Grid-connected test method for grid-construction type energy storage power station covering multi-level full scene

Through the multi-level and full-scene grid-connected testing method for grid-type energy storage power stations, the problem of insufficient comprehensive performance evaluation of grid-type energy storage power stations in the existing technology is solved, and a comprehensive verification of grid-type energy storage power stations is achieved. and improve the reliability of the power grid operation.

CN118937831APending Publication Date: 2024-11-12ELECTRIC POWER SCI RES INST OF STATE GRID XINJIANG ELECTRIC POWER CO LTD
View PDF 0 Cites 1 Cited by

Patent Information

Application Number
CN202410824294.3
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-06-25
Publication Date
2024-11-12

AI Technical Summary

Technical Problem

The existing energy storage power station testing methods are difficult to comprehensively evaluate the performance of grid-type energy storage power stations under complex environments and various operating conditions. There is a lack of network-type energy storage system testing and evaluation methods, and the test data processing is carried out. The analysis is not accurate enough, which affects the accurate evaluation of the performance of grid-type energy storage power stations.

Method used

A grid-connected testing method for grid-type energy storage power stations covering multiple levels and all scenarios is proposed, including grid-type energy storage unit-level grid-type characteristic testing, multi-unit coordination control testing, power station-level grid-type characteristic testing and joint operation testing. The performance of the energy storage power plant is evaluated through detailed testing steps and methods.

Benefits of technology

It has achieved comprehensive, efficient and accurate verification of the performance of grid-type energy storage power stations, improved the operating reliability of grid-type energy storage power stations, provided safety and stability guarantees for the development of new power systems, and provided technology for the development of new power systems. support.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure FT_1
    Figure FT_1
  • Figure SMS_1
    Figure SMS_1
  • Figure SMS_2
    Figure SMS_2
Patent Text Reader

Abstract

The invention relates to the technical field of grid-forming type energy storage grid-connected test methods, in particular to a grid-forming type energy storage power station grid-connected test method covering a multi-level full scene, which comprises a grid-forming type energy storage unit level grid-forming characteristic test method. The invention discloses a network construction type energy storage multi-unit coordination control test method. The invention relates to a method for testing grid-construction characteristics of a grid-construction type energy storage power station level. The invention relates to a basic grid-connected performance test method for a network construction type energy storage power station level. The invention relates to a combined operation test method for network-following type and network-constructing type energy storage systems / power stations. According to the invention, a powerful technical support is provided for the grid-connected test of the network-building type energy storage power station, the problem of network-building capability verification of the network-building type energy storage system is solved, and an important guarantee is provided for safe and stable operation of a power system. Meanwhile, the application of the method can promote the further development and optimization of the network-building type energy storage technology, provides a set of solutions for the network-building type energy storage multi-scene application adapted to the development of a novel power system, and promotes the large-scale application of the new energy technology and the intelligent upgrading of the power system.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of grid-connected energy storage test methods, and is a grid-connected energy storage power station test method covering multiple levels and full scenarios. Background Art

[0002] With the transformation of the global energy structure, the proportion of new energy in the power system has gradually increased; the intermittent and volatile characteristics of new energy power generation have affected the stable operation of the power grid. Energy storage technology, as a key means to solve this problem, has been widely studied and applied; and grid-type energy storage technology, as an important form, its testing methods and evaluation indicators play a key role in the safe and reliable grid-connected operation of grid-type energy storage power stations.

[0003] Traditional energy storage power station testing methods usually only target a single level or scenario, making it difficult to fully evaluate the performance of a grid-connected energy storage power station in various complex environments and operating conditions. Therefore, a grid-connected energy storage power station test method covering multiple levels and all scenarios is proposed, which is of great significance for verifying the performance of a grid-connected energy storage power station and improving the reliability of grid operation.

[0004] However, the existing testing methods have the following problems: 1) There is a lack of testing and evaluation methods for the networking capability of grid-connected energy storage systems; 2) There is a lack of consideration of various operating scenarios of grid-type energy storage power stations, and it is unable to cover all possible operating situations of grid-type energy storage power stations; 3) The processing and analysis of test data are not accurate and comprehensive enough, which affects the accurate evaluation of the performance of grid-connected energy storage power stations. Summary of the invention

[0005] The present invention provides a grid-connected testing method for a grid-connected energy storage power station covering multiple levels and all scenarios, which overcomes the shortcomings of the above-mentioned prior art. It can comprehensively, efficiently and accurately verify the performance of a grid-connected energy storage power station, and test the grid-connected energy storage power station or system at multiple levels and in all scenarios.

[0006] The technical solution of the present invention is achieved by the following measures: a grid-connected testing method for a multi-level and full-scenario grid-connected energy storage power station, comprising: Testing method for grid-building characteristics of grid-building energy storage units; Test method for coordinated control of multiple units of grid-connected energy storage; Testing method for grid-type energy storage power station-level grid-type characteristics; Basic grid-connected performance test method for grid-connected energy storage power stations; Test methods for joint operation of grid-following and grid-building energy storage systems / power stations.

[0007] The following are further optimizations and / or improvements to the above technical solutions: The method for testing the networking characteristics of the networking type energy storage unit level includes the following sub-steps: 1.1) Frequency adaptability test; The frequency adaptability test in step 1.1) requires the grid-connected energy storage system to maintain operation within a frequency deviation of ±2 Hz; N Above and 0.3P N To 0.4P N Tests are carried out under charging or discharging conditions in the power range to verify the ability of the grid-connected energy storage system to withstand abnormal grid frequency; 1.2) One frequency modulation test; The step 1.2) of the primary frequency modulation test requires that the primary frequency modulation power response time of the grid-connected energy storage system should be less than 0.2s, and it should be able to be flexibly adjusted according to the access to the power grid; the primary frequency modulation active power adjustment deviation should not be greater than 2%; N Above and 0.3P N To 0.4P N The test is carried out under the power range, charging condition or discharging condition; the ability of the grid-connected energy storage system to output primary frequency modulation active power when the grid frequency deviates; the test content includes the following sub-steps: 1.2.1) One frequency modulation dead zone test; 1.2.2) Frequency step disturbance test; 1.2.3) One-time frequency modulation and amplitude limiting test; 1.3) Inertia response test; The inertia response test in step 1.3) requires that the maximum inertia time constant of the grid-type energy storage system is not less than 20 seconds, and the active power change ∆P I Should not be less than 10% P N , the response time should not be greater than 0.5s, and the error between the actual active power and the active power command should not exceed ±2%P N , and can be flexibly adjusted according to the needs of the access system; respectively at 0.7P N Above and 0.3P N To 0.4P N Tests are carried out under charging or discharging conditions in the power range; verifying the ability of the grid-connected energy storage system to output active inertia response when the grid frequency deviates; 1.4) Damping control test; The damping control test in step 1.4) requires that the grid-connected energy storage system has an autonomous damping suppression function. When the system has a low-frequency oscillation of 0.2Hz to 2.5Hz, and the frequency oscillation amplitude of the grid-connected point is greater than 0.003Hz, the energy storage system should be able to suppress the oscillation. The active power change ∆PD The maximum value should not be less than 10% P N , and not more than 30% P N , the response time should not be greater than 0.5s, respectively at 0.7P N To 0.9P N and 0.3P N To 0.4P N Tests are carried out under charging or discharging conditions in the power range; verifying the damping control capability of the grid-connected energy storage system when the grid oscillates at a low frequency; 1.5) Phase jump test; The phase jump test in step 1.5) requires that the amplitude and phase angle of the voltage at the machine end of the grid-connected converter of the grid-connected energy storage system should have a certain maintenance capability in the steady state and transient process, be able to share the unbalanced power of the grid, and the power response time should not exceed 5ms; at 20%P N to 80% P N Tests are carried out under charging or discharging conditions in the power range; verifying the ability of the grid-connected energy storage system to quickly inject active power when the grid phase changes; 1.6) Voltage withstand test; The voltage tolerance test in step 1.6) requires that the terminal voltage of the grid-type energy storage system should be able to be flexibly adjusted within the range of 0 to 130% according to the needs of the system; N Above and 0.3P N To 0.4P N The test is carried out under the power range, charging condition or discharging condition; the low voltage tolerance, high voltage tolerance, continuous high voltage tolerance and continuous low voltage tolerance of the grid-type energy storage system are examined; 1.7) Overload capacity test; The above step 1.7) overload capacity test requires that the AC side current of the grid-type energy storage system should be able to operate continuously for a long time at 110% of the rated current, the continuous operation time should be no less than 2 minutes at 120% of the rated current, and the continuous operation time should be no less than 1 minute at 150% of the rated current, and it should have a short-term overload capacity of 300% of the rated current for 10 seconds; the energy storage system is connected to the public power grid, all parameters are adjusted to normal working conditions, and the overload capacity test is performed under charging or discharging conditions respectively; the overload capacity of the grid-type energy storage system is verified; The test content includes the following sub-steps: 1.7.1) 1.1 times overload test; 1.7.2) 1.2 times overload test; 1.7.3) 1.5 times overload test; 1.7.4) 3 times overload test; 1.8) Follow / build network (follow network, build network) mode switching test; The step 1.8) switching between the following and building-grid modes involves connecting the building-grid energy storage system to the public power grid, adjusting all parameters to normal working conditions, and conducting a following and building-grid mode switching test to verify the ability of the building-grid energy storage system to switch between the following and building-grid modes. The test content includes the following sub-steps: 1.8.1) Test the switching from network construction to network following mode; 1.8.2) Test the switching mode from following network to building network.

[0008] The grid-type energy storage multi-unit coordinated control test method includes the following sub-steps: 2.1) Coordination test between network construction and network construction energy storage unit; The coordination test between the network building and the network building energy storage unit includes the following sub-steps: 2.1.1) Frequency adaptability test; The frequency adaptability test in step 2.1.1) requires that multiple grid-type energy storage units can maintain operation within a frequency deviation of ±2Hz; N Above and 0.3P N To 0.4P N Conduct tests under charging or discharging conditions in the power range; verify the ability of multiple grid-connected energy storage units to withstand abnormal grid frequency; 2.1.2) One frequency modulation test; The step 2.1.2) of the primary frequency modulation test requires that the response time of multiple grid-connected energy storage units should be less than 0.2s, and that they should be able to be flexibly adjusted according to the access to the power grid, and that the primary frequency modulation active power adjustment deviation should not be greater than 2%; N Above and 0.3P N To 0.4P N The test is carried out under the power range, charging condition or discharging condition; the coordination of the ability of multiple grid-connected energy storage units to output primary frequency modulation active power when the grid frequency deviates; the test content includes the following sub-steps: 2.1.2.1) One frequency modulation dead zone test; 2.1.2.2) Primary frequency modulation dynamic performance test; 2.1.2.3) One-time frequency modulation and amplitude limiting test; 2.1.3) Inertia response test; The inertia response test in step 2.1.3) requires that the maximum value of the inertia time constant of multiple grid-type energy storage units is not less than 20 seconds, and the active power change ∆P I Should not be less than 10% P N, the response time should not be greater than 0.5s, and the error between the actual active power and the active power command should not exceed ±2%P N , and can be flexibly adjusted according to the needs of the access system; respectively at 0.7P N Above and 0.3P N To 0.4P N Tests are carried out under charging or discharging conditions in the power range; verifying the ability of multiple grid-connected energy storage units to output active inertia response when the grid frequency deviates; 2.1.4) Damping control test; The damping control test in step 2.1.4) requires that multiple grid-type energy storage units have autonomous damping suppression function. When the system has low-frequency oscillations of 0.2Hz to 2.5Hz, and the frequency oscillation amplitude of the grid-connected point is greater than 0.003Hz, multiple grid-type energy storage units should adjust the active power through additional damping control to suppress low-frequency oscillations. The active power change ∆P D The maximum value should not be less than 10%P N , and not more than 30%P N , the response time should not be greater than 0.5s, respectively at 0.7P N To 0.9P N and 0.3P N To 0.4P N Conduct tests in the power range, charging conditions or discharging conditions; verify the ability to suppress oscillations when low-frequency oscillations occur between multiple grid-type energy storage units; 2.1.5) Phase jump test; The phase jump test in step 2.1.5) requires that the amplitude and phase angle of the voltage at the terminal of the grid-connected converter of multiple grid-connected energy storage units should have a certain maintenance capability in the steady state and transient process, be able to share the unbalanced power of the grid, and the power response time should not exceed 5ms; at 20%P N To 80%P N Tests are carried out under charging or discharging conditions in the power range; verifying the ability of multiple grid-connected energy storage units to quickly inject active power when the grid phase jumps; 2.1.6) Voltage withstand test; The voltage tolerance test in step 2.1.6) requires that the terminal voltage of multiple grid-type energy storage units should be able to be flexibly adjusted within the range of 0 to 130% according to the needs of the system; N To 0.3P N and greater than 0.7P N Tests are carried out under charging or discharging conditions within the power range; the low voltage tolerance, high voltage tolerance, continuous high voltage tolerance, and continuous low voltage tolerance of multiple grid-type energy storage units are examined; 2.1.7) Overload capacity test; The overload capacity test of step 2.1.7) requires that the AC side current of multiple grid-type energy storage units should be able to operate continuously for a long time at 110% of the rated current, the continuous operation time should be no less than 2 minutes at 120% of the rated current, and the continuous operation time should be no less than 1 minute at 150% of the rated current, and have a short-term overload capacity of 300% of the rated current for 10 seconds; connect multiple grid-type energy storage units to the public power grid, adjust all parameters to normal working conditions, and perform overload capacity tests in the charging or discharging state respectively; verify the overload capacity of multiple grid-type energy storage units; the test content includes the following sub-steps: 2.1.7.1) 1.1 times overload test; 2.1.7.2) 1.2 times overload test; 2.1.7.3) 1.5 times overload test; 2.1.7.4) 3 times overload test; 2.2) Coordination test of grid-building and grid-following energy storage units; The coordination test of the network construction and the grid-following energy storage unit includes the following sub-steps: 2.2.1) Frequency adaptability test; The frequency adaptability test in step 2.2.1) requires that the grid-building and grid-following energy storage units can maintain operation within a frequency deviation of ±2Hz; N Above and 0.3P N To 0.4P N Tests are carried out under charging or discharging conditions in the power range to verify the ability of the grid-building and grid-following energy storage units to withstand frequency anomalies in the grid; 2.2.2) One frequency modulation test; The primary frequency modulation test in step 2.2.2) requires that the response time of the grid-building and grid-following energy storage units should be less than 0.2s, and that they should be able to be flexibly adjusted according to the access to the grid. The primary frequency modulation active power adjustment deviation should not be greater than 2%. N Above and 0.3P N To 0.4P N The test is carried out under charging or discharging conditions in the power range of the power grid; the coordination of the ability of the grid-building and grid-following energy storage units to output primary frequency modulation active power when the grid frequency deviates is examined; the test content includes the following sub-steps: 2.2.2.1) One frequency modulation dead zone test; 2.2.2.2) Primary frequency modulation dynamic performance test; 2.2.2.3) One-time frequency modulation and amplitude limiting test; 2.2.3) Inertia response test; The inertia response test in step 2.2.3) requires that the maximum inertia time constant of the grid-building and grid-following energy storage units should be no less than 20 seconds, and the active power change ∆P I Should not be less than 10% P N , the response time should not be greater than 0.5s, and the error between the actual active power and the active power command should not exceed ±2%P N , and can be flexibly adjusted according to the needs of the access system; respectively at 0.7P N Above and 0.3P N To 0.4P N Tests are carried out under charging or discharging conditions in the power range of the grid; verifying the ability of the grid-building and grid-following energy storage units to output active inertia response when the grid frequency deviates; 2.2.4) Damping control test; The damping control test in step 2.2.4) requires that the grid-building and grid-following energy storage units have autonomous damping suppression function. When the grid experiences low-frequency oscillation of 0.2Hz to 2.5Hz, and the frequency oscillation amplitude of the grid connection point is greater than 0.003Hz, the grid-building and grid-following energy storage units should adjust the active power through additional damping control to suppress the low-frequency oscillation. The active power change ∆P D The maximum value should not be less than 10%P N , and not more than 30%P N , the response time should not be greater than 0.5s, respectively at 0.7P N To 0.9P N and 0.3P N To 0.4P N Tests are carried out under charging or discharging operating conditions in the power range of the grid; verify the ability to suppress oscillations when low-frequency oscillations occur between the grid-building and grid-following energy storage units; 2.2.5) Phase jump test; The phase jump test in step 2.2.5) requires that the amplitude and phase angle of the voltage at the terminal of the grid-forming converter and the grid-following energy storage unit should have a certain maintenance capability in the steady state and transient process, be able to share the unbalanced power of the grid, and the power response time should not exceed 5ms; at 20%P N to 80% P N Tests are carried out under charging or discharging conditions in the power range of the grid; verifying the ability of the grid-building and grid-following energy storage units to quickly inject active power when the grid phase jumps; 2.2.6) Voltage withstand capability test; The voltage tolerance test in step 2.2.6) requires that the terminal voltage of the grid-connecting and grid-following energy storage units should be able to be flexibly adjusted within the range of 0 to 130% according to the needs of the system; N Above and 0.3P N To 0.4P NThe test is carried out under charging or discharging conditions within the power range; the low voltage tolerance, high voltage tolerance, continuous high voltage tolerance and continuous low voltage tolerance of the grid-building and grid-following energy storage units are examined; 2.2.7) Overload capacity test; The overload capacity test in step 2.2.7) requires that the AC side current of the grid-building and grid-following energy storage units should be able to operate continuously for a long time at 110% of the rated current, and the continuous operation time should be no less than 2 minutes at 120% of the rated current; the energy storage system is connected to the public power grid, all parameters are adjusted to normal working conditions, and the overload capacity test is performed in the charging or discharging state respectively; the overload capacity of the grid-building and grid-following energy storage units is verified; the test content includes the following sub-steps: 2.2.7.1) 1.1 times overload test; 2.2.7.2) 1.2 times overload test; 2.2.7.3) 1.5 times overload test; 2.2.7.4) 3 times overload test.

[0009] The method for testing the grid-building characteristics of a grid-building type energy storage power station comprises the following sub-steps: 3.1) Frequency adaptability test; The frequency adaptability test in step 3.1) requires the grid-connected energy storage power station to maintain operation within a frequency deviation of ±2Hz; N Above and 0.3P N To 0.4P N Tests are carried out under charging or discharging conditions in the power range of the grid; verifying the ability of the grid-type energy storage power station to withstand abnormal grid frequency; 3.2) One frequency modulation test; The primary frequency modulation test in step 3.2) requires that the primary frequency modulation power response time of the grid-connected energy storage power station should be less than 0.2s, and it should be able to be flexibly adjusted according to the access to the grid; the primary frequency modulation active power adjustment deviation should not be greater than 2%; N Above and 0.3P N To 0.4P N The test is carried out under the power range, charging condition or discharging condition; the ability of the grid-type energy storage power station to output primary frequency modulation active power when the grid frequency deviates; the test content includes the following sub-steps: 3.2.1) One frequency modulation dead zone test; 3.2.2) Frequency step disturbance test; 3.2.3) One-time frequency modulation and amplitude limiting test; 3.3) Inertia response test; The inertia response test in step 3.3) requires that the maximum inertia time constant of the grid-type energy storage power station should be no less than 20 seconds, and the active power change ∆P I Should not be less than 10% P N , the response time should not be greater than 0.5s, and the error between the actual active power and the active power command should not exceed ±2%P N , and can be flexibly adjusted according to the needs of the access power station; respectively at 0.7P N Above and 0.3P N To 0.4P N Tests are carried out under charging or discharging conditions in the power range of the grid; verifying the ability of the grid-connected energy storage power station to output active inertia response when the grid frequency deviates; 3.4) Damping control test; The damping control test in step 3.4) requires that the grid-connected energy storage power station has an autonomous damping suppression function. When the power station has a low-frequency oscillation of 0.2Hz to 2.5Hz, and the frequency oscillation amplitude of the grid-connected point is greater than 0.003Hz, the energy storage should be able to suppress the oscillation, and the active power change ∆P D The maximum value should not be less than 10% P N , and not more than 30% P N , the response time should not be greater than 0.5s, respectively at 0.7P N To 0.9P N and 0.3P N To 0.4P N Tests are carried out under charging or discharging conditions in the power range of the power grid; verifying the damping control capability of the grid-connected energy storage power station when the grid oscillates at a low frequency; 3.5) Phase jump test; The phase jump test in step 3.5) requires that the amplitude and phase angle of the voltage at the machine end of the grid-connected energy storage power station in the steady state and transient process should have a certain maintenance ability, be able to share the unbalanced power of the grid, and the power response time should not exceed 5ms; at 20%P N to 80% P N Tests are carried out under charging or discharging conditions in the power range of the grid; verifying the ability of the grid-connected energy storage power station to quickly inject active power when the grid phase jumps; 3.6) Voltage withstand test; The voltage tolerance test in step 3.6) requires that the terminal voltage of the grid-type energy storage power station should be able to be flexibly adjusted within the range of 0 to 130% according to the needs of the power station; N Above and 0.3P N To 0.4P NTests are carried out under charging or discharging conditions within the power range; the low voltage tolerance, high voltage tolerance, continuous high voltage tolerance, and continuous low voltage tolerance of the grid-type energy storage power station are examined; 3.7) Overload capacity test; The above step 3.7) overload capacity test requires that the AC side current of the grid-type energy storage power station should be able to operate continuously for a long time at 110% of the rated current, the continuous operation time should be no less than 2 minutes at 120% of the rated current, and the continuous operation time should be no less than 1 minute at 150% of the rated current, and it should have a short-term overload capacity of 300% of the rated current for 10 seconds; the energy storage power station is connected to the public power grid, all parameters are adjusted to normal working conditions, and the overload capacity test is performed under charging or discharging conditions respectively; the overload capacity of the grid-type energy storage power station is verified; The test content includes the following sub-steps: 3.7.1) 1.1 times overload test; 3.7.2) 1.2 times overload test; 3.7.3) 1.5 times overload test; 3.7.4) 3 times overload test; 3.8) Follow / build network (follow network, build network) mode switching test; The step 3.8) switching between the following and building grid modes involves connecting the building grid energy storage power station to the public grid, adjusting all parameters to normal working conditions, and conducting a following and building grid mode switching test; verifying the ability of the building grid energy storage power station to switch between the following and building grid modes; the test content includes the following sub-steps: 3.8.1) Test the switching from network construction to network following mode; 3.8.2) Test the switching mode from following network to building network.

[0010] The basic grid-connected performance test method of the grid-connected energy storage power station includes the following sub-steps: 4.1) Active power control test; The active power control test in step 4.1) is to connect the grid-type energy storage power station to the public power grid, adjust all parameters to normal working conditions, and test the active power regulation capability in the grid-type control mode; examine the active power control accuracy, active power command response, and regulation time of the grid-type energy storage power station; the test content includes the following sub-steps: 4.1.1) Power test; 4.1.2) Power reduction test; 4.2) Automatic generation control (AGC) test; The step 4.2) automatic power generation control test requires the grid-type energy storage power station to receive and respond to the AGC command sent by the dispatcher; connect the grid-type energy storage power station to the public power grid, adjust all parameters to normal working conditions, and carry out the AGC test in the charging or discharging state; examine the active power control accuracy, active power command response, and adjustment time of the grid-type energy storage power station; 4.3) Reactive power regulation capability test; The reactive power regulation capability test in step 4.3 is to connect the grid-type energy storage power station to the public power grid, adjust all parameters to normal working conditions, and perform reactive power regulation capability test and power factor regulation capability test in the grid-type control mode; examine the reactive power regulation capability and power factor regulation capability of the grid-type energy storage power station in the grid-type control mode; the test content includes the following sub-steps: 4.3.1) Reactive power regulation capability test; 4.3.2) Power factor regulation capability test; 4.4) Automatic voltage control (AVC) test; The step 4.4) automatic voltage control test requires the grid-type energy storage power station to receive and respond to the AVC command sent by the dispatcher; connect the grid-type energy storage power station to the public power grid, adjust all parameters to normal working conditions, and conduct the test under charging or discharging conditions; examine whether the grid-type energy storage power station has the automatic voltage control function; 4.5) Charge and discharge response time test; The step 4.5) charging and discharging response time test is to adjust the grid-type energy storage power station to the hot standby state, and then conduct tests in the charging or discharging state of the grid-type energy storage power station; the charging and discharging response time of the grid-type energy storage power station in the grid control mode is examined; the test content includes the following sub-steps: 4.5.1) Charging response time test; 4.5.2) Discharge response time test; 4.6) Charge and discharge adjustment time test; The step 4.6) charge and discharge adjustment time test is to adjust the grid-type energy storage power station to the hot standby state, and then conduct tests in the charging or discharging state of the energy storage power station; the charge and discharge adjustment time of the energy storage power station in the grid control mode is examined; the test content includes the following sub-steps: 4.6.1) Charge adjustment time test; 4.6.2) Discharge adjustment time test; 4.7) Charge and discharge conversion time test; The step 4.7) charge-discharge conversion time test, under rated power charge-discharge conditions, adjust the grid-type energy storage power station to a hot standby state, and perform a charge-to-discharge conversion time test; verify the charge-discharge conversion time of the grid-type energy storage power station under the grid control mode; 4.8) Overload capacity test; The overload capacity test in step 4.8) requires that the AC side current of the grid-type energy storage power station should be able to operate continuously for a long time at 110% of the rated current, the continuous operation time should be no less than 2 minutes at 120% of the rated current, and the continuous operation time should be no less than 1 minute at 150% of the rated current, and it should have a short-term overload capacity of 300% of the rated current for 10 seconds; the grid-type energy storage power station is connected to the public power grid, all parameters are adjusted to normal working conditions, and the overload capacity test is performed in the charging or discharging state respectively; the overload capacity of the grid-type energy storage power station is examined; the test content includes the following sub-steps: 4.8.1) 1.1 times overload test; 4.8.2) 1.2 times overload test; 4.8.3) 1.5 times overload test; 4.8.4) 3.0 times overload test; 4.9) Rated energy and conversion efficiency test; The step 4.9) rated energy and conversion efficiency test requires the grid-type energy storage power station to test the charging energy and discharging energy and rated power energy conversion efficiency of the grid-type energy storage power station under stable operation and rated power charging or discharging conditions; and examine the rated energy and rated energy conversion efficiency of the grid-type energy storage power station under the grid control mode; the test content includes the following sub-steps: 4.9.1) Rated energy test; 4.9.2) Rated power conversion efficiency test; 4.10) Power quality test; In step 4.10) the power quality test is to measure the grid-type energy storage power station in the charging or discharging state for three consecutive days; to examine the power quality of the grid-type energy storage power station in the grid control mode; the test content includes the following sub-steps: 4.10.1) Three-phase voltage unbalance test; 4.10.2) Harmonic test; 4.10.3) Voltage deviation test; 4.10.4) Voltage fluctuation and flicker test; 4.10.5) DC component test; 4.11) Black start test; The step 4.11) black start test requires that the grid-type energy storage power station has a black start function. During the black start period, there should be no obvious circulating current or oscillation problems between the converters, and the maximum deviation of the effective current value should not be greater than 5%; verifying the island grid self-starting capability of the grid-type energy storage power station converter.

[0011] The joint operation test method of the grid-connected energy storage power station includes the following sub-steps: 5.1) Joint operation test of grid-connected and grid-building energy storage systems; 5.2) Joint operation test of grid-connected and grid-building energy storage power stations.

[0012] The step 5.1) joint operation test of the grid-following and grid-building energy storage systems includes the following sub-steps: 5.1.1) Active power control test; 5.1.2) Automatic generation control (AGC) test; 5.1.3) Reactive power control test; 5.1.4) Automatic voltage control (AVC) test; 5.1.5) One frequency modulation test; 5.1.6) Test the switching between follow / build network mode.

[0013] The step 5.1.1) active power control test is to connect the energy storage power station operated in conjunction with the grid to the public grid, adjust all parameters to normal working conditions, and perform power increase and power decrease tests; examine the power control accuracy, response time and adjustment time of the energy storage power station operated in conjunction with the grid; The step 5.1.2) automatic generation control (AGC) test requires the energy storage power station operated in conjunction with the grid to receive and respond to the AGC command sent by the dispatcher; the energy storage power station operated in conjunction with the grid is connected to the public grid, all parameters are adjusted to normal working conditions, and the AGC test is carried out in the charging or discharging state; the AGC control accuracy, response time and adjustment time of the energy storage power station operated in conjunction with the grid are examined; The reactive power regulation capability test in step 5.1.3) is to connect the energy storage power station operated in conjunction with the grid to the public grid, adjust all parameters to normal working conditions, and conduct reactive power regulation capability test in charging or discharging mode; examine the reactive power control accuracy and power factor regulation capability of the energy storage power station operated in conjunction with the grid; the test content includes the following sub-steps: 5.1.3.1) Charging mode test; 5.1.3.2) Discharge mode test; 5.1.3.3) Power factor regulation capability test; The step 5.1.4) automatic voltage control (AVC) test requires the energy storage power station operated in conjunction with the grid to receive and respond to the AVC command sent by the dispatcher; the energy storage power station operated in conjunction with the grid is connected to the public grid, all parameters are adjusted to normal working conditions, and the AVC test is carried out in the charging or discharging state; the voltage control performance of the energy storage power station operated in conjunction with the grid in response to the AVC system is examined; the test content includes the following sub-steps: 5.1.4.1) Reactive power control test; 5.1.4.2) Voltage control test; The primary frequency modulation test in step 5.1.5) requires that the primary frequency modulation power response time of the energy storage power station jointly operated with the network should be less than 0.2s, and it should be able to be flexibly adjusted according to the needs of the access system, and the primary frequency modulation active power adjustment deviation should not be greater than 2%; respectively at 0.7P N Above and 0.3P N To 0.4P N Tests are carried out under charging or discharging conditions in the power range of the power grid; the coordination of the ability of the energy storage power station jointly operated with the grid to output primary frequency regulation active power when the grid frequency deviates; The step 5.1.6) of the network mode switching test includes the following sub-steps: 5.1.6.1) Test the switching from network construction to network following mode; 5.1.6.2) Test the switching mode from following network to building network.

[0014] The step 5.2) of the joint operation test of the grid-connected and grid-connected energy storage power stations includes the following sub-steps: 5.2.1) Active power control test; 5.2.2) Automatic generation control (AGC) test; 5.2.3) Reactive power control test; 5.2.4) Automatic Voltage Control (AVC) test; 5.2.5) One frequency modulation test; 5.2.6) Test the switching between follow / build network mode.

[0015] In step 5.2.1) active power control test, multiple grid-connected / constructed energy storage power stations are connected to the public power grid, all parameters are adjusted to normal working conditions, and power increase and power reduction tests are performed; the power control accuracy, response time and adjustment time of multiple grid-connected / constructed energy storage power stations are examined; The automatic generation control (AGC) test in step 5.2.2 requires multiple grid-connected / constructed energy storage power stations to receive and respond to the AGC instructions sent by the dispatcher; multiple grid-connected / constructed energy storage power stations are connected to the public power grid, all parameters are adjusted to normal working conditions, and the AGC test is carried out under the charging / discharging state; the AGC control accuracy, response time and adjustment time of multiple grid-connected / constructed energy storage power stations are examined; The reactive power regulation capability test in step 5.2.3) is to connect multiple grid-connected / grid-connected energy storage power stations to the public grid, adjust all parameters to normal working conditions, and conduct reactive power regulation capability test in charging or discharging mode; examine the reactive power control accuracy and power factor regulation capability of multiple grid-connected / grid-connected energy storage power stations; the test content includes the following sub-steps: 5.2.3.1) Charging mode test; 5.2.3.2) Discharge mode test; 5.2.3.3) Power factor regulation capability test; The automatic voltage control (AVC) test in step 5.2.4 requires multiple grid-connected / constructed energy storage power stations to receive and respond to the AVC instructions sent by the dispatcher; multiple grid-connected / constructed energy storage power stations are connected to the public grid, all parameters are adjusted to normal working conditions, and the AVC test is carried out in the charging or discharging state; the voltage control performance of multiple grid-connected / constructed energy storage power stations in response to the AVC system is examined; the test content includes the following sub-steps: 5.2.4.1) Reactive power control test; 5.2.4.2) Voltage control test; The primary frequency modulation test in step 5.2.5) requires that the primary frequency modulation power response time of multiple follow-up / grid-connected energy storage power stations should be less than 0.2s, and can be flexibly adjusted according to the needs of the access system, and the primary frequency modulation active power adjustment deviation should not exceed 2%; respectively, at 0.7P N and 0.3P N To 0.4P N The test is carried out under charging and discharging conditions in a power range of 1000MW and 800MW respectively; the coordination of the ability of multiple grid-connected / grid-connected energy storage power stations to output primary frequency-modulation active power when the grid frequency deviates is examined.

[0016] The step 5.2.6) of the network mode switching test includes the following sub-steps: 5.2.6.1) Test the switching from network construction to network following mode; 5.2.6.2) Test the switching mode from following network to building network.

[0017] The present invention proposes a grid-connected test method for grid-connected energy storage power stations covering multiple levels and all scenarios. The method comprehensively evaluates the grid-connected performance of grid-connected energy storage power stations in different scenarios according to different test requirements, so as to improve the operation level of grid-connected energy storage power stations and ensure the safe and stable operation of new power systems.

[0018] It first introduces the grid-connected test requirements of grid-connected energy storage power stations, and explains the importance and necessity of multi-level full-scenario grid-connected testing. Secondly, from the energy storage unit level to the test level of the energy storage power station jointly operated with the grid to the joint operation of multiple energy storage power stations, the design ideas and implementation steps of the test method are described in detail. Finally, for the different application scenarios of grid-connected energy storage power stations, the characteristics and advantages of the test method are summarized, as well as the application prospects in the field of grid-connected testing of grid-connected energy storage power stations.

[0019] The grid-connected test method for a multi-level, full-scenario grid-connected energy storage power station described in the present invention first performs a unit-level grid-connected characteristic test. After the test result is qualified, a multi-unit coordinated control test is performed. After the test result is qualified, a power station-level basic grid-connected performance test is performed. After the test result is qualified, an energy storage system / power station joint operation test is finally performed.

[0020] The present invention provides a strong technical support for the grid-connected test of the grid-type energy storage power station, and solves the problem of verifying the grid-type energy storage system's grid-connected capability, providing an important guarantee for the safe and stable operation of the power system. At the same time, the application of this method will promote the further development and optimization of grid-type energy storage technology, provide a complete set of solutions for the multi-scenario application of grid-type energy storage that adapts to the development of new power systems, and promote the large-scale application of new energy technologies and the intelligent upgrade of power systems. BRIEF DESCRIPTION OF THE DRAWINGS

[0021] Attached Figure 1 This is the high voltage adaptability test curve. DETAILED DESCRIPTION

[0022] The present invention is not limited by the following embodiments, and specific implementation methods can be determined based on the technical solution of the present invention and actual conditions.

[0023] System / power station: includes intra-station and inter-station power station.

[0024] The present invention will be further described below in conjunction with embodiments: The present invention provides a grid-connected testing method for a multi-level and full-scenario grid-connected energy storage power station, comprising: 1) Testing method for grid-connected energy storage unit-level grid-connected characteristics; 2) Test method for coordinated control of multiple units of grid-connected energy storage; 3) Testing method for grid-type energy storage power station-level grid-type characteristics; 4) Basic grid-connected performance test method for grid-connected energy storage power stations; 5) Test method for joint operation of grid-connected energy storage system / power station.

[0025] The step 1) of testing the networking characteristics of the networking type energy storage unit level includes the following sub-steps: 1.1) Frequency adaptability test; 1.2) One frequency modulation test; 1.3) Inertia response test; 1.4) Damping control test; 1.5) Phase jump test; 1.6) Voltage withstand test; 1.7) Overload capacity test; 1.8) Test the switching between follow / build network mode.

[0026] The step 1.1) of the frequency adaptability test includes the following sub-steps: a. Set the grid-connected energy storage system operation mode to discharge mode; b. Adjust the output of the grid simulation device to the rated voltage and rated frequency of the grid-forming energy storage system; c. Set the active power output of the grid-connected energy storage system to 70% P N To 100% P N Operate within the range; d. Adjust the power grid simulation device so that the frequency of the test point of the grid-type energy storage system is stepped from 50Hz to 46.45Hz, 46.55Hz, 47.5Hz and 48.45Hz respectively for 1min and then restored to 50Hz; adjust the power grid simulation device so that the frequency of the test point of the grid-type energy storage system is stepped from 50Hz to 48.55Hz, 49.5Hz and 50.45Hz respectively for 10min and then restored to 50Hz; adjust the power grid simulation device so that the frequency of the test point of the grid-type energy storage system is stepped from 50Hz to 50.55Hz, 51Hz, 52Hz, 52.55Hz and 53.05 respectively for 1min and then restored to 50Hz; e. Use a data acquisition device to synchronously record the frequency, active power effective value and reactive power effective value of the test point of the grid-type energy storage system at a period of 20ms, and record at least the data from 1 minute before the frequency step to 1 minute after the frequency returns to 50Hz; f. Draw frequency-time, active power-time and reactive power-time curves; g. Record the discharge status of the grid-type energy storage system and the alarm information when the frequency exceeds the limit; h. Set the grid-connected energy storage system operation mode to charging mode and repeat steps b) to g).

[0027] The step 1.2) of a frequency modulation test includes the following sub-steps: 1.2.1) Primary frequency modulation dead zone test a. Set the primary frequency modulation parameters of the grid-forming energy storage system and connect the grid-forming energy storage system and related testing and measuring equipment; b. Adjust the grid-type energy storage system to P N Constant power discharge to the grid-type energy storage system discharge cut-off condition; c. The grid-type energy storage system shall be no less than 20%P N Charging; d. Gradually increase the grid connection point frequency value in steps of 0.01 Hz until the active power starts to change regularly. Run each frequency setting value for 5 seconds and record the output frequency value at the time when the active power changes regularly during the frequency disturbance process; e. Gradually reduce the grid connection point frequency value in steps of 0.01 Hz until the active power starts to change regularly. Run each frequency setting value for 5 seconds and record the output frequency value at the time when the active power changes regularly during the frequency disturbance process; f. Repeat d) to e); g. Adjust the grid-type energy storage system to P N Constant power charging until the energy storage station charging cut-off condition; h. Adjust the grid-type energy storage system to not less than 20%P N Discharge is performed; i. Repeat d) to f).

[0028] 1.2.2) Frequency step disturbance test a. Connect the data acquisition device to the voltage transformer (PT) and current transformer (CT) at the test point, and connect the frequency signal generator to the energy storage power station monitoring system; b. Adjust the grid-type energy storage system to P N Constant power discharge to the grid-type energy storage system discharge cut-off condition; c. The grid-type energy storage system is under unlimited power and limited power operation states, and the active power is charged according to the grid-type energy storage system operation state and power range in Table 1; d. Use the frequency signal generator to output the frequency step disturbance signal according to Table 1, and test each working condition twice; e. Record voltage, current, frequency and power values ​​during the test; f. Calculate the primary frequency modulation response lag time, rise time, adjustment time and active power control deviation; g. Adjust the grid-type energy storage system to P N Constant power charging until the grid-connected energy storage system charging cut-off condition; h. The grid-type energy storage system is under unlimited power and limited power operation states, and the active power is charged according to the operation state and power range of the grid-type energy storage system in Table 1; i. Use the frequency signal generator to output the frequency step disturbance signal according to Table 1, and test each working condition twice; j. Record voltage, current, frequency and power values ​​during the test; k. Calculate the primary frequency modulation response lag time, rise time, regulation time and active power control deviation.

[0029] 1.2.3) Primary FM limit test a. Connect the data acquisition device to the voltage transformer (PT) and current transformer (CT) at the test point, and connect the power grid simulation device to the grid-type energy storage system monitoring system; b. Adjust the grid-type energy storage system to P N Constant power discharge to the grid-type energy storage system discharge cut-off condition; c. Adjust the grid-type energy storage system to 20%P N Charging; d. Set the frequency value of the grid connection point to gradually increase in steps of 0.01Hz until the active power reaches the limit value and stops changing. Each frequency setting value runs for 5s. The maximum frequency difference step should not exceed ±0.5Hz. Record the output frequency value at the time when the active power changes regularly during the frequency disturbance process. e. Set the frequency value of the grid connection point to be gradually reduced in steps of 0.01Hz until the active power reaches the limit value and stops changing. Each frequency setting value runs for 5s. The maximum frequency difference step should not exceed ±0.5Hz. Record the output frequency value at the time when the active power changes regularly during the frequency disturbance process. f. Adjust the grid-type energy storage system to P N Constant power charging until the grid-connected energy storage system charging cut-off condition; g. Adjust the grid-type energy storage system to 20%P N Discharge is performed; h. Repeat steps d) to g).

[0030] The step 1.3) of the inertia response test includes the following sub-steps: a. Set the operation mode of the grid-connected energy storage system to charging mode; b. Adjust the grid-connected energy storage system to operate at 10%P N To 30%P N Under the working conditions; c. Use the frequency signal generator to output the frequency change rate disturbance signal according to Table 2, and test each working condition twice; d. Record voltage, current, frequency and power values ​​during the test; e. Calculate the inertia response rise time, the maximum active power adjustment and the active power control deviation; f. Adjust the grid-type energy storage system to operate at no less than 70%P N Repeat steps c) to e) under the working condition; g. Set the grid-connected energy storage system operation mode to discharge mode; h. Repeat steps b) to f).

[0031] The step 1.4) of the damping control test includes the following sub-steps: a. Adjust the grid-type energy storage system to 50%P N Discharge is performed; b. Adjust the damping coefficient of the grid-type energy storage system to the minimum within the allowable range provided by the manufacturer; c. ±10%P N Perform power step and continue running for 30 seconds; d. Record the power and frequency curves of the grid-connected point of the grid-connected energy storage system; e. Adjust the damping coefficient of the grid-type energy storage system to the middle and maximum values ​​of the damping coefficient range provided by the manufacturer; f. Compare the three test result curves to verify the effect and function of damping control; g. Adjust the grid-type energy storage system to 50%P N To charge, repeat steps b) to f); h. Collect data on the voltage and current on the AC side of the grid-type energy storage system and calculate the active power; i. Calculate the power response of frequency disturbance and draw the amplitude and phase curves.

[0032] The phase jump test in step 1.5) includes the following sub-steps: a. Set the output of the power grid simulation device to rated voltage and rated frequency; b. Set the active power output of the grid-connected energy storage system to 20%P N To 80%P N within the interval; c. Adjust the grid simulation device so that the output voltage phase angle steps from the initial phase angle to 30°, 60°, -30°, and -60° respectively, and maintain for at least 10 seconds before recovery; d. Record the voltage, current, active power curve and status of the energy storage converter at the AC port during the test. The record should include data from 3 seconds before the phase step to 6 seconds after the phase returns to normal.

[0033] The step 1.6) of the voltage tolerance test includes the following sub-steps: 1.6.1) Low voltage withstand test: a. Randomly select an energy storage system of the same model and specification in the energy storage power station as the test object, and close the Other energy storage systems under the same busbar as the energy storage system. When there are multiple energy storage systems of different models and specifications in the energy storage power station, the same models and specifications should be selected for testing according to the actual situation of the energy storage power station; b. Connect the power grid simulation device in series with the grid-type energy storage system under test, and connect the data acquisition device to the voltage transformer (PT) and current transformer (CT) at the test point; c. The test should select at least two drop points, which should include 0%Un and any point between 20%Un and 90%Un; d. Low voltage faults should include three-phase symmetrical faults of the line and one type of asymmetrical faults of the line in Table 3, and the voltage drop point should meet the above requirements; e. Set the output of the power grid simulation device to rated voltage and rated frequency; f. Set the grid-connected energy storage system to operate in discharge mode; g. Adjust the active power of the grid-connected energy storage system to 10%P N To 30%P N within the scope; h. Control the fault-generating device to perform three-phase symmetrical voltage drop, which lasts for 10 seconds; i. Record the waveforms of voltage and current at the test point of the grid-type energy storage system, and at least record the data from 3 s before the voltage drops to 6 s after the voltage returns to normal; j. Repeat steps i) to j) once; k. Control the fault-generating device to cause asymmetric voltage drop; l. Record the waveforms of voltage and current at the test point of the grid-type energy storage system, and at least record the data from 3 s before the voltage drops to 6 s after the voltage returns to normal; m. Repeat steps l) to m) 1 time; n. Adjust the grid-type energy storage system to operate at no less than 70%P N Repeat steps i) to n) under the working condition; o. Adjust the charging mode of the grid-connected energy storage system and repeat steps h) to o).

[0034] 1.6.2) High voltage withstand test: a. Randomly select an energy storage system of the same model and specification in the energy storage power station as the test object, and shut down other energy storage systems under the same bus as the energy storage system under test. When there are multiple energy storage systems of different models and specifications in the energy storage power station, the same models and specifications should be selected for testing according to the actual situation of the energy storage power station; b. Connect the power grid simulation device in series with the grid-type energy storage system under test, and connect the data acquisition device to the voltage transformer (PT) and current transformer (CT) at the test point; c. The high voltage withstand test should be selected at 115%, 120%, 125% and 130%, and Figure 1 The curve requires the time to be selected; d. Set the output of the power grid simulation device to rated voltage and rated frequency; e. Adjust the grid-type energy storage system to P N Constant power charging until the energy storage system charging cut-off condition; f. Set the grid-connected energy storage system to operate in discharge mode; g. Adjust the active power of the grid-connected energy storage system to 10%P N To 30%P N ; h. Control the voltage fault generating device to raise the three-phase symmetrical voltage; i. Record the waveform of the output voltage and current of the grid-connected energy storage system. The record should include data from 3 s before the voltage drops to 6 s after the voltage returns to normal; j. Repeat steps g) to i) 1 time; k. Adjust the grid-type energy storage system to operate at no less than 70%P N Under the working condition, repeat steps h) to j); l. Adjust the grid-type energy storage system to P N Constant power discharge until the energy storage system discharge cut-off condition; m. Set the grid-connected energy storage system to operate in charging mode and repeat steps g) to k).

[0035] 1.6.3) Continuous high / low voltage tolerance test: a. Randomly select an energy storage system of the same model and specification in the energy storage power station as the test object, and shut down other energy storage systems under the same bus as the energy storage system under test. When there are multiple energy storage systems of different models and specifications in the energy storage power station, the same models and specifications should be selected for testing according to the actual situation of the energy storage power station; b. Connect the power grid simulation device in series with the grid-type energy storage system under test, and connect the data acquisition device with the voltage transformer (PT) and current transformer (CT) at the test point; c. The continuous low and high voltage withstand capability test should be carried out at the test points and time specified in Table 4. The time interval between two consecutive low and high voltages should be 2s; d. Adjust the grid-type energy storage system to P N Constant power charging to the charging cut-off condition of the grid-connected energy storage system; e. The output of the power grid simulation device is set to rated voltage and rated frequency; f. Set the grid-connected energy storage system to operate in discharge mode; g. Adjust the grid-connected energy storage system to operate at 10%P N To 30%P N Under the working conditions; h. Control the continuous fault generating device to conduct three-phase symmetrical voltage low-high continuous fault; i. Record the waveforms of the voltage and current at the AC port of the energy storage converter. The records should include data from 3 s before the fault to 6 s after the voltage returns to normal; j. Repeat steps h) to i) 1 time; k. Adjust the energy storage converter to operate at no less than 70%P N Under the working condition, repeat steps h) to i); l. Adjust the grid-type energy storage system to P N Constant power discharge to the grid-type energy storage system discharge cut-off condition; m. Adjust the energy storage converter to operate in charging mode and repeat steps g) to k).

[0036] The above step 1.7) overload capacity test includes the following sub-steps: 1.7.1) 1.1 times overload test, adjust the grid-type energy storage system to hot standby state, set the grid-type energy storage system to carry out 1.1P N The corresponding reactive power value is continuously operated for 10 minutes. The time series power is measured at the grid-connected point of the grid-connected energy storage system. The average power value every 0.2s is taken as one point, and the measured data is recorded.

[0037] 1.7.2) 1.2 times overload test, adjust the grid-type energy storage system to hot standby state, set the grid-type energy storage system to carry out 1.2P respectively in the charging / discharging state N The corresponding reactive power value is continuously run for 1 minute. The time series power is measured at the grid-connected point of the grid-connected energy storage system. The average power value every 0.2s is taken as one point, and the measured data is recorded.

[0038] 1.7.3) 1.5 times overload test, adjust the grid-type energy storage system to hot standby state, set the grid-type energy storage system to carry out 1.5P in charge / discharge state respectively N The corresponding reactive power value is run continuously for 30 seconds. The time series power is measured at the grid-connected point of the grid-connected energy storage system. The average power value every 0.2 seconds is taken as one point, and the measured data is recorded.

[0039] 1.7.4) Adjust the grid-connected energy storage system to hot standby state, set the grid-connected energy storage system to charge / discharge state, simulate a three-phase symmetrical line fault through a power grid simulation device to make the voltage drop to 0.2Un for 10s, measure the sequential power at the grid-connected point of the grid-connected energy storage system, take the average power value every 0.2s as one point, record the measured data, and verify whether the total current of the grid-connected energy storage system can reach 3 times the rated current and last for 10s.

[0040] The step 1.8) of switching the network mode includes the following sub-steps: 1.8.1) Test the switch from network construction to network following mode a. Adjust the grid-building energy storage system to operate in the grid-building mode; b. Adjust the grid-type energy storage system to 50%P N Discharge and run continuously for 3 minutes; c. Switch the grid-connected energy storage system mode to the grid-following operation mode; d. Record the voltage, current and power of the grid-connected point of the grid-connected energy storage system; e. Conduct phase angle jump tolerance test; f. Record the status of the grid-connected energy storage system and confirm whether the grid-connected energy storage system has switched to the grid-following operation mode; g. Adjust the grid-type energy storage system to 50%P N Discharge and run continuously for 3 minutes; h. Repeat steps c) to f).

[0041] 1.8.2) Test the switch from network following to network building mode a. The grid-connected energy storage system is regulated to operate in the grid-following mode; b. Adjust the grid-type energy storage system to 50%P N Discharge and run continuously for 3 minutes; c. Switch the grid-building energy storage system mode to the grid-building operation mode; d. Record the voltage, current and power of the grid-connected point of the grid-connected energy storage system; e. Conduct phase angle jump tolerance test; f. Record the status of the grid-building energy storage system and confirm whether the grid-building energy storage system has switched to the grid-building operation mode; g. Adjust the grid-type energy storage system to 50%P N Discharge and run continuously for 3 minutes; h. Repeat steps c) to f).

[0042] The step 2) of the grid-type energy storage multi-unit coordinated control test method includes the following sub-steps: 2.1) Coordination test between network construction and network construction energy storage unit; 2.2) Coordinated testing of grid-building and grid-following energy storage units.

[0043] The step 2.1) of coordinating the network construction and the network construction energy storage unit includes the following sub-steps: 2.1.1) Frequency adaptability test; 2.1.2) One frequency modulation test; 2.1.3) Inertia response test; 2.1.4) Damping control test; 2.1.5) Phase jump test; 2.1.6) Voltage withstand test; 2.1.7) Overload capacity test; The step 2.1.1) of the frequency adaptability test includes the following sub-steps: a. Set the operation mode of multiple grid-type energy storage units to discharge mode; b. Adjust the output of the grid simulation device to the rated voltage and rated frequency of the energy storage system; c. Set multiple grid-connected energy storage units to output active power at 70% P N To 100% P N Operate within the range; d. Adjust the power grid simulation device so that the frequencies of multiple grid-type energy storage unit test points are stepped from 50Hz to 46.45Hz, 46.55Hz, 47.5Hz and 48.45Hz respectively for 1min and then restored to 50Hz; adjust the power grid simulation device so that the frequencies of multiple grid-type energy storage unit test points are stepped from 50Hz to 48.55Hz, 49.5Hz and 50.45Hz respectively for 10min and then restored to 50Hz; adjust the power grid simulation device so that the frequencies of multiple grid-type energy storage unit test points are stepped from 50Hz to 50.55Hz, 51Hz, 52Hz, 52.55Hz and 53.05 respectively for 1min and then restored to 50Hz; e. Use a data acquisition device to synchronously record the frequency, active power effective value and reactive power effective value of multiple grid-type energy storage unit test points at a period of 20ms, and record at least the data from 1 minute before the frequency step to 1 minute after the frequency returns to 50Hz; f. Draw frequency-time, active power-time and reactive power-time curves; g. Record the discharge status of multiple grid-type energy storage units and the alarm information when the frequency exceeds the limit; h. Set the operation mode of multiple grid-connected energy storage units to charging mode and repeat steps b) to g).

[0044] The step 2.1.2) of a frequency modulation test includes the following sub-steps: 2.1.2.1) Primary frequency modulation dead zone test a. Set the primary frequency modulation parameters of multiple grid-type energy storage units, and connect multiple grid-type energy storage units and related testing and measuring equipment; b. Adjust multiple grid-type energy storage units to P N Constant power discharge to the energy storage power station discharge cut-off condition; c. Multiple grid-type energy storage units with a capacity of not less than 20%P N Charging; d. Gradually increase the grid connection point frequency value in steps of 0.01 Hz until the active power starts to change regularly. Run each frequency setting value for 5 seconds and record the output frequency value at the time when the active power changes regularly during the frequency disturbance process; e. Gradually reduce the grid connection point frequency value in steps of 0.01 Hz until the active power starts to change regularly. Run each frequency setting value for 5 seconds and record the output frequency value at the time when the active power changes regularly during the frequency disturbance process; f. Repeat d) to e); g. Adjust multiple grid-type energy storage units to P N Constant power charging until the energy storage station charging cut-off condition; h. Adjust multiple grid-type energy storage units to not less than 20%P N Discharge is performed; i. Repeat d) to f).

[0045] 2.1.2.2) Frequency step disturbance test a. Connect the data acquisition device to the voltage transformer (PT) and current transformer (CT) at the test point, and connect the frequency signal generator to multiple network-type energy storage unit monitoring systems; b. Adjust multiple grid-type energy storage units to P N Constant power discharge to the energy storage power station discharge cut-off condition; c. Multiple grid-type energy storage units are charged under unlimited power and limited power operating conditions, and the active power is tested according to the operating conditions and power ranges of multiple grid-type energy storage units in Table 5; d. Use the frequency signal generator to output the frequency step disturbance signal according to Table 5, and test each working condition twice; e. Record voltage, current, frequency and power values ​​during the test; f. Calculate the primary frequency modulation response lag time, rise time, adjustment time and active power control deviation; g. Adjust multiple grid-type energy storage units to P N Constant power charging until the energy storage station charging cut-off condition; h. Multiple grid-type energy storage units are charged with active power in accordance with the operating states and power ranges of multiple grid-type energy storage units in Table 5 under unlimited power and limited power operating states; i. Use the frequency signal generator to output the frequency step disturbance signal according to Table 5, and test each working condition twice; j. Record voltage, current, frequency and power values ​​during the test; k. Calculate the primary frequency modulation response lag time, rise time, regulation time and active power control deviation.

[0046] 2.1.2.3) Primary FM limit test a. Connect the data acquisition device to the voltage transformer (PT) and current transformer (CT) at the test point, and connect the frequency signal generator to multiple network-type energy storage unit monitoring systems; b. Adjust multiple grid-type energy storage units to P N Constant power discharge to the discharge cut-off conditions of multiple grid-type energy storage units; c. Adjust multiple grid-type energy storage units to 20%P N Charging; d. Set the frequency value of the grid connection point to gradually increase in steps of 0.01Hz until the active power reaches the limit value and stops changing. Each frequency setting value runs for 5s. The maximum frequency difference step should not exceed ±0.5Hz. Record the output frequency value at the time when the active power changes regularly during the frequency disturbance process. e. Set the frequency value of the grid connection point to be gradually reduced in steps of 0.01Hz until the active power reaches the limit value and stops changing. Each frequency setting value runs for 5s. The maximum frequency difference step should not exceed ±0.5Hz. Record the output frequency value at the time when the active power changes regularly during the frequency disturbance process. f. Adjust multiple grid-type energy storage units to P N Constant power charging until the energy storage station charging cut-off condition; g. Adjust multiple grid-type energy storage units to 20%P N Discharge is performed; h. Repeat steps d) to g).

[0047] The step 2.1.3) of the inertia response test includes the following sub-steps: a. Set the operation mode of multiple grid-connected energy storage units to charging mode; b. Adjust multiple grid-type energy storage units to operate at 10%P N To 30%P N Under the working conditions; c. Use the frequency signal generator to output the frequency change rate disturbance signal according to Table 6, and test each working condition twice; d. Record voltage, current, frequency and power values ​​during the test; e. Calculate the inertia response rise time, the maximum active power adjustment and the active power control deviation; f. Adjust the storage capacity of multiple grid-type energy storage units to operate at no less than 70%P N Repeat steps c) to e) under the working condition; g. Setting the operation mode of multiple grid-type energy storage units to discharge mode; h. Repeat steps b) to f).

[0048] The damping control test in step 2.1.4) includes the following sub-steps: a. Adjust multiple grid-type energy storage units to 50%P N Discharge is performed; b. Adjust the damping coefficients of multiple grid-type energy storage units to the minimum within the allowable range provided by the manufacturer; c. ±10%P N Perform power step and continue running for 30 seconds; d. Record the power and frequency curves of multiple grid-connected energy storage units; e. Adjust the damping coefficients of multiple grid-type energy storage units to the middle and maximum values ​​of the damping coefficient range provided by the manufacturer. f. Compare the three test result curves to verify the effect and function of damping control; g. Adjust multiple grid-type energy storage units to 50%P N To charge, repeat steps b) to f); h. Collect the voltage and current data of the AC side of multiple grid-type energy storage units and calculate the active power; i. Calculate the power response of frequency disturbance and draw the amplitude and phase curves.

[0049] The phase jump test in step 2.1.5) includes the following sub-steps: a. Set the output of the power grid simulation device to rated voltage and rated frequency; b. Set the output active power of multiple grid-connected energy storage units to 20%P N To 80%P N within the interval; c. Adjust the grid simulation device so that the output voltage phase angle steps from the initial phase angle to 30°, 60°, -30°, and -60° respectively, and maintain for at least 10 seconds before recovery; d. Record the voltage, current, active power curve and status of the energy storage converter at the AC port during the test. The record should include data from 3 seconds before the phase step to 6 seconds after the phase returns to normal.

[0050] The voltage tolerance test in step 2.1.6) includes the following sub-steps: 2.1.6.1) Low voltage withstand capability test a. Randomly select an energy storage system of the same model and specification from multiple grid-type energy storage units as the test object, and shut down other energy storage systems under the same bus as the energy storage system under test. When there are multiple energy storage systems of multiple models and specifications in multiple grid-type energy storage units, the same model and specification should be selected for testing according to the actual situation of the energy storage power station; b. Connect the power grid simulation device in series with the energy storage system under test, and connect the data acquisition device to the voltage transformer (PT) and current transformer (CT) at the test point; c. The test should select at least two drop points, which should include 0%Un and any point between 20%Un and 90%Un; d. Low voltage faults should include three-phase symmetrical faults of the line and one type of asymmetrical faults of the line in Table 7, and the voltage drop point should meet the above requirements; e. Set the output of the power grid simulation device to rated voltage and rated frequency; f. Set the energy storage system to operate in discharge mode; g. Adjust the active power of the energy storage system to 10%P N To 30%P N within the scope; h. Control the fault-generating device to perform three-phase symmetrical voltage drop, which lasts for 10 seconds; i. Record the waveforms of voltage and current at the test point of the energy storage system. The data should be recorded at least from 3 s before the voltage drops to 6 s after the voltage returns to normal; j. Repeat steps i) to j) once; k. Control the fault-generating device to cause asymmetric voltage drop; l. Record the waveforms of voltage and current at the test point of the energy storage system, and at least record the data from 3 s before the voltage drops to 6 s after the voltage returns to normal; m. Repeat steps l) to m) 1 time; n. Adjust the energy storage system to operate at no less than 70%P N Repeat steps i) to n) under the working condition; o. Adjust the energy storage system to operate in charging mode and repeat steps h) to o).

[0051] 2.1.6.2) High voltage withstand capability test a. Randomly select an energy storage system of the same model and specification from multiple grid-type energy storage units as the test object, and shut down other energy storage systems under the same bus as the energy storage system under test. When there are multiple energy storage systems of multiple models and specifications in multiple grid-type energy storage units, the same model and specification should be selected for testing according to the actual situation of the energy storage power station; b. Connect the power grid simulation device in series with the energy storage system under test, and connect the data acquisition device to the voltage transformer (PT) and current transformer (CT) at the test point; c. The high voltage withstand test should be selected at 115%, 120%, 125% and 130%, and Figure 1 The curve requires the time to be selected; d. Set the output of the power grid simulation device to rated voltage and rated frequency; e. Adjust the energy storage system to P N Constant power charging until the energy storage system charging cut-off condition; f. Set the energy storage system to operate in discharge mode; g. Adjust the active power of the energy storage system to 10%P N Up to 30%3P N ; h. Control the voltage fault generating device to raise the three-phase symmetrical voltage; i. Record the waveforms of the output voltage and current of the energy storage system. The records should include data from 3 s before the voltage drops to 6 s after the voltage returns to normal; j. Repeat steps g) to i) 1 time; k. Adjust the energy storage system to operate at no less than 70%P N Under the working condition, repeat steps h) to j); l. Adjust the energy storage system to P N Constant power discharge until the energy storage system discharge cut-off condition; m. Set the energy storage system to operate in charging mode and repeat steps g) to k).

[0052] 2.1.6.3) Continuous high / low voltage withstand test a. Randomly select an energy storage system of the same model and specification from multiple grid-type energy storage units as the test object, and shut down other energy storage systems under the same bus as the energy storage system under test. When there are multiple energy storage systems of multiple models and specifications in multiple grid-type energy storage units, the same model and specification should be selected for testing according to the actual situation of the energy storage power station; b. Connect the power grid simulation device in series with the energy storage system under test, and connect the data acquisition device to the voltage transformer (PT) and current transformer (CT) at the test point; c. The continuous low and high voltage withstand capability test should be carried out at the test points and time specified in Table 8. The time interval between two consecutive low and high voltages should be 2s; d. Adjust the energy storage system to P N Constant power charging until the energy storage system charging cut-off condition; e. The output of the power grid simulation device is set to rated voltage and rated frequency; f. Set the energy storage system to operate in discharge mode; g. Adjust the energy storage system to operate at 10%P N To 30%P N Under the working conditions; h. Control the continuous fault generating device to conduct three-phase symmetrical voltage low-high continuous fault; i. Record the waveforms of the voltage and current at the AC port of the energy storage converter. The records should include data from 3 s before the fault to 6 s after the voltage returns to normal; j. Repeat steps h) to i) 1 time; k. Adjust the energy storage converter to operate at no less than 70%P N Under the working condition, repeat steps h) to i); l. Adjust the energy storage system to P N Constant power discharge until the energy storage system discharge cut-off condition; m. Adjust the energy storage converter to operate in charging mode and repeat steps g) to k).

[0053] The overload capacity test in step 2.1.7) includes the following sub-steps: 2.1.7.1) 1.1 times overload test, adjust multiple grid-type energy storage units to hot standby state, set multiple grid-type energy storage units to carry out 1.1P in charge / discharge state respectively N The corresponding reactive power value is run continuously for 10 minutes, and the time-series power is measured at the grid-connected points of multiple grid-connected energy storage units. The average power value every 0.2s is taken as one point, and the measured data is recorded.

[0054] 2.1.7.2) 1.2 times overload test, adjust multiple grid-type energy storage units to hot standby state, set multiple grid-type energy storage units to carry out 1.2P in charge / discharge state respectively N The corresponding reactive power value is run continuously for 2 minutes. The time-series power is measured at the grid-connected points of multiple grid-connected energy storage units. The average power value every 0.2s is taken as one point, and the measured data is recorded.

[0055] 2.1.7.3) 1.5 times overload test, adjust multiple grid-type energy storage units to hot standby state, set multiple grid-type energy storage units to carry out 1.5P in charge / discharge state respectively NThe corresponding reactive power value is run continuously for 30 seconds. The time series power is measured at the grid-connected points of multiple grid-connected energy storage units. The average power value every 0.2 seconds is taken as one point, and the measured data is recorded.

[0056] 2.1.7.4) Adjust multiple grid-connected energy storage units to hot standby status, set multiple grid-connected energy storage units in charging / discharging status, simulate a three-phase symmetrical line fault through a power grid simulation device to make the voltage drop to 0.2Un for 10s, measure the sequential power at the grid connection points of multiple grid-connected energy storage units, take the average power value every 0.2s as one point, record the measured data, and verify whether the total current of multiple grid-connected energy storage units can reach 3 times the rated current and last for 10s.

[0057] The step 2.2) of coordinating the grid construction and grid-connected energy storage unit test includes the following sub-steps: 2.2.1) Frequency adaptability test; 2.2.2) One frequency modulation test; 2.2.3) Inertia response test; 2.2.4) Damping control test; 2.2.5) Phase jump test; 2.2.6) Voltage withstand capability test; 2.2.7) Overload capacity test.

[0058] The frequency adaptability test in step 2.2.1) includes the following sub-steps: a. Set the operation mode of the grid-building and grid-following energy storage units to discharge mode; b. Adjust the output of the grid simulation device to the rated voltage and rated frequency of the energy storage system; c. Set the active power output of the grid-building and grid-following energy storage units to 70% P N To 100% P N Operate within the range; d. Adjust the power grid simulation device so that the frequency of the test point of the grid-building and grid-following energy storage unit is stepped from 50Hz to 46.45Hz, 46.55Hz, 47.5Hz and 48.45Hz respectively for 1min and then restored to 50Hz; adjust the power grid simulation device so that the frequency of the test point of the grid-building and grid-following energy storage unit is stepped from 50Hz to 48.55Hz, 49.5Hz and 50.45Hz respectively for 10min and then restored to 50Hz; adjust the power grid simulation device so that the frequency of the test point of the grid-building and grid-following energy storage unit is stepped from 50Hz to 50.55Hz, 51Hz, 52Hz, 52.55Hz and 53.05 respectively for 1min and then restored to 50Hz; e. Use the data acquisition device to synchronously record the frequency, active power effective value and reactive power effective value of the test point of the network construction and grid-following energy storage units at a period of 20ms, and record at least the data from 1 minute before the frequency step to 1 minute after the frequency returns to 50Hz; f. Draw frequency-time, active power-time and reactive power-time curves; g. Record the discharge status of the grid-building and grid-following energy storage units and the alarm information when the frequency exceeds the limit; h. Set the operation mode of the grid-building and grid-following energy storage units to charging mode, and repeat steps b) to g).

[0059] The step 2.2.2) of a frequency modulation test includes the following sub-steps: 2.2.2.1) Primary frequency modulation dead zone test a. Set the primary frequency modulation parameters of the grid-building and grid-following energy storage units, and connect the grid-building and grid-following energy storage units and related testing and measuring equipment; b. Adjust the grid-building and grid-following energy storage units to P N Constant power discharge to the grid-building and grid-following energy storage unit discharge cut-off conditions; c. The grid-connected and grid-following energy storage units shall be no less than 20%P N Charging; d. Gradually increase the grid connection point frequency value in steps of 0.01 Hz until the active power starts to change regularly. Run each frequency setting value for 5 seconds and record the output frequency value at the time when the active power changes regularly during the frequency disturbance process; e. Gradually reduce the grid connection point frequency value in steps of 0.01 Hz until the active power starts to change regularly. Run each frequency setting value for 5 seconds and record the output frequency value at the time when the active power changes regularly during the frequency disturbance process; f. Repeat d) to f); g. Adjust the grid-building and grid-following energy storage units to P N Constant power charging until the energy storage station charging cut-off condition; h. Adjust the grid-connected and grid-following energy storage units to not less than 20%P N Discharge is performed; i. Repeat d) to f).

[0060] 2.2.2.2) Frequency step disturbance test a. Connect the data acquisition device to the voltage transformer (PT) and current transformer (CT) at the test point, and connect the frequency signal generator to the network construction and grid-following energy storage unit monitoring system; b. Adjust the grid-building and grid-following energy storage units to P N Constant power discharge to the energy storage power station discharge cut-off condition; c. The grid-building and grid-following energy storage units are charged and tested in the unlimited power and limited power operating states according to the operating states and power ranges of the grid-building and grid-following energy storage units in Table 2; d. Use the frequency signal generator to output the frequency step disturbance signal according to Table 2, and test each working condition twice; e. Record voltage, current, frequency and power values ​​during the test; f. Calculate the primary frequency modulation response lag time, rise time, adjustment time and active power control deviation; g. Adjust the grid-building and grid-following energy storage units to P N Constant power charging until the energy storage station charging cut-off condition; h. When the grid-building and grid-following energy storage units are in the unlimited power and limited power operating states, the active power is charged according to the operating states and power ranges of the grid-building and grid-following energy storage units in Table 2; i. Use the frequency signal generator to output the frequency step disturbance signal according to Table 9, and test each working condition twice; j. Record voltage, current, frequency and power values ​​during the test; k. Calculate the primary frequency modulation response lag time, rise time, regulation time and active power control deviation.

[0061] 2.2.2.3) Primary FM limit test a. Connect the data acquisition device to the voltage transformer (PT) and current transformer (CT) at the test point, and connect the frequency signal generator to the network construction and grid-following energy storage unit monitoring system; b. Adjust the grid-building and grid-following energy storage units to P N Constant power discharge to the grid-building and grid-following energy storage unit discharge cut-off conditions; c. Adjust the grid-building and grid-following energy storage units to 20%P N Charging; d. Set the frequency value of the grid connection point to gradually increase in steps of 0.01Hz until the active power reaches the limit value and stops changing. Each frequency setting value runs for 5s. The maximum frequency difference step should not exceed ±0.5Hz. Record the output frequency value at the time when the active power changes regularly during the frequency disturbance process. e. Set the frequency value of the grid connection point to be gradually reduced in steps of 0.01Hz until the active power reaches the limit value and stops changing. Each frequency setting value runs for 5s. The maximum frequency difference step should not exceed ±0.5Hz. Record the output frequency value at the time when the active power changes regularly during the frequency disturbance process. f. Adjust the grid-building and grid-following energy storage units to P N Constant power charging until the charging cut-off conditions of the grid-building and grid-following energy storage units are met; g. Adjust the grid-building and grid-following energy storage units to 20%PN Discharge is performed; h. Repeat steps d) to g).

[0062] The step 2.2.3) of the inertia response test includes the following sub-steps: a. Set the operation mode of the grid-building and grid-following energy storage units to charging mode; b. Adjust the grid-connected and grid-following energy storage units to operate at 10%P N To 30%P N Under the working conditions; c. Use the frequency signal generator to output the frequency change rate disturbance signal according to Table 10, and test each working condition twice; d. Record voltage, current, frequency and power values ​​during the test; e. Calculate the inertia response rise time, the maximum active power adjustment and the active power control deviation; f. Adjust the grid-connected and grid-following energy storage units to operate at no less than 70%P N Repeat steps c) to e) under the working condition; g. Set the operation mode of the grid-building and grid-following energy storage units to discharge mode; h. Repeat steps b) to f).

[0063] The damping control test in step 2.2.4) includes the following sub-steps: a. Adjust the grid-building and grid-following energy storage units to 50%P N Discharge is performed; b. Adjust the damping coefficient of the grid-building and grid-following energy storage unit stations to the minimum within the allowable range provided by the manufacturer; c. ±10%P N Perform power step and continue running for 30 seconds; d. Record the power and frequency curves of the grid connection points of the grid-building and grid-following energy storage units; e. Adjust the damping coefficient of the grid-building and grid-following energy storage units to the middle and maximum values ​​of the damping coefficient range provided by the manufacturer. f. Compare the three test result curves to verify the effect and function of damping control.

[0064] g. Adjust the grid-building and grid-following energy storage units to 50%P N To charge, repeat steps b) to f); h. Collect the voltage and current data of the AC side of the grid-building and grid-following energy storage units, and calculate the active power; i. Calculate the power response of frequency disturbance and draw the amplitude and phase curves.

[0065] The phase jump test in step 2.2.5) includes the following sub-steps: a. Set the output of the power grid simulation device to rated voltage and rated frequency; b. Set the active power output of the grid-connecting and grid-following energy storage units to 20%P N To 80%P N within the interval; c. Adjust the grid simulation device so that the output voltage phase angle steps from the initial phase angle to 30°, 60°, -30°, and -60° respectively, and maintain for at least 10 seconds before recovery; d. Record the voltage, current, active power curve and status of the energy storage converter AC port during the test. The record should include data from 3s before the phase step to 6s after the phase returns to normal; The voltage tolerance test in step 2.2.6) includes the following sub-steps: 2.2.6.1) Low voltage withstand capability test a. Randomly select an energy storage system of the same model and specification in the grid-building and grid-following energy storage units as the test object, and shut down other energy storage systems under the same bus as the energy storage system under test. When there are multiple energy storage systems of different models and specifications in the grid-building and grid-following energy storage units, the same models and specifications should be selected for testing according to the actual situation of the energy storage power station; b. Connect the power grid simulation device in series with the energy storage system under test, and connect the data acquisition device to the voltage transformer (PT) and current transformer (CT) at the test point; c. The test should select at least two drop points, which should include 0%Un and any point between 20%Un and 90%Un; d. Low voltage faults should include three-phase symmetrical faults of the line and one type of asymmetrical faults of the line in Table 11, and the voltage drop point should meet the above requirements; e. Set the output of the power grid simulation device to rated voltage and rated frequency; f. Set the energy storage system to operate in discharge mode; g. Adjust the active power of the energy storage system to 10%P N To 30%P N within the scope; h. Control the fault-generating device to perform three-phase symmetrical voltage drop, which lasts for 10 seconds; i. Record the waveforms of voltage and current at the test point of the energy storage system. The data should be recorded at least from 3 s before the voltage drops to 6 s after the voltage returns to normal; j. Repeat steps i) to j) once; k. Control the fault-generating device to cause asymmetric voltage drop; l. Record the waveforms of voltage and current at the test point of the energy storage system, and at least record the data from 3 s before the voltage drops to 6 s after the voltage returns to normal; m. Repeat steps l) to m) 1 time; n. Adjust the energy storage system to operate at no less than 70%P N Repeat steps i) to n) under the working condition; o. Adjust the energy storage system to operate in charging mode and repeat steps h) to o).

[0066] 2.2.6.2) High voltage withstand capability test a. Randomly select an energy storage system of the same model and specification in the grid-building and grid-following energy storage units as the test object, and shut down other energy storage systems under the same bus as the energy storage system under test. When there are multiple energy storage systems of different models and specifications in the grid-building and grid-following energy storage units, the same models and specifications should be selected for testing according to the actual situation of the energy storage power station; b. Connect the power grid simulation device in series with the energy storage system under test, and connect the data acquisition device to the voltage transformer (PT) and current transformer (CT) at the test point; c. The high voltage withstand test should be selected at 115%, 120%, 125% and 130%, and Figure 1 The curve requires a time to be selected.

[0067] d. Set the output of the power grid simulation device to rated voltage and rated frequency; e. Adjust the energy storage system to P N Constant power charging until the energy storage system charging cut-off condition; f. Set the energy storage system to operate in discharge mode; g. Adjust the active power of the energy storage system to 10%P N Up to 30%3P N ; h. Control voltage fault generating device to raise three-phase symmetrical voltage; i. Record the waveform of the output voltage and current of the energy storage system. The record should include data from 3 seconds before the voltage drops to 6 seconds after the voltage returns to normal; j. Repeat steps g) to i) 1 time; k. Adjust the energy storage system to operate at no less than 70%P N Under the working condition, repeat steps h) to j); l. Adjust the energy storage system to P N Constant power discharge until the energy storage system discharge cut-off condition; m. Set the energy storage system to operate in charging mode and repeat steps g) to k).

[0068] 2.2.6.3) Continuous high / low voltage tolerance test a. Randomly select an energy storage system of the same model and specification in the grid-building and grid-following energy storage units as the test object, and shut down other energy storage systems under the same bus as the energy storage system under test. When there are multiple energy storage systems of different models and specifications in the grid-building and grid-following energy storage units, the same models and specifications should be selected for testing according to the actual situation of the energy storage power station; b. Connect the power grid simulation device in series with the energy storage system under test, and connect the data acquisition device to the voltage transformer (PT) and current transformer (CT) at the test point; c. The continuous low and high voltage withstand capability test should be carried out at the test points and time specified in Table 12. The time interval between two consecutive low and high voltages should be 2s; d. Adjust the energy storage system to P N Constant power charging until the energy storage system charging cut-off condition; e. The output of the power grid simulation device is set to rated voltage and rated frequency; f. Set the energy storage system to operate in discharge mode; g. Adjust the energy storage system to operate at 10%P N To 30%P N Under the working conditions; h. Control the continuous fault generating device to perform three-phase symmetrical voltage low-high continuous fault; i. Record the waveforms of the voltage and current at the AC port of the energy storage converter. The records should include data from 3 s before the fault to 6 s after the voltage returns to normal; j. Repeat steps h) to i) 1 time; k. Adjust the energy storage converter to operate at no less than 70%P N Under the working condition, repeat steps h) to i); l. Adjust the energy storage system to P N Constant power discharge until the energy storage system discharge cut-off condition; m. Adjust the energy storage converter to operate in charging mode and repeat steps g) to k).

[0069] The overload capacity test in step 2.2.7) includes the following sub-steps: 2.2.7.1) 1.1 times overload test, adjust the grid-building and grid-following energy storage units to hot standby state, set the grid-building and grid-following energy storage units to carry out 1.1P N The corresponding reactive power value is run continuously for 10 minutes. The time-series power is measured at the grid connection point between the grid-building and grid-following energy storage units. The average power value every 0.2s is taken as one point, and the measured data is recorded.

[0070] 2.2.7.2) 1.2 times overload test, adjust the grid-building and grid-following energy storage units to hot standby state, set the grid-building and grid-following energy storage units to carry out 1.2P N The corresponding reactive power value is run continuously for 2 minutes. The time-series power is measured at the grid connection point between the grid-building and grid-following energy storage units. The average power value every 0.2s is taken as one point, and the measured data is recorded.

[0071] 2.2.7.3) 1.5 times overload test, adjust the grid-building and grid-following energy storage units to hot standby state, set the grid-building and grid-following energy storage units to carry out 1.5P N The corresponding reactive power value is run continuously for 30 seconds. The time series power is measured at the grid connection point between the grid-building and grid-following energy storage units. The average power value every 0.2 seconds is taken as one point, and the measured data is recorded.

[0072] 2.2.7.4) Adjust the energy storage system to hot standby state, set the charging / discharging state of the grid-forming and grid-following energy storage units, simulate the three-phase symmetrical fault of the line through the power grid simulation device to make the voltage drop to 0.2Un, and last for 10s. Measure the sequential power at the grid connection point of the grid-forming and grid-following energy storage units, take the average power value every 0.2s as one point, record the measured data, and verify whether the total current of the grid-forming and grid-following energy storage units can reach 3 times the rated current and last for 10s.

[0073] The step 3) of testing the grid-type energy storage power station-level grid-type characteristics includes the following sub-steps: 3.1) Frequency adaptability test; 3.2) One frequency modulation test; 3.3) Inertia response test; 3.4) Damping control test; 3.5) Phase jump test; 3.6) Voltage withstand test; 3.7) Overload capacity test; 3.8) Test the switching between follow / build network mode.

[0074] The step 3.1) of the frequency adaptability test includes the following sub-steps: a. Set the operation mode of the grid-connected energy storage power station to discharge mode; b. Adjust the output of the grid simulation device to the rated voltage and rated frequency of the grid-type energy storage power station; c. Set the grid-connected energy storage power station to output active power at 70% P N To 100% P N Operate within the range; d. Adjust the power grid simulation device so that the frequency of the test point of the grid-type energy storage power station is stepped from 50Hz to 46.45Hz, 46.55Hz, 47.5Hz and 48.45Hz respectively for 1min and then restored to 50Hz; adjust the power grid simulation device so that the frequency of the test point of the grid-type energy storage power station is stepped from 50Hz to 48.55Hz, 49.5Hz and 50.45Hz respectively for 10min and then restored to 50Hz; adjust the power grid simulation device so that the frequency of the test point of the grid-type energy storage power station is stepped from 50Hz to 50.55Hz, 51Hz, 52Hz, 52.55Hz and 53.05 respectively for 1min and then restored to 50Hz; e. Use the data acquisition device to synchronously record the frequency, effective value of active power and effective value of reactive power of the test point of the grid-type energy storage power station with a period of 20ms, and record at least the data from 1 minute before the frequency step to 1 minute after the frequency returns to 50Hz; f. Draw frequency-time, active power-time and reactive power-time curves; g. Record the discharge status of the grid-type energy storage power station and the alarm information when the frequency exceeds the limit; h. Set the grid-connected energy storage power station operation mode to charging mode and repeat steps b) to g).

[0075] The step 3.2) of a frequency modulation test includes the following sub-steps: 3.2.1) Primary frequency modulation dead zone test a. Set the primary frequency modulation parameters of the grid-type energy storage power station, and connect the grid-type energy storage power station and related testing and measuring equipment; b. Adjustment of grid-type energy storage power station with P N Discharge at constant power to the grid-type energy storage power station discharge cut-off conditions; c. Grid-type energy storage power station shall be no less than 20%P N Charging; d. Gradually increase the grid connection point frequency value in steps of 0.01 Hz until the active power starts to change regularly. Run each frequency setting value for 5 seconds and record the output frequency value at the time when the active power changes regularly during the frequency disturbance process; e. Gradually reduce the grid connection point frequency value in steps of 0.01 Hz until the active power starts to change regularly. Run each frequency setting value for 5 seconds and record the output frequency value at the time when the active power changes regularly during the frequency disturbance process; f. Repeat d) to e); g. Adjustment of grid-type energy storage power station with P N Constant power charging until the energy storage station charging cut-off condition; h. Adjust the grid-type energy storage power station to not less than 20%P N Discharge is performed; i. Repeat d) to f).

[0076] 3.2.2) Frequency step disturbance test a. Connect the data acquisition device to the voltage transformer (PT) and current transformer (CT) at the test point, and connect the frequency signal generator to the energy storage power station monitoring station; b. Adjustment of grid-type energy storage power station with P N Discharge at constant power to the grid-type energy storage power station discharge cut-off conditions; c. The grid-type energy storage power station is charged with active power in accordance with the grid-type energy storage power station operating state and power range in Table 1 under the unlimited power and limited power operating states; d. Use the frequency signal generator to output the frequency step disturbance signal according to Table 1, and test each working condition twice; e. Record voltage, current, frequency and power values ​​during the test; f. Calculate the primary frequency modulation response lag time, rise time, adjustment time and active power control deviation; g. Adjustment of grid-type energy storage power station with P N Constant power charging to the charging cut-off condition of the grid-connected energy storage power station; h. The grid-type energy storage power station is charged with active power in accordance with the operating state and power range of the grid-type energy storage power station in Table 1 under the unlimited power and limited power operating states; i. Use the frequency signal generator to output the frequency step disturbance signal according to Table 1, and test each working condition twice; j. Record voltage, current, frequency and power values ​​during the test; k. Calculate the primary frequency modulation response lag time, rise time, regulation time and active power control deviation.

[0077] 3.2.3) Primary FM limit test a. Connect the data acquisition device to the voltage transformer (PT) and current transformer (CT) at the test point, and connect the power grid simulation device to the monitoring station of the grid-type energy storage power station; b. Adjustment of grid-type energy storage power station with P N Discharge at constant power to the grid-type energy storage power station discharge cut-off conditions; c. Adjust the grid-type energy storage power station to 20%P N Charging; d. Set the frequency value of the grid connection point to gradually increase in steps of 0.01Hz until the active power reaches the limit value and stops changing. Each frequency setting value runs for 5s. The maximum frequency difference step should not exceed ±0.5Hz. Record the output frequency value at the time when the active power changes regularly during the frequency disturbance process. e. Set the frequency value of the grid connection point to be gradually reduced in steps of 0.01Hz until the active power reaches the limit value and stops changing. Each frequency setting value runs for 5s. The maximum frequency difference step should not exceed ±0.5Hz. Record the output frequency value at the time when the active power changes regularly during the frequency disturbance process. f. Adjustment of grid-type energy storage power station with P N Constant power charging to the charging cut-off condition of the grid-connected energy storage power station; g. Adjust the grid-type energy storage power station to 20%P N Discharge is performed; h. Repeat steps d) to g).

[0078] The step 3.3) of the inertia response test includes the following sub-steps: a. Set the operation mode of the grid-connected energy storage power station to charging mode; b. Adjust the grid-type energy storage power station to operate at 10%P N To 30%P N Under the working conditions; c. Use the frequency signal generator to output the frequency change rate disturbance signal according to Table 2, and test each working condition twice; d. Record voltage, current, frequency and power values ​​during the test; e. Calculate the inertia response rise time, the maximum active power adjustment and the active power control deviation; f. The grid-type energy storage power station is operated at not less than 70%P N Repeat steps c) to e) under the working condition; g. Set the grid-type energy storage power station operation mode to discharge mode; h. Repeat steps b) to f).

[0079] The step 3.4) of the damping control test includes the following sub-steps: a. Adjust the grid-type energy storage power station to 50%P N Discharge is performed; b. Adjust the damping coefficient of the grid-type energy storage power station to the minimum within the allowable range provided by the manufacturer; c. ±10%P N Perform power step and continue running for 30 seconds; d. Record the power and frequency curves of the grid-connected point of the grid-connected energy storage power station; e. Adjust the damping coefficient of the grid-type energy storage power station to the middle and maximum values ​​of the damping coefficient range provided by the manufacturer; f. Compare the three test result curves to verify the effect and function of damping control; g. Adjust the grid-type energy storage power station to 50%P NTo charge, repeat steps b) to f); h. Collect the voltage and current data of the AC side of the grid-type energy storage power station and calculate the active power; i. Calculate the power response of frequency disturbance and draw the amplitude and phase curves.

[0080] The phase jump test in step 3.5) includes the following sub-steps: a. Set the output of the power grid simulation device to rated voltage and rated frequency; b. Set the active power output of the grid-connected energy storage power station to 20%P N To 80%P N within the interval; c. Adjust the grid simulation device so that the output voltage phase angle steps from the initial phase angle to 30°, 60°, -30°, and -60° respectively, and maintain for at least 10 seconds before recovery; d. Record the voltage, current, active power curve and status of the energy storage converter at the AC port during the test. The record should include data from 3 seconds before the phase step to 6 seconds after the phase returns to normal.

[0081] The voltage tolerance test in step 3.6) includes the following sub-steps: 3.6.1) Low voltage withstand test: a. Randomly select an energy storage power station of the same model and specification as the test object, close the Other energy storage power stations under the same busbar as the energy storage power station. When there are multiple energy storage power stations of different models and specifications in the energy storage power station, the same models and specifications should be selected for testing according to the actual situation of the energy storage power station site; b. Connect the power grid simulation device in series with the grid-type energy storage power station under test, and connect the data acquisition device to the voltage transformer (PT) and current transformer (CT) at the test point; c. The test should select at least two drop points, which should include 0%Un and any point between 20%Un and 90%Un; d. Low voltage faults should include three-phase symmetrical faults of the line and one type of asymmetrical faults of the line in Table 3, and the voltage drop point should meet the above requirements; e. Set the output of the power grid simulation device to rated voltage and rated frequency; f. Set the grid-type energy storage power station to operate in discharge mode; g. Adjust the active power of the grid-connected energy storage power station to 10%P N To 30%P N within the scope; h. Control the fault-generating device to perform three-phase symmetrical voltage drop, which lasts for 10 seconds; i. Record the waveforms of voltage and current at the test point of the grid-type energy storage power station. At least the data from 3 s before the voltage drops to 6 s after the voltage returns to normal should be recorded; j. Repeat steps i) to j) once; k. Control the fault-generating device to cause asymmetric voltage drop; l. Record the waveforms of voltage and current at the test point of the grid-type energy storage power station, and at least record the data from 3 seconds before the voltage drops to 6 seconds after the voltage returns to normal; m. Repeat steps l) to m) 1 time; n.Regulating grid-type energy storage power station operates at not less than 70%P N Repeat steps i) to n) under the working condition; o. Adjust the grid-type energy storage power station to operate in charging mode, and repeat steps h) to o).

[0082] 3.6.2) High voltage withstand test: a. Randomly select an energy storage power station of the same model and specification as the test object, and shut down other energy storage power stations under the same bus as the energy storage power station under test. When there are multiple energy storage power stations of different models and specifications in the energy storage power station, the same model and specification should be selected for testing according to the actual situation of the energy storage power station on site; b. Connect the power grid simulation device in series with the grid-type energy storage power station under test, and connect the data acquisition device to the voltage transformer (PT) and current transformer (CT) at the test point; c. The high voltage withstand test should be selected at 115%, 120%, 125% and 130%, and Figure 1 The curve requires the time to be selected; d. Set the output of the power grid simulation device to rated voltage and rated frequency; e. Adjustment of grid-type energy storage power station with P N Constant power charging until the energy storage station charging cut-off condition; f. Set the grid-type energy storage power station to operate in discharge mode; g. Adjust the active power of the grid-connected energy storage power station to 10%P N To 30%P N ; h. Control the voltage fault generating device to raise the three-phase symmetrical voltage; i. Record the waveform of the output voltage and current of the grid-type energy storage power station. The record should include data from 3 seconds before the voltage drops to 6 seconds after the voltage returns to normal; j. Repeat steps g) to i) 1 time; k. The grid-type energy storage power station is operated at not less than 70%P N Under the working condition, repeat steps h) to j); l. Adjustment of grid-type energy storage power station with P N Constant power discharge to the energy storage power station discharge cut-off condition; m. Set the grid-connected energy storage power station to operate in charging mode and repeat steps g) to k).

[0083] 3.6.3) Continuous high / low voltage tolerance test: a. Randomly select an energy storage power station of the same model and specification in the energy storage power station as the test object, and shut down other energy storage power stations under the same bus as the energy storage power station under test. When there are multiple energy storage power stations of different models and specifications in the energy storage power station, the same model and specification should be selected for testing according to the actual situation of the energy storage power station on site; b. Connect the power grid simulation device in series with the grid-type energy storage power station under test, and connect the data acquisition device to the voltage transformer (PT) and current transformer (CT) at the test point; c. The continuous low and high voltage withstand capability test should be carried out at the test points and time specified in Table 4. The time interval between two consecutive low and high voltages should be 2s; d. Adjustment of grid-type energy storage power station with P N Constant power charging to the charging cut-off condition of the grid-connected energy storage power station; e. The output of the power grid simulation device is set to rated voltage and rated frequency; f. Set the grid-type energy storage power station to operate in discharge mode; g. The grid-type energy storage power station operates at 10%P N To 30%P N Under the working conditions; h. Control the continuous fault generating device to conduct three-phase symmetrical voltage low-high continuous fault; i. Record the waveforms of the voltage and current at the AC port of the energy storage converter. The records should include data from 3 s before the fault to 6 s after the voltage returns to normal; j. Repeat steps h) to i) 1 time; k. Adjust the energy storage converter to operate at no less than 70%P N Under the working condition, repeat steps h) to i); l. Adjustment of grid-type energy storage power station with P N Discharge at constant power to the grid-type energy storage power station discharge cut-off conditions; m. Adjust the energy storage converter to operate in charging mode and repeat steps g) to k).

[0084] The overload capacity test in step 3.7) includes the following sub-steps: 3.7.1) 1.1 times overload test, adjust the grid-type energy storage power station to hot standby state, set the grid-type energy storage power station to carry out 1.1PN The corresponding reactive power value is run continuously for 10 minutes. The time series power is measured at the grid-connected point of the grid-type energy storage power station. The average power value every 0.2s is taken as one point, and the measured data is recorded.

[0085] 3.7.2) 1.2 times overload test, adjust the grid-type energy storage power station to hot standby state, set the grid-type energy storage power station to carry out 1.2P under charging / discharging state respectively N The corresponding reactive power value is run continuously for 1 minute. The time series power is measured at the grid-connected point of the grid-type energy storage power station. The average power value every 0.2s is taken as one point, and the measured data is recorded.

[0086] 3.7.3) 1.5 times overload test, adjust the grid-type energy storage power station to hot standby state, set the grid-type energy storage power station to carry out 1.5P under charging / discharging state respectively N The corresponding reactive power value is run continuously for 30 seconds. The time series power is measured at the grid-connected point of the grid-connected energy storage power station. The average power value every 0.2 seconds is taken as one point, and the measured data is recorded.

[0087] 3.7.4) Adjust the grid-type energy storage power station to the hot standby state, set the grid-type energy storage power station in the charging / discharging state, simulate the three-phase symmetrical fault of the line through the power grid simulation device to make the voltage drop to 0.2Un, and last for 10s. Measure the timing power at the grid-type energy storage power station connection point, take the average power value every 0.2s as one point, record the measured data, and verify whether the total current of the grid-type energy storage power station can reach 3 times the rated current and last for 10s.

[0088] The step 3.8) of switching the network mode includes the following sub-steps: 3.8.1) Test of switching from network construction mode to network following mode a. The grid-forming energy storage power station operates in the grid-forming mode; b. Adjust the grid-type energy storage power station to 50%P N Discharge and run continuously for 3 minutes; c. Switch the grid-connected energy storage power station mode to the grid-following operation mode; d. Record the voltage, current and power of the grid-connected point of the grid-connected energy storage power station; e. Conduct phase angle jump tolerance test; f. Record the status of the grid-connected energy storage power station and confirm whether the grid-connected energy storage power station has switched to the grid-connected operation mode; g. Adjust the grid-type energy storage power station to 50%P N Discharge and run continuously for 3 minutes; h. Repeat steps c) to f).

[0089] 3.8.2) Test of switching from network following mode to network building mode a. The regulating grid-type energy storage power station operates in the grid-following mode; b. Adjust the grid-type energy storage power station to 50%P N Discharge and run continuously for 3 minutes; c. Switch the grid-building energy storage power station mode to the grid-building operation mode; d. Record the voltage, current and power of the grid-connected point of the grid-connected energy storage power station; e. Conduct phase angle jump tolerance test; f. Record the status of the grid-connected energy storage power station and confirm whether the grid-connected energy storage power station has switched to the grid-connected operation mode; g. Adjust the grid-type energy storage power station to 50%P N Discharge and run continuously for 3 minutes; h. Repeat steps c) to f).

[0090] The step 4) of the basic grid-connected performance test method of the grid-connected energy storage power station includes the following sub-steps: 4.1) Active power control test; 4.2) Automatic generation control (AGC) test; 4.3) Reactive power regulation capability test; 4.4) Automatic voltage control (AVC) test; 4.5) Charge and discharge response time test; 4.6) Charge and discharge adjustment time test; 4.7) Charge and discharge conversion time test; 4.8) Overload capacity test; 4.9) Rated energy and conversion efficiency test; 4.10) Power quality test; 4.11) Black start test.

[0091] The step 4.1) active power control test includes the following sub-steps: 4.1.1) Power test: a. Set the active power of the grid-connected energy storage power station to 0; b. Adjust the active power setting value step by step to 0, -0.25 P N , -0.5 P N , -0.75 P N , -P N 、-0.75P N 、-0.5P N 、-0.25P N , 0, each power setting value runs continuously for 30 seconds, and the measured data is recorded; c. Calculate the response time, regulation time and control deviation of active power control.

[0092] 4.1.2) Power reduction test a. Set the active power of the grid-connected energy storage power station to P N ; b. Adjust the active power setting value step by step to 0, 0.25 P N , 0.5 P N , 0.75P N , P N , 0.75P N , 0.5 P N , 0.25P N , 0, each power setting value runs continuously for 30 seconds, and the measured data is recorded; c. Calculate the response time, regulation time and control deviation of active power control.

[0093] The step 4.2) Automatic Generation Control (AGC) test includes the following sub-steps: a. Set the active power of the grid-connected energy storage power station to 0; b. The dispatcher manually issues the AGC load command and adjusts the active power setting value to 0.25P step by step N , 0.5P N , 0.75P N , P N , 0.75P N , 0.5P N , 0.25P N , 0; c. Record the load of the unit; d. Set the active power of the grid-connected energy storage power station to 0; e. The dispatcher manually issues the AGC load command and adjusts the active power setting value to -0.25P step by step N 、-0.5P N 、-0.75P N , -P N 、-0.75P N 、-0.5P N 、-0.25P N , 0; f. Record the unit load conditions.

[0094] The reactive power regulation capability test in step 4.3) includes the following sub-steps: 4.3.1) Reactive power regulation capability test, the specific steps of the test method are as follows: a. Set the active charging power of the grid-connected energy storage power station to P N ; b. The grid-connected energy storage power station is regulated to operate in the maximum inductive reactive power output working mode; c. Measure the time-series power at the grid-connected point of the grid-connected energy storage power station, record the active power and reactive power for at least 30 seconds, take the average power value every 0.2 seconds as one point, and calculate the average active power and reactive power within the second 15 seconds; d. Adjust the active power of the grid-connected energy storage power station to 0.9P N , 0.8P N , 0.7P N , 0.6P N , 0.5P N , 0.4P N , 0.3P N , 0.2P N , 0.1P N , 0, repeat steps b) to c); e. Adjust the grid-connected energy storage power station to operate in the maximum capacitive reactive power output working mode, and repeat steps c) to d); f. With active power as the horizontal axis and reactive power as the vertical axis, draw the power envelope diagram of the grid-type energy storage power station.

[0095] g. The grid-connected energy storage power station is in discharge mode with active power P N Discharge, repeat steps b) to f) 4.3.2) Power factor regulation capability test, the specific steps of the test method are as follows: a. Adjust the active power of the grid-type energy storage power station to 0.25P N , 0.5P N , 0.75P N , P N Four points; b. Adjust the power factor of the grid-type energy storage power station from leading 0.95 to lagging 0.95 continuously, with the adjustment range not exceeding 0.01, and measure and record the actual output power factor of the grid-type energy storage power station; c. Adjust the active power of the grid-connected energy storage power station to 0.25P N , 0.5P N , 0.75P N , P N Four points; d. Adjust the power factor of the grid-type energy storage power station from leading 0.95 and continuously adjust it to lagging 0.95. The adjustment range shall not exceed 0.01. Measure and record the actual output power factor of the energy storage system.

[0096] The step 4.4) of the automatic voltage control (AVC) test includes the following sub-steps: a. Check the AGC interface information and record it; b. Issue a discharge command at rated power to the grid-type energy storage power station for continuous operation for 2 minutes; c. Use the data acquisition device to collect the current, voltage and power of the test point and draw a real-time power curve; d. Calculate the response time, regulation time and control accuracy of active power; e. Issue a discharge command at rated power to the grid-type energy storage power station for continuous operation for 2 minutes; f. Record the operating status of the grid-type energy storage power station after receiving the signal.

[0097] The step 4.5) charge and discharge response time test includes the following sub-steps: a. Record the time when the grid-type energy storage power station receives the control signal, recorded as tc1; b. Record the moment when the charging power of the grid-connected energy storage power station reaches 90% of the rated power for the first time, recorded as tc2; c. Calculate the charging response time according to RTc=tc2-tc1; d. Repeat the above steps twice, and the charging response time takes the maximum value of the three test results.

[0098] The step 4.6) charge and discharge adjustment time test includes the following sub-steps: a. Record the moment when the grid-type energy storage power station receives the control signal, recorded as tc3; b. Record the starting time when the deviation of the charging power of the grid-type energy storage power station is maintained within ±2% of the rated power, recorded as tc4; c. Calculate the charging adjustment time according to ΔTc=tc4-tc3; d. Repeat the above steps twice, and the charging adjustment time takes the maximum value of the three test results.

[0099] The step 4.7) charge-discharge conversion time test includes the following sub-steps: a. Set the grid-type energy storage power station to charge at rated power, send a command to discharge at rated power to the grid-type energy storage power station, and record the time t1 from charging at 90% rated power to discharging at 90% rated power; b. Repeat the above steps twice, and take the maximum value of the three test results for the charge to discharge conversion time.

[0100] The overload capacity test of step 4.8) includes the following sub-steps: 4.8.1) 1.1 times overload test, adjust the grid-type energy storage power station to hot standby state, set the grid-type energy storage power station to carry out 1.1P NThe corresponding reactive power value is run continuously for 10 minutes. The time series power is measured at the grid-connected point of the grid-type energy storage power station. The average power value every 0.2s is taken as one point, and the measured data is recorded.

[0101] 4.8.2) 1.2 times overload test, adjust the grid-type energy storage power station to hot standby state, set the grid-type energy storage power station to carry out 1.2P in the charging / discharging state respectively N The corresponding reactive power value is run continuously for 2 minutes. The time series power is measured at the grid-connected point of the grid-type energy storage power station. The average power value every 0.2s is taken as one point, and the measured data is recorded.

[0102] 4.8.3) 1.5 times overload test, adjust the grid-type energy storage power station to hot standby state, set the grid-type energy storage power station to carry out 1.5P in the charging / discharging state respectively N The corresponding reactive power value is run continuously for 30 seconds. The time series power is measured at the grid-connected point of the grid-connected energy storage power station. The average power value every 0.2 seconds is taken as one point, and the measured data is recorded.

[0103] 4.8.4) Adjust the grid-type energy storage power station to the hot standby state, set the grid-type energy storage power station in the charging / discharging state, simulate the three-phase symmetrical fault of the line through the power grid simulation device to make the voltage drop to 0.2Un, and last for 10s. Measure the timing power at the grid-type energy storage power station connection point, take the average power value every 0.2s as one point, record the measured data, and verify whether the total current of the grid-type energy storage power station can reach 3 times the rated current and last for 10s.

[0104] The step 4.9) rated energy and conversion efficiency test includes the following sub-steps: 4.9.1) Rated energy test, the specific steps of the test method are as follows: a. Discharge at rated power until the discharge termination condition is reached and then stop discharging; b. Stop charging when charging reaches the charging termination condition at rated power. Record the energy Ec and auxiliary energy consumption Wc of the grid-connected energy storage power station during this charging process; c. Discharge at rated power until the discharge termination condition is reached and then stop discharging. Record the energy En and auxiliary energy consumption Wn of the grid-type energy storage power station during this discharge process; d. Repeat steps b) to c) twice, and record the charge and discharge energy Ec, En and auxiliary energy consumption Wc, Wn each time; e. Calculate the average value according to the formula, and record Ec and En as the rated charging energy and rated discharging energy of the grid-type energy storage power station.

[0105] f. Repeat steps a) to e) at 1C and 0.5C rates.

[0106] 4.9.2) Rated power conversion efficiency test, the specific steps of the test method are as follows: a. Discharge at rated power until the discharge termination condition is reached and then stop discharging; b. Stop charging when charging reaches the charging termination condition at rated power. Record the energy Ec and auxiliary energy consumption Wc of the grid-connected energy storage power station during this charging process; c. Discharge at rated power until the discharge termination condition is reached and then stop discharging. Record the energy En and auxiliary energy consumption Wn of the grid-type energy storage power station during this discharge process; d. Repeat steps b) and c) twice, and record the charge and discharge energy Ec, En and auxiliary energy consumption Wc, Wn each time; e. Calculate the energy conversion efficiency according to the formula; f. Repeat steps a) to e) at 1C and 0.5C rates.

[0107] The step 4.10) of the power quality test includes the following sub-steps: a. RMS value of three-phase voltage during the test period; b. RMS value of three-phase current during the test period; c. The total distortion rate of the voltage waveform during the test period and the 95% probability statistical value; d. Total distortion rate of current waveform and 95% probability statistical value during the test period; e. The effective value of the fundamental wave and the 2-25th voltage harmonic components and 95% probability statistical values ​​during the test period; f. The fundamental wave effective value and 2-25th current harmonic components and 95% probability statistical values ​​during the test period; g. Unbalance of three-phase voltage at the measuring point during the test period; h. Long-term flicker value of voltage at the measuring point during the test period; i. Apparent power, active power, reactive power and power factor of the measuring point during the test period; j.Measure the DC component of three-phase current.

[0108] The step 4.11) black start test includes the following sub-steps: a. Turn off the switch of the entire station grid connection point, disconnect the load in the station, and close the transformer in the energy storage collection line in the station; b. A black start command is issued by the background or the co-control, and the energy storage converter starts automatically with no-load and zero-voltage of the upper transformer; c. Record the relevant waveforms. After the voltage stabilizes, record the effective value of the line voltage, frequency value, and three-phase voltage imbalance.

[0109] The step 5) and the grid-connected energy storage system / power station joint operation test method include the following sub-steps: 5.1) Joint operation test of grid-connected and grid-building energy storage systems; 5.2) Joint operation test of grid-connected and grid-building energy storage power stations.

[0110] The step 5.1) joint operation test of the grid-following and grid-building energy storage systems includes the following sub-steps: 5.1.1) Active power control test; 5.1.2) Automatic generation control (AGC) test; 5.1.3) Reactive power control test; 5.1.4) Automatic voltage control (AVC) test; 5.1.5) One frequency modulation test; 5.1.6) Test the switching between follow / build network mode.

[0111] The step 5.1.1) of active power control test includes the following sub-steps: 5.1.1.1) Power test: a. Set the active power of the energy storage power station operated in conjunction with the grid to 0; b. Adjust the active power setting value step by step to 0, -0.25 P N , -0.5 P N , -0.75 P N , -P N 、-0.75P N 、-0.5P N 、-0.25P N , 0, each power setting value runs continuously for 30 seconds, and the measured data is recorded; c. Calculate the response time, regulation time and control deviation of active power control.

[0112] 5.1.1.2) Power reduction test a. Set the active power of the energy storage power station operated in conjunction with the grid to P N ; b. Adjust the active power setting value step by step to 0, 0.25 P N , 0.5 P N , 0.75P N , P N , 0.75P N , 0.5 P N , 0.25P N , 0, each power setting value runs continuously for 30 seconds, and the measured data is recorded; c. Calculate the response time, regulation time and control deviation of active power control.

[0113] The step 5.1.2) Automatic Generation Control (AGC) test includes the following sub-steps: a. Set the active power of the energy storage power station operated in conjunction with the grid to 0; b. The dispatcher manually issues the AGC load command and adjusts the active power setting value to 0.25P step by step N , 0.5P N , 0.75P N , P N , 0.75P N , 0.5P N , 0.25P N , 0; c. Record the load of the unit; d. Set the active power of the energy storage power station operated in conjunction with the grid to 0; e. The dispatcher manually issues the AGC load command and adjusts the active power setting value to -0.25P step by step N 、-0.5P N 、-0.75P N , -P N 、-0.75P N 、-0.5P N 、-0.25P N , 0; f. Record the unit load conditions.

[0114] The reactive power regulation capability test of step 5.1.3) includes the following sub-steps: 5.1.3.1) Reactive power regulation capability test a. Set the active charging power of the energy storage power station operated in conjunction with the grid to P N ; b. The energy storage power station operated in conjunction with the regulation / grid is operated in the maximum inductive reactive power output working mode; c. Measure the time-series power at the grid connection point of the energy storage power station that operates in conjunction with the grid / construction grid, record the active power and reactive power for at least 30 seconds, take the average power value every 0.2 seconds as one point, and calculate the average active power and reactive power within the second 15 seconds; d. Adjust the active power of the energy storage power station in joint operation with the grid to 0.9P N , 0.8P N , 0.7P N , 0.6P N , 0.5P N , 0.4P N , 0.3P N , 0.2P N , 0.1P N , 0, repeat steps b) to c); e. Adjust the energy storage power station operated in conjunction with the grid to operate in the maximum capacitive reactive power output mode, and repeat steps c) to d); f. With active power as the horizontal axis and reactive power as the vertical axis, draw the power envelope diagram of the energy storage power station jointly operated with the grid; g. The energy storage power station operated in conjunction with the adjustment / grid is in discharge mode with active power P N Discharge and repeat steps b) to f).

[0115] 5.1.3.2) Power factor regulation capability test a. Adjust the active power of the energy storage power station operated in conjunction with the grid to 0.25P N , 0.5P N , 0.75P N , P N Four points; b. Adjust the power factor of the energy storage power station operated in conjunction with the grid from leading 0.95 to lagging 0.95, with the adjustment range not exceeding 0.01, and measure and record the actual output power factor of the energy storage power station operated in conjunction with the grid; c. Adjust the charging active power of the energy storage power station operated in conjunction with the grid to 0.25P N , 0.5P N , 0.75P N , P N Four points; d. Adjust the power factor of the energy storage power station that operates in conjunction with the grid from leading 0.95 to lagging 0.95, with an adjustment range of no more than 0.01, and measure and record the actual output power factor of the energy storage power station that operates in conjunction with the grid.

[0116] The step 5.1.4) of the automatic voltage control (AVC) test includes the following sub-steps: a. Check the AGC interface information and record it; b. Issue a discharge command at rated power to the energy storage power station operating in conjunction with the grid / grid, and run continuously for 2 minutes; c. Use the data acquisition device to collect the current, voltage and power of the test point and draw a real-time power curve; d. Calculate the response time, regulation time and control accuracy of active power; e. Issue a discharge command at rated power to the energy storage power station operating in conjunction with the grid / grid, and run continuously for 2 minutes; f. Record the operating status of the energy storage power station after receiving the signal.

[0117] The step 5.1.5) of a frequency modulation test includes the following sub-steps: 5.1.5.1) Primary frequency modulation dead zone test a. Set the primary frequency modulation parameters of the energy storage power station that operates in conjunction with the grid, and connect the energy storage power station that operates in conjunction with the grid and related testing and measuring equipment; b. Adjust the energy storage power station operated in conjunction with the grid to P N Constant power discharge to the discharge cut-off condition of the energy storage power station in joint operation with the grid; c. Energy storage power stations that operate in conjunction with the grid shall be no less than 20%P N Charging; d. Gradually increase the grid connection point frequency value in steps of 0.01 Hz until the active power starts to change regularly. Run each frequency setting value for 5 seconds and record the output frequency value at the time when the active power changes regularly during the frequency disturbance process; e. Gradually reduce the grid connection point frequency value in steps of 0.01 Hz until the active power starts to change regularly. Run each frequency setting value for 5 seconds and record the output frequency value at the time when the active power changes regularly during the frequency disturbance process; f. Repeat d) to f); g. Adjustment and / or grid-connected energy storage power station with P N Constant power charging until the charging cut-off condition of the energy storage power station jointly operated with the grid; h. The energy storage power station operated in conjunction with the regulation / grid shall be no less than 20%P N Discharge is performed; i. Repeat d) to f).

[0118] 5.1.5.2) Frequency step disturbance test a. Connect the data acquisition device to the voltage transformer (PT) and current transformer (CT) at the test point, and connect the frequency signal generator to the energy storage power station monitoring system that operates in conjunction with the grid; b. Adjust the energy storage power station operated in conjunction with the grid to P N Constant power discharge to the discharge cut-off condition of the energy storage power station in joint operation with the grid; c. The energy storage power station operated in conjunction with the grid is charged under the unlimited power and limited power operation states, and the active power is charged according to the operation state and power range of the energy storage power station operated in conjunction with the grid in Table 2; d. Use the frequency signal generator to output the frequency step disturbance signal according to Table 13, and test each working condition twice; e. Record voltage, current, frequency and power values ​​during the test; f. Calculate the primary frequency modulation response lag time, rise time, adjustment time and active power control deviation; g. Adjustment and / or grid-connected energy storage power station with PN Constant power charging until the energy storage station charging cut-off condition; h. The energy storage power station operated in conjunction with the grid is charged under the unlimited power and limited power operation states with active power according to the energy storage power station operation state and power range in Table 2; i. Use the frequency signal generator to output the frequency step disturbance signal according to Table 13, and test each working condition twice; j. Record voltage, current, frequency and power values ​​during the test; k. Calculate the primary frequency modulation response lag time, rise time, regulation time and active power control deviation.

[0119] 5.1.5.3) Primary FM limit test a. Connect the data acquisition device to the voltage transformer (PT) and current transformer (CT) at the test point, and connect the frequency signal generator to the energy storage power station monitoring system; b. Adjust the energy storage power station operated in conjunction with the grid to P N Constant power discharge to the energy storage power station discharge cut-off condition; c. The energy storage power station operated in conjunction with the regulation / grid is 20%P N Charging; d. Set the frequency value of the grid connection point to gradually increase in steps of 0.01Hz until the active power reaches the limit value and stops changing. Each frequency setting value runs for 5s. The maximum frequency difference step should not exceed ±0.5Hz. Record the output frequency value at the time when the active power changes regularly during the frequency disturbance process. e. Set the frequency value of the grid connection point to be gradually reduced in steps of 0.01Hz until the active power reaches the limit value and stops changing. Each frequency setting value runs for 5s. The maximum frequency difference step should not exceed ±0.5Hz. Record the output frequency value at the time when the active power changes regularly during the frequency disturbance process. f. Adjustment and / or grid-connected energy storage power station with P N Constant power charging until the energy storage station charging cut-off condition; g. Adjust the energy storage power station operated in conjunction with the grid at 20%P N Discharge is performed; h. Repeat steps d) to g).

[0120] The step 5.1.6) of the network mode switching test includes the following sub-steps: 5.1.6.1) Test of switching from network construction mode to network following mode a. The energy storage power station operated in conjunction with regulation and grid construction operates in grid construction mode; b. Adjust the energy storage power station operated in conjunction with the grid to 50%P NDischarge and run continuously for 3 minutes; c. Switch the energy storage power station mode of joint operation with / building the grid to the grid operation mode; d. Record the voltage, current and power of the energy storage power station connected to the grid in joint operation with the grid; e. Conduct phase angle jump tolerance test; f. Record the status of the energy storage power station in joint operation with the grid / grid, and confirm whether the energy storage power station has switched to the grid operation mode; g. Adjust the energy storage power station operated in conjunction with the grid to 50%P N Discharge and run continuously for 3 minutes; h. Repeat steps c) to f).

[0121] 5.1.6.2) Test of switching from network following to network building mode a. The energy storage power station for regulating and following / building the grid operates in the following grid mode; b. Adjust the energy storage power station operated in conjunction with the grid to 50%P N Discharge and run continuously for 3 minutes; c. Switch the energy storage power station mode of joint operation with / with the grid to the grid operation mode; d. Record the voltage, current and power of the energy storage power station connected to the grid in joint operation with the grid; e. Conduct phase angle jump tolerance test; f. Record the status of the energy storage power station that is jointly operated with the grid and confirm whether the energy storage power station that is jointly operated with the grid is No, switch to the network operation mode; g. Adjust the energy storage power station operated in conjunction with the grid to 50%P N Discharge and run continuously for 3 minutes; h. Repeat steps c) to f).

[0122] The step 5.2) of the joint operation test of the grid-connected and grid-connected energy storage power stations includes the following sub-steps: 5.2.1) Active power control test; 5.2.2) Automatic generation control (AGC) test; 5.2.3) Reactive power control test; 5.2.4) Automatic Voltage Control (AVC) test; 5.2.5) One frequency modulation test; 5.2.6) Test the switching between follow / build network mode.

[0123] The step 5.2.1) of active power control test includes the following sub-steps: 5.2.1.1) Power test a. Set the active power of multiple grid-connected / grid-connected energy storage power stations to 0; b. Adjust the active power setting value step by step to 0, -0.25 P N , -0.5 P N , -0.75 P N , -P N 、-0.75P N、 -0.5P N 、-0.25P N , 0, each power setting value runs continuously for 30 seconds, and the measured data is recorded; c. Calculate the response time, regulation time and control deviation of active power control.

[0124] 5.2.1.2) Power reduction test a. Set multiple grid-connected / grid-connected energy storage power stations with active power of P N ; b. Adjust the active power setting value step by step to 0, 0.25 P N , 0.5 P N , 0.75P N , P N , 0.75P N , 0.5 P N , 0.25P N , 0, each power setting value runs continuously for 30 seconds, and the measured data is recorded; c. Calculate the response time, regulation time and control deviation of active power control.

[0125] The step 5.2.2) Automatic Generation Control (AGC) test includes the following sub-steps: a. Set the active power of multiple grid-connected / grid-connected energy storage power stations to 0; b. The dispatcher manually issues the AGC load command and adjusts the active power setting value to 0.25P step by step N , 0.5P N , 0.75P N , P N , 0.75P N , 0.5P N , 0.25P N , 0; c. Record the load of the unit; d. Set the active power of multiple grid-connected / grid-connected energy storage power stations to 0; e. The dispatcher manually issues the AGC load command and adjusts the active power setting value to -0.25P step by step N 、-0.5P N , -0.75P N , -P N 、-0.75P N 、-0.5P N 、-0.25P N , 0; f. Record the unit load conditions.

[0126] The reactive power regulation capability test of step 5.2.3) includes the following sub-steps: 5.2.3.1) Reactive power regulation capability test a. Set multiple grid-connected / grid-connected energy storage power stations with charging active power of P N ; b. Adjust multiple grid-connected / grid-connected energy storage power stations to operate in the maximum inductive reactive power output working mode; c. Measure the time-series power at multiple grid-connected / grid-connected energy storage power stations, record the active power and reactive power for at least 30 seconds, take the average power value every 0.2 seconds as one point, and calculate the average active power and reactive power within the next 15 seconds; d. Adjust the charging active power of multiple follow-up / grid energy storage power stations to 0.9P N , 0.8P N , 0.7P N , 0.6P N , 0.5P N , 0.4P N , 0.3P N , 0.2P N , 0.1P N , 0, repeat steps b) to c); e. Adjust multiple grid-connected / grid-connected energy storage power stations to operate in the maximum capacitive reactive power output working mode, and repeat steps c) to d); f. Draw the power envelope diagram of the energy storage system with active power as the horizontal axis and reactive power as the vertical axis; g. Adjust multiple grid-connected / grid-connected energy storage power stations in discharge mode with active power P N Discharge and repeat steps b) to f).

[0127] 5.2.3.2) Power factor regulation capability test a. Adjust the discharge active power of multiple grid-connected / grid-connected energy storage power stations to 0.25P N , 0.5P N , 0.75P N , P N Four points; b. Adjust the power factors of multiple grid-connected / grid-connected energy storage power stations from leading 0.95 to lagging 0.95 continuously, with the adjustment range not exceeding 0.01, and measure and record the actual output power factors of multiple grid-connected / grid-connected energy storage power stations; c. Adjust the charging active power of multiple grid-connected / grid-connected energy storage power stations to 0.25P N , 0.5P N , 0.75P N , P N Four points; d. Adjust the power factors of multiple grid-connected / grid-connected energy storage power stations from leading 0.95 to lagging 0.95 continuously, with an adjustment range of no more than 0.01, and measure and record the actual output power factors of multiple grid-connected / grid-connected energy storage power stations.

[0128] The step 5.2.4) of the automatic voltage control (AVC) test includes the following sub-steps: a. Check the AGC interface information and record it; b. Issue discharge instructions at rated power to multiple grid-connected / connected energy storage power stations for continuous operation for 2 minutes; c. Use the data acquisition device to collect the current, voltage and power of the test point and draw a real-time power curve; d. Calculate the response time, regulation time and control accuracy of active power; e. Issue discharge instructions at rated power to multiple grid-connected / connected energy storage power stations for continuous operation for 2 minutes; f. Record the operating status of multiple networked / constructed energy storage power stations after receiving the signal.

[0129] The step 5.2.5) of a frequency modulation test includes the following sub-steps: 5.2.5.1) Primary frequency modulation dead zone test a. Set the primary frequency modulation parameters of multiple grid-connected / constructed energy storage power stations, and connect multiple grid-connected / constructed energy storage power stations and related testing and measuring equipment; b. Adjust multiple grid-connected / grid-connected energy storage power stations to P N Constant power discharge to multiple grid-connected / grid-connected energy storage power stations discharge cut-off conditions; c. Multiple grid-connected / grid-connected energy storage power stations with a capacity of no less than 20%P N Charging; d. Gradually increase the grid connection point frequency value in steps of 0.01 Hz until the active power starts to change regularly. Run each frequency setting value for 5 seconds and record the output frequency value at the time when the active power changes regularly during the frequency disturbance process; e. Gradually reduce the grid connection point frequency value in steps of 0.01 Hz until the active power starts to change regularly. Run each frequency setting value for 5 seconds and record the output frequency value at the time when the active power changes regularly during the frequency disturbance process; f. Repeat d) to f); g. Adjust multiple grid-connected / grid-connected energy storage power stations to P N Constant power charging to the charging cut-off conditions of multiple grid-connected / grid-connected energy storage power stations; h. Adjust multiple grid-connected / grid-connected energy storage power stations to not less than 20%P N Discharge is performed; i. Repeat d) to f).

[0130] 5.2.5.2) Frequency step disturbance test a. The data acquisition device is connected to the voltage transformer (PT) and current transformer (CT) of the test point, and the frequency signal generator is connected to multiple grid-connected / grid-connected energy storage power station monitoring systems; b. Adjust multiple grid-connected / grid-connected energy storage power stations to P N Constant power discharge to multiple grid-connected / grid-connected energy storage power stations discharge cut-off conditions; c. Multiple grid-connected / constructed energy storage power stations are charged under unlimited power and limited power operation conditions, and the active power is charged according to the operation conditions and power ranges of multiple grid-connected / constructed energy storage power stations in Table 14; d. Use the frequency signal generator to output the frequency step disturbance signal according to Table 14, and test each working condition twice; e. Record voltage, current, frequency and power values ​​during the test; f. Calculate the primary frequency modulation response lag time, rise time, adjustment time and active power control deviation; g. Adjust multiple grid-connected / grid-connected energy storage power stations to P N Constant power charging to the charging cut-off conditions of multiple grid-connected / grid-connected energy storage power stations; h Multiple grid-connected / constructed energy storage power stations are charged under unlimited power and limited power operation conditions, and the active power is charged according to the operation conditions and power ranges of multiple grid-connected / constructed energy storage power stations in Table 14; i. Use the frequency signal generator to output the frequency step disturbance signal according to Table 14, and test each working condition twice; j. Record voltage, current, frequency and power values ​​during the test; k. Calculate the primary frequency modulation response lag time, rise time, regulation time and active power control deviation.

[0131] 5.2.5.3) Primary FM limit test a. Connect the data acquisition device to the voltage transformer (PT) and current transformer (CT) at the test point, and connect the frequency signal generator to multiple grid-connected / grid-connected energy storage power station monitoring systems; b. Adjust multiple grid-connected / grid-connected energy storage power stations to P N Constant power discharge to the energy storage power station discharge cut-off condition; c. Adjust multiple grid-connected / grid-connected energy storage power stations to 20%P N Charging; d. Set the frequency value of the grid connection point to gradually increase in steps of 0.01Hz until the active power reaches the limit value and stops changing. Each frequency setting value runs for 5s. The maximum frequency difference step should not exceed ±0.5Hz. Record the output frequency value at the time when the active power changes regularly during the frequency disturbance process. e. Set the frequency value of the grid connection point to be gradually reduced in steps of 0.01Hz until the active power reaches the limit value and stops changing. Each frequency setting value runs for 5s. The maximum frequency difference step should not exceed ±0.5Hz. Record the output frequency value at the time when the active power changes regularly during the frequency disturbance process. f. Adjust multiple grid-connected / grid-connected energy storage power stations to P N Constant power charging until the energy storage station charging cut-off condition; g. Adjust multiple grid-connected / grid-connected energy storage power stations to 20%P N Discharge is performed; h. Repeat steps d) to g).

[0132] The step 5.2.6) of the network mode switching test includes the following sub-steps: 5.2.6.1) Test of switching from network construction to network following mode a. Adjust multiple grid-connected / grid-connected energy storage power stations to operate in grid-connected mode; b. Adjust multiple grid-connected / grid-connected energy storage power stations to 50%P N Discharge and run continuously for 3 minutes; c. Switch multiple grid-following / grid-building energy storage power station modes to grid-following operation mode; d. Record the voltage, current and power of multiple grid-connected energy storage power stations; e. Conduct phase angle jump tolerance test; f. Record the status of the energy storage power station and confirm whether the energy storage power station has switched to the grid-following operation mode; g. Adjust multiple grid-connected / grid-connected energy storage power stations to 50%P N Discharge and run continuously for 3 minutes; h. Repeat steps c) to f).

[0133] 5.2.6.2) Test of switching from network following to network building mode a. Adjust multiple grid-following / grid-building energy storage power stations to operate in grid-following mode; b. Adjust multiple grid-connected / grid-connected energy storage power stations to 50%P N Discharge and run continuously for 3 minutes; c. Switch multiple follow-up / grid-building energy storage power station modes to grid-building operation mode; d. Record the voltage, current and power of multiple grid-connected energy storage power stations; e. Conduct phase angle jump tolerance test; f. Record the status of multiple grid-connected / grid-connected energy storage power stations, and confirm whether multiple grid-connected / grid-connected energy storage power stations have switched to grid-connected operation mode; g. When adjusting multiple grid-connected / grid-connected energy storage power stations, use 50%P N Discharge and run continuously for 3 minutes; h. Repeat steps c) to f).

[0134] The present invention proposes a grid-connected testing method for a grid-connected energy storage power station that covers multiple levels and all scenarios. In view of the limitations of traditional testing methods, the present invention comprehensively considers various factors in the operation of the energy storage power station, including energy storage requirements in different scenarios, energy storage performance in different test scenarios, etc. In order to achieve comprehensive testing, we have adopted a variety of testing means and methods, including simulation, actual operation testing, etc. Through the testing method of the present invention, the performance of a grid-connected energy storage power station in different scenarios and working conditions can be effectively evaluated, providing strong support for the further development and application of energy storage technology.

[0135] The above technical features constitute the embodiments of the present invention, which have strong adaptability and implementation effect. Non-essential technical features can be added or reduced according to actual needs to meet the requirements of different situations.

Claims

1. A grid-connected test method for a multi-level and full-scenario grid-connected energy storage power station, characterized in that: include: Testing method for grid-building characteristics of grid-building energy storage units; Test method for coordinated control of multiple units of grid-connected energy storage; Testing method for grid-type energy storage power station-level grid-type characteristics; Basic grid-connected performance test method for grid-connected energy storage power stations; Test methods for joint operation of grid-following and grid-building energy storage systems / power stations.

2. The grid-connected testing method for a multi-level and full-scenario grid-connected energy storage power station according to claim 1 is characterized in that: The method for testing the networking characteristics of the networking type energy storage unit level includes the following sub-steps: 1.1) Frequency adaptability test; The frequency adaptability test in step 1.1) requires the grid-connected energy storage system to maintain operation within a frequency deviation of ±2 Hz; N Above and 0.3P N To 0.4P N Tests are carried out under charging or discharging conditions in the power range to verify the ability of the grid-connected energy storage system to withstand abnormal grid frequency; 1.2) One frequency modulation test; The step 1.2) of the primary frequency modulation test requires that the primary frequency modulation power response time of the grid-connected energy storage system should be less than 0.2s, and it should be able to be flexibly adjusted according to the access to the power grid; the primary frequency modulation active power adjustment deviation should not be greater than 2%; N Above and 0.3P N To 0.4P N The test is carried out under the power range, charging condition or discharging condition; the ability of the grid-connected energy storage system to output primary frequency modulation active power when the grid frequency deviates; The test content includes the following sub-steps: 1.2.1) One frequency modulation dead zone test; 1.2.2) Frequency step disturbance test; 1.2.3) One-time frequency modulation and amplitude limiting test; 1.3) Inertia response test; The inertia response test in step 1.3) requires that the maximum inertia time constant of the grid-type energy storage system is not less than 20 seconds, and the active power change ∆P I Should not be less than 10% P N , the response time should not be greater than 0.5s, and the error between the actual active power and the active power command should not exceed ±2%P N , and can be flexibly adjusted according to the needs of the access system; At 0.7P N Above and 0.3P N To 0.4P N Tests are carried out under charging or discharging conditions in the power range; verifying the ability of the grid-connected energy storage system to output active inertia response when the grid frequency deviates; 1.4) Damping control test; The damping control test in step 1.4) requires that the grid-connected energy storage system has an autonomous damping suppression function. When the system has a low-frequency oscillation of 0.2Hz to 2.5Hz, and the frequency oscillation amplitude of the grid-connected point is greater than 0.003Hz, the energy storage system should be able to suppress the oscillation. The active power change ∆P D The maximum value should not be less than 10% P N , and not more than 30% P N , the response time should not be greater than 0.5s, respectively at 0.7P N To 0.9P N and 0.3P N To 0.4P N Tests are carried out under charging or discharging conditions in the power range; verifying the damping control capability of the grid-connected energy storage system when the grid oscillates at a low frequency; 1.5) Phase jump test; The phase jump test in step 1.5) requires that the amplitude and phase angle of the voltage at the machine end of the grid-connected converter of the grid-connected energy storage system should have a certain maintenance capability in the steady state and transient process, be able to share the unbalanced power of the grid, and the power response time should not exceed 5ms; at 20%P N to 80% P N Tests are carried out under charging or discharging conditions in the power range; verifying the ability of the grid-connected energy storage system to quickly inject active power when the grid phase changes; 1.6) Voltage withstand test; The voltage tolerance test in step 1.6) requires that the terminal voltage of the grid-type energy storage system should be able to be flexibly adjusted within the range of 0 to 130% according to the needs of the system; N Above and 0.3P N To 0.4P N The test is carried out under the power range, charging condition or discharging condition; the low voltage tolerance, high voltage tolerance, continuous high voltage tolerance and continuous low voltage tolerance of the grid-type energy storage system are examined; 1.7) Overload capacity test; The above step 1.7) overload capacity test requires that the AC side current of the grid-type energy storage system should be able to operate continuously for a long time at 110% of the rated current, the continuous operation time should be no less than 2 minutes at 120% of the rated current, and the continuous operation time should be no less than 1 minute at 150% of the rated current, and it should have a short-term overload capacity of 300% of the rated current for 10 seconds; the energy storage system is connected to the public power grid, all parameters are adjusted to normal working conditions, and the overload capacity test is performed under charging or discharging conditions respectively; the overload capacity of the grid-type energy storage system is verified; The test content It includes the following sub-steps: 1.7.1) 1.1 times overload test; 1.7.2) 1.2 times overload test; 1.7.3) 1.5 times overload test; 1.7.4) 3 times overload test; 1.8) Network following and network building mode switching test; In the step 1.8) switching between the grid-following and grid-building modes, the grid-building energy storage system is connected to the public power grid, all parameters are adjusted to normal working conditions, and the grid-following and grid-building mode switching test is performed; the ability of the grid-building energy storage system to switch between the grid-following mode and the grid-building mode is verified; The test content It includes the following sub-steps: 1.8.1) Test the switching from network construction to network following mode; 1.8.2) Test the switching mode from following network to building network.

3. The grid-connected testing method for a multi-level, full-scenario grid-connected energy storage power station according to claim 1 or 2, characterized in that: The grid-type energy storage multi-unit coordinated control test method includes the following sub-steps: 2.1) Coordination test between network construction and network construction energy storage unit; The coordination test between the network building and the network building energy storage unit includes the following sub-steps: 2.1.1) Frequency adaptability test; The frequency adaptability test in step 2.1.1) requires that multiple grid-type energy storage units can maintain operation within a frequency deviation of ±2Hz; N Above and 0.3P N To 0.4P N Conduct tests under charging or discharging conditions in the power range; verify the ability of multiple grid-connected energy storage units to withstand abnormal grid frequency; 2.1.2) One frequency modulation test; The step 2.1.2) of the primary frequency modulation test requires that the response time of multiple grid-connected energy storage units should be less than 0.2s, and that they should be able to be flexibly adjusted according to the access to the power grid, and that the primary frequency modulation active power adjustment deviation should not be greater than 2%; N Above and 0.3P N To 0.4P N The test is carried out under the power range, charging condition or discharging condition; the coordination of the ability of multiple grid-connected energy storage units to output primary frequency modulation active power when the grid frequency deviates; the test content includes the following sub-steps: 2.1.2.1) One frequency modulation dead zone test; 2.1.2.2) Primary frequency modulation dynamic performance test; 2.1.2.3) One-time frequency modulation and amplitude limiting test; 2.1.3) Inertia response test; The inertia response test in step 2.1.3) requires that the maximum value of the inertia time constant of multiple grid-type energy storage units is not less than 20 seconds, and the active power change ∆P I Should not be less than 10% PN , the response time should not be greater than 0.5s, and the error between the actual active power and the active power command should not exceed ±2%P N , and can be flexibly adjusted according to the needs of the access system; At 0.7P N Above and 0.3P N To 0.4P N Conduct tests under charging or discharging conditions in the power range; verify the ability of multiple grid-connected energy storage units to output active inertia response when the grid frequency deviates; 2.1.4) Damping control test; The damping control test in step 2.1.4) requires that multiple grid-type energy storage units have autonomous damping suppression function. When the system has low-frequency oscillations of 0.2Hz to 2.5Hz, and the frequency oscillation amplitude of the grid-connected point is greater than 0.003Hz, multiple grid-type energy storage units should adjust the active power through additional damping control to suppress low-frequency oscillations. The active power change ∆P D The maximum value should not be less than 10%P N , and not more than 30%P N , the response time should not be greater than 0.5s, respectively at 0.7P N To 0.9P N and 0.3P N To 0.4P N Conduct tests in the power range, charging conditions or discharging conditions; verify the ability to suppress oscillations when low-frequency oscillations occur between multiple grid-type energy storage units; 2.1.5) Phase jump test; The phase jump test in step 2.1.5) requires that the amplitude and phase angle of the voltage at the terminal of the grid-connected converter of multiple grid-connected energy storage units should have a certain maintenance capability in the steady state and transient process, be able to share the unbalanced power of the grid, and the power response time should not exceed 5ms; at 20%P N To 80%P N Tests are carried out under charging or discharging conditions in the power range; verifying the ability of multiple grid-connected energy storage units to quickly inject active power when the grid phase jumps; 2.1.6) Voltage withstand capability test; The voltage tolerance test in step 2.1.6) requires that the terminal voltage of multiple grid-type energy storage units should be able to be flexibly adjusted within the range of 0 to 130% according to the needs of the system; N To 0.3P N and greater than 0.7P N Tests are carried out under charging or discharging conditions within the power range; the low voltage tolerance, high voltage tolerance, continuous high voltage tolerance, and continuous low voltage tolerance of multiple grid-type energy storage units are examined; 2.1.7) Overload capacity test; The overload capacity test of step 2.1.7) requires that the AC side current of multiple grid-type energy storage units should be able to operate continuously for a long time at 110% of the rated current, the continuous operation time should be no less than 2 minutes at 120% of the rated current, and the continuous operation time should be no less than 1 minute at 150% of the rated current, and have a short-term overload capacity of 300% of the rated current for 10 seconds; connect multiple grid-type energy storage units to the public power grid, adjust all parameters to normal working conditions, and perform overload capacity tests in the charging or discharging state respectively; verify the overload capacity of multiple grid-type energy storage units; The test content includes the following sub-steps: 2.1.7.1) 1.1 times overload test; 2.1.7.2) 1.2 times overload test; 2.1.7.3) 1.5 times overload test; 2.1.7.4) 3 times overload test; 2.2) Coordination test of grid-building and grid-following energy storage units; The coordination test of the network construction and the grid-following energy storage unit includes the following sub-steps: 2.2.1) Frequency adaptability test; The frequency adaptability test in step 2.2.1) requires that the grid-building and grid-following energy storage units can maintain operation within a frequency deviation of ±2Hz; N Above and 0.3P N To 0.4P N Tests are carried out under charging or discharging conditions in the power range to verify the ability of the grid-building and grid-following energy storage units to withstand frequency anomalies in the grid; 2.2.2) One frequency modulation test; The primary frequency modulation test in step 2.2.2) requires that the response time of the grid-building and grid-following energy storage units should be less than 0.2s, and that they should be able to be flexibly adjusted according to the access to the grid. The primary frequency modulation active power adjustment deviation should not be greater than 2%. N Above and 0.3P N To 0.4P N The test is carried out under charging or discharging conditions in the power range of the power grid; the coordination of the ability of the grid-building and grid-following energy storage units to output primary frequency modulation active power when the grid frequency deviates is examined; the test content includes the following sub-steps: 2.2.2.1) One frequency modulation dead zone test; 2.2.2.2) Primary frequency modulation dynamic performance test; 2.2.2.3) One-time frequency modulation and amplitude limiting test; 2.2.3) Inertia response test; The inertia response test in step 2.2.3) requires that the maximum inertia time constant of the grid-building and grid-following energy storage units should be no less than 20 seconds, and the active power change ∆P I Should not be less than 10% P N , the response time should not be greater than 0.5s, and the error between the actual active power and the active power command should not exceed ±2%P N , and can be flexibly adjusted according to the needs of the access system; At 0.7P N Above and 0.3P N To 0.4P N Tests are carried out under charging or discharging conditions in the power range of the grid; verifying the ability of the grid-building and grid-following energy storage units to output active inertia response when the grid frequency deviates; 2.2.4) Damping control test; The damping control test in step 2.2.4) requires that the grid-building and grid-following energy storage units have autonomous damping suppression function. When the grid experiences low-frequency oscillation of 0.2Hz to 2.5Hz, and the frequency oscillation amplitude of the grid connection point is greater than 0.003Hz, the grid-building and grid-following energy storage units should adjust the active power through additional damping control to suppress the low-frequency oscillation. The active power change ∆P D The maximum value should not be less than 10%P N , and not more than 30%P N , the response time should not be greater than 0.5s, respectively at 0.7P N To 0.9P N and 0.3P N To 0.4P N Tests are carried out under charging or discharging operating conditions in the power range of the grid; verify the ability to suppress oscillations when low-frequency oscillations occur between the grid-building and grid-following energy storage units; 2.2.5) Phase jump test; The phase jump test in step 2.2.5) requires that the amplitude and phase angle of the voltage at the terminal of the grid-forming converter and the grid-following energy storage unit should have a certain maintenance capability in the steady state and transient process, be able to share the unbalanced power of the grid, and the power response time should not exceed 5ms; at 20%P N to 80% P N Tests are carried out under charging or discharging conditions in the power range of the grid; verifying the ability of the grid-building and grid-following energy storage units to quickly inject active power when the grid phase jumps; 2.2.6) Voltage withstand capability test; The voltage tolerance test in step 2.2.6) requires that the terminal voltage of the grid-connecting and grid-following energy storage units should be able to be flexibly adjusted within the range of 0 to 130% according to the needs of the system; N Above and 0.3P N To 0.4P N The test is carried out under charging or discharging conditions within the power range; the low voltage tolerance, high voltage tolerance, continuous high voltage tolerance and continuous low voltage tolerance of the grid-building and grid-following energy storage units are examined; 2.2.7) Overload capacity test; The overload capacity test in step 2.2.7) requires that the AC side current of the grid-connecting and grid-following energy storage units should be able to operate continuously for a long time at 110% of the rated current, and the continuous operation time should be no less than 2 minutes at 120% of the rated current; Connect the energy storage system to the public grid, adjust all parameters to normal working conditions, and perform overload capacity tests in the charging or discharging state; verify the overload capacity of the grid-building and grid-following energy storage units; The test content includes the following sub-steps: 2.2.7.1) 1.1 times overload test; 2.2.7.2) 1.2 times overload test; 2.2.7.3) 1.5 times overload test; 2.2.7.4) 3 times overload test.

4. The grid-connected testing method for a multi-level, full-scenario grid-connected energy storage power station according to claim 1, 2 or 3, characterized in that: The method for testing the grid-building characteristics of a grid-building type energy storage power station comprises the following sub-steps: 3.1) Frequency adaptability test; The frequency adaptability test in step 3.1) requires the grid-connected energy storage power station to maintain operation within a frequency deviation of ±2Hz; N Above and 0.3P N To 0.4P N Tests are carried out under charging or discharging conditions in the power range of the grid; verifying the ability of the grid-type energy storage power station to withstand abnormal grid frequency; 3.2) One frequency modulation test; The primary frequency modulation test in step 3.2) requires that the primary frequency modulation power response time of the grid-connected energy storage power station should be less than 0.2s, and it should be able to be flexibly adjusted according to the access to the grid; the primary frequency modulation active power adjustment deviation should not be greater than 2%; N Above and 0.3P N To 0.4P N The test is carried out under the power range, charging condition or discharging condition; the ability of the grid-type energy storage power station to output primary frequency modulation active power when the grid frequency deviates; The test content includes the following sub-steps: 3.2.1) One frequency modulation dead zone test; 3.2.2) Frequency step disturbance test; 3.2.3) One-time frequency modulation and amplitude limiting test; 3.3) Inertia response test; The inertia response test in step 3.3) requires a network type Energy storage power station The maximum value of the inertia time constant is not less than 20 seconds, and the active power change ∆P I Should not be less than 10% P N, the response time should not be greater than 0.5s, and the error between the actual active power and the active power command should not exceed ±2%P N , and can be flexibly adjusted according to the needs of access to the power station; At 0.7P N Above and 0.3P N To 0.4P N Tests are carried out under charging or discharging conditions in the power range of the grid; verifying the ability of the grid-connected energy storage power station to output active inertia response when the grid frequency deviates; 3.4) Damping control test; The damping control test in step 3.4) requires that the grid-connected energy storage power station has an autonomous damping suppression function. When the power station has a low-frequency oscillation of 0.2Hz to 2.5Hz, and the frequency oscillation amplitude of the grid-connected point is greater than 0.003Hz, the energy storage should be able to suppress the oscillation, and the active power change ∆P D The maximum value should not be less than 10% P N , and not more than 30% P N , the response time should not be greater than 0.5s, respectively at 0.7P N To 0.9P N and 0.3P N To 0.4P N Tests are carried out under charging or discharging conditions in the power range of the power grid; verifying the damping control capability of the grid-connected energy storage power station when the grid oscillates at a low frequency; 3.5) Phase jump test; The phase jump test in step 3.5) requires that the amplitude and phase angle of the voltage at the machine end of the grid-connected energy storage power station in the steady state and transient process should have a certain maintenance ability, be able to share the unbalanced power of the grid, and the power response time should not exceed 5ms; at 20%P N to 80% P N Tests are carried out under charging or discharging conditions in the power range of the grid; verifying the ability of the grid-connected energy storage power station to quickly inject active power when the grid phase jumps; 3.6) Voltage withstand test; The voltage tolerance test in step 3.6) requires that the terminal voltage of the grid-type energy storage power station should be able to be flexibly adjusted within the range of 0 to 130% according to the needs of the power station; N Above and 0.3P N To 0.4P N Tests are carried out under charging or discharging conditions within the power range; the low voltage tolerance, high voltage tolerance, continuous high voltage tolerance, and continuous low voltage tolerance of the grid-type energy storage power station are examined; 3.7) Overload capacity test; The above step 3.7) overload capacity test requires that the AC side current of the grid-type energy storage power station should be able to operate continuously for a long time at 110% of the rated current, the continuous operation time should be no less than 2 minutes at 120% of the rated current, and the continuous operation time should be no less than 1 minute at 150% of the rated current, and it should have a short-term overload capacity of 300% of the rated current for 10 seconds; the energy storage power station is connected to the public power grid, all parameters are adjusted to normal working conditions, and the overload capacity test is performed under charging or discharging conditions respectively; the overload capacity of the grid-type energy storage power station is verified; The test content It includes the following sub-steps: 3.7.1) 1.1 times overload test; 3.7.2) 1.2 times overload test; 3.7.3) 1.5 times overload test; 3.7.4) 3 times overload test; 3.8) Network following and network building mode switching test; Step 3.8) Switching between the grid-following and grid-building modes: connecting the grid-building energy storage power station to the public grid, adjusting all parameters to normal working conditions, and performing a grid-following and grid-building mode switching test; verifying the ability of the grid-building energy storage power station to switch between the grid-following mode and the grid-building mode; The test content includes the following sub-steps: 3.8.1) Test the switching from network construction to network following mode; 3.8.2) Test the switching mode from following network to building network.

5. The grid-connected testing method for a multi-level, full-scenario grid-connected energy storage power station according to claim 1, 2, 3 or 4, characterized in that: The basic grid-connected performance test method of the grid-connected energy storage power station includes the following sub-steps: 4.1) Active power control test; In step 4.1) active power control test, the grid-type energy storage power station is connected to the public power grid, all parameters are adjusted to normal working conditions, and the active power regulation capability test is performed in the grid-type control mode; the active power control accuracy, active power command response, and regulation time of the grid-type energy storage power station are examined; The test content includes the following sub-steps: 4.1.1) Power test; 4.1.2) Power reduction test; 4.2) Automatic power generation control test; The step 4.2) automatic power generation control test requires the grid-type energy storage power station to receive and respond to the AGC command sent by the dispatcher; connect the grid-type energy storage power station to the public power grid, adjust all parameters to normal working conditions, and carry out the AGC test in the charging or discharging state; examine the active power control accuracy, active power command response, and adjustment time of the grid-type energy storage power station; 4.3) Reactive power regulation capability test; The reactive power regulation capability test in step 4.3 is to connect the grid-type energy storage power station to the public power grid, adjust all parameters to normal working conditions, and perform reactive power regulation capability test and power factor regulation capability test in the grid-type control mode; examine the reactive power regulation capability and power factor regulation capability of the grid-type energy storage power station in the grid-type control mode; the test content includes the following sub-steps: 4.3.1) Reactive power regulation capability test; 4.3.2) Power factor regulation capability test; 4.4) Automatic voltage control test; The step 4.4) automatic voltage control test requires the grid-type energy storage power station to receive and respond to the AVC command sent by the dispatcher; connect the grid-type energy storage power station to the public power grid, adjust all parameters to normal working conditions, and conduct the test under charging or discharging conditions; examine whether the grid-type energy storage power station has the automatic voltage control function; 4.5) Charge and discharge response time test; The step 4.5) charging and discharging response time test is to adjust the grid-type energy storage power station to the hot standby state, and then conduct tests in the charging or discharging state of the grid-type energy storage power station; the charging and discharging response time of the grid-type energy storage power station in the grid control mode is examined; the test content includes the following sub-steps: 4.5.1) Charging response time test; 4.5.2) Discharge response time test; 4.6) Charge and discharge adjustment time test; The step 4.6) charge and discharge adjustment time test is to adjust the grid-type energy storage power station to the hot standby state, and then conduct tests in the charging or discharging state of the energy storage power station; the charge and discharge adjustment time of the energy storage power station in the grid control mode is examined; the test content includes the following sub-steps: 4.6.1) Charge adjustment time test; 4.6.2) Discharge adjustment time test; 4.7) Charge and discharge conversion time test; The step 4.7) charge-discharge conversion time test, under rated power charge-discharge conditions, adjust the grid-type energy storage power station to a hot standby state, and perform a charge-to-discharge conversion time test; verify the charge-discharge conversion time of the grid-type energy storage power station under the grid control mode; 4.8) Overload capacity test; The overload capacity test in step 4.8) requires that the AC side current of the grid-type energy storage power station should be able to operate continuously for a long time at 110% of the rated current, the continuous operation time should be no less than 2 minutes at 120% of the rated current, and the continuous operation time should be no less than 1 minute at 150% of the rated current, and it should have a short-term overload capacity of 300% of the rated current for 10 seconds; the grid-type energy storage power station is connected to the public power grid, all parameters are adjusted to normal working conditions, and the overload capacity test is performed in the charging or discharging state respectively; the overload capacity of the grid-type energy storage power station is examined; the test content includes the following sub-steps: 4.8.1) 1.1 times overload test; 4.8.2) 1.2 times overload test; 4.8.3) 1.5 times overload test; 4.8.4) 3.0 times overload test; 4.9) Rated energy and conversion efficiency test; The step 4.9) rated energy and conversion efficiency test requires the grid-type energy storage power station to test the charging energy and discharging energy and rated power energy conversion efficiency of the grid-type energy storage power station under stable operation and rated power charging or discharging conditions; and examine the rated energy and rated energy conversion efficiency of the grid-type energy storage power station under the grid control mode; the test content includes the following sub-steps: 4.9.1) Rated energy test; 4.9.2) Rated power conversion efficiency test; 4.10) Power quality test; In step 4.10) the power quality test is to measure the grid-type energy storage power station in the charging or discharging state for three consecutive days; to examine the power quality of the grid-type energy storage power station in the grid control mode; the test content includes the following sub-steps: 4.10.1) Three-phase voltage unbalance test; 4.10.2) Harmonic test; 4.10.3) Voltage deviation test; 4.10.4) Voltage fluctuation and flicker test; 4.10.5) DC component test; 4.11) Black start test; The step 4.11) black start test requires that the grid-type energy storage power station has a black start function. During the black start period, there should be no obvious circulating current or oscillation problems between the converters, and the maximum deviation of the effective current value should not be greater than 5%; verifying the island grid self-starting capability of the grid-type energy storage power station converter.

6. The grid-connected testing method for a multi-level and full-scenario grid-connected energy storage power station according to any one of claims 1 to 5, characterized in that: The joint operation test method of the grid-connected energy storage power station includes the following sub-steps: 5.1) Joint operation test of grid-connected and grid-building energy storage systems; 5.2) Joint operation test of grid-connected and grid-building energy storage power stations.

7. The grid-connected testing method for a multi-level and full-scenario grid-connected energy storage power station according to claim 6 is characterized in that: The step 5.1) joint operation test of the grid-following and grid-building energy storage systems includes the following sub-steps: 5.1.1) Active power control test; 5.1.2) Automatic power generation control test; 5.1.3) Reactive power control test; 5.1.4) Automatic voltage control test; 5.1.5) One frequency modulation test; 5.1.6) Test the switching between network following and network building modes.

8. The grid-connected testing method for a multi-level and full-scenario grid-connected energy storage power station according to claim 7 is characterized in that: In step 5.1.1) active power control test, the energy storage power station operated in conjunction with the grid or the grid-building is connected to the public grid, all parameters are adjusted to normal working conditions, and power increase and power reduction tests are performed; the power control accuracy, response time and adjustment time of the energy storage power station operated in conjunction with the grid or the grid-building are examined; The step 5.1.2) automatic power generation control test requires the energy storage power station operated in conjunction with the grid or the grid-building to receive and respond to the AGC command sent by the dispatcher; the energy storage power station operated in conjunction with the grid or the grid-building is connected to the public grid, all parameters are adjusted to normal working conditions, and the AGC test is carried out in the charging or discharging state; the AGC control accuracy, response time and adjustment time of the energy storage power station operated in conjunction with the grid or the grid-building are examined; Step 5.1.3) reactive power regulation capability test: connect the energy storage power station operated in conjunction with the grid or the grid-building to the public grid, adjust all parameters to normal working conditions, and perform reactive power regulation capability test in charging or discharging mode; examine the reactive power control accuracy and power factor regulation capability of the energy storage power station operated in conjunction with the grid or the grid-building; The test content includes the following sub-steps: 5.1.3.1) Charging mode test; 5.1.3.2) Discharge mode test; 5.1.3.3) Power factor regulation capability test; The automatic voltage control test in step 5.1.4 requires the energy storage power station operated in conjunction with the grid or the grid-building to receive and respond to the AVC instruction sent by the dispatcher; the energy storage power station operated in conjunction with the grid or the grid-building is connected to the public grid, all parameters are adjusted to normal working conditions, and the AVC test is carried out in the charging or discharging state; the voltage control performance of the energy storage power station operated in conjunction with the grid or the grid-building in response to the AVC system is examined; the test content includes the following sub-steps: 5.1.4.1) Reactive power control test; 5.1.4.2) Voltage control test; The primary frequency modulation test in step 5.1.5) requires that the primary frequency modulation power response time of the energy storage power station in joint operation with the grid and the grid-building power station should be less than 0.2s, and can be flexibly adjusted according to the needs of the access system, and the primary frequency modulation active power adjustment deviation should not exceed 2%; N Above and 0.3P N To 0.4P N The test is carried out under charging or discharging conditions in the power range of the power grid; the coordination of the ability of the energy storage power station jointly operated with the grid and the grid to output primary frequency regulation active power when the grid frequency deviates; The step 5.1.6) network following and network building mode switching test includes the following sub-steps: 5.1.6.1) Test the switching from network construction to network following mode; 5.1.6.2) Test the switching mode from following network to building network.

9. The grid-connected testing method for a multi-level, full-scenario grid-connected energy storage power station according to claim 6, 7 or 8, characterized in that: The step 5.2) of the joint operation test of the grid-connected and grid-connected energy storage power stations includes the following sub-steps: 5.2.1) Active power control test; 5.2.2) Automatic power generation control test; 5.2.3) Reactive power control test; 5.2.4) Automatic voltage control test; 5.2.5) One frequency modulation test; 5.2.6) Test the switching between network following and network building modes.

10. The grid-connected testing method for a multi-level and full-scenario grid-connected energy storage power station according to claim 9 is characterized in that: In step 5.2.1) active power control test, multiple grid-connected and grid-building energy storage power stations are connected to the public grid, all parameters are adjusted to normal working conditions, and power increase and power reduction tests are performed; the power control accuracy, response time and adjustment time of multiple grid-connected and grid-building energy storage power stations are examined; The automatic generation control test of step 5.2.2) requires multiple grid-connected and grid-forming energy storage power stations to receive and respond to the AGC instructions sent by the dispatcher; multiple grid-connected and grid-forming energy storage power stations are connected to the public power grid, all parameters are adjusted to normal working conditions, and the AGC test is carried out in the charging or discharging state; the AGC control accuracy, response time and adjustment time of multiple grid-connected and grid-forming energy storage power stations are examined; The reactive power regulation capability test of step 5.2.3) is to connect multiple grid-connected and grid-forming energy storage power stations to the public grid, adjust all parameters to normal working conditions, and conduct reactive power regulation capability test in charging or discharging mode; examine the reactive power control accuracy and power factor regulation capability of multiple grid-connected and grid-forming energy storage power stations; The test content includes the following sub-steps: 5.2.3.1) Charging mode test; 5.2.3.2) Discharge mode test; 5.2.3.3) Power factor regulation capability test; The automatic voltage control test of step 5.2.4) requires multiple grid-connected and grid-forming energy storage power stations to receive and respond to the AVC instructions sent by the dispatcher; multiple grid-connected and grid-forming energy storage power stations are connected to the public power grid, all parameters are adjusted to normal working conditions, and the AVC test is carried out in the charging or discharging state; the voltage control performance of multiple grid-connected and grid-forming energy storage power stations in response to the AVC system is examined; the test content includes the following sub-steps: 5.2.4.1) Reactive power control test; 5.2.4.2) Voltage control test; The primary frequency modulation test in step 5.2.5) requires that the primary frequency modulation power response time of multiple grid-following and grid-building energy storage power stations should be less than 0.2s, and that they should be able to be flexibly adjusted according to the needs of the access system, and the primary frequency modulation active power adjustment deviation should not be greater than 2%; N and 0.3P N To 0.4P N The test was carried out under the power range of charging and discharging conditions; the coordination of the ability of multiple grid-following and grid-building energy storage power stations to output primary frequency regulation active power when the grid frequency deviates; The step 5.2.6) of the network following and network building mode switching test includes the following sub-steps: 5.2.6.1) Test the switching from network construction to network following mode; 5.2.6.2) Test the switching mode from following network to building network.