Earthwork analysis method and system based on airport site selection elevation data
By obtaining elevation data and building a high-precision TIN model, combined with the excavation and filling analysis tool, the problem of low calculation accuracy of earth and stone volume in airport site selection is solved, and more accurate calculation of earth and stone volume and three-dimensional display is achieved, reducing the construction of mountainous airports Project cost.
Patent Information
- Application Number
- CN202410944745.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-15
- Publication Date
- 2024-11-12
AI Technical Summary
During the airport site selection stage, it is difficult to obtain accurate terrain data, resulting in low accuracy in calculating the amount of earth and rock, affecting site selection decisions. Especially in the construction of mountainous airports, the cost of earthwork engineering may exceed 60% of the total cost.
By obtaining the elevation basic data of the area to be selected, high-precision contours are extracted using spatial interpolation, the TIN model is constructed and converted into a DEM model, and combined with the excavation and filling analysis tool, the amount of earth and stone can be calculated to achieve three-dimensional display and visualization.
It improves the accuracy and scientificity of the calculation of earth and rock volume, reduces uncertainty in site selection decisions, reduces project costs, and enhances the three-dimensional visualization effect before and after construction.
Smart Images

Figure CN118940363A_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the field of airport engineering technology, and in particular to an earthwork engineering analysis method and system based on airport site elevation data. Background Art
[0002] Mountain airports have complex terrain. In order to ensure the clearance of aircraft, obstacles near the proposed airport, especially on the take-off and landing routes, should be cleared. For mountain airports, earthwork is crucial, and its engineering costs may exceed 60% of the airport construction costs. Airport site selection is the first step in airport construction. During the airport site selection stage, it is generally necessary to compare three or more sites, and the amount of earthwork is an important indicator for considering the feasibility of airport site selection.
[0003] However, in the existing technology, it is usually difficult to obtain relatively accurate terrain data during the site selection stage, and the earthwork volume cannot be calculated or the calculation accuracy is extremely low, which directly affects the site selection decision of the airport. Therefore, it is particularly important to rationally calculate the earthwork volume during the site selection stage for the construction of mountain airport projects. Summary of the invention
[0004] To achieve the above objectives, this application provides the following technical solutions:
[0005] According to a first aspect of the present invention, the present invention claims protection for an earthwork engineering analysis method based on airport site elevation data, comprising:
[0006] Obtain basic elevation data of the area to be selected, extract multiple high-precision contour lines using spatial interpolation, and obtain the first contour line set;
[0007] Preprocessing the first contour line set, constructing a first TIN model of the area to be selected and converting it into a first DEM model;
[0008] Exporting the contour line set after packaging preprocessing as a CAD file, in which the terrain contour lines after construction design are made through the existing terrain contour lines in the CAD file;
[0009] Importing the terrain contour lines after construction design into ArcGIS to create a second TIN model after earthwork operations;
[0010] Converting the second TIN model after earthwork construction into a second DEM model and three-dimensionally displaying the first DEM model and the second DEM model;
[0011] Based on the first DEM model and the second DEM model, a cut and fill analysis tool is used to analyze and obtain the cut and fill earthwork volume.
[0012] Furthermore, the step of obtaining basic elevation data of the area to be selected and extracting a plurality of high-precision contour lines by spatial interpolation to obtain a first contour line set also includes:
[0013] Download the required digital elevation model DEM data of the excavated mountainous area in the site selection area from the geospatial data cloud platform;
[0014] The download accuracy of the digital elevation model DEM data is the first distance accuracy;
[0015] Determine the central meridian zone of the region, calculate the parameters required for projection change, and use the projection transformation function of ArcGIS to convert the downloaded digital elevation model DEM data from the geographic space coordinate system to the plane coordinate system;
[0016] Using a contour tool, extracting terrain contour lines of the digital elevation model DEM data;
[0017] The interval between the contour lines is set to a second distance.
[0018] Furthermore, the preprocessing of the first contour line set, constructing a first TIN model of the area to be selected and converting it into a first DEM model, further includes:
[0019] Performing spatial interpolation on the first contour line set to draw a second contour line set, wherein the second contour line set has a higher precision than the first contour line set;
[0020] Screening the second set of contour lines to delete contour lines whose length is shorter than a preset threshold or are partially unreasonable;
[0021] Using the smooth line tool in the toolbox to smooth the second contour line set after the screening process;
[0022] Based on the smoothed high-precision terrain data, the first TIN model of irregular triangulated network is created;
[0023] The first TIN model is converted into a DEM model, and ArcScene is used to achieve a high-precision three-dimensional display of the original terrain of the site area.
[0024] Furthermore, the exporting and packaging of the pre-processed contour line set is a CAD file, in which the terrain contour lines after construction design are made by using the existing terrain contour lines, and further includes:
[0025] The second contour line set data after smoothing is exported into a dwg file readable by CAD through a conversion tool;
[0026] Based on the clearance and topographic factors of the site, combined with the three-dimensional visualization effect of the original terrain, the terrain contour lines after construction design are made in the dwg file through the existing terrain contour lines.
[0027] Furthermore, the method of using a cut and fill analysis tool to analyze and obtain the cut and fill earthwork volume based on the first DEM model and the second DEM model also includes:
[0028] Based on the first DEM model and the second DEM model, the elevation change corresponding to the calculated pixel before and after the proposed design is calculated;
[0029] The area size of the pixel is obtained, and the amount of excavation or filling is calculated in combination with the corresponding elevation change.
[0030] According to a second aspect of the present invention, the present invention claims protection for an earthwork engineering analysis system based on airport site elevation data, comprising:
[0031] The contour extraction module obtains the basic elevation data of the area to be selected, extracts multiple high-precision contours using spatial interpolation, and obtains the first contour set;
[0032] A current status model building module preprocesses the first contour line set, builds a first TIN model of the area to be sited and converts it into a first DEM model;
[0033] A packaging module exports the packaged preprocessed contour line set as a CAD file, and in the CAD file, the terrain contour lines after construction design are made by using the existing terrain contour lines;
[0034] A construction model building module imports the terrain contour lines after construction design into ArcGIS to create a second TIN model after earthwork operations;
[0035] A three-dimensional display module, which converts the second TIN model after earthwork construction into a second DEM model and displays the first DEM model and the second DEM model in three dimensions;
[0036] The earthwork calculation module uses a cut and fill analysis tool to analyze the cut and fill earthwork volume based on the first DEM model and the second DEM model.
[0037] Furthermore, the contour extraction module further includes:
[0038] Download the required digital elevation model DEM data of the excavated mountainous area in the site selection area from the geospatial data cloud platform;
[0039] The download accuracy of the digital elevation model DEM data is the first distance accuracy;
[0040] Determine the central meridian zone of the region, calculate the parameters required for projection change, and use the projection transformation function of ArcGIS to convert the downloaded digital elevation model DEM data from the geographic space coordinate system to the plane coordinate system;
[0041] Using a contour tool, extracting terrain contour lines of the digital elevation model DEM data;
[0042] The interval between the contour lines is set to a second distance.
[0043] Furthermore, the current status model building module further includes:
[0044] Performing spatial interpolation on the first contour line set to draw a second contour line set, wherein the second contour line set has a higher precision than the first contour line set;
[0045] Screening the second set of contour lines to delete contour lines whose length is shorter than a preset threshold or are partially unreasonable;
[0046] Using the smooth line tool in the toolbox to smooth the second contour line set after the screening process;
[0047] Based on the smoothed high-precision terrain data, the first TIN model of irregular triangulated network is created;
[0048] The first TIN model is converted into a DEM model, and ArcScene is used to achieve a high-precision three-dimensional display of the original terrain of the site area.
[0049] Furthermore, the packaging module further includes:
[0050] The second contour line set data after smoothing is exported into a dwg file readable by CAD through a conversion tool;
[0051] Based on the clearance and topographic factors of the site, combined with the three-dimensional visualization effect of the original terrain, the terrain contour lines after construction design are made in the dwg file through the existing terrain contour lines.
[0052] Furthermore, the earthwork calculation module further includes:
[0053] Based on the first DEM model and the second DEM model, the elevation change corresponding to the calculated pixel before and after the proposed design is calculated;
[0054] The area size of the pixel is obtained, and the amount of excavation or filling is calculated in combination with the corresponding elevation change.
[0055] The present application relates to the field of airport engineering technology, and in particular to an earthwork engineering analysis method and system based on airport site selection elevation data, obtaining the basic elevation data of the area to be sited, extracting contour lines to obtain a first contour line set; constructing a first TIN model after preprocessing and converting it into a first DEM model; exporting and encapsulating the preprocessed contour line set as a CAD file, and making terrain contour lines after construction design through the existing terrain contour lines; importing ArcGIS to create a second TIN model after earthwork engineering operations and converting it into a second DEM model for three-dimensional display; combining with the cut and fill analysis tool for analysis to obtain the cut and fill earthwork volume. The present invention utilizes the existing DEM digital elevation model to extract the required terrain data of the site area, comprehensively considering the lack of existing terrain data for calculating earthwork engineering, the low accuracy of terrain data, etc., so that the earthwork calculation results are more scientific and reasonable, and the situation before and after the construction of the earthwork engineering is displayed in three dimensions, with a stronger visualization effect. BRIEF DESCRIPTION OF THE DRAWINGS
[0056] Figure 1 A workflow diagram of an earthwork engineering analysis method based on airport site elevation data as claimed in an embodiment of the present application;
[0057] Figure 2 A contour display diagram of an earthwork engineering analysis method based on airport site selection elevation data as claimed in an embodiment of the present application;
[0058] Figure 3 A schematic diagram of a first TIN model of an earthwork engineering analysis method based on airport site elevation data claimed in an embodiment of the present application;
[0059] Figure 4 A schematic diagram of a current terrain DEM model of an earthwork engineering analysis method based on airport site elevation data as claimed in an embodiment of the present application;
[0060] Figure 5 A three-dimensional visualization diagram of the current terrain of an earthwork engineering analysis method based on airport site elevation data as claimed in the embodiment of the present application;
[0061] Figure 6 A schematic diagram of a TIN model of terrain after cut and fill of an earthwork engineering analysis method based on airport site elevation data as claimed in an embodiment of the present application;
[0062] Figure 7 A three-dimensional visualization diagram of the post-design terrain of an earthwork engineering analysis method based on airport site elevation data as claimed in an embodiment of the present application;
[0063] Figure 8A schematic diagram showing a space for displaying cut-and-fill analysis of an earthwork engineering analysis method based on airport site elevation data as claimed in an embodiment of the present application;
[0064] Fig. 9 A structural module diagram of an earthwork engineering analysis system based on airport site elevation data, as claimed in an embodiment of the present application. DETAILED DESCRIPTION
[0065] The following will be combined with the drawings in the embodiments of the present application to clearly and completely describe the technical solutions in the embodiments of the present application. Obviously, the described embodiments are only part of the embodiments of the present application, not all of the embodiments. Based on the embodiments in the present application, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of this application.
[0066] The terms "first", "second" and "third" in this application are only used for descriptive purposes and cannot be understood as indicating or implying relative importance or implicitly indicating the number of indicated technical features. Therefore, the features defined as "first", "second" and "third" can explicitly or implicitly include at least one of the features. In the description of this application, the meaning of "multiple" is at least two, such as two, three, etc., unless otherwise clearly and specifically defined. All directional indications in the embodiments of the present application (such as up, down, left, right, front, back...) are only used to explain the relative position relationship, movement, etc. between the components under a certain specific posture (as shown in the accompanying drawings). If the specific posture changes, the directional indication also changes accordingly. In addition, the terms "including" and "having" and any of their variations are intended to cover non-exclusive inclusions. For example, a process, method, system, product or device that includes a series of steps or units is not limited to the listed steps or units, but optionally also includes steps or units that are not listed, or optionally also includes other steps or units inherent to these processes, methods, products or devices.
[0067] Reference to "embodiments" herein means that a particular feature, structure, or characteristic described in conjunction with the embodiments may be included in at least one embodiment of the present application. The appearance of the phrase in various locations in the specification does not necessarily refer to the same embodiment, nor is it an independent or alternative embodiment that is mutually exclusive with other embodiments. It is explicitly and implicitly understood by those skilled in the art that the embodiments described herein may be combined with other embodiments.
[0068] The earthwork volume of the site selection phase of a mountain airport can be as much as one million cubic meters compared to the earthwork volume calculated during the construction drawing phase. The difference between the estimated investment and the estimated investment is huge, which may eventually lead to errors in site selection decisions. The reason for this is that the time is tight during the site selection phase, and detailed terrain surveys and measurements cannot be carried out. Often, only low-precision terrain data can be used to estimate the earthwork volume. However, low-precision terrain data may not accurately reflect the actual terrain conditions, and even the use of a high-precision grid method will lead to large errors in the calculation of earthwork volume. Moreover, based on low-precision terrain data, the calculation of earthwork volume in the site selection phase is usually estimated by simplified calculation methods, which may not take into account the complexity and variability of the actual terrain, resulting in a certain degree of uncertainty in the estimation of earthwork volume.
[0069] According to the first embodiment of the present invention, the present invention claims a method for analyzing earthwork engineering based on airport site elevation data, referring to Figure 1 ,include:
[0070] Obtain basic elevation data of the area to be selected, extract multiple high-precision contour lines using spatial interpolation, and obtain the first contour line set;
[0071] Preprocessing the first contour line set, constructing a first TIN model of the area to be selected and converting it into a first DEM model;
[0072] Exporting the contour line set after packaging preprocessing as a CAD file, in which the terrain contour lines after construction design are made through the existing terrain contour lines in the CAD file;
[0073] Importing the terrain contour lines after construction design into ArcGIS to create a second TIN model after earthwork operations;
[0074] Converting the second TIN model after earthwork construction into a second DEM model and three-dimensionally displaying the first DEM model and the second DEM model;
[0075] Based on the first DEM model and the second DEM model, a cut and fill analysis tool is used to analyze and obtain the cut and fill earthwork volume.
[0076] Furthermore, the step of obtaining basic elevation data of the area to be selected and extracting a plurality of high-precision contour lines by spatial interpolation to obtain a first contour line set also includes:
[0077] Download the required digital elevation model DEM data of the excavated mountainous area in the site selection area from the geospatial data cloud platform;
[0078] The download accuracy of the digital elevation model DEM data is the first distance accuracy;
[0079] Determine the central meridian zone of the region, calculate the parameters required for projection change, and use the projection transformation function of ArcGIS to convert the downloaded digital elevation model DEM data from the geographic space coordinate system to the plane coordinate system;
[0080] Using a contour tool, extracting terrain contour lines of the digital elevation model DEM data;
[0081] The interval between the contour lines is set to a second distance.
[0082] Among them, in this embodiment, the required digital elevation model (DEM) data of the excavated mountain area is downloaded from a platform such as a geospatial data cloud, and the download accuracy is 30m (the highest downloadable accuracy);
[0083] Determine the central meridian area of the region, calculate the 7 parameters required for projection change through 91 bitmap and other software or applet, and use ArcGIS's projection transformation function to convert the downloaded current DEM data from the geographic space coordinate system to the CGCS2000 plane coordinate system, which can ensure higher accuracy in earthwork calculation;
[0084] The contour line tool in ArcToolbox was used to extract the terrain contour lines of the downloaded DEM, and the contour line interval was set to 10m;
[0085] Furthermore, the preprocessing of the first contour line set, constructing a first TIN model of the area to be selected and converting it into a first DEM model, further includes:
[0086] Performing spatial interpolation on the first contour line set to draw a second contour line set, wherein the second contour line set has a higher precision than the first contour line set;
[0087] Screening the second set of contour lines to delete contour lines whose length is shorter than a preset threshold or are partially unreasonable;
[0088] Using the smooth line tool in the toolbox to smooth the second contour line set after the screening process;
[0089] Based on the smoothed high-precision terrain data, the first TIN model of irregular triangulated network is created;
[0090] The first TIN model is converted into a DEM model, and ArcScene is used to achieve a high-precision three-dimensional display of the original terrain of the site area.
[0091] Among them, in this embodiment, in the local area of the terrain, the elevation correction is made by using the on-site measurement, and the contour lines less than 30m are screened out by using the line length attribute and deleted (this part of the contour lines is caused by the dem error);
[0092] ArcGIS software was used again to smooth the contour lines, and the final map was as follows: Figure 2 As shown;
[0093] Create a TIN model from the generated terrain contours, such as Figure 3 As shown;
[0094] Based on the first TIN model created, a new DEM model with improved accuracy (10m accuracy) is constructed, such as Figure 4 As shown;
[0095] Based on the current terrain DEM model, ArcScene software is used to realize the visualization of three-dimensional terrain. Figure 5 As shown;
[0096] Furthermore, the exporting and packaging of the pre-processed contour line set is a CAD file, in which the terrain contour lines after construction design are made by using the existing terrain contour lines, and further includes:
[0097] The second contour line set data after smoothing is exported into a dwg file readable by CAD through a conversion tool;
[0098] Based on the clearance and topographic factors of the site, combined with the three-dimensional visualization effect of the original terrain, the terrain contour lines after construction design are made in the dwg file through the existing terrain contour lines.
[0099] In this embodiment, the current contour lines are exported as dwg files, combined with the current three-dimensional topographic map (the bright color display of the area exceeding the clearance can be controlled, etc.), and then the clearance conditions and topography are comprehensively considered in CAD to perform preliminary terrain design on the current contour lines;
[0100] Read the proposed design contour lines in the dwg file format after the preliminary design changes into ArcGIS;
[0101] Construct the terrain TIN model after the proposed design, such as Figure 6 As shown;
[0102] The proposed TIN model is converted into a DEM model (10m accuracy), and the three-dimensional terrain is visualized using ArcScene software. Figure 7 As shown;
[0103] Furthermore, the method of using a cut and fill analysis tool to analyze and obtain the cut and fill earthwork volume based on the first DEM model and the second DEM model also includes:
[0104] Based on the first DEM model and the second DEM model, the elevation change corresponding to the calculated pixel before and after the proposed design is calculated;
[0105] The area size of the pixel is obtained, and the amount of excavation or filling is calculated in combination with the corresponding elevation change.
[0106] In this embodiment, the volume of earthwork for excavation and filling is calculated based on the current DEM data and the DEM data after the proposed design. The calculation principle is shown in Formula 1. In this example, the main design is excavation. Figure 8 As shown, the black area is the area that needs to be excavated, the white area is the area that needs to be filled (not available in this example), and the remaining gray areas have no excavation or filling.
[0107] V=[cell(area)]×ΔZ (Formula 1)
[0108] Where: V is the calculated earthwork volume (m 3 ); cell(area) is the area of a pixel to be calculated in the DEM data. In this example, the area of a single pixel is 100m 2 ; ΔZ is the elevation change (m) corresponding to the calculated pixel before and after the proposed design.
[0109] In addition, the cut and fill volume of each area can be calculated through the generated cut and fill spatial display map attribute table. In this example, the cut volume calculated for the two cut areas is 169200685.18m 3 and 1989704.91m 3 .
[0110] According to a second embodiment of the present invention, the present invention claims a system for analyzing earthwork engineering based on airport site elevation data, referring to Fig. 9 ,include:
[0111] The contour extraction module obtains the basic elevation data of the area to be selected, extracts multiple high-precision contours using spatial interpolation, and obtains the first contour set;
[0112] A current status model building module preprocesses the first contour line set, builds a first TIN model of the area to be sited and converts it into a first DEM model;
[0113] A packaging module exports the packaged preprocessed contour line set as a CAD file, and in the CAD file, the terrain contour lines after construction design are made by using the existing terrain contour lines;
[0114] A construction model building module imports the terrain contour lines after construction design into ArcGIS to create a second TIN model after earthwork operations;
[0115] A three-dimensional display module, which converts the second TIN model after earthwork construction into a second DEM model and displays the first DEM model and the second DEM model in three dimensions;
[0116] The earthwork calculation module uses a cut and fill analysis tool to analyze the cut and fill earthwork volume based on the first DEM model and the second DEM model.
[0117] Furthermore, the contour extraction module further includes:
[0118] Download the required digital elevation model DEM data of the excavated mountainous area in the site selection area from the geospatial data cloud platform;
[0119] The download accuracy of the digital elevation model DEM data is the first distance accuracy;
[0120] Determine the central meridian zone of the region, calculate the parameters required for projection change, and use the projection transformation function of ArcGIS to convert the downloaded digital elevation model DEM data from the geographic space coordinate system to the plane coordinate system;
[0121] Using a contour tool, extracting terrain contour lines of the digital elevation model DEM data;
[0122] The interval between the contour lines is set to a second distance.
[0123] Furthermore, the current status model building module further includes:
[0124] Performing spatial interpolation on the first contour line set to draw a second contour line set, wherein the second contour line set has a higher precision than the first contour line set;
[0125] Screening the second set of contour lines to delete contour lines whose length is shorter than a preset threshold or are partially unreasonable;
[0126] Using the smooth line tool in the toolbox to smooth the second contour line set after the screening process;
[0127] Based on the smoothed high-precision terrain data, the first TIN model of irregular triangulated network is created;
[0128] The first TIN model is converted into a DEM model, and ArcScene is used to achieve a high-precision three-dimensional display of the original terrain of the site area.
[0129] Furthermore, the packaging module further includes:
[0130] The second contour line set data after smoothing is exported into a dwg file readable by CAD through a conversion tool;
[0131] Based on the clearance and topographic factors of the site, combined with the three-dimensional visualization effect of the original terrain, the terrain contour lines after construction design are made in the dwg file through the existing terrain contour lines.
[0132] Furthermore, the earthwork calculation module further includes:
[0133] Based on the first DEM model and the second DEM model, the elevation change corresponding to the calculated pixel before and after the proposed design is calculated;
[0134] The area size of the pixel is obtained, and the amount of excavated earth and stone or the amount of filled earth and stone is calculated in combination with the corresponding elevation change.
[0135] In the several embodiments provided in the present application, it should be understood that the disclosed systems, devices and methods can be implemented in other ways. For example, the device embodiments described above are only schematic. For example, the division of units is only a logical function division. There may be other division methods in actual implementation. For example, multiple units or components can be combined or integrated into another system, or some features can be ignored or not executed. Another point is that the mutual coupling or direct coupling or communication connection shown or discussed can be an indirect coupling or communication connection through some interfaces, devices or units, which can be electrical, mechanical or other forms.
[0136] In addition, each functional unit in each embodiment of the present application can be integrated into one processing unit, or each unit can exist physically separately, or two or more units can be integrated into one unit. The above integrated unit can be implemented in the form of hardware or in the form of software functional units. The above is only an implementation method of the present application, and does not limit the patent scope of the present application. Any equivalent structure or equivalent process transformation made using the contents of the specification and drawings of this application, or directly or indirectly used in other related technical fields, is also included in the patent protection scope of the present application.
[0137] The specific implementation methods of the invention are described in detail above, but they are only examples, and the present application is not limited to the specific implementation methods described above. For those skilled in the art, any equivalent modification or substitution of the invention is also within the scope of the present application, and therefore, the equalization, modification, and improvement made without departing from the spirit and principle of the present application should be included in the scope of the present application.
Claims
1. An earthwork engineering analysis method based on airport site elevation data, characterized in that: include: Obtain basic elevation data of the area to be selected, extract multiple high-precision contour lines using spatial interpolation, and obtain the first contour line set; Preprocessing the first contour line set, constructing a first TIN model of the area to be selected and converting it into a first DEM model; Exporting the contour line set after packaging preprocessing as a CAD file, in which the terrain contour lines after construction design are made through the existing terrain contour lines in the CAD file; Importing the terrain contour lines after construction design into ArcGIS to create a second TIN model after earthwork operations; Converting the second TIN model after earthwork construction into a second DEM model and three-dimensionally displaying the first DEM model and the second DEM model; Based on the first DEM model and the second DEM model, a cut and fill analysis tool is used to analyze and obtain the cut and fill earthwork volume.
2. The earthwork engineering analysis method based on airport site elevation data according to claim 1 is characterized in that: The step of obtaining basic elevation data of the area to be selected and extracting a plurality of high-precision contour lines by spatial interpolation to obtain a first contour line set also includes: Download the required digital elevation model DEM data of the excavated mountainous area in the site selection area from the geospatial data cloud platform; The download accuracy of the digital elevation model DEM data is the first distance accuracy; Determine the central meridian zone of the region, calculate the parameters required for projection change, and use the projection transformation function of ArcGIS to convert the downloaded digital elevation model DEM data from the geographic space coordinate system to the plane coordinate system; Using a contour tool, extracting terrain contour lines of the digital elevation model DEM data; The interval between the contour lines is set to a second distance.
3. The earthwork engineering analysis method based on airport site elevation data according to claim 1 is characterized in that: The preprocessing of the first contour line set, constructing a first TIN model of the area to be selected and converting it into a first DEM model, further includes: Performing spatial interpolation on the first contour line set to draw a second contour line set, wherein the second contour line set has a greater accuracy than the first contour line set; Screening the second set of contour lines to delete contour lines whose length is shorter than a preset threshold or are partially unreasonable; Using the smooth line tool in the toolbox to smooth the second contour line set after the screening process; Based on the smoothed high-precision terrain data, the first TIN model of irregular triangulated network is created; The first TIN model is converted into a DEM model, and ArcScene is used to achieve a high-precision three-dimensional display of the original terrain of the site area.
4. The earthwork engineering analysis method based on airport site elevation data according to claim 3 is characterized in that: The export packaged pre-processed contour line set is a CAD file, in which the terrain contour lines after construction design are made by using the existing terrain contour lines, and further includes: The second contour line set data after smoothing is exported into a dwg file readable by CAD through a conversion tool; Based on the clearance and topographic factors of the site, combined with the three-dimensional visualization effect of the original terrain, the terrain contour lines after construction design are made in the dwg file through the existing terrain contour lines.
5. The earthwork engineering analysis method based on airport site elevation data according to claim 1 is characterized in that: The method of using a cut and fill analysis tool to analyze the cut and fill earthwork volume based on the first DEM model and the second DEM model further includes: Based on the first DEM model and the second DEM model, the elevation change corresponding to the calculated pixel before and after the proposed design is calculated; The area size of the pixel is obtained, and the amount of excavated earth and stone or the amount of filled earth and stone is calculated in combination with the corresponding elevation change.
6. An earthwork engineering analysis system based on airport site elevation data, characterized in that: include: The contour extraction module obtains the basic elevation data of the area to be selected, extracts multiple high-precision contours using spatial interpolation, and obtains the first contour set; A current status model building module preprocesses the first contour line set, builds a first TIN model of the area to be sited and converts it into a first DEM model; A packaging module exports the packaged preprocessed contour line set as a CAD file, and in the CAD file, the terrain contour lines after construction design are made by using the existing terrain contour lines; A construction model building module imports the terrain contour lines after construction design into ArcGIS to create a second TIN model after earthwork operations; A three-dimensional display module, which converts the second TIN model after earthwork construction into a second DEM model and displays the first DEM model and the second DEM model in three dimensions; The earthwork calculation module uses a cut and fill analysis tool to analyze the cut and fill earthwork volume based on the first DEM model and the second DEM model.
7. The earthwork engineering analysis system based on airport site elevation data according to claim 6 is characterized in that: The contour extraction module further includes: Download the required digital elevation model DEM data of the excavated mountainous area in the site selection area from the geospatial data cloud platform; The download accuracy of the digital elevation model DEM data is the first distance accuracy; Determine the central meridian zone of the region, calculate the parameters required for projection change, and use the projection transformation function of ArcGIS to convert the downloaded digital elevation model DEM data from the geographic space coordinate system to the plane coordinate system; Using a contour tool, extracting terrain contour lines of the digital elevation model DEM data; The interval between the contour lines is set to a second distance.
8. The earthwork engineering analysis system based on airport site elevation data according to claim 6 is characterized in that: The current situation model building module further includes: Performing spatial interpolation on the first contour line set to draw a second contour line set, wherein the second contour line set has a greater accuracy than the first contour line set; Screening the second set of contour lines to delete contour lines whose length is shorter than a preset threshold or are partially unreasonable; Using the smooth line tool in the toolbox to smooth the second contour line set after the screening process; Based on the smoothed high-precision terrain data, the first TIN model of irregular triangulated network is created; The first TIN model is converted into a DEM model, and ArcScene is used to achieve a high-precision three-dimensional display of the original terrain of the site area.
9. The earthwork engineering analysis system based on airport site elevation data according to claim 8, characterized in that: The packaging module further includes: The second contour line set data after smoothing is exported into a dwg file readable by CAD through a conversion tool; Based on the clearance and topographic factors of the site, combined with the three-dimensional visualization effect of the original terrain, the terrain contour lines after construction design are made in the dwg file through the existing terrain contour lines.
10. The earthwork engineering analysis system based on airport site elevation data according to claim 6, characterized in that: The earthwork calculation module further includes: Based on the first DEM model and the second DEM model, the elevation change corresponding to the calculated pixel before and after the proposed design is calculated; The area size of the pixel is obtained, and the amount of excavation or filling is calculated in combination with the corresponding elevation change.
Citation Information
Patent Citations
Earth volume measurement method and apparatus, computer device and storage medium
CN110657855A
Unmanned aerial vehicle naked eye 3D all-digital mapping method
CN115077490A
Earthwork volume calculation method based on unmanned aerial vehicle three-dimensional scanning live-action modeling
CN115909091A
Earthwork design support system using digital map data
JP2002081008A
Method of assisting detection of man-made structures in a digital elevation map (DEM)