Debugging instrument
By designing a debugger for central air conditioning, using the interface structure, central control structure, vacuum structure and balance structure, the problems of accuracy and efficiency of traditional refrigerant filling are solved, and the efficiency and accuracy of refrigerant filling are improved.
Patent Information
- Application Number
- CN202410581281.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-05-11
- Publication Date
- 2024-11-08
Smart Images

Figure CN118912757A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of air-conditioning refrigerant injection, and in particular to a debugging instrument. Background Art
[0002] With the development of smart homes, central air conditioners will become a popular choice. However, as the central air conditioner market continues to expand, the quality of central air conditioner system installation technology has not been standardized and effectively supervised in the air-conditioning industry after its rise.
[0003] The traditional installation process requires the installer to carry a lot of tools and equipment to complete the work effectively, which greatly increases the cost and efficiency of the installation project. In addition, due to the excessive amount of equipment carried, multiple self-inspections are required, and the filling process relies on equipment such as electronic scales, resulting in low accuracy in refrigerant filling. Summary of the invention
[0004] The main purpose of the present invention is to provide a debugging instrument, aiming to improve the accuracy and efficiency of refrigerant filling.
[0005] To achieve the above object, the debugging device proposed by the present invention comprises:
[0006] Body;
[0007] An interface structure, the interface structure being arranged on a side surface of the machine body;
[0008] A central control structure, which is disposed in the body, is connected to the interface structure, and controls the opening and closing of the interface structure;
[0009] A vacuum pumping structure, wherein the vacuum pumping structure is connected to the central control structure, the vacuum pumping structure is connected to a balancing structure and balances the pressure of the vacuum pumping structure, and a calibration piece is provided between the vacuum pumping structure and the central control structure;
[0010] Wherein, the vacuum pumping structure also includes a control structure, which is arranged on the machine body and electrically connected to the central control structure.
[0011] Optionally, the vacuum pumping structure includes a vacuum pump body, the vacuum pump body is connected to the central control structure through a pipeline, and the vacuum pump body is connected to the balancing structure through a pipeline;
[0012] The vacuum pump body is arranged in the machine body, or the vacuum pump body is placed outside the machine body.
[0013] Optionally, the vacuum pumping structure also includes a support seat, the support seat is arranged in the machine body, the central control structure is arranged on the top surface of the support seat, the calibration piece and the vacuum pump body are arranged on the support seat, the vacuum pump body is connected to the calibration piece, and the calibration piece is connected to the central control structure.
[0014] Optionally, the balancing structure includes a pressure balancing part, and the pressure balancing part is connected to the vacuum pump body.
[0015] Optionally, the interface structure includes an input interface component and an output interface component, and both the input interface component and the output interface component are connected to the central control structure through a pipeline.
[0016] Optionally, the central control structure includes a plurality of valve components, the plurality of valve components are spaced apart on the top surface of the support seat, the plurality of valve components are respectively connected to the input interface assembly and the output interface assembly through pipelines, and the plurality of valve components are electrically connected to the control structure.
[0017] Optionally, the central control structure further comprises an exhaust port, and the valve member connected to the output interface assembly is connected to the exhaust port via a pipeline;
[0018] The central control structure also includes a high-pressure protection sensor and a low-pressure protection sensor. The plurality of valve components are electrically connected to the high-pressure protection sensor and the low-pressure protection sensor. The high-pressure protection sensor and the low-pressure protection sensor are electrically connected to the control structure.
[0019] Optionally, the output interface assembly includes high and low pressure pipe interfaces, air pipe interfaces and liquid pipe interfaces, and the high and low pressure pipe interfaces, the air pipe interfaces and the liquid pipe interfaces are spaced apart on the side of the body, and the plurality of valve components are respectively connected to the high and low pressure pipe interfaces, the air pipe interfaces and the liquid pipe interfaces through pipelines.
[0020] Optionally, the input interface assembly is connected to the flow meter via a pipeline, the flow meter is connected to the one-way valve via a pipeline, and the one-way valve is connected to one of the valve components via a pipeline.
[0021] Optionally, a weighing structure is further included, and the weighing structure is arranged on the machine body and is used to weigh the refrigerant.
[0022] The technical solution of the present invention is connected to the interface of the central air-conditioning through an interface structure, and realizes self-checking of looseness and leakage through the central control structure and the quantitative injection of refrigerant. Then the vacuum structure is used for pressure detection, and the vacuum structure is pressure balanced through the balance structure. When the pipeline in the central air-conditioning is vacuumed, the gas passes through the calibration part, and the pipeline volume data is accurately obtained in combination with the ambient temperature, humidity and atmospheric pressure, and the pipeline is negatively pressurized to detect leaks. Secondly, according to the pipeline volume data, refrigerant is injected into the pipeline. Due to the ambient temperature, humidity and atmospheric pressure, accurate refrigerant injection amount data is obtained through data calculation, and precise injection is achieved, thereby improving the efficiency and accuracy of injection. BRIEF DESCRIPTION OF THE DRAWINGS
[0023] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on the structures shown in these drawings without paying creative work.
[0024] Figure 1 It is a structural schematic diagram of a first embodiment of a debugging device of the present invention;
[0025] Figure 2 It is a partial structural diagram of the first embodiment of the debugging instrument of the present invention;
[0026] Figure 3 It is a schematic diagram of the partial structure of the built-in vacuum pump body of the first embodiment of the debugging instrument of the present invention;
[0027] Figure 4 It is a partial side view of the structure of the built-in vacuum pump body of the first embodiment of the debugging instrument of the present invention;
[0028] Figure 5 It is a partial rear view schematic diagram of a built-in vacuum pump body of the first embodiment of the debugging instrument of the present invention;
[0029] Figure 6 It is a structural schematic diagram of a second embodiment of the debugging device of the present invention;
[0030] Figure 7 It is a structural schematic diagram of a third embodiment of the debugging device of the present invention;
[0031] Figure 8 It is a partial structural diagram of the third embodiment of the debugging instrument of the present invention.
[0032] Description of Figure Numbers:
[0033]
[0034]
[0035] The realization of the purpose, functional features and advantages of the present invention will be further explained in conjunction with embodiments and with reference to the accompanying drawings. DETAILED DESCRIPTION
[0036] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0037] It should be noted that all directional indications in the embodiments of the present invention (such as up, down, left, right, front, back, etc.) are only used to explain the relative position relationship, movement status, etc. between the components under a certain specific posture (as shown in the accompanying drawings). If the specific posture changes, the directional indication will also change accordingly.
[0038] In the present invention, unless otherwise clearly specified and limited, the terms "connection", "fixation", etc. should be understood in a broad sense. For example, "fixation" can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection or an indirect connection through an intermediate medium, it can be the internal connection of two elements or the interaction relationship between two elements, unless otherwise clearly defined. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.
[0039] In addition, in the present invention, descriptions such as "first", "second", etc. are only used for descriptive purposes and cannot be understood as indicating or implying their relative importance or implicitly indicating the number of technical features indicated. Therefore, the features defined as "first" and "second" may explicitly or implicitly include at least one of the features. In addition, the meaning of "and / or" appearing in the full text is to include three parallel solutions. Taking "A and / or B as an example", it includes solution A, or solution B, or solutions that satisfy both A and B. In addition, the technical solutions between the various embodiments can be combined with each other, but it must be based on the ability of ordinary technicians in this field to implement. When the combination of technical solutions is contradictory or cannot be implemented, it should be deemed that such combination of technical solutions does not exist and is not within the scope of protection required by the present invention.
[0040] The invention provides a debugging instrument.
[0041] Reference Figures 1 to 8 , Figure 1 It is a structural schematic diagram of a first embodiment of a debugging device of the present invention; Figure 2 It is a partial structural diagram of the first embodiment of the debugging instrument of the present invention; Figure 3 It is a schematic diagram of the partial structure of the built-in vacuum pump body of the first embodiment of the debugging instrument of the present invention; Figure 4 It is a partial side view of the structure of the built-in vacuum pump body of the first embodiment of the debugging instrument of the present invention; Figure 5 It is a partial rear view schematic diagram of a built-in vacuum pump body of the first embodiment of the debugging instrument of the present invention; Figure 6 It is a structural schematic diagram of a second embodiment of the debugging device of the present invention; Figure 7 It is a structural schematic diagram of a third embodiment of the debugging device of the present invention; Figure 8 It is a partial structural diagram of the third embodiment of the debugging instrument of the present invention.
[0042] In the embodiment of the present invention, the debugging instrument 1000; Figures 1 to 8 As shown, including:
[0043] Body 10;
[0044] An interface structure 30, the interface structure 30 is arranged on the side of the body 10;
[0045] A central control structure 40, which is disposed in the machine body 10, is connected to the interface structure 30, and controls the opening and closing of the interface structure 30;
[0046] A vacuum pumping structure 60, wherein the vacuum pumping structure 60 is connected to the central control structure 40, the vacuum pumping structure 60 is connected to a balancing structure and balances the pressure of the vacuum pumping structure 60, and a calibration component 70 is provided between the vacuum pumping structure 60 and the central control structure 40;
[0047] The vacuum pumping structure 60 further includes a control structure, which is disposed on the machine body 10 and is electrically connected to the central control structure.
[0048] like Figure 1 to Figure 2 As shown, the interface structure 30 is arranged on the side of the body 10. The interface structure 30 is used to connect the high and low pressure pipe interfaces, the air pipe interface and the liquid pipe interface of the central air conditioner, so as to realize the exchange of gas in the pipe equipment inside the central air conditioner. The interface structure 30 is used to connect the refrigerant tank to output the refrigerant.
[0049] It can be understood that the interface structure 30 is arranged on the side of the body 10 so as to be connected to the interface of the central air conditioner through a pipeline.
[0050] like Figures 2 to 5 As shown, the central control structure 40 is connected to the interface structure 30 to control the opening and closing of the interface structure 30 to facilitate subsequent vacuuming and refrigerant injection operations.
[0051] In order to accurately realize the precise filling of refrigerant and the calculation of the volume of the pipeline in the central air conditioner, it is necessary to calculate the ambient temperature, humidity and atmospheric pressure. Therefore, a temperature and humidity sensor 65 and a positioning module are provided in the body 10. The temperature and humidity sensor 65 is used to measure and read the temperature and humidity of the current environment of the body 10. The positioning module is used to realize the current positioning of the body 10, and obtain the atmospheric pressure data according to the Internet of Things and the weather at the location, so as to cooperate with the temperature, humidity and atmospheric pressure data, so as to accurately calculate the pipeline volume and facilitate the accurate calculation of the filling amount of the refrigerant.
[0052] It should be noted that, in order to facilitate the movement of the body 10 , a plurality of rotating wheels are provided on the bottom surface of the body 10 .
[0053] It should be noted that, in order to facilitate the transportation of the machine body 10 , a plurality of handles are provided at intervals on the top surface of the machine body 10 .
[0054] In order to facilitate the operation of the debugger 1000 , an energy module 50 is arranged on the side of the body 10 , and the energy module 50 includes a power module 52 and a heat dissipation module 51 . The heat dissipation module 51 is arranged on one side of the power module 52 to provide energy for the operation of the debugger 1000 .
[0055] It should be noted that the heat dissipation module is a heat dissipation fan.
[0056] The technical solution of the present invention is connected to the interface of the central air conditioner through the interface structure 30, and realizes self-checking of looseness and leakage through the central control structure 40 and the quantitative injection of refrigerant. Then the vacuum structure 60 performs pressure detection, and the vacuum structure 60 is pressure balanced through the balance structure. When the pipeline in the central air conditioner is vacuumed, the gas passes through the calibration part 70, and the pipeline volume data is accurately obtained in combination with the ambient temperature, humidity and atmospheric pressure, and the pipeline is negatively pressurized to detect leaks. Secondly, according to the pipeline volume data, refrigerant is injected into the pipeline. Due to the ambient temperature, humidity and atmospheric pressure, accurate refrigerant injection amount data is obtained through data calculation, and precise injection is achieved, thereby improving the efficiency and accuracy of injection.
[0057] In order to facilitate the vacuuming operation and negative pressure detection, the vacuuming structure 60 includes a vacuum pump body 62, the vacuum pump body 62 is connected to the central control structure 40 through a pipeline, and the vacuum pump body 62 is connected to the balance structure through a pipeline;
[0058] The vacuum pump body 62 is disposed inside the machine body 10 , or the vacuum pump body 62 is placed outside the machine body 10 .
[0059] It can be understood that the vacuum pump body 62 is connected to the central control structure 40 through a pipeline. When the vacuum pump body 62 is working, the central control structure 40 controls the opening and closing of the pipeline in the body 10, and realizes the vacuum operation of the pipeline in the central air conditioner through the interface structure and the pipeline.
[0060] It should be noted that the vacuum pump body 62 is connected to the balancing structure through a pipeline. Due to the temperature, humidity and atmospheric pressure data of the location of the body 10, the output pressure of the vacuum pump body 62 is prone to deviation from the actual output pressure. The output pressure of the vacuum pump body 62 is compensated through the balancing structure to ensure the accuracy of the vacuum operation, so as to facilitate the accuracy of the central air-conditioning pipeline volume measurement.
[0061] In order to facilitate the movement of the machine body 10 and to facilitate the refrigerant injection of different central air conditioners, the vacuum pump body 62 is arranged in the machine body 10 .
[0062] In order to facilitate the reduction of the volume of the machine body 10, the vacuum pump body 62 is arranged outside the machine body 10, so that workers can move the machine body 10 conveniently when filling the central air conditioner with refrigerant.
[0063] In order to support the central control structure 40 and the vacuum pump body 62 arranged in the body 10, the vacuum extraction structure 60 also includes a support seat 61, the support seat 61 is arranged in the body 10, the central control structure 40 is arranged on the top surface of the support seat 61, the calibration component 70 and the vacuum pump body 62 are arranged on the support seat 61, the vacuum pump body 62 is connected to the calibration component 70, and the calibration component 70 is connected to the central control structure 40.
[0064] It is understandable that the temperature and humidity sensor 65 and the positioning module are both arranged on the supporting base 61 .
[0065] like Figures 2 to 5 As shown, the setting of the support seat 61 realizes the support of the central control structure 40, and the support seat 61 is connected in the body 10 to ensure the stability of the support of the central control structure 40, and because the vacuum pump body 62 is arranged in the body 10, the vacuum pump body 62 is arranged in the support seat 61 to ensure the stability of the support of the vacuum pump body 62.
[0066] It can be understood that the calibration member 70 is disposed on the support seat 61 to ensure the stability of the calibration member 70 .
[0067] It should be noted that the calibration part 70 is a calibration tank, which is connected to the interface structure 30, and the calibration tank is connected to the central control structure 40. When the vacuum pump body 62 performs a vacuum operation, the gas in the central air-conditioning pipe enters the calibration tank, so as to realize the volume measurement of the central air-conditioning pipe.
[0068] In order to realize automatic control of the debugging instrument 1000, a control structure is arranged on the support base 61, and the control structure includes a main control board 63 and a drive control board 64. The main control board 63 is electrically connected to the drive control board 64, and the drive control board 64 is electrically connected to the central control structure 40, so as to realize automatic control of the central control structure 40.
[0069] In order to facilitate display operation, an LED display screen 20 is provided on the side of the body 10 , and the LED display screen 20 is electrically connected to the main control board 63 .
[0070] In order to achieve compensation for the output pressure of the vacuum pump body 62 , the balancing structure includes pressure balancing parts, and the pressure balancing parts are all connected to the vacuum pump body 62 .
[0071] It can be understood that the balancing structure is connected to the vacuum pump body 62, and the balancing structure is used to balance the problem of changes in the output air pressure of the vacuum pump body 62 caused by changes in air pressure and temperature and humidity, thereby avoiding the impact of differences in output air pressure on the accuracy and efficiency of the vacuum pumping operation of the central air-conditioning pipeline.
[0072] It is understandable that, upon sensing the change in the output pressure of the vacuum pump body 62 , the pressure balance member works to compensate for the output pressure of the vacuum pump body 62 , thereby ensuring the normal progress of the vacuum pumping operation.
[0073] It should be noted that the main control board 63 is electrically connected to the pressure balance member.
[0074] Optionally, the interface structure 30 includes an input interface component 31 and an output interface component 32 , and both the input interface component 31 and the output interface component 32 are connected to the central control structure 40 through a pipeline.
[0075] It can be understood that the output interface component 32 is used to connect the pipe interface of the central air conditioner, and the input interface component 31 is connected to the output port of the refrigerant, that is, the refrigerant tank, so that the refrigerant enters the central air conditioning pipeline through the input interface component 31 and the output interface component 32, thereby realizing the measurement and filling of the pipeline.
[0076] It should be noted that the input interface assembly 31 is connected to the refrigerant tank via a pipeline.
[0077] Optionally, the central control structure 40 includes a plurality of valve components 41, and the plurality of valve components 41 are spaced apart on the top surface of the support seat 61, and the plurality of valve components 41 are respectively connected to the input interface assembly 31 and the output interface assembly 32 through pipelines, and the plurality of valve components 41 are electrically connected to the control structure.
[0078] It should be noted that the valve member 41 is a solenoid valve.
[0079] It can be understood that the multiple valve components 41 are arranged at intervals and are arranged on the support seat 61. The multiple valve components 41 are connected to the input interface component 31 and the output interface component 32 in sequence through pipelines, so that the valve components 41 control the opening and closing of the corresponding pipelines.
[0080] It can be understood that when the debugging instrument is self-checked, the valve component 41 required for the self-check is opened accordingly, so that the refrigerant in the refrigerant tank enters the pipeline of the central air conditioner in sequence through the pipeline in the body 10, so as to realize the self-check of the looseness and leakage of the pipeline connection port and the pipeline connection port in the body.
[0081] In order to remind the staff, a voice broadcast module is provided in the body 10. When a gas leak occurs during the self-check process, the voice broadcast module plays a warning message.
[0082] Optionally, the central control structure 40 further includes an exhaust port 42 , and the valve member 41 connected to the output interface assembly 32 is connected to the exhaust port 42 via a pipeline.
[0083] It should be noted that the exhaust port is connected to each of the valve components 41 . When the self-inspection or the debugging instrument 1000 is performing factory inspection, it is necessary to perform a leak detection on the refrigerant transported in the pipeline. Therefore, after the inspection is completed, the refrigerant needs to be discharged and collected, so that the refrigerant can be discharged through the exhaust port 42 .
[0084] Optionally, the central control structure 40 also includes a high-pressure protection sensor 43 and a low-pressure protection sensor 44, and the plurality of valve components 41 are electrically connected to the high-pressure protection sensor 43 and the low-pressure protection sensor 44, and the high-pressure protection sensor 43 and the low-pressure protection sensor 44 are electrically connected to the control structure.
[0085] In order to prevent the gas pressure transmitted from the interface structure 30 from being too high or too low, the high-pressure protection sensor 43 and the low-pressure protection sensor 44 are provided to monitor the input and output refrigerant at all times to ensure the normal transmission of the refrigerant.
[0086] It can be understood that the high-voltage protection sensor 43 and the low-voltage protection sensor 44 are both electrically connected to the drive control board 64 .
[0087] It should be noted that, in order to facilitate the control of the APP and data transmission, a communication module is provided in the body 10 , and the communication module is electrically connected to the main control board 63 .
[0088] It is understandable that after the refrigerant filling is completed, the location of some construction sites during the debugging of the air conditioner, atmospheric pressure data, the calculated filling quantity of each pipeline and the actual refrigerant filling quantity parameters are automatically transmitted to the back-end of each manufacturer to facilitate data collection and detection by each manufacturer to ensure the operation of the equipment.
[0089] It is understandable that the user's mobile phone or other terminal devices control the operation of the debugger 1000 through communication devices.
[0090] Optionally, the output interface assembly 32 includes a high- and low-pressure pipe interface 321, an air pipe interface 322 and a liquid pipe interface 323, and the high- and low-pressure pipe interface 321, the air pipe interface 322 and the liquid pipe interface 323 are spaced apart on the side of the body 10, and the plurality of valve components 41 are respectively connected to the high- and low-pressure pipe interface 321, the air pipe interface 322 and the liquid pipe interface 323 through pipelines.
[0091] It can be understood that the high and low pressure interface 321, the air pipe interface 322 and the liquid pipe interface 323 are arranged so as to be connected one-to-one with the interface of the central pipeline, so as to ensure the normal progress of the detection during the self-inspection, vacuuming, negative pressure detection and the like.
[0092] It should be noted that the high and low pressure interfaces 321, the air pipe interface 322 and the liquid pipe interface 323 can all be threaded interfaces. When the pipeline is connected to the output interface assembly 32, it is connected by rotation, and the connection is more stable and avoids leakage.
[0093] like Figures 7 and 8 As shown, when the vacuum pump body 62 is placed outside the machine body, a vacuum pump body interface is set on the side of the machine body 10, the vacuum pump body interface is connected to the vacuum pump body 62 through a hose, and the power cord of the vacuum pump body 62 is connected to the power interface of the debugger product, and the start and stop of the vacuum pump is controlled by the debugger.
[0094] In order to avoid the influence of excessive pressure on the valve component 41 when the refrigerant tank outputs refrigerant, the input interface assembly 31 is connected to the flow meter 81 through a pipeline, the flow meter 81 is connected to the one-way valve 80 through a pipeline, and the one-way valve 80 is connected to one of the valve components 41 through a pipeline.
[0095] It is understandable that the flow meter 81 is provided to facilitate flow measurement of the output refrigerant to ensure accurate filling.
[0096] It can be understood that, with the setting of the one-way valve 80, the refrigerant output from the refrigerant tank passes through the flow meter 81 and the one-way valve 80 and enters the valve component 41. Due to the one-way valve 80, the high-pressure refrigerant is restricted by the one-way valve 80, avoiding impact on the valve component 41 and causing damage to the valve component 41, thereby ensuring the safety of the components in the debugging instrument 1000.
[0097] It is understandable that the pipeline can be a hose to ensure that various components can be neatly arranged in the body 10.
[0098] like Figures 1 to 5 as well as Figures 7 and 8As shown, no weighing structure 90 is provided on the outer surface of the machine body 10, and the refrigerant is measured by relying on the flow meter 81 to ensure the quantitative delivery of the refrigerant and the accuracy of the delivery.
[0099] Optionally, a weighing structure 90 is further included, and the weighing structure 90 is arranged on the body 10 and is used to weigh the refrigerant.
[0100] like Figure 6 As shown, in order to ensure the accuracy of refrigerant filling, after the negative pressure detection is completed and the refrigerant filling volume is determined, the refrigerant tank is weighed before and after the refrigerant filling, so as to determine the refrigerant filling amount and improve the filling efficiency.
[0101] It should be noted that the weighing structure 90 includes an electronic scale and a pressure sensor, the electronic scale is connected to the pressure sensor, the electronic scale is arranged on the surface of the body 10, and the pressure sensor is connected to the main control board.
[0102] It can be understood that the refrigerant tank is placed on the electronic scale, and the quality of the refrigerant tank is detected by a pressure sensor.
[0103] In order to ensure the detection of the air-conditioning operation status after the refrigerant injection is completed, a three-in-one detection module is provided on the body 10 .
[0104] It is understandable that the three-in-one detection module is connected to the communication module through communication.
[0105] It is understandable that after the refrigerant is injected, the air conditioner is operated, and the temperature, humidity, wind speed and other data of the air conditioning outlet are detected through the three-in-one detection module, and the data is stored and uploaded to ensure the smooth operation of the detection.
[0106] The above description is only a preferred embodiment of the present invention, and does not limit the patent scope of the present invention. All equivalent structural changes made by using the contents of the present invention specification and drawings under the inventive concept of the present invention, or directly / indirectly applied in other related technical fields are included in the patent protection scope of the present invention.
Claims
1. A debugging instrument, characterized in that: include: Body; An interface structure, the interface structure being arranged on a side surface of the machine body; A central control structure, which is disposed in the body, is connected to the interface structure, and controls the opening and closing of the interface structure; A vacuum pumping structure, wherein the vacuum pumping structure is connected to the central control structure, the vacuum pumping structure is connected to a balancing structure and balances the pressure of the vacuum pumping structure, and a calibration piece is provided between the vacuum pumping structure and the central control structure; Wherein, the vacuum pumping structure also includes a control structure, which is arranged on the machine body and electrically connected to the central control structure.
2. The debugging instrument according to claim 1, characterized in that: The vacuum pump structure includes a vacuum pump body, the vacuum pump body is connected to the central control structure through a pipeline, and the vacuum pump body is connected to the balance structure through a pipeline; The vacuum pump body is arranged in the machine body, or the vacuum pump body is placed outside the machine body.
3. The debugging instrument as claimed in claim 2, characterized in that: The vacuum pumping structure also includes a support seat, which is arranged in the machine body, the central control structure is arranged on the top surface of the support seat, the calibration piece and the vacuum pump body are arranged on the support seat, the vacuum pump body is connected to the central control structure, and the calibration piece is connected to the central control structure.
4. The debugging instrument as claimed in claim 2, characterized in that: The balancing structure includes pressure balancing parts, and the pressure balancing parts are all connected to the vacuum pump body.
5. The debugging instrument as claimed in claim 3, characterized in that: The interface structure includes an input interface component and an output interface component, and both the input interface component and the output interface component are connected to the central control structure through pipelines.
6. The debugging instrument as claimed in claim 5, characterized in that: The central control structure includes a plurality of valve components, which are spaced apart on the top surface of the support seat, are respectively connected to the input interface assembly and the output interface assembly through pipelines, and are electrically connected to the control structure.
7. The debugging instrument according to claim 6, characterized in that: The central control structure also includes an exhaust port, and the valve member connected to the output interface assembly is connected to the exhaust port through a pipeline; The central control structure also includes a high-pressure protection sensor and a low-pressure protection sensor. The plurality of valve components are electrically connected to the high-pressure protection sensor and the low-pressure protection sensor. The high-pressure protection sensor and the low-pressure protection sensor are electrically connected to the control structure.
8. The debugging instrument according to claim 6, characterized in that: The output interface assembly includes high and low pressure pipe interfaces, an air pipe interface and a liquid pipe interface. The high and low pressure pipe interfaces, the air pipe interface and the liquid pipe interface are spaced apart on the side of the body. The plurality of valve components are respectively connected to the high and low pressure pipe interfaces, the air pipe interface and the liquid pipe interface through pipelines.
9. The debugging instrument according to claim 6, characterized in that: The input interface component is connected to the flow meter through a pipeline, the flow meter is connected to the one-way valve through a pipeline, and the one-way valve is connected to one of the valve components through a pipeline.
10. The debugging instrument according to claim 6, characterized in that: It also includes a weighing structure, which is arranged on the machine body and is used to weigh the refrigerant.