Pipe orifice butt joint auxiliary tool and pipe orifice butt joint method

By setting a positioning mounting seat and adjustable laser emitter at the connection between the ribs and steel plates of the hull structure, the axial distance of the pre-installed pipe openings is solved, and the problem of difficulty in controlling axial installation accuracy in the prior art is achieved, and high efficiency is achieved , accurate docking operation.

CN118907344APending Publication Date: 2024-11-08CSSC HUANGPU WENCHONG SHIPBUILDING CO LTD
View PDF 0 Cites 1 Cited by

Patent Information

Application Number
CN202411201251.6
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-29
Publication Date
2024-11-08

AI Technical Summary

Technical Problem

In the installation of ship pipes, the installation accuracy of the pre-installed pipe ports is difficult to control, resulting in large measurement deviations, low efficiency, and largely affected by equipment and human factors.

Method used

Using a positioning mount and adjustable first and second laser emitters, the maximum and minimum distance values ​​of the pre-installed pipe ports are determined by forming the first and second wheelbase laser surfaces, simplifying the docking process and improving accuracy .

Benefits of technology

It improves the efficiency and accuracy of docking operations, reduces the influence of equipment and human factors, is simple to operate, saves time and effort, and ensures docking quality.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118907344A_ABST
    Figure CN118907344A_ABST
Patent Text Reader

Abstract

The invention belongs to the technical field of ship assembly, and discloses a pipe orifice butt joint auxiliary tool and a pipe orifice butt joint method. The pipe orifice butt joint auxiliary tool comprises a positioning mounting seat, a first laser transmitter and a second laser transmitter, the positioning mounting seat is arranged at the joint of a ship structure rib plate and a ship structure steel plate, and the first laser transmitter and the second laser transmitter are adjustably arranged on the positioning mounting seat. The first and second shaft distance laser surfaces are respectively used for forming a first shaft distance laser surface and a second shaft distance laser surface. The maximum axle distance and the minimum axle distance between the pipe orifice of the preassembled pipe and the closing opening are determined through the first axle distance laser surface and the second axle distance laser surface, so that the accurate butt joint position of the preassembled pipe can be determined only by moving the pipe orifice of the preassembled pipe to the position between the first axle distance laser surface and the second axle distance laser surface during butt joint, the operation is simple, and the working efficiency is high. Compared with the prior art, time and labor are saved, the butt joint operation efficiency is improved, the influence of equipment factors and human factors is reduced, the deviation during measurement is reduced, and the measurement precision is improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of ship assembly, and in particular to a pipe orifice docking auxiliary tool and a pipe orifice docking method. Background Art

[0002] As the precision control of ship pipe and outfitting installation begins, the precision of pipe and outfitting pre-installation needs to be further improved. Therefore, the closing sleeve connection design is adopted at the closing mouth instead of the closing pipe connection design, that is, a closing sleeve is used to complete the connection of pipe and outfitting at the closing mouth. The closing sleeve connection requires the closing sleeve to be pre-installed and fixed on the pre-installed pipe at one end. After the adjacent sections are butt-jointed, the closing sleeve is moved to the middle of the two pre-installed pipes for welding and fixing to complete the butt-jointing of the pre-installed pipes.

[0003] In order to ensure that the pre-installed pipes are properly docked during closing, it is necessary to control the assembly accuracy of the pre-installed pipe mouth, including the installation accuracy in the height direction, left-right direction and axial direction of the pre-installed pipe mouth. The installation accuracy in the axial direction is the most important. It is necessary to avoid the pre-installed pipe mouth being too far away from the closing mouth, resulting in insufficient overlap of the closing sleeve and not meeting the assembly requirements, and to prevent the pre-installed pipe mouth from exceeding the closing mouth, resulting in interference between the two pre-installed pipes during the closing mouth docking process. In order to control the installation accuracy of the pre-installed pipe in the axial direction, it is necessary to measure the installation distance of the pre-installed pipe mouth during the construction process. The existing technology uses a plumb line to set the pre-installed pipe mouth, project the pre-installed pipe mouth onto the segmented structure, and then use a tape measure, steel ruler and other tools to directly measure the distance from the closing mouth of the segmented structure to the projected position. If the segment is not placed horizontally, deviation adjustment processing is also required.

[0004] However, in order to determine the axial accuracy of the pre-installed pipe mouth during docking using this method, it is necessary to measure the axial distance while installing it. The plumb line must be re-placed after each adjustment of the pre-installed pipe, and the accuracy can only be measured with a ruler after the plumb line is stabilized. This process is not only complicated, time-consuming and labor-intensive, which reduces the efficiency of the docking operation, but also because this method is greatly affected by equipment and human factors, resulting in large measurement deviations and low measurement accuracy. Summary of the invention

[0005] The purpose of the present invention is to provide a pipe orifice docking auxiliary tooling and a pipe orifice docking method, which are simple to operate, save time and effort, have high docking efficiency, are less affected by equipment factors and human factors, and have high measurement accuracy.

[0006] To achieve this object, the present invention adopts the following technical solutions:

[0007] Provided is a pipe butt joint auxiliary tool, which is used to assist two pre-assembled pipes in butt jointing at a closing mouth, and comprises:

[0008] A positioning mounting seat, which is arranged at the junction of the hull structure rib plate and the hull structure steel plate and is tightly fitted with the hull structure rib plate and the hull structure steel plate;

[0009] A first laser emitter, the first laser emitter is adjustably disposed on the positioning mounting seat, and the first laser emitter is used to form a first wheelbase laser plane;

[0010] A second laser emitter is adjustably disposed on the positioning mounting seat and is located on a side of the first laser emitter away from the closing opening. The second laser emitter is used to form a second wheelbase laser surface.

[0011] Optionally, the positioning mounting seat includes a first positioning plate and a second positioning plate, the first positioning plate is vertically connected to the second positioning plate, the first positioning plate abuts against the hull structure steel plate, the second positioning plate abuts against the hull structure rib plate, and the first laser emitter and the second laser emitter are both arranged on the side of the first positioning plate away from the hull structure steel plate.

[0012] Optionally, the positioning mounting seat also includes a limit plate, which is vertically connected to the first positioning plate and is located on the side of the first positioning plate facing the closing mouth, and the limit plate abuts against the side of the hull structural steel plate facing the closing mouth.

[0013] Optionally, the positioning mounting seat further includes a first magnetic component, which is disposed on the first positioning plate and is used to allow the first positioning plate to be adsorbed on the hull structure steel plate.

[0014] Optionally, the positioning mounting seat further includes a second magnetic component, which is disposed on the second positioning plate and is used to allow the second positioning plate to be adsorbed on the hull structure rib.

[0015] Optionally, the first laser emitter includes a first laser generating component and a first magnetic base, the first laser generating component is disposed on the first magnetic base and is used to generate a planar laser beam, and the first magnetic base is adsorbed on the positioning mounting seat.

[0016] Optionally, the second laser emitter includes a second laser generating element and a second magnetic base, the second laser generating element is disposed on the second magnetic base and is used to generate a planar laser beam, and the second magnetic base is adsorbed on the positioning mounting seat.

[0017] Optionally, the second wheelbase laser plane and the first wheelbase laser plane are both parallel to the plane where the closing opening is located.

[0018] On the other hand, a pipe orifice docking method is also provided, wherein the pipe orifice docking method completes the docking operation of the two pre-installed pipes by using two sets of pipe orifice docking auxiliary tooling as described in any one of the above items, and the pipe orifice docking method comprises the following steps:

[0019] S1, determining the maximum distance value and the minimum distance value between the pipe openings of the two pre-installed pipes and the closing opening;

[0020] S2, respectively arranging the positioning mounting seats of the two sets of the pipe opening docking auxiliary fixtures at the corresponding joints of the hull structure ribs and the hull structure steel plates, and determining the maximum and minimum distance values ​​of the pipe openings of the pre-installed pipes from the closing openings at the points on the positioning mounting seats;

[0021] S3, adjusting the positions of the first laser emitter and the second laser emitter on the positioning mounting seat, so that the first wheelbase laser plane and the minimum distance value between the pipe mouth of the pre-installed tube and the closing mouth coincide with the point on the positioning mounting seat, and the second wheelbase laser plane and the maximum distance value between the pipe mouth of the pre-installed tube and the closing mouth coincide with the point on the positioning mounting seat;

[0022] S4, placing the pipe mouth of the pre-installed pipe with the closed sleeve between the first wheelbase laser surface and the second wheelbase laser surface of one set of the pipe mouth docking auxiliary tooling;

[0023] S5, placing the pipe opening of the pre-installed pipe that is not sleeved with the closing sleeve between the first wheelbase laser surface and the second wheelbase laser surface of another set of the pipe opening docking auxiliary tooling;

[0024] S6, sliding the closing sleeve to the butt joint of the two pre-installed pipes and welding and fixing them, so as to complete the butt joint operation of the pipe ends of the two pre-installed pipes at the closing opening.

[0025] Beneficial effects of the present invention:

[0026] The present invention provides a pipe orifice docking auxiliary tooling, by arranging a first laser emitter and a second laser emitter which can be adjusted on a positioning mounting seat arranged at the junction of a hull structure rib plate and a hull structure steel plate, so as to determine the maximum wheelbase and the minimum wheelbase of the pipe orifice of the pre-installed pipe from the closing mouth according to the first wheelbase laser plane formed by the first laser emitter and the second wheelbase laser plane formed by the second laser emitter, so that when docking, it is only necessary to move the pipe orifice of the pre-installed pipe between the first wheelbase laser plane and the second wheelbase laser plane to determine the accurate docking position of the pre-installed pipe, the operation is simple, time-saving and labor-saving, and the efficiency of the docking operation is improved. Compared with using a plumb bob to determine the position of the pipe orifice of the pre-installed pipe through projection calculation, the tooling is less affected by equipment factors and human factors, the deviation during measurement is reduced, and the measurement accuracy is improved.

[0027] The present invention also provides a pipe orifice docking method, which can quickly and accurately achieve the docking operation of two pre-installed pipes by applying the above-mentioned pipe orifice docking auxiliary tooling, greatly reducing the time of the docking operation and ensuring the quality of the docking operation. BRIEF DESCRIPTION OF THE DRAWINGS

[0028] Figure 1 It is an assembly diagram of the pipe orifice butt joint auxiliary tooling provided by the present invention;

[0029] Figure 2 This is a front view of the pipe orifice docking auxiliary tooling provided by the present invention;

[0030] Figure 3 It is a side view of the pipe orifice docking auxiliary tooling provided by the present invention;

[0031] Figure 4 It is a schematic diagram of the pipe orifice docking auxiliary tooling provided by the present invention assisting the pre-installed pipe in determining the axial distance.

[0032] In the figure:

[0033] 100, hull structural ribs; 200, hull structural steel plates; 300, closing mouth; 400, pre-installed pipe; 500, closing casing;

[0034] 1. Positioning mounting seat; 11. First positioning plate; 12. Second positioning plate; 13. Limiting plate; 14. First magnetic member; 15. Second magnetic member;

[0035] 2. First laser emitter; 21. First wheelbase laser surface; 22. First laser generating element; 23. First magnetic base;

[0036] 3. Second laser emitter; 31. Second wheelbase laser surface; 32. Second laser generating element; 33. Second magnetic base. DETAILED DESCRIPTION

[0037] The present invention will be further described in detail below in conjunction with the accompanying drawings and embodiments. It is to be understood that the specific embodiments described herein are only used to explain the present invention, rather than to limit the present invention. It should also be noted that, for ease of description, only parts related to the present invention, rather than all structures, are shown in the accompanying drawings.

[0038] In the description of the present invention, unless otherwise clearly specified and limited, the terms "connected", "connected", and "fixed" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection or an indirect connection through an intermediate medium, it can be the internal connection of two elements or the interaction relationship between two elements. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.

[0039] In the present invention, unless otherwise clearly specified and limited, a first feature being "above" or "below" a second feature may include that the first and second features are in direct contact, or may include that the first and second features are not in direct contact but are in contact through another feature between them. Moreover, a first feature being "above", "above" and "above" a second feature includes that the first feature is directly above and obliquely above the second feature, or simply indicates that the first feature is higher in level than the second feature. A first feature being "below", "below" and "below" a second feature includes that the first feature is directly below and obliquely below the second feature, or simply indicates that the first feature is lower in level than the second feature.

[0040] In the description of this embodiment, the terms "upper", "lower", "right", etc., directions or positional relationships are based on the directions or positional relationships shown in the drawings, and are only for the convenience of description and simplification of operation, rather than indicating or implying that the device or element referred to must have a specific direction, be constructed and operated in a specific direction, and therefore cannot be understood as limiting the present invention. In addition, the terms "first" and "second" are only used to distinguish in the description and have no special meaning.

[0041] As the precision control of ship pipe and outfitting installation begins, the precision of pipe and outfitting pre-installation needs to be further improved. Therefore, the closing sleeve connection design is adopted at the closing mouth instead of the closing pipe connection design, that is, a closing sleeve is used to complete the connection of pipe and outfitting at the closing mouth. The closing sleeve connection requires the closing sleeve to be pre-installed and fixed on the pre-installed pipe at one end. After the adjacent sections are butt-jointed, the closing sleeve is moved to the middle of the two pre-installed pipes for welding and fixing to complete the butt-jointing of the pre-installed pipes.

[0042] In order to ensure that the pre-installed pipes are properly docked during closing, it is necessary to control the assembly accuracy of the pre-installed pipe mouth, including the installation accuracy in the height direction, left-right direction and axial direction of the pre-installed pipe mouth. The installation accuracy in the axial direction is the most important. It is necessary to avoid the pre-installed pipe mouth being too far away from the closing mouth, resulting in insufficient overlap of the closing sleeve and not meeting the assembly requirements, and to prevent the pre-installed pipe mouth from exceeding the closing mouth, resulting in interference between the two pre-installed pipes during the closing mouth docking process. In order to control the installation accuracy of the pre-installed pipe in the axial direction, it is necessary to measure the installation distance of the pre-installed pipe mouth during the construction process. The existing technology uses a plumb line to set the pre-installed pipe mouth, project the pre-installed pipe mouth onto the segmented structure, and then use a tape measure, steel ruler and other tools to directly measure the distance from the closing mouth of the segmented structure to the projected position. If the segment is not placed horizontally, deviation adjustment processing is also required.

[0043] However, in order to determine the axial accuracy of the pre-installed pipe mouth during docking using this method, it is necessary to measure the axial distance while installing it. The plumb line must be re-placed after each adjustment of the pre-installed pipe, and the accuracy can only be measured with a ruler after the plumb line is stabilized. This process is not only complicated, time-consuming and labor-intensive, which reduces the efficiency of the docking operation, but also because this method is greatly affected by equipment and human factors, resulting in large measurement deviations and low measurement accuracy.

[0044] Therefore, in order to quickly and accurately complete the docking operation and reduce the influence of equipment factors and human factors, this embodiment provides a pipe mouth docking auxiliary tooling, which is used to assist two pre-installed pipes in docking at the closing mouth.

[0045] like Figures 1 to 4 As shown, the pipe mouth docking auxiliary tooling includes a positioning mounting seat 1, a first laser emitter 2 and a second laser emitter 3. The positioning mounting seat 1 is arranged at the junction of the hull structure rib 100 and the hull structure steel plate 200, and is tightly fitted with the hull structure rib 100 and the hull structure steel plate 200. The first laser emitter 2 is adjustably arranged on the positioning mounting seat 1. The first laser emitter 2 is used to form a first wheelbase laser surface 21. The second laser emitter 3 is adjustably arranged on the positioning mounting seat 1 and is located on the side of the first laser emitter 2 away from the closing mouth 300. The second laser emitter 3 is used to form a second wheelbase laser surface 31.

[0046] By arranging a first laser emitter 2 and a second laser emitter 3 which can be adjusted on the positioning mounting seat 1 on the joint of the hull structure rib 100 and the hull structure steel plate 200, the maximum wheelbase and the minimum wheelbase of the pipe mouth of the pre-installed pipe 400 from the closing mouth 300 are determined according to the first wheelbase laser surface 21 formed by the first laser emitter 2 and the second wheelbase laser surface 31 formed by the second laser emitter 3, so that when docking, it is only necessary to move the pipe mouth of the pre-installed pipe 400 between the first wheelbase laser surface 21 and the second wheelbase laser surface 31 to determine the accurate docking position of the pre-installed pipe 400, which is simple to operate, saves time and labor, improves the efficiency of the docking operation, and compared with using a plumb line to determine the position of the pipe mouth of the pre-installed pipe 400 through projection calculation, it is less affected by equipment factors and human factors, reduces the deviation during measurement, and improves the accuracy of measurement.

[0047] Alternatively, if Figure 1 , Figure 2 As shown, the positioning mounting seat 1 includes a first positioning plate 11 and a second positioning plate 12, the first positioning plate 11 is vertically connected to the second positioning plate 12, the first positioning plate 11 abuts on the hull structure steel plate 200, and the second positioning plate 12 abuts on the hull structure rib plate 100, and the first laser emitter 2 and the second laser emitter 3 are both arranged on the side of the first positioning plate 11 away from the hull structure steel plate 200. Since the angle at the junction of the hull structure steel plate 200 and the hull structure rib plate 100 is a right angle, the first positioning plate 11 and the second positioning plate 12 are vertically connected to ensure that the positioning mounting seat 1 composed of the first positioning plate 11 and the second positioning plate 12 can be closely attached to the junction of the hull structure steel plate 200 and the hull structure rib plate 100, thereby ensuring the accuracy during measurement.

[0048] In this embodiment, the positioning mounting seat 1 composed of the first positioning plate 11 and the second positioning plate 12 can be directly made of angle steel, which is easy to obtain and reduces the production cost. In other embodiments, the first positioning plate 11 and the second positioning plate 12 can be vertically connected by welding to form the positioning mounting seat 1.

[0049] Alternatively, if Figure 1 , Figure 2 As shown, the positioning mounting seat 1 further includes a limiting plate 13, which is vertically connected to the first positioning plate 11 and is located on the side of the first positioning plate 11 facing the closing opening 300, and the limiting plate 13 abuts against the side of the hull structure steel plate 200 facing the closing opening 300. By connecting the limiting plate 13 abutting against the side of the hull structure steel plate 200 facing the closing opening 300 on the side of the first positioning plate 11 facing the closing opening 300, the positioning mounting seat 1 is fixed to avoid displacement between the positioning mounting seat 1 and the hull structure steel plate 200, resulting in inaccurate positions of the first wheelbase laser surface 21 and the second wheelbase laser surface 31.

[0050] In this embodiment, the limiting plate 13 is connected to the side of the first positioning plate 11 facing the closing opening 300 by welding.

[0051] Alternatively, if Figure 2 As shown, the positioning mounting seat 1 further includes a first magnetic member 14, which is disposed on the first positioning plate 11 and is used to make the first positioning plate 11 adsorb on the hull structure steel plate 200. By arranging the first magnetic member 14 on the first positioning plate 11, the detachable connection between the first positioning plate 11 and the hull structure steel plate 200 is achieved, and the hull structure steel plate 200 is protected during disassembly and assembly.

[0052] In this embodiment, in order to ensure the firmness of the connection between the first positioning plate 11 and the hull structural steel plate 200, the positioning mounting seat 1 includes a plurality of first magnetic members 14 disposed on the first positioning plate 11, wherein the first magnetic members 14 are magnets.

[0053] Alternatively, if Figure 2 As shown, the positioning mounting seat 1 further includes a second magnetic member 15, which is disposed on the second positioning plate 12 and is used to make the second positioning plate 12 adsorb on the hull structure rib 100. By arranging the second magnetic member 15 on the second positioning plate 12, the second positioning plate 12 and the hull structure rib 100 are detachably connected, and the hull structure rib 100 is protected during disassembly.

[0054] In this embodiment, in order to ensure the firmness of the connection between the second positioning plate 12 and the hull structure rib 100, the positioning mounting seat 1 includes a plurality of second magnetic members 15 arranged on the second positioning plate 12, wherein the second magnetic members 15 are magnets.

[0055] Alternatively, if Figure 2 As shown, the first laser emitter 2 includes a first laser generating element 22 and a first magnetic base 23. The first laser generating element 22 is disposed on the first magnetic base 23 and is used to generate a planar laser beam. The first magnetic base 23 is adsorbed on the positioning mounting seat 1. The first laser emitter 2 is connected to the positioning mounting seat 1 through the first magnetic base 23, and the position of the first laser emitter 2 can be adjusted on the positioning mounting seat 1.

[0056] Alternatively, if Figure 2As shown, the second laser emitter 3 includes a second laser generating element 32 and a second magnetic base 33. The second laser generating element 32 is disposed on the second magnetic base 33 and is used to generate a planar laser beam. The second magnetic base 33 is adsorbed on the positioning mounting seat 1. The second laser emitter 3 is connected to the positioning mounting seat 1 through the second magnetic base 33, and the position of the second laser emitter 3 can be adjusted on the positioning mounting seat 1.

[0057] Alternatively, if Figure 1 , Figure 4 As shown, the second wheelbase laser plane 31 and the first wheelbase laser plane 21 are both parallel to the plane where the closing opening 300 is located. By keeping the second wheelbase laser plane 31 and the first wheelbase laser plane 21 parallel to the plane where the closing opening 300 is located, the accuracy of the measurement is ensured.

[0058] In this embodiment, a pipe orifice docking method is also provided. The pipe orifice docking method uses two sets of the above-mentioned pipe orifice docking auxiliary tooling to complete the docking operation of two pre-installed pipes 400. The pipe orifice docking method includes the following steps:

[0059] S1, determining the maximum distance value and the minimum distance value between the pipe openings of the two pre-installed pipes 400 and the closing opening 300;

[0060] S2, respectively set the positioning mounting seats 1 of the two sets of pipe opening docking auxiliary fixtures at the corresponding joints of the hull structure ribs 100 and the hull structure steel plates 200, and determine the maximum and minimum distance values ​​of the pipe openings of the pre-installed pipes 400 from the closing openings 300 at the points on the positioning mounting seats 1;

[0061] S3, adjusting the positions of the first laser emitter 2 and the second laser emitter 3 on the positioning mounting seat 1, so that the first wheelbase laser plane 21 and the minimum distance value from the tube mouth of the pre-installed tube 400 to the closing mouth 300 coincide with the point position on the positioning mounting seat 1, and the second wheelbase laser plane 31 and the maximum distance value from the tube mouth of the pre-installed tube 400 to the closing mouth 300 coincide with the point position on the positioning mounting seat 1;

[0062] S4, placing the pipe mouth of the pre-installed pipe 400 sleeved with the closing sleeve 500 between the first wheelbase laser surface 21 and the second wheelbase laser surface 31 of one set of pipe mouth docking auxiliary tooling;

[0063] S5, placing the pipe mouth of the pre-assembled pipe 400 which is not sleeved with the closing sleeve 500 between the first wheelbase laser surface 21 and the second wheelbase laser surface 31 of another set of pipe mouth docking auxiliary tooling;

[0064] S6, sliding the closing sleeve 500 to the butt joint of the two pre-installed pipes 400 and welding and fixing them, thereby completing the butt joint operation of the pipe ends of the two pre-installed pipes 400 at the closing opening 300.

[0065] The pipe mouth docking method can quickly and accurately achieve the docking operation of two pre-installed pipes 400 by applying the above-mentioned pipe mouth docking auxiliary tooling, greatly reducing the time of the docking operation and ensuring the quality of the docking operation.

[0066] Obviously, the above embodiments of the present invention are merely examples for clearly illustrating the present invention, and are not intended to limit the embodiments of the present invention. For those skilled in the art, various obvious changes, readjustments and substitutions can be made without departing from the protection scope of the present invention. It is not necessary and impossible to list all the embodiments here. Any modifications, equivalent substitutions and improvements made within the spirit and principles of the present invention should be included in the protection scope of the claims of the present invention.

Claims

1. A pipe butt joint auxiliary tool, the pipe butt joint auxiliary tool is used to assist two pre-assembled pipes (400) to butt joint at the closing mouth (300), It is characterized in that The pipe orifice butt joint auxiliary tooling comprises: A positioning mounting seat (1), the positioning mounting seat (1) being arranged at the junction of the hull structure rib plate (100) and the hull structure steel plate (200), and being closely fitted with the hull structure rib plate (100) and the hull structure steel plate (200); A first laser emitter (2), the first laser emitter (2) being adjustably arranged on the positioning mounting seat (1), the first laser emitter (2) being used to form a first wheelbase laser surface (21); A second laser emitter (3), the second laser emitter (3) being adjustably arranged on the positioning mounting seat (1) and located on a side of the first laser emitter (2) away from the closing opening (300), the second laser emitter (3) being used to form a second wheelbase laser surface (31).

2. The pipe joint auxiliary tooling according to claim 1, It is characterized in that The positioning mounting seat (1) comprises a first positioning plate (11) and a second positioning plate (12), wherein the first positioning plate (11) is vertically connected to the second positioning plate (12), the first positioning plate (11) abuts against the hull structure steel plate (200), and the second positioning plate (12) abuts against the hull structure rib plate (100), and the first laser emitter (2) and the second laser emitter (3) are both arranged on a side of the first positioning plate (11) away from the hull structure steel plate (200).

3. The pipe joint auxiliary tooling according to claim 2, It is characterized in that The positioning mounting seat (1) also includes a limit plate (13), which is vertically connected to the first positioning plate (11) and is located on the side of the first positioning plate (11) facing the closing opening (300), and the limit plate (13) abuts against the side of the hull structural steel plate (200) facing the closing opening (300).

4. The pipe joint auxiliary tooling according to claim 2, It is characterized in that The positioning mounting seat (1) further comprises a first magnetic component (14), wherein the first magnetic component (14) is arranged on the first positioning plate (11) and is used to make the first positioning plate (11) adsorb on the hull structure steel plate (200).

5. The pipe joint auxiliary tooling according to claim 2, It is characterized in that The positioning mounting seat (1) further comprises a second magnetic component (15), wherein the second magnetic component (15) is arranged on the second positioning plate (12) and is used to make the second positioning plate (12) adsorbed on the hull structure rib plate (100).

6. The pipe joint auxiliary tooling according to claim 1, It is characterized in that The first laser emitter (2) comprises a first laser generating component (22) and a first magnetic base (23); the first laser generating component (22) is arranged on the first magnetic base (23) and is used to generate a planar laser beam; the first magnetic base (23) is adsorbed on the positioning mounting seat (1).

7. The pipe joint auxiliary tooling according to claim 1, It is characterized in that The second laser emitter (3) comprises a second laser generating element (32) and a second magnetic base (33); the second laser generating element (32) is arranged on the second magnetic base (33) and is used to generate a planar laser beam; the second magnetic base (33) is adsorbed on the positioning mounting seat (1).

8. The pipe joint auxiliary tooling according to claim 1, It is characterized in that The second wheelbase laser plane (31) and the first wheelbase laser plane (21) are both parallel to the plane where the closing opening (300) is located.

9. Pipe connection method, It is characterized in that The pipe orifice docking method completes the docking operation of two pre-installed pipes (400) by applying two sets of pipe orifice docking auxiliary tooling according to any one of claims 1 to 8, and the pipe orifice docking method comprises the following steps: S1, determining a maximum distance value and a minimum distance value between the pipe openings of the two pre-installed pipes (400) and the closing opening (300); S2, respectively arranging the positioning mounting seats (1) of the two sets of the pipe opening docking auxiliary fixtures at the corresponding joints of the hull structure ribs (100) and the hull structure steel plates (200), and determining the points on the positioning mounting seats (1) at which the maximum distance value and the minimum distance value of the pipe opening of the pre-installed pipe (400) from the closing opening (300) are located; S3, adjusting the positions of the first laser emitter (2) and the second laser emitter (3) on the positioning mounting seat (1) so that the first wheelbase laser plane (21) and the minimum distance value between the tube mouth of the pre-installed tube (400) and the closing opening (300) coincide with each other at a point on the positioning mounting seat (1), and so that the second wheelbase laser plane (31) and the maximum distance value between the tube mouth of the pre-installed tube (400) and the closing opening (300) coincide with each other at a point on the positioning mounting seat (1); S4, arranging the pipe mouth of the pre-installed pipe (400) sleeved with the closing sleeve (500) between the first wheelbase laser surface (21) and the second wheelbase laser surface (31) of one set of the pipe mouth docking auxiliary tooling; S5, arranging the pipe mouth of the pre-assembled pipe (400) not sleeved with the closing sleeve (500) between the first wheelbase laser surface (21) and the second wheelbase laser surface (31) of another set of pipe mouth docking auxiliary tooling; S6. Slide the closing sleeve (500) to the butt joint of the two pre-installed pipes (400) and weld and fix them, thereby completing the butt joint operation of the pipe ends of the two pre-installed pipes (400) at the closing opening (300).