandering section swing unsteadily, and the river flow changes dramatically. The channel thalassemia line often changes dramatically after the flood season. On the one hand, the swing of the thalassemia line reflects the changes in the river width of the river channel, which can reflect the changes in the mainstream of the river channel to a certain extent. On the other hand, the changes in the thalassemia line have a direct impact on the changes in the scouring and silting of the riverbed.

[0003] The swing law of the fenestration line of alluvial rivers is relatively complex, and there are many influencing factors. There are few related studies at home and abroad. Existing studies have established empirical relationships between double factors and above and the swing width of the fenestration line, and analyzed the swing intensity characteristics and laws of the overall fenestration line of the river. After the river bank protection construction, the overall swing amplitude of the river fenestration line has decreased, and the swing amplitude of the fenestration line of continuous bends has decreased most significantly. The adjustment changes of local river sections under the conditions of bank protection projects have been ignored, and there is a lack of quantitative analysis of the dynamic changes of the fenestration line of continuous bends in local river sections. Therefore, the study of the swing width prediction of the fenestration line of continuous bends is not only of great significance to the law of river evolution, but also of great reference significance to the swing of the fenestration line of continuous bends in winding rivers.

[0004] Therefore, it is an urgent problem for technical personnel in this field to propose a method for predicting the swing width of the deep channel line of a continuous curve under the influence of bank protection engineering to solve the problems existing in the prior art. Summary of the invention

[0005] In view of this, the present invention provides a method for predicting the swing width of the deep channel line of a continuous curve under the influence of a bank protection project to solve the problems existing in the prior art.

[0006] In order to achieve the above object, the present invention adopts the following technical solution:

[0007] A method for predicting the swing width of the deep channel line of a continuous curve under the influence of a bank protection project comprises the following steps:

[0008] S1. Obtain remote sensing images and use ArcGIS software to extract the river centerline as the river depth line analysis object;

[0009] S2. Establish a curve coordinate system, and intercept three curve abyssal lines according to the coordinate system. The interception range is from the center of the first curve coordinate circle to the initial shore point of the next curve abyssal line, so that the three curve coordinate systems after interception return to one center, and use Origin software to fit the common line of the three curve abyssal lines;

[0010] S3. Determine the approximate shore length and initial unshore length of the deep channel line, collect the hydrological data of the river section and combine the various influencing parameter indicators to fit the empirical relationship of the initial unshore length;

[0011] S4. According to the initial unbanked length, river section hydrological data and indicators of each bend, the straight length of the deep-water line out of the shore is fitted;

[0012] S5. Take the length of the outbound straight line as the horizontal coordinate, and measure the longitudinal values ​​of the three curve swings in turn according to the 20 points evenly divided by the length of the outbound straight line. Fit the functional relationship of the swing width of the continuous curve deep-water line to verify the accuracy of this formula and compare it with the actual deep-water line.

[0013] In the above method, optionally, the specific content of S1 is:

[0014] Based on remote sensing images and the water index method in ArcGIS, water bodies are extracted according to the largest difference in water reflection between different bands. The river boundary line in the dry season is processed according to the extracted water body, and the river centerline is extracted through ArcGIS vectorization tool ArcScan as the main analysis object of the river depth line.

[0015] In the above method, optionally, S1 specifically comprises the following steps:

[0016] S101. To obtain the planar morphology of the river channel, the dry season satellite images were downloaded based on the 30-meter resolution Landsat8-OLI and 30-meter resolution Landsat9-OLI. Based on the water index method in ArcGIS, the water body was extracted according to the large difference between the water body reflections in different bands:

[0017]

[0018] MNDWI is the improved normalized difference water index, p(Green) is the reflectance of the green band, and p(MIR) is the reflectance of the mid-infrared band;

[0019] S102. Based on the extracted water bodies, river boundary lines of different years are obtained by processing, and river center lines are extracted using ArcGIS vectorization tool ArcScan based on the river boundary lines of different years.

[0020] In the above method, optionally, S2 specifically includes the following steps:

[0021] S201: The coordinate system takes the midpoint of the length of each bend revetment project as the origin O, and the extension line connecting the origin to the center of the revetment project as the ordinate. According to the coordinate system, three bend depth lines are intercepted, and the interception range is from the center of the first bend coordinate circle to the initial shore point of the next bend depth line. Each bend is rotated by a certain angle to be located in the same horizontal plane, so that the intercepted three bend coordinate systems belong to a new rectangular coordinate system;

[0022] S202: In the new rectangular coordinate system, select a preset point on the horizontal axis, use CAD to measure the coordinate values ​​of the three curve depth lines, and use Origin software to fit the common line of the three curve depth lines according to the coordinate values, and separate the common line and the curve depth line in turn.

[0023] In the above method, optionally, S3 specifically includes the following steps:

[0024] S301: Find the shore entry and exit points of each bend deep channel, and define the distance from the shore entry point to the initial end of the revetment as the initial unshored length L i , define the distance from the shore exit to the initial end of the revetment as the original length L, fix the original length L, determine the original length of each bend, and collect the approximate shore length;

[0025] S302: Based on S301, determine the initial unlanded length L i , collect the hydrological data of the river section and the indicators of each bend, calculate the average flow and sediment content in the flood seasons of previous years, further analyze the water-sediment combination, consider that the correlation coefficient between the sliding average water and sediment and the shore entry point is the highest when n=4, calculate the average water flow scouring intensity in the four years before the flood season, and the flood season water flow scouring intensity F i and the average water flow intensity in the previous four years The expressions are:

[0026]

[0027] In the formula, is the annual average flow, in m 3 / s, is the annual average sediment content, in kg / m 3 , is the average water flow scouring intensity in the i-th year, in m, and n is the number of years of the sliding mean;

[0028] S303, collect the river section gradient and the corresponding bed sand particle size, calculate the flat water depth, and further calculate the relative mobility M of the riverbed components:

[0029]

[0030] Where M is the relative mobility of the riverbed components, J is the slope, the unit is ‰, and D 35is the particle size of the bed sand composition that is smaller than 35% of the particle size, in mm, and h is the water depth under flat beach flow;

[0031] S304, based on S302 and S303, fitting an empirical relationship of initial unlanded length;

[0032]

[0033] Where, L i is the initial unlanded length, is the average water flow scouring intensity in the previous n years, M is the relative mobility of the soil, and R is the bending radius of the bank protection.

[0034] In the above method, optionally, S4 specifically includes the following steps:

[0035] S401: Collect the annual runoff and annual sediment transport of the current river section hydrological station, obtain the bending radius of the bend bank protection project, and fit the straight line length L of the deep channel out of the shore e :

[0036] L e =-0.0026W+0.00005Q s -0.8305R-0.7435L c +6.613

[0037] Where, L e is the straight length of the deep channel out of the shore, W is the annual runoff, Q s is the sediment transport volume, R is the bending radius of the bank protection project, L c It is the approximate shore length of the deep channel line.

[0038] It can be seen from the above technical solutions that, compared with the prior art, the present invention provides a method for predicting the swing width of the deep channel line of a continuous curve under the influence of a bank protection project, which has the following beneficial effects:

[0039] (1) This application takes the deep-water line of a continuous curved river section as the research object, adopts the method of multiple regression analysis, quantitatively analyzes the relationship between the swing width of the deep-water line and water and sediment factors and boundary conditions, establishes relevant empirical formulas and function formulas, substitutes the calculated values ​​of each point of the three bends' outbound straight line in 2022 into the fitted formula for verification, and compares the calculated deep-water line imported into ArcGIS with the actual deep-water line. The change in the predicted value is close to the change in the actual value. Although there are large differences in some parts, it can basically reflect the swing trend of the deep-water line of the continuous bend under the effect of bank protection;

[0040] (2) The first type of formula can be used to generalize the simulation of the swing of the deep-water line in continuous bends of the same type of river with a multi-upward trend and a swing range of 500m-600m; the second type of formula can be used to generalize the simulation of the swing of the deep-water line with a gradually rising trend and a swing range of 150m-500m. It has important reference significance for the swing of the deep-water line in continuous bends of winding rivers. BRIEF DESCRIPTION OF THE DRAWINGS

[0041] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on the provided drawings without paying creative work.

[0042] Figure 1 It is a flow chart of a method for predicting the swing width of the deep channel line of a continuous curve under the influence of a bank protection project disclosed by the present invention;

[0043] Figure 2 It is a schematic diagram of the swing analysis of the river channel deep-water line disclosed in the present invention;

[0044] Figure 3 It is a correlation diagram of the initial unmoored length, the calculated value of the outbound straight length and the actual value disclosed in the present invention, wherein 3a is a correlation diagram of the initial unmoored length and the calculated value of the outbound straight length, and 3b is a correlation diagram of the initial unmoored length and the actual value of the outbound straight length;

[0045] Figure 4 4a is a relationship diagram between the swing width of the deep-sea line and the length of the straight line out of the shore disclosed in the present invention, wherein 4b is a relationship diagram between the swing width of the deep-sea line and the length of the straight line out of the shore of the second type, and 4b is a relationship diagram between the swing width of the deep-sea line and the length of the straight line out of the shore of the second type;

[0046] Figure 5 A comparison diagram of the calculated and measured plane of the continuous multi-curve deep-water line disclosed in the present invention;

[0047] Figure 6 It is an absolute error diagram of the calculated value and actual value of the continuous multi-curve deep-water line disclosed in the present invention, wherein 6a is the absolute error between the calculated value and the actual value of the deep-water line of curves 1, 2 and 3 in 2022 calculated by the first and second formulas, 6b is the absolute error comparison between the calculated value and the actual value of the deep-water line of curve 1 from 2018 to 2022 calculated by the first formula, and 6c is the absolute error comparison between the calculated value and the actual value of the deep-water line of curves 2 and 3 from 2018 to 2022 calculated by the second formula. DETAILED DESCRIPTION

[0048] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0049] In this application, relational terms such as first and second, etc. are used only to distinguish one entity or operation from another entity or operation, and do not necessarily require or imply any such actual relationship or order between these entities or operations. The terms "include", "comprise" or any other variants thereof are intended to cover non-exclusive inclusion, so that a process, method, article or device including a series of elements includes not only those elements, but also other elements not explicitly listed, or also includes elements inherent to such process, method, article or device. In the absence of more restrictions, the elements defined by the sentence "comprise one..." do not exclude the existence of other identical elements in the process, method, article or device including the elements.

[0050] See also Figure 1 As shown, the present invention discloses a method for predicting the swing width of the deep channel line of a continuous curve under the influence of a bank protection project, comprising the following steps:

[0051] S1. Obtain remote sensing images and use ArcGIS software to extract the river centerline as the river depth line analysis object;

[0052] S2. Establish a curve coordinate system, and intercept three curve abyssal lines according to the coordinate system. The interception range is from the center of the first curve coordinate circle to the initial shore point of the next curve abyssal line, so that the three curve coordinate systems after interception return to one center, and use Origin software to fit the common line of the three curve abyssal lines;

[0053] S3. Determine the approximate shore length and initial unshore length of the deep channel line, collect the hydrological data of the river section and combine the various influencing parameter indicators to fit the empirical relationship of the initial unshore length;

[0054] S4. According to the initial unbanked length, river section hydrological data and indicators of each bend, the straight length of the deep-water line out of the shore is fitted;

[0055] S5. Take the length of the outbound straight line as the horizontal coordinate, and measure the longitudinal values ​​of the three curve swings in turn according to the 20 points evenly divided by the length of the outbound straight line. Fit the functional relationship of the swing width of the continuous curve deep-water line to verify the accuracy of this formula and compare it with the actual deep-water line.

[0056] Furthermore, the specific content of S1 is:

[0057] Based on remote sensing images and according to the water body index method in ArcGIS, water bodies are extracted according to the largest difference between water body reflections in different bands. The river boundary line of the dry season from 2016 to 2022 is processed according to the extracted water body. The river centerline is extracted through ArcGIS vectorization tool ArcScan as the main analysis object of the river depth line.

[0058] Furthermore, S1 specifically includes the following steps:

[0059] S101. To obtain the planar morphology of the river channel, the 2016-2022 dry season satellite imagery was downloaded based on the 30-meter resolution Landsat8-OLI and 30-meter resolution Landsat9-OLI. Based on the water index method in ArcGIS, the water body was extracted based on the large difference in water body reflection between different bands:

[0060]

[0061] MNDWI is the improved normalized difference water index, p(Green) is the reflectance of the green band, and p(MIR) is the reflectance of the mid-infrared band;

[0062] S102. Based on the extracted water bodies, river boundary lines of different years are obtained by processing, and river center lines are extracted using ArcGIS vectorization tool ArcScan based on the river boundary lines of different years.

[0063] Further, see Figure 2 The schematic diagram of the analysis of the river channel deep line swing is shown in S2, which specifically includes the following steps:

[0064] S201: The coordinate system takes the midpoint of the length of each bend revetment project as the origin O, and the extension line connecting the origin to the center of the revetment project as the ordinate. According to the coordinate system, three bend deep lines are intercepted (the deep lines from 2016 to 2022, but because the second and third bend revetment projects were completed in 2018, the deep lines are intercepted from 2018). The interception range is from the center of the first bend coordinate circle to the initial shore point of the next bend deep line. Each bend is rotated by a certain angle so that it is located on the same horizontal plane, and the three intercepted bend coordinate systems are returned to a new rectangular coordinate system;

[0065] S202: In the new rectangular coordinate system, select a preset number of points on the horizontal axis (for example, 40, 45 or 50, the denser the horizontal coordinate points are, the more accurate the fitting common line is), use CAD to measure the coordinate values ​​of the three curve depth lines, and use Origin software to fit the common line of the three curve depth lines according to the coordinate values, and separate the common line and the curve depth line in turn.

[0066] Furthermore, S3 specifically includes the following steps:

[0067] S301: Find the shore entry and exit points of each bend deep channel, and define the distance from the shore entry point to the initial end of the revetment as the initial unshored length L i , define the distance from the outbound point to the initial end of the revetment as the original length L. Since the outbound point range of the river channel deep-water line in different years is relatively close, the outbound point range of the deep-water line of each bend can be approximately determined, the original length L is fixed, the original length of each bend is determined, and the approximate shore length is collected;

[0068] S302: Based on S301, determine the initial unlanded length L i The initial unbanked length is closely related to the water and sediment conditions, the soil composition of the riverbed, and the bending radius of the bank protection project. The hydrological data of the river section and the indicators of each bend are collected, and the average flow and sediment content in the flood seasons of previous years are calculated. Considering that the adjustment of the river channel morphology under the non-equilibrium state is not only related to the current water and sediment conditions, but also affected by the lag effect of the water and sediment conditions in the previous years, the water and sediment combination is further analyzed. Considering that the correlation coefficient between the sliding average water and sediment and the shore entry point is the highest when n=4, the average water flow scouring intensity in the four years before the flood season is calculated, and the flood season water flow scouring intensity F i and the average water flow intensity in the previous four years The expressions are:

[0069]

[0070] In the formula, is the annual average flow, in m 3 / s, is the annual average sediment content, in kg / m 3 , is the average water flow scouring intensity in the i-th year, in m, and n is the number of years of the sliding mean;

[0071] S303, collected the river section gradient and the corresponding bed sand particle size, calculated the flat beach water depth from 2018 to 2022, and further calculated the relative mobility M of the riverbed components:

[0072]

[0073] Where M is the relative mobility of the riverbed components, J is the slope, the unit is ‰, and D 35 is the particle size of the bed sand composition that is smaller than 35% of the particle size, in mm, and h is the water depth under flat beach flow;

[0074] S304, based on S302 and S303, fitting an empirical relationship of initial unlanded length;

[0075]

[0076] Where, Li is the initial unlanded length, is the average water flow scouring intensity in the previous n years, M is the relative mobility of the soil, and R is the bending radius of the bank protection.

[0077] For details, see Figure 3 As shown, Figure 3 a is the correlation diagram between the initial unmarched length and the calculated straight length out of the shore. Figure 3 b is the correlation diagram between the initial un-docked length and the actual value of the straight length out of the shore.

[0078] Further, S4 specifically includes the following steps:

[0079] S401: Collect the annual runoff and annual sediment transport of the current river section hydrological station, obtain the bending radius of the bend bank protection project, and fit the straight line length L of the deep channel out of the shore e :

[0080] L e =-0.0026W+0.00005Q s -0.8305R-0.7435L c +6.613

[0081] Where, L e is the straight length of the deep channel out of the shore, W is the annual runoff, Q s is the sediment transport volume, R is the bending radius of the bank protection project, L c It is the approximate shore length of the deep channel line.

[0082] S501. The length of the outbound straight line is evenly divided into 20 points each year. The length of the outbound straight line is used as the horizontal axis. According to the 20 points evenly divided by the length of the outbound straight line, the longitudinal values ​​of the swing of the three curves are measured in turn. The No. 1 curve shows a multi-upward trend, and the No. 2 and No. 3 curves show a gradual upward trend. The swing range of the deep line of the No. 1 curve is 542m, while the swing range of the deep line of the No. 2 and No. 3 curves is 162m and 420m respectively. In order to further analyze the annual deep line swing of continuous curves width, so bend 1 is classified as the first category, bends 2 and 3 are classified as the second category. Because the deep channel line of bend 2 is below the length of the straight line out of the shore, in order to facilitate fitting with the deep channel line of bend 3, the first 10 points of the deep channel line of bend 2 are raised by 200m each year, 11 to 15 points are raised by 400m, and the last 5 points are raised by 600m. After the results are calculated, the corresponding values ​​of each point are subtracted. The deep channels of the two types of bends are fitted according to the 20 lateral values ​​each year. For details, see Figure 4 is the relationship between the swing width of the deep channel and the length of the straight line out of the shore, where Figure 4 a is the relationship between the swing width of the first type of deep-water line and the length of the straight line out of the shore, Figure 4b is the relationship between the swing width of the second-type deep-water line and the length of the straight line out of the shore. The formulas for the first and second types are as follows:

[0083]

[0084] y2=0.0174x 1.348 -130.627

[0085] Where x is the straight line length out of the shore, in meters;

[0086] S502. To verify the accuracy of this formula, the points of the 2022 outbound straight line are substituted for verification. Figure 6 As shown in the figure, it is the absolute error diagram of the calculated value and the actual value of the continuous multi-curve deep-sea line. Figure 6 a is the absolute error between the calculated value and the actual value of the deep-sea line of curves 1, 2, and 3 in 2022 calculated by the first and second formulas, Figure 6 b is the absolute error comparison between the calculated value and the actual value of the deep-sea line of Curve 1 from 2018 to 2022 calculated by the first type of formula, Figure 6 c is the absolute error comparison between the calculated value and the actual value of the deep-water line of curves 2 and 3 calculated by the second formula from 2018 to 2022. The number of absolute errors between the calculated value and the actual value of the three curves in 2022 is less than or equal to 50m, 80m, and 110m, accounting for 48%, 67%, and 92% of the total number, while the number of absolute errors between the calculated value and the actual value of curve 1 from 2018 to 2022 is less than or equal to 50m, 100m, and 150m, accounting for 30%, 65%, and 86% of the total number, and the proportion of curves 2 and 3 from 2018 to 2022 is 49.5%, 83.5%, and 96.5%. The calculated values ​​of 20 points in each curve in 2022 are entered into CAD respectively, each point is connected for spline fitting, and then imported into ArcGIS for comparison with the actual deep-water line. For details, see Figure 5 , is a comparison diagram of the calculated and measured plane of the continuous multi-bend deep channel line. That is, the predicted value change is close to the actual value change. Although there are large differences in some parts, it can basically reflect the swing trend of the deep channel line under the effect of bank protection in continuous bends.

[0087] Each embodiment in this specification is described in a progressive manner, and the same or similar parts between the embodiments can refer to each other, and each embodiment focuses on the differences from other embodiments. In particular, for the system or system embodiment, since it is basically similar to the method embodiment, the description is relatively simple, and the relevant parts can refer to the partial description of the method embodiment. The system and system embodiments described above are merely schematic, wherein the units described as separate components may or may not be physically separated, and the components displayed as units may or may not be physical units, that is, they may be located in one place, or they may be distributed on multiple network units. Some or all of the modules may be selected according to actual needs to achieve the purpose of the scheme of this embodiment. Ordinary technicians in this field can understand and implement it without creative work.

[0088] The above description of the disclosed embodiments enables one skilled in the art to implement or use the present invention. Various modifications to these embodiments will be apparent to one skilled in the art, and the general principles defined herein may be implemented in other embodiments without departing from the spirit or scope of the present invention. Therefore, the present invention will not be limited to the embodiments shown herein, but rather to the widest scope consistent with the principles and novel features disclosed herein.

Claims

1. A method for predicting the swing width of the deep channel line of a continuous curve under the influence of bank protection engineering. It is characterized in that The following steps are involved: S1. Obtain remote sensing images and use ArcGIS software to extract the river centerline as the river depth line analysis object; S2. Establish a curve coordinate system, and intercept three curve abyssal lines according to the coordinate system. The interception range is from the center of the first curve coordinate circle to the initial shore point of the next curve abyssal line, so that the three curve coordinate systems after interception return to one center, and use Origin software to fit the common line of the three curve abyssal lines; S3. Determine the approximate shore length and initial unshore length of the deep channel line, collect the hydrological data of the river section and combine the various influencing parameter indicators to fit the empirical relationship of the initial unshore length; S4. According to the initial unbanked length, river section hydrological data and indicators of each bend, the straight length of the deep-water line out of the shore is fitted; S5. Take the length of the outbound straight line as the horizontal coordinate, and measure the longitudinal values ​​of the three curve swings in turn according to the 20 points evenly divided by the length of the outbound straight line. Fit the functional relationship of the swing width of the continuous curve deep-water line to verify the accuracy of this formula and compare it with the actual deep-water line.

2. According to the method for predicting the swing width of the deep channel line of a continuous curve under the influence of a bank protection project as described in claim 1, It is characterized in that The specific contents of S1 are: Based on remote sensing images and the water index method in ArcGIS, water bodies are extracted according to the largest difference in water reflection between different bands. The river boundary line in the dry season is processed according to the extracted water body, and the river centerline is extracted through ArcGIS vectorization tool ArcScan as the main analysis object of the river depth line.

3. According to the method for predicting the swing width of the deep channel line of a continuous curve under the influence of a bank protection project as described in claim 2, It is characterized in that S1 specifically includes the following steps: S101. To obtain the planar morphology of the river channel, the dry season satellite images were downloaded based on the 30-meter resolution Landsat8-OLI and 30-meter resolution Landsat9-OLI. Based on the water index method in ArcGIS, the water body was extracted according to the large difference between the water body reflections in different bands: MNDWI is the improved normalized difference water index, p(Green) is the reflectance of the green band, and p(MIR) is the reflectance of the mid-infrared band; S102. Based on the extracted water bodies, river boundary lines of different years are obtained by processing, and river center lines are extracted using ArcGIS vectorization tool ArcScan based on the river boundary lines of different years.

4. According to the method for predicting the swing width of the deep channel line of a continuous curve under the influence of a bank protection project as described in claim 1, It is characterized in that S2 specifically includes the following steps: S201: The coordinate system takes the midpoint of the length of each bend revetment project as the origin O, and the extension line connecting the origin to the center of the revetment project as the ordinate. According to the coordinate system, three bend depth lines are intercepted, and the interception range is from the center of the first bend coordinate circle to the initial shore point of the next bend depth line. Each bend is rotated by a certain angle to be located in the same horizontal plane, so that the intercepted three bend coordinate systems belong to a new rectangular coordinate system; S202: In the new rectangular coordinate system, select a preset point on the horizontal axis, use CAD to measure the coordinate values ​​of the three curve depth lines, and use Origin software to fit the common line of the three curve depth lines according to the coordinate values, and separate the common line and the curve depth line in turn.

5. According to the method for predicting the swing width of the deep channel line of a continuous curve under the influence of a bank protection project as described in claim 1, It is characterized in that S3 specifically includes the following steps: S301: Find the shore entry and exit points of each bend deep channel, and define the distance from the shore entry point to the initial end of the revetment as the initial unshored length L i , define the distance from the shore exit to the initial end of the revetment as the original length L, fix the original length L, determine the original length of each bend, and collect the approximate shore length; S302: Based on S301, determine the initial unlanded length L i , collect the current river section hydrological data and each bend index, calculate the average flow and sediment content in the flood seasons of previous years, further analyze the water-sediment combination, consider that the sliding average water and sediment has the highest correlation coefficient with the shore entry point when n=4, calculate the average water flow scouring intensity in the four years before the flood season, and the flood season water flow scouring intensity F i and the average water flow intensity in the previous four years The expressions are: In the formula, is the annual average flow, in m 3 / s, is the annual average sediment content, in kg / m 3 , is the average water flow scouring intensity in the i-th year, and n is the number of years of the sliding mean; S303, collect the river section gradient and the corresponding bed sand particle size, calculate the flat water depth, and further calculate the relative mobility M of the riverbed components: Where M is the relative mobility of the riverbed components, J is the slope, the unit is ‰, and D 35 is the particle size of the bed sand composition that is smaller than 35% of the particle size, in mm; h is the water depth under flat beach flow, in m; S304, based on S302 and S303, fitting an empirical relationship of initial unlanded length; Where, L i is the initial unlanded length, is the average water flow scouring intensity in the previous n years, M is the relative mobility of the soil, and R is the bending radius of the bank protection.

6. According to claim 1, a method for predicting the swing width of the deep channel line of a continuous curve under the influence of a bank protection project, It is characterized in that S4 specifically includes the following steps: S401: Collect the annual runoff and annual sediment transport of the current river section hydrological station, obtain the bending radius of the bend bank protection project, and fit the straight line length L of the deep channel out of the shore e : L e =-0.0026W+0.00005Q s -0.8305R-0.7435L c +6.613 Where, L e is the straight length of the deep channel out of the shore, W is the annual runoff, Q s is the sediment transport volume, R is the bending radius of the bank protection project, L c It is the approximate shore length of the deep channel line.