Debris flow monitoring, forecasting and early warning method and system

By automatically collecting and calculating environmental data in the monitoring area and calculating the prediction probability and flow rate of the mudslide flow, the problems of low intelligence and inaccurate early warning caused by artificial rainfall survey in the existing technology are solved, and a high-intelligent mudslide early warning is achieved.

CN118918695APending Publication Date: 2024-11-08NANJING UNIV OF INFORMATION SCI & TECH
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411355462.5
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-09-27
Publication Date
2024-11-08

AI Technical Summary

Technical Problem

The existing mudslide monitoring and early warning methods rely on manual rainfall survey, with low intelligence and difficult to guarantee the accuracy of early warning, and cannot effectively warn before mudslide occurs.

Method used

By collecting the environmental humidity, soil internal pressure, real-time satellite cloud map, annual average rainfall and geological data of the monitoring area, the predicted probability and flow rate of the mudslide flow are calculated, and early warning information is automatically issued. The entire process does not require manual survey of the rainfall.

Benefits of technology

High intelligent early warning before mudslides occur, ensuring the accuracy of the early warning and not relying on manual intervention.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118918695A_ABST
    Figure CN118918695A_ABST
Patent Text Reader

Abstract

The invention discloses a debris flow monitoring, forecasting and early warning method and system, and belongs to the technical field of debris flow early warning, and the method comprises the following steps: collecting the environment humidity and soil internal pressure of a monitoring region, and obtaining a real-time satellite cloud picture, annual average rainfall and geological data of the monitoring region; calculating the predicted rainfall according to the number of cumulonimbus and the annual average rainfall, and calculating the soil humidity of the monitored area according to the predicted rainfall and the environment humidity; calculating the soil weight according to the internal pressure of the soil and the geological data; and calculating a debris flow prediction probability according to the soil weight, the soil humidity and the predicted rainfall, calculating a predicted debris flow velocity when the debris flow prediction probability is greater than a preset debris flow occurrence threshold, comparing the predicted debris flow velocity with the historical maximum runoff velocity of the monitoring area, and sending out different early warning information according to different comparison results. Manual rainfall survey is not needed, early warning can be carried out before mountain torrents and debris flows occur, the monitoring intelligence degree is high, and the early warning accuracy can be guaranteed.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to a debris flow monitoring, forecasting and early warning method and system, belonging to the technical field of debris flow early warning. Background Art

[0002] Debris flow is a rapid transfer of water and soil in small watersheds in mountainous areas. It breaks out suddenly, is highly destructive, and often causes devastating disasters. The combination and superposition of factors such as active geological structures, huge terrain height differences, abundant rainfall brought by monsoon climate, dense population distribution, and high-intensity human activities have led to the widespread development of debris flows in mountainous areas, which account for about 2 / 3 of China's land area, and frequent disasters.

[0003] The existing method of debris flow monitoring and early warning is to establish simple survey points in mountainous areas and adopt simple survey methods, that is, mainly rely on manual survey of rainfall and early warning after debris flow occurs. The intelligence level of monitoring and prediction is low and it is difficult to ensure the accuracy of early warning. Summary of the invention

[0004] The technical problem to be solved by the present invention is to overcome the defects of the prior art and provide a debris flow monitoring, forecasting and early warning method and system, which does not require manual rainfall survey and can issue early warnings before flash floods and debris flows occur. The monitoring is highly intelligent and can ensure the accuracy of early warnings.

[0005] In order to solve the above technical problems, the technical solution adopted by the present invention is:

[0006] In a first aspect, the present invention provides a debris flow monitoring, forecasting and early warning method, comprising the following steps:

[0007] Collect environmental humidity and soil internal pressure in the monitoring area, as well as obtain real-time satellite cloud images, annual average rainfall and geological data of the monitoring area;

[0008] Extract the number of cumulonimbus clouds in the real-time satellite cloud image, calculate the predicted rainfall based on the number of cumulonimbus clouds and the annual average rainfall, and then calculate the soil moisture in the monitored area based on the predicted rainfall and ambient humidity;

[0009] Soil density is calculated based on soil internal pressure and geological data;

[0010] The predicted probability of debris flow is calculated based on soil weight, soil moisture and predicted rainfall. When the predicted probability of debris flow is greater than the preset debris flow threshold, the predicted debris flow velocity is calculated based on geological data.

[0011] The predicted debris flow velocity will be compared with the historical maximum runoff velocity in the monitoring area, and different warning information will be issued based on the comparison results.

[0012] The rainfall prediction formula is used to calculate the predicted rainfall based on the number of cumulonimbus clouds and the annual average rainfall, specifically:

[0013] ,

[0014] Where R is the predicted rainfall, S is the number of cumulonimbus clouds above within the specified time, and R t is the average annual rainfall in the monitoring area.

[0015] The soil moisture in the monitored area is calculated based on the predicted rainfall and ambient humidity using a humidity calculation formula, specifically:

[0016] , where C is soil moisture and P is ambient humidity.

[0017] The soil gravity is calculated based on the soil internal pressure and geological data using the soil gravity calculation formula, specifically:

[0018] ,

[0019] in is the soil weight, k is the soil internal pressure, I C is the slope of the monitoring area, g is the gravity acceleration constant, and h is the roughness of the debris flow gully bed.

[0020] The debris flow prediction probability is calculated based on soil weight, soil moisture and predicted rainfall using a debris flow prediction formula, specifically:

[0021] ,

[0022] Where F is the predicted probability of debris flow, For environmental factors.

[0023] The debris flow velocity is predicted by calculating the geological data using the debris flow analysis formula, which is:

[0024] ,

[0025] Where V c is the predicted velocity of debris flow, h is the average radius of the monitoring area, I c is the vertical drop ratio, is the weight of water, is the flash flood discharge coefficient.

[0026] The environmental factors The calculation method is as follows:

[0027] ,

[0028] Where P is the perimeter of the monitoring area, A is the area of ​​the monitoring area, I c is the longitudinal gradient of the slope bed, and C is the soil moisture.

[0029] Debris flow threshold The calculation method is as follows:

[0030] ,

[0031] Where Q p is the maximum safe discharge flow in the monitoring area in history, W c is the historical maximum runoff velocity in the monitoring area, and B is the width of the section in the monitoring area.

[0032] When the predicted debris flow velocity exceeds the historical maximum runoff velocity in the monitoring area by 0.85 times but not more than 1.1 times, the alarm level is judged to be level three. When the predicted debris flow velocity exceeds the historical maximum runoff velocity in the monitoring area by more than 1.1 times but not more than 1.3 times, the alarm level is judged to be level two. When the predicted debris flow velocity exceeds the historical maximum runoff velocity in the monitoring area by 1.3 times or more, the alarm level is judged to be level one.

[0033] In a second aspect, the present invention provides a debris flow monitoring, forecasting and early warning system, including a cloud server, a data acquisition module and a signal transmission tower. The cloud server is provided with a monitoring and forecasting module, and the monitoring and forecasting module includes a data processing unit, a detection and early warning unit and an early warning unit. The data processing unit is used to obtain real-time satellite cloud images, annual average rainfall and geological data of the monitoring area, extract the number of cumulonimbus clouds in the real-time satellite cloud images, and receive the environmental humidity and soil internal pressure sent by the monitoring data acquisition module, and then calculate the predicted rainfall according to the number of cumulonimbus clouds and the annual average rainfall, and then calculate the predicted rainfall according to the predicted rainfall and the environmental humidity. The soil moisture in the monitoring area is finally calculated based on the internal pressure of the soil and the geological data to obtain the soil density; the detection and early warning unit is used to calculate the predicted probability of debris flow based on the soil density, soil moisture and predicted rainfall sent by the data processing unit, and compare the debris flow probability with the debris flow occurrence threshold to judge the debris flow prediction probability. When the debris flow probability is greater than the debris flow occurrence threshold, the predicted debris flow velocity is calculated; the early warning unit is used to receive the predicted debris flow velocity sent by the detection and early warning unit, and compare the predicted debris flow velocity with the historical maximum runoff velocity in the monitoring area, and send different early warning information to the signal transmission tower according to different comparison results.

[0034] The beneficial effects of the present invention are as follows: the present invention provides a debris flow monitoring, forecasting and early warning method and system, which collect the environmental humidity and internal soil pressure of the monitoring area, as well as obtain the real-time satellite cloud map, annual average rainfall and geological data of the monitoring area, and can automatically obtain the debris flow prediction probability and the predicted debris flow velocity through calculations based on the above data, and subsequently issue different early warning information for different predicted debris flow velocities. The whole process does not require manual survey of rainfall, and can issue early warnings before flash floods and debris flows occur. The monitoring is highly intelligent and can ensure the accuracy of early warnings. BRIEF DESCRIPTION OF THE DRAWINGS

[0035] Figure 1 It is a schematic diagram of the hardware structure of the present invention;

[0036] Figure 2 It is a schematic diagram of the system block structure of the present invention;

[0037] The reference numerals in the figure are as follows: 1- cloud server; 2- data acquisition module; 3- signal transmission tower; 4- monitoring and forecasting module; 5- data processing unit; 6- detection and early warning unit; 7- early warning unit. DETAILED DESCRIPTION

[0038] The present invention will be further described below in conjunction with the accompanying drawings. The following embodiments are only used to more clearly illustrate the technical solutions of the present invention and are not intended to limit the protection scope of the present invention.

[0039] Example 1

[0040] The present invention discloses a debris flow monitoring, forecasting and early warning method, comprising the following steps:

[0041] Step 1: Collect the environmental humidity and soil internal pressure of the monitoring area, and obtain real-time satellite cloud images, annual average rainfall and geological data of the monitoring area.

[0042] Step 2: Extract the number of cumulonimbus clouds in the real-time satellite cloud image, and calculate the predicted rainfall based on the number of cumulonimbus clouds and the annual average rainfall. The rainfall prediction formula is as follows:

[0043] ,

[0044] Where R is the predicted rainfall, S is the number of cumulonimbus clouds above within the specified time, and R t is the average annual rainfall in the monitoring area.

[0045] Then, the soil moisture in the monitored area is calculated based on the predicted rainfall and ambient humidity, using the humidity calculation formula, which is:

[0046] , where C is soil moisture and P is ambient humidity.

[0047] Step 3: Calculate the soil density based on the soil internal pressure and geological data using the soil density calculation formula, specifically:

[0048] ,

[0049] in is the soil weight, k is the soil internal pressure, I C is the slope of the monitoring area, g is the gravity acceleration constant, and h is the roughness of the debris flow gully bed.

[0050] Step 4: Calculate the debris flow prediction probability based on soil weight, soil moisture and predicted rainfall, using the debris flow prediction formula, specifically:

[0051] ,

[0052] Where F is the predicted probability of debris flow, For environmental factors.

[0053] Environmental factors The calculation method is as follows:

[0054] ,

[0055] Where P is the perimeter of the monitoring area, A is the area of ​​the monitoring area, I c is the longitudinal gradient of the slope bed, and C is the soil moisture.

[0056] When the predicted probability of debris flow is greater than the preset debris flow threshold, the predicted debris flow velocity is calculated based on the geological data, and the debris flow analysis formula is used, which is:

[0057] ,

[0058] Where V c is the predicted velocity of debris flow, h is the average radius of the monitoring area, I c is the vertical drop ratio, is the weight of water, is the flash flood discharge coefficient.

[0059] Debris flow threshold The calculation method is as follows:

[0060] ,

[0061] Where Q p is the maximum safe discharge flow in the monitoring area in history, W c is the historical maximum runoff velocity in the monitoring area, and B is the width of the section in the monitoring area.

[0062] Step 5: Compare the predicted debris flow velocity with the historical maximum runoff velocity of the monitoring area, and issue different warning information according to the comparison results. When the predicted debris flow velocity exceeds the historical maximum runoff velocity of the monitoring area by 0.85 times but not more than 1.1 times, the alarm level is judged to be level 3, and the warning information is sent to the TV stations and radio stations in the circular area with a radius of L and the monitoring area as the center, once every 24 hours; when the predicted debris flow velocity exceeds the historical maximum runoff velocity of the monitoring area by more than 1.1 times but not more than 1.3 times, the alarm level is judged to be level 2, and the warning information is sent to the mobile phones of users in the circular area with a radius of 1.5L and the monitoring area as the center, once every 12 hours; when the predicted debris flow velocity exceeds the historical maximum runoff velocity of the monitoring area by 1.3 times or more, the alarm level is judged to be level 1, and the mobile phones of users in the circular area with a radius of 1.5L and the monitoring area as the center are called, and the warning voice is played after the call is connected, and the call frequency is once every 6 hours.

[0063] The present invention can automatically obtain the predicted probability of debris flow and the predicted debris flow velocity through calculations based on automatically collected data, and subsequently issue different early warning information for different predicted debris flow velocities. The entire process does not require manual rainfall surveys, and early warnings can be issued before flash floods and debris flows occur. The monitoring is highly intelligent and can ensure the accuracy of early warnings.

[0064] Example 2

[0065] like Figure 1 and Figure 2 As shown, the present invention discloses a debris flow monitoring, forecasting and early warning system, including a cloud server 1, a data acquisition module 2 and a signal transmission tower 3. The signal transmission tower 3 and the data acquisition module 2 are both connected to the cloud server 1 through a 5G data network. The data acquisition module 2 is arranged in a location in the monitoring area where the cross-section of the channel is regular, the channel scouring and silting changes are small, the channel bed is straight, and the slopes on both sides are high and steep. The data acquisition module 2 includes a stress sensor and an environmental humidity sensor with wireless communication function. The stress sensor collects the internal pressure of the soil, and the environmental humidity sensor collects the environmental humidity.

[0066] The cloud server 1 is provided with a monitoring and forecasting module 4, which includes a data processing unit 5, a detection and early warning unit 6 and an early warning unit 7. The data processing unit 5 is used to obtain the real-time satellite cloud map, the annual average rainfall and geological data of the monitoring area, extract the number of cumulonimbus clouds in the real-time satellite cloud map from the real-time satellite cloud map, and receive the environmental humidity and soil internal pressure sent by the monitoring data acquisition module 2, and then calculate the predicted rainfall according to the number of cumulonimbus clouds and the annual average rainfall, and then calculate the soil moisture of the monitoring area according to the predicted rainfall and the environmental humidity, and finally calculate the soil weight according to the soil internal pressure and geological data.

[0067] The detection and early warning unit 6 is used to calculate the predicted probability of debris flow based on the soil weight, soil moisture and predicted rainfall sent by the data processing unit 5, and compare the debris flow probability with the debris flow occurrence threshold to judge the predicted probability of debris flow. When the debris flow probability is greater than the debris flow occurrence threshold, the predicted debris flow velocity is calculated.

[0068] The early warning unit 7 is used to receive the predicted debris flow velocity sent by the detection and early warning unit 6, and compare the predicted debris flow velocity with the historical maximum runoff velocity in the monitoring area, and send different early warning information to the signal transmission tower 3 according to different comparison results.

[0069] When the predicted debris flow velocity exceeds the historical maximum runoff velocity of the monitoring area by more than 0.85 times and not more than 1.1 times, the early warning unit 7 determines that the alarm level is level 3, and the early warning unit 7 controls the signal transmission tower 3 to send warning information to the TV stations and radio stations in the circular area with a radius of L with the monitoring area as the center, and the frequency is once every 24 hours;

[0070] When the predicted debris flow velocity exceeds the historical maximum runoff velocity of the monitoring area by more than 1.1 times and not more than 1.3 times, the early warning unit 7 determines that the alarm level is level 2, and the early warning unit 7 controls the signal transmission tower 3 to send warning information to the user's mobile phone in the circular area with a radius of 1.5L with the monitoring area as the center, and the frequency is once every 12 hours;

[0071] When the predicted debris flow velocity exceeds the historical maximum runoff velocity of the monitoring area by more than 1.3 times, the early warning unit 7 determines that the alarm level is level one. The early warning unit 7 will control the signal transmission tower 3 to call the user's mobile phone in a circular area with a radius of 1.5L and the monitoring area as the center, and play the early warning voice after the call is connected, with a frequency of once every 6 hours.

[0072] The present invention is described with reference to flowcharts and / or block diagrams of methods, devices (systems), and computer program products according to embodiments of the present invention. It should be understood that each process and / or block in the flowchart and / or block diagram, as well as the combination of processes and / or blocks in the flowchart and / or block diagram, can be implemented by computer program instructions. These computer program instructions can be provided to a processor of a general-purpose computer, a special-purpose computer, an embedded processor, or other programmable data processing device to produce a machine, so that the instructions executed by the processor of the computer or other programmable data processing device generate instructions for implementing the processes in the flowchart and / or block diagram. Figure 1 A process or multiple processes and / or boxes Figure 1 A device that provides the functions specified in a block or multiple blocks.

[0073] These computer program instructions may also be stored in a computer-readable memory capable of directing a computer or other programmable data processing device to operate in a specific manner, so that the instructions stored in the computer-readable memory produce an article of manufacture comprising an instruction device, which implements the process Figure 1 A process or multiple processes and / or boxes Figure 1 A function specified in one or more boxes.

[0074] These computer program instructions can also be loaded onto a computer or other programmable data processing device so that a series of operating steps are executed on the computer or other programmable device to produce a computer-implemented process, thereby providing instructions for implementing the process. Figure 1 A process or multiple processes and / or boxes Figure 1 The steps for the functions specified in one or more boxes.

[0075] The above is only a preferred embodiment of the present invention. It should be pointed out that for ordinary technicians in this technical field, several improvements and modifications can be made without departing from the principle of the present invention. These improvements and modifications should also be regarded as the scope of protection of the present invention.

Claims

1. A debris flow monitoring, forecasting and early warning method, characterized in that: The following steps are involved: Collect environmental humidity and soil internal pressure in the monitoring area, as well as obtain real-time satellite cloud images, annual average rainfall and geological data of the monitoring area; Extract the number of cumulonimbus clouds in the real-time satellite cloud image, calculate the predicted rainfall based on the number of cumulonimbus clouds and the annual average rainfall, and then calculate the soil moisture in the monitored area based on the predicted rainfall and ambient humidity; Soil density is calculated based on soil internal pressure and geological data; The predicted probability of debris flow is calculated based on soil weight, soil moisture and predicted rainfall. When the predicted probability of debris flow is greater than the preset debris flow threshold, the predicted debris flow velocity is calculated based on geological data. The predicted debris flow velocity will be compared with the historical maximum runoff velocity in the monitoring area, and different warning information will be issued based on the comparison results.

2. The debris flow monitoring, forecasting and early warning method according to claim 1 is characterized in that: The rainfall prediction formula is used to calculate the predicted rainfall based on the number of cumulonimbus clouds and the annual average rainfall, specifically: , Where R is the predicted rainfall, S is the number of cumulonimbus clouds above within the specified time, and R t is the average annual rainfall in the monitoring area.

3. The debris flow monitoring, forecasting and early warning method according to claim 2 is characterized in that: The soil moisture in the monitored area is calculated based on the predicted rainfall and ambient humidity using a humidity calculation formula, specifically: , where C is soil moisture and P is ambient humidity.

4. The debris flow monitoring, forecasting and early warning method according to claim 3 is characterized by: The soil gravity is calculated based on the soil internal pressure and geological data using the soil gravity calculation formula, specifically: , in is the soil weight, k is the soil internal pressure, I C is the slope of the monitoring area, g is the gravitational acceleration constant, and h is the roughness of the debris flow gully bed.

5. The debris flow monitoring, forecasting and early warning method according to claim 4 is characterized in that: The debris flow prediction probability is calculated based on soil weight, soil moisture and predicted rainfall using a debris flow prediction formula, specifically: , Where F is the predicted probability of debris flow, For environmental factors.

6. The debris flow monitoring, forecasting and early warning method according to claim 5 is characterized by: The debris flow velocity is predicted by calculating the geological data using the debris flow analysis formula, which is: , Where V c is the predicted velocity of debris flow, h is the average radius of the monitoring area, I c is the vertical drop ratio, is the weight of water, is the flash flood discharge coefficient.

7. The debris flow monitoring, forecasting and early warning method according to claim 6 is characterized by: The environmental factors The calculation method is as follows: , Where P is the perimeter of the monitoring area, A is the area of ​​the monitoring area, I c is the longitudinal gradient of the slope bed, and C is the soil moisture.

8. The debris flow monitoring, forecasting and early warning method according to claim 7 is characterized by: Debris flow threshold The calculation method is as follows: , Where Q p is the maximum safe discharge flow in the monitoring area in history, W c is the historical maximum runoff velocity in the monitoring area, and B is the width of the section in the monitoring area.

9. The debris flow monitoring, forecasting and early warning method according to claim 8 is characterized in that: When the predicted debris flow velocity exceeds the historical maximum runoff velocity in the monitoring area by 0.85 times but not more than 1.1 times, the alarm level is judged to be level three. When the predicted debris flow velocity exceeds the historical maximum runoff velocity in the monitoring area by more than 1.1 times but not more than 1.3 times, the alarm level is judged to be level two. When the predicted debris flow velocity exceeds the historical maximum runoff velocity in the monitoring area by 1.3 times or more, the alarm level is judged to be level one.

10. A debris flow monitoring, forecasting and early warning system, characterized in that: The invention comprises a cloud server (1), a data acquisition module (2) and a signal transmission tower (3), wherein the cloud server (1) is provided with a monitoring and forecasting module (4), wherein the monitoring and forecasting module (4) comprises a data processing unit (5), a detection and early warning unit (6) and an early warning unit (7), wherein the data processing unit (5) is used to obtain a real-time satellite cloud image, an annual average rainfall and geological data of a monitoring area, extract the number of cumulonimbus clouds in the real-time satellite cloud image from the real-time satellite cloud image, and receive the environmental humidity and soil internal pressure sent by the monitoring data acquisition module (2), and then calculate the predicted rainfall according to the number of cumulonimbus clouds and the annual average rainfall, and then calculate the monitoring area according to the predicted rainfall and the environmental humidity. The soil moisture of the domain is finally calculated based on the internal soil pressure and geological data to obtain the soil density; the detection and early warning unit (6) is used to calculate the debris flow prediction probability based on the soil density, soil moisture and predicted rainfall sent by the data processing unit (5), and compare the debris flow probability with the debris flow occurrence threshold to determine the debris flow prediction probability; when the debris flow probability is greater than the debris flow occurrence threshold, the predicted debris flow velocity is calculated; the early warning unit (7) is used to receive the predicted debris flow velocity sent by the detection and early warning unit (6), and compare the predicted debris flow velocity with the historical maximum runoff velocity of the monitoring area, and send different early warning information to the signal transmission tower (3) according to different comparison results.