Partition plate structure for double-layer directly-buried pipeline and construction method of double-layer directly-buried pipeline
Through the partition structure for double-layer direct buried pipelines, the combination of support columns, elastic and rigid support members is used to solve the problem of parallel pipeline settlement in municipal pipelines, stable support and prevent overturning of the pipelines are achieved, and construction quality and efficiency are improved.
Patent Information
- Application Number
- CN202411322544.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-20
- Publication Date
- 2024-11-12
AI Technical Summary
In the planning and design of municipal pipelines, the parallel problems of direct buried pipelines lead to settlement or displacement, which may cause problems such as pushing, water discharge and air leakage, and it is difficult to effectively monitor and prevent them through conventional methods.
The partition structure for double-layer direct buried pipes is adopted, including support columns fixed to the foundation, elastic support members and rigid support members. The elastic support members are supported during the settlement process of the upper pipe and replaced by rigid support members after the settlement is stable. , a concrete fixed structure is formed to prevent unnecessary movement.
Effectively isolate the upper and lower pipes, prevent overturning, adaptively adjust settlement, improve construction quality, shorten construction time, reduce the impact on municipal projects, and extend the life of the upper pipes.
Smart Images

Figure CN118935092A_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to the technical field of civil engineering, and in particular relates to a baffle structure for a double-layer directly buried pipeline and a construction method for the double-layer directly buried pipeline. Background Art
[0002] Municipal pipelines are the lifeblood of the city, and they are related to the lives of thousands of households. To ensure the safe operation of municipal pipelines, the state has formulated corresponding national standards for various municipal pipelines such as gas, heat, water supply, sewage, rainwater, electricity, and reclaimed water. For large and medium-sized cities, the planning, design, construction, and maintenance of municipal pipelines is an extremely complex matter, especially for municipal pipelines radiating from municipal trunk roads, whose spatial intersection is inevitable. In the planning and design process of municipal pipelines, local parallel problems are often inevitable. However, since direct buried pipelines cannot be observed through conventional visual methods to see whether they have settled or moved after operation, in order to ensure that the displacement of a single pipeline will not affect the operation of other pipelines, relevant protection measures are often required to prevent unpredictable jacking between different pipelines, causing underground water and gas leakage problems, and then causing accidents. Summary of the invention
[0003] In order to solve all or part of the above problems, the purpose of the present invention is to provide a baffle structure for a double-layer direct buried pipeline and a construction method for a double-layer direct buried pipeline. The baffle structure for a double-layer direct buried pipeline of the present invention solves the protection problem of parallel pipelines and can adaptively and elastically adjust the settlement of the upper pipeline.
[0004] According to one aspect of the present invention, there is provided a partition structure for a double-layer directly buried pipeline, comprising two rows of support columns fixed on a foundation, wherein the two rows of support columns extend along the length direction of the lower pipeline, the upper end of each support column is fixedly connected to the lower end of an elastic support member, and the upper end of each elastic support member is connected to a support plate, wherein the support plate is used to support the upper pipeline, and the elastic support member is used to support the upper pipeline during the settlement of the upper pipeline; and further comprising a rigid support member, wherein the rigid support member is used to support the support plate and the upper pipeline after the settlement of the upper pipeline is stabilized.
[0005] Furthermore, the elastic support member is a spring.
[0006] Furthermore, the upper pipeline is arranged on an upper bracket, and the upper bracket is fixed on the support plate.
[0007] Furthermore, the lower layer pipeline is arranged on a lower bracket, and the lower bracket is fixed on a foundation.
[0008] Furthermore, the rigid support member is a support tube, the height of which is equal to the distance between the support plate and the corresponding support column after the upper pipeline has settled and stabilized, and each support tube is supported between the support plate and the corresponding support column after the upper pipeline has settled and stabilized.
[0009] Furthermore, cement slurry is poured into the support tube, so that the support column, the support tube and the support plate form a concrete fixed structure through the cement slurry.
[0010] Furthermore, each of the support tubes includes an inner tube and an outer tube which are sleeved together, each of the support tubes is sleeved on the outside of the corresponding elastic support member, the lower end of each of the outer tubes is arranged on the corresponding support column, and each of the outer tubes is connected to a fixing screw, and the height of the inner tube extending out of the outer tube can be fixed by adjusting the fixing screw so that the upper end of the inner tube contacts the support plate.
[0011] The present invention also provides a construction method for a double-layer direct buried pipeline, comprising:
[0012] Two rows of support columns are fixed on the foundation, and the two rows of support columns are arranged to extend along the length direction of the lower layer pipeline, and an elastic support member is fixedly connected to the upper end of each support column;
[0013] Install the lower layer pipeline and carry out landfill, and after the lower layer pipeline settles and stabilizes, set a support plate on the upper part of the elastic support member;
[0014] Installing the upper pipeline, and supporting the support plate and the upper pipeline with a rigid support member after the upper pipeline settles and stabilizes;
[0015] The upper pipeline is landfilled.
[0016] Furthermore, the method of supporting the support plate and the upper pipeline by using a rigid support member after the upper pipeline settles and stabilizes further comprises:
[0017] After the upper pipeline settles and stabilizes, the support tube is used as a rigid support member, and the number of support tubes equal to the number of the support columns is set, and the height of the support tube is equal to the distance between the support plate and the corresponding support column after the upper pipeline settles and stabilizes;
[0018] Each of the support tubes is supported between the corresponding support column and the support plate, so that the support plate and the upper pipeline are supported by the support tube.
[0019] Furthermore, after each of the support tubes is supported between the corresponding support column and the support plate, so as to support the support plate and the upper pipeline through the support tube, the method further includes:
[0020] Cement slurry is poured into each of the support tubes to form a fixed structure among the support column, the support tube and the support plate through the cement slurry.
[0021] It can be seen from the above technical scheme that the double-layer direct buried pipeline partition structure and the double-layer direct buried pipeline construction method provided by the present invention have the following beneficial effects:
[0022] The baffle structure for double-layer direct buried pipelines of the present invention solves the problem of protecting parallel pipelines, and can effectively isolate the upper pipeline and the lower pipeline to prevent the upper and lower pipelines from being pushed up. The present invention can adaptively and elastically adjust the settlement of the upper pipeline through the arrangement of the support plate and the elastic support member, and can eliminate the influence of uneven settlement, uneven load and pipeline slope, thereby greatly improving the construction quality and shortening the construction time.
[0023] The double-layer direct buried pipeline partition structure of the present invention adopts an assembled method for construction and adjustment, which can effectively deal with problems caused by pipeline slope changes, on-site adjustments, renovation projects, etc., speed up the construction progress, and minimize the impact on the people during the municipal engineering construction process.
[0024] The present invention uses rigid supports to replace elastic supports between support columns and support plates after the upper pipeline settles and stabilizes, so that the upper pipeline after the settlement stabilizes will not produce unnecessary movements such as shaking due to the presence of the elastic supports during the landfill process. BRIEF DESCRIPTION OF THE DRAWINGS
[0025] Figure 1 It is a front view of a double-layer direct buried pipeline partition structure according to an embodiment of the present invention;
[0026] Figure 2 A side view of a double-layer direct buried pipeline partition structure according to an embodiment of the present invention;
[0027] The reference numerals in the figure are: support plate 1, elastic support member 2, rigid support member 3, support column 4. DETAILED DESCRIPTION
[0028] In order to better understand the purpose, structure and function of the present invention, the following is a further detailed description of a baffle structure for a double-layer direct buried pipeline and a construction method for a double-layer direct buried pipeline of the present invention in conjunction with the accompanying drawings.
[0029] like Figure 1-Figure 2As shown, it shows a partition structure for a double-layer direct-buried pipeline in an embodiment of the present invention, including two rows of support columns 4 fixed on a foundation, the two rows of support columns 4 extend along the length direction of the lower pipeline, the upper end of each support column 4 is fixedly connected to the lower end of an elastic support member 2, the upper end of each elastic support member 2 is connected to a support plate 1, the support plate 1 is used to support the upper pipeline, and the elastic support member 2 is used to support the upper pipeline during the settlement of the upper pipeline; it also includes a rigid support member 3, the rigid support member 3 is used to support the support plate 1 and the upper pipeline after the settlement of the upper pipeline is stable.
[0030] The double-layer direct buried pipeline partition structure of this embodiment includes two rows of support columns 4, corresponding elastic support members 2, rigid support members 3 and support plates. The columns are fixed on the foundation, and the elastic support members 2 are used to support the upper layer pipeline and the support plate, so that the upper layer pipeline on the support plate can settle evenly; when the upper layer pipeline settles, the elastic support members 2 no longer play a supporting role, and the upper layer pipeline and the support plate are supported by the rigid support members 3.
[0031] During the specific construction, for example, the elastic support member 2 is first connected to the support column 4, and then the lower pipeline is installed and buried. Then the support plate 1 is connected to the elastic support member 2, and then the upper pipeline is laid. After the upper pipeline settles and stabilizes, the rigid support member 3 is used to replace the elastic support member 2 and support it between the support column 4 and the support plate 1, and finally the upper pipeline is buried.
[0032] As an extended solution, the baffle structure for double-layer direct buried pipes in this embodiment can also be used in the case of three or more layers of pipes. Specifically, take three layers as an example: first, connect the elastic support member 2 to the support column 4, then install the lower layer of pipes and bury the lower layer of pipes, then connect the support plate 1 to the elastic support member 2, and then lay the middle pipe. After the settlement of the middle pipe is stable, use the rigid support member 3 to replace the elastic support member 2 and support it between the support column 4 and the support plate 1. Then, set the support column 4 and the elastic support member 2 on the support plate 1, bury the middle pipe, set another layer of support plate 1 above the middle pipe, lay the topmost pipe, and after the settlement of the upper pipe is stable, use the rigid support member 3 to replace the elastic support member 2 and support it between the support column 4 and the support plate 1. Finally, bury the upper pipe.
[0033] The baffle structure for double-layer direct buried pipelines in the embodiment of the present invention solves the protection problem of parallel pipelines, and can effectively isolate the upper pipeline and the lower pipeline to prevent the upper and lower pipelines from being pushed and other problems. This embodiment can adaptively and elastically adjust the settlement of the upper pipeline through the setting of the support plate 1 and the elastic support member 2, and can eliminate the influence of uneven settlement, uneven load and pipeline slope, thereby greatly improving the construction quality and shortening the construction time.
[0034] The baffle structure for double-layer direct buried pipelines in the embodiment of the present invention is constructed and adjusted by an assembled method, which can effectively deal with problems caused by changes in pipeline slope, on-site adjustments, renovation projects, etc., speed up the construction progress, and minimize the impact on the people during the construction of municipal engineering projects; the setting of the elastic support member in the embodiment of the present invention releases the interaction force between the upper pipeline and the support plate, overcoming the situation in the prior art that the upper pipeline generates large internal stress due to the force of the support plate, thereby improving the life of the upper pipeline.
[0035] In the embodiment of the present invention, after the upper pipeline has settled and stabilized, the rigid support member 3 is used to replace the elastic support member 2 to support between the support column 4 and the support plate 1, so that the upper pipeline after the settlement is stabilized will not produce unnecessary movements such as shaking due to the presence of the elastic support member 2 during the landfill process.
[0036] In one embodiment, the elastic support member 2 is a spring, the upper end of the spring is fixedly connected to the support plate 1 , and the lower end of the spring is fixedly connected to the corresponding support column 4 .
[0037] In one embodiment, the upper pipeline is arranged on an upper bracket, which is fixed on the support plate 1; the lower pipeline is arranged on a lower bracket, which is fixed on the foundation.
[0038] The upper pipeline of this embodiment is arranged on the upper bracket, and the upper bracket is arranged on the support plate 1. The upper bracket can make the upper pipeline partially stable at the planned design elevation, thereby preventing the upper pipeline from being affected by the upper traffic and causing settlement and other problems.
[0039] The lower pipeline of this embodiment is arranged on the lower bracket, and the lower bracket is arranged on the foundation. The lower pipe support can make the lower pipeline locally stable at the planned design elevation, and at the same time can reduce the settlement problem caused by large burial depth, uneven backfill and insufficient compaction, and realize local reinforcement of the lower pipeline to ensure that the lower pipeline will not settle.
[0040] In one embodiment, the rigid support member 3 is a support tube, the height of the support tube is equal to the distance between the support plate 1 and the corresponding support column 4 after the upper pipeline has settled and stabilized, and each support tube is supported between the support plate 1 and the corresponding support column 4 after the upper pipeline has settled and stabilized.
[0041] In this embodiment, the rigid support member 3 is a support tube, and the height of the support tube is equal to the distance between the support plate 1 and the corresponding support column 4 after the upper pipeline has settled and stabilized. Therefore, when the support tube is set on the support column 4, the upper end of the support tube just contacts the support plate 1, so that the support tube plays a role of supporting between the support plate 1 and the corresponding support column 4 after the upper pipeline has settled and stabilized, so that the upper pipeline after the settlement is stable will not produce unnecessary movements such as shaking during the landfill process due to the presence of the elastic support member 2.
[0042] In one embodiment, cement slurry is poured into the support tube, so that the support column 4, the support tube and the support plate 1 form a fixed structure through the cement slurry to support the upper pipeline.
[0043] In specific implementation, after the upper pipeline has settled and stabilized, a support tube is first used to replace the elastic support member 2 to support between the support plate 1 and the support column 4, and then cement slurry is poured into the support tube, so that the support column 4, the support tube and the support plate 1 form a concrete fixed structure, and then the support plate 1 is supported by the concrete fixed structure, thereby avoiding the support tube from being crushed.
[0044] In a specific implementation, for example, each support tube includes an inner tube and an outer tube which are sleeved together, each support tube is sleeved on the outside of the corresponding elastic support member 2, the lower end of each outer tube is arranged on the corresponding support column 4, and each outer tube is connected with a fixing screw. By adjusting the fixing screw, the height of the inner tube extending out of the outer tube can be fixed so that the upper end of the inner tube contacts the support plate 1.
[0045] In this embodiment, the support cylinder includes an inner cylinder and an outer cylinder, and a set screw is connected to the outer cylinder. Therefore, by tightening the set screw, the set screw can be pressed against the inner cylinder, so that the inner cylinder can be fixed at a corresponding height.
[0046] During specific construction, before laying the upper pipeline, the height of the support tube is minimized by loosening the set screws. At this time, the elastic support member 2 is exposed outside the support tube, and then the upper pipeline is laid. After the upper pipeline is laid, the upper pipeline is pressed on the upper bracket, and the upper bracket is located on the support plate 1. The support plate 1 is supported by the elastic support member 2. At this time, the elastic support member 2 is in a compressed state. When the compression amount of the elastic support member 2 remains unchanged, the inner tube is adjusted so that the upper end of the inner tube contacts the support plate 1, and then the set screws are tightened to keep the height of the support tube unchanged.
[0047] The arrangement of this embodiment makes it convenient to adjust the support tube to a corresponding height, so that the support tube can replace the elastic support member 2 and be supported between the support column 4 and the support plate 1; on the other hand, the process of adjusting the support tube will not affect the elastic support member 2.
[0048] The embodiment of the present invention also provides a construction method of a double-layer direct buried pipeline, comprising the following steps:
[0049] Step S001: fixing two rows of support columns on the foundation, and setting the two rows of support columns to extend along the length direction of the lower layer pipeline, and fixing an elastic support member at the upper end of each support column;
[0050] Step S002: installing the lower layer pipeline and performing landfilling, and setting a support plate on the upper part of the elastic support member after the lower layer pipeline settles stably;
[0051] Step S003: installing the upper pipeline, and supporting the support plate and the upper pipeline with a rigid support member after the upper pipeline settles and stabilizes;
[0052] Step S004: landfill the upper pipeline.
[0053] The construction method of the embodiment of the present invention solves the protection problem of parallel pipelines, can effectively isolate the upper pipeline and the lower pipeline, and prevent the upper and lower pipelines from causing problems such as pushing. This embodiment can adaptively and elastically adjust the settlement of the upper pipeline through the setting of support plates and elastic support members, and can eliminate the influence of uneven settlement, uneven load and pipeline slope, thereby greatly improving the construction quality and shortening the construction time.
[0054] Among them, in step S003, after the upper pipeline settles and stabilizes, supporting the support plate and the upper pipeline with a rigid support member further includes:
[0055] After the upper pipeline settles and stabilizes, the support tube is used as a rigid support member, and the number of support tubes equal to the number of support columns is set, and the height of the support tube is equal to the distance between the support plate and the corresponding support column after the upper pipeline settles and stabilizes;
[0056] Each support tube is supported between a corresponding support column and a support plate, so that the support plate and the upper pipeline are supported by the support tube.
[0057] In this embodiment, the support tube plays the role of supporting between the support plate and the corresponding support column after the upper pipeline has settled and stabilized, so that the upper pipeline after settling and stabilizing will not produce unnecessary movements such as shaking due to the presence of the elastic support parts during the landfill process.
[0058] Wherein, after each support tube is supported between the corresponding support column and the support plate respectively so as to support the support plate and the upper pipeline through the support tube, the construction method further comprises:
[0059] Cement slurry is poured into each support tube so that the support column, support tube and support plate form a fixed structure through the cement slurry to support the upper pipeline.
[0060] In this embodiment, cement slurry is poured into the support tube, so that the support column, the support tube and the support plate form a concrete fixed structure, and the support plate is then supported by the concrete fixed structure, thereby avoiding the situation in which the support tube is crushed due to poor strength at the support tube in the later stage.
[0061] Finally, when the lower layer pipeline is buried in step S002, the elastic support member needs to be exposed above the burial height, so as to ensure that the elastic support member can play a role of elastic support for the upper layer pipeline.
[0062] It should be noted that, unless otherwise specified, the technical terms or scientific terms used in this application should have the common meanings understood by those skilled in the art to which the present invention belongs.
[0063] In this application, unless otherwise clearly specified and limited, the terms "installed", "connected", "connected", "fixed" and the like should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection or an indirect connection through an intermediate medium, it can be the internal connection of two elements or the interaction relationship between two elements. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.
[0064] Finally, it should be noted that the above embodiments are only used to illustrate the technical solutions of the present invention, rather than to limit them; although the present invention has been described in detail with reference to the aforementioned embodiments, those skilled in the art should understand that they can still modify the technical solutions described in the aforementioned embodiments, or replace some or all of the technical features therein by equivalents; and these modifications or replacements do not make the essence of the corresponding technical solutions deviate from the scope of the technical solutions of the embodiments of the present invention, and they should all be included in the scope of the claims and specification of the present invention. In particular, as long as there is no structural conflict, the various technical features mentioned in each embodiment can be combined in any way. The present invention is not limited to the specific embodiments disclosed herein, but includes all technical solutions that fall within the scope of the claims.
Claims
1. A double-layer direct buried pipeline partition structure, It is characterized in that It includes two rows of support columns fixed on the foundation, the two rows of support columns extend along the length direction of the lower pipeline, the upper end of each support column is fixedly connected to the lower end of an elastic support member, the upper end of each elastic support member is connected to a support plate, the support plate is used to support the upper pipeline, and the elastic support member is used to support the upper pipeline during the settlement of the upper pipeline; it also includes a rigid support member, which is used to support the support plate and the upper pipeline after the settlement of the upper pipeline is stable.
2. The double-layer direct buried pipeline partition structure according to claim 1, It is characterized in that The elastic supporting member is a spring.
3. The double-layer direct buried pipeline partition structure according to claim 1, It is characterized in that The upper pipeline is arranged on an upper bracket, and the upper bracket is fixed on the supporting plate.
4. The double-layer direct buried pipeline partition structure according to claim 1, It is characterized in that The lower layer pipeline is arranged on a lower bracket, and the lower bracket is fixed on a foundation.
5. The double-layer direct buried pipeline partition structure according to claim 1, It is characterized in that The rigid support member is a support tube, the height of which is equal to the distance between the support plate and the corresponding support column after the upper pipeline has settled and stabilized, and each support tube is supported between the support plate and the corresponding support column after the upper pipeline has settled and stabilized.
6. The double-layer direct buried pipeline partition structure according to claim 5, It is characterized in that The support tube is filled with cement slurry, so that the support column, the support tube and the support plate form a concrete fixed structure through the cement slurry.
7. The double-layer direct buried pipeline partition structure according to claim 5, It is characterized in that Each of the support tubes comprises an inner tube and an outer tube which are sleeved together, each of the support tubes is sleeved on the outside of the corresponding elastic support member, the lower end of each of the outer tubes is arranged on the corresponding support column, and each of the outer tubes is connected with a set screw, and the height of the inner tube extending out of the outer tube can be fixed by adjusting the set screw so that the upper end of the inner tube contacts the support plate.
8. A construction method for a double-layer direct buried pipeline. It is characterized in that include: Two rows of support columns are fixed on the foundation, and the two rows of support columns are arranged to extend along the length direction of the lower layer pipeline, and an elastic support member is fixedly connected to the upper end of each support column; Install the lower layer pipeline and carry out landfill, and after the lower layer pipeline settles and stabilizes, set a support plate on the upper part of the elastic support member; Installing the upper pipeline, and supporting the support plate and the upper pipeline with a rigid support member after the upper pipeline settles and stabilizes; The upper pipeline is landfilled.
9. The construction method according to claim 8, It is characterized in that The method of supporting the support plate and the upper pipeline by using a rigid support member after the upper pipeline settles and stabilizes further comprises: After the upper pipeline settles and stabilizes, the support tube is used as a rigid support member, and the number of support tubes equal to the number of the support columns is set, and the height of the support tube is equal to the distance between the support plate and the corresponding support column after the upper pipeline settles and stabilizes; Each of the support tubes is supported between the corresponding support column and the support plate, so that the support plate and the upper pipeline are supported by the support tube.
10. The construction method according to claim 9, It is characterized in that After supporting each of the support cylinders between the corresponding support column and the support plate to support the support plate and the upper layer pipeline through the support cylinder, the method further includes: Cement slurry is poured into each of the support tubes to form a fixed structure among the support column, the support tube and the support plate through the cement slurry.