Power distribution network topological structure evaluation method adapted to access of various distributed resources
The multi-attribute evaluation index system for the distribution network topology structure was established through entropy weight method and hierarchical analysis method, which solved the problem that the existing technology could not effectively analyze and optimize the access of multiple distributed resources, and achieved the optimization of the new distribution network topology structure. , improves the comprehensive performance of the distribution network.
Patent Information
- Application Number
- CN202410957398.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-17
- Publication Date
- 2024-11-12
AI Technical Summary
The existing technology cannot effectively analyze and optimize the access of multiple distributed resources (such as distributed small hydropower, distributed photovoltaics, energy storage and electric vehicles) in the new distribution network, resulting in the inability to achieve 'water and light charging and storage' collaboration. The topology of the distribution network operating is preferred.
The entropy weight method and hierarchical analysis method are used to establish a multi-attribute evaluation index system for the distribution network topology structure, including reliability, economy, open capacity and controllability indicators, and calculate the comprehensive score of the distribution network topology structure to select suitable ones. Topology.
The new distribution network topology structure of a variety of distributed resources has been optimized, the reliability, economy and controllability of the distribution network have been improved, and the needs of the "water and light charging and storage" access scenarios have been adapted.
Smart Images

Figure CN118941105A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the field of distribution network topology evaluation, and more specifically, to a distribution network topology evaluation method suitable for access of multiple distributed resources. Background Art
[0002] Under the background of the construction of new power systems, distributed clean energy represented by distributed photovoltaic and small hydropower has ushered in rapid development; by the end of 2023, the total installed capacity of photovoltaic power stations in China will be 608.92GW, of which distributed power will be 254.44GW, accounting for 42%. 42,400 small hydropower stations have been built in China, with a total installed capacity of more than 81 million kilowatts; at the same time, in order to reduce carbon emissions in the transportation industry, deep electrification of transportation has become a major development trend in the future. At present, the number of new energy vehicles in China has reached 20.41 million. Distributed hydropower, photovoltaic, electric vehicle charging network, various energy storage equipment and distribution network are deeply coupled, forming a new "water-light charging and storage" distribution network structure; different distribution network forms have different requirements for grid attributes such as economy and reliability. How to choose the optimal grid structure under differentiated requirements, while considering the future distributed source-load uncertainty, to adapt to the future distribution network scenario with multiple elements of water-light charging and storage, is an urgent problem to be solved.
[0003] For example, patent 202110307207.3 "A comprehensive evaluation method for distribution network grid structure considering load release" uses grid structure scoring and takes into account the impact of year-on-year load, but lacks analysis of the future distribution network access to distributed small hydropower, distributed photovoltaics, energy storage and electric vehicles; in the context of existing technology, it does not propose an evaluation index system that is suitable for new distribution networks, does not consider distribution network scenarios with multiple distributed resources access, and does not evaluate the topological structure adapted to different distributed resource structures of the distribution network. It cannot effectively analyze the impact of distributed small hydropower, distributed photovoltaics, energy storage and electric vehicles on the topological structure, and cannot achieve the optimization of new distribution network topological structures that consider the coordinated operation of "hydropower, photovoltaics, charging and storage" in the future. Summary of the invention
[0004] The purpose of the present invention is to provide a distribution network topology structure evaluation method that is adaptable to the access of multiple distributed resources, and to the evaluation of the distribution network topology structure that is adaptable to the access of "hydropower, photovoltaic, charging and storage". On the basis of traditional reliability and economic evaluation indicators, as well as newly added topological structure, open capacity and controllability indicators, a new distribution network topology structure multi-attribute evaluation index system is established, and the entropy weight method and hierarchical analysis method are used to calculate various indicators under various distribution network scenarios, thereby realizing the optimization of the new distribution network topology structure containing multiple distributed resources such as "hydropower, photovoltaic, charging and storage".
[0005] The above technical objectives of the present invention are achieved through the following technical solutions:
[0006] In a first aspect, the present application provides a method for evaluating a distribution network topology structure that is adaptable to access of multiple distributed resources, including the following specific steps:
[0007] Acquire distribution network data of the distribution network topology to be evaluated, and calculate evaluation indicators based on the distribution network data, the evaluation indicators including a first indicator and a second indicator, the first indicator including a reliability indicator and an economic indicator, and the second indicator including a controllability indicator, an open capacity indicator and a topology structure indicator;
[0008] Based on the entropy weight method, each secondary indicator in each first indicator and each secondary indicator in each second indicator are weighted to obtain the second indicator weight of each secondary indicator;
[0009] Based on the hierarchical analysis method, each first indicator and each second indicator are weighted to obtain the first indicator weight of each first indicator and each second indicator;
[0010] The comprehensive score of the distribution network topology structure is calculated by using each first indicator weight and each second indicator weight, and the distribution network topology structure is evaluated based on the comprehensive score.
[0011] Based on the above technical solution, the present invention can also be improved as follows.
[0012] Furthermore, the above reliability indicators include the average power outage frequency of the system, the average power outage time of the system, the power supply capacity and the load loss, among which:
[0013] The average power outage frequency of the system is as follows:
[0014]
[0015] The average power outage time of the system is as follows:
[0016]
[0017] The power supply can be considered as follows:
[0018]
[0019] The load loss is specifically:
[0020]
[0021] In the above formula, N LP represents the set of all nodes in the distribution network topology, α x represents the annual average power outage frequency of load point x; U x represents the annual average power outage time of node x; N xrepresents the number of users of node x, P x is the load of node x; SAIFI represents the average power outage frequency of the system, SAIDI represents the average power outage time of the system, ASAI represents the power supply can be considered, and ENS represents the load loss.
[0022] Furthermore, the above economic indicators include total investment cost, power outage loss cost and unit load cost, among which:
[0023] The total investment cost is as follows:
[0024] F IC =Z+F OC -F DC ,in, F OC =λ 1 Z, F DC =λ 2 Z;
[0025] In the formula, F IC represents the total investment cost, Z represents the line cost and equipment cost, and F OC represents the operation and maintenance cost, F DC represents cost recovery, Z line represents the unit investment cost of the line, l I Indicates the line length, represents the investment cost of equipment J, λ 1 , 2 Indicates the multiple experience value respectively;
[0026] The specific cost of power outage loss is:
[0027]
[0028] In the formula, F SC represents the power outage loss cost for one year, ρ D Represents the local electricity price; K P Indicates the ratio of power outage loss cost to electricity price; U i represents the voltage at node i, P i represents the load of node i;
[0029] The unit load costs are as follows:
[0030]
[0031] In the formula, C UC Represents the unit load cost, P L Indicates the total system load, F IC represents the total investment cost, F SC Represents the cost of power outage losses in one year.
[0032] Furthermore, the above-mentioned open capacity indicators include the minimum time-series open capacity and the open capacity, where:
[0033] The minimum time-sequential open capacity is as follows:
[0034] C n,j,t =min(C o,j,t ,C T ),t=1,2,…,N;
[0035] The open capacity is as follows:
[0036]
[0037] In the above formula, C n,j,t It represents the minimum sequentially open capacity of the line considering the component's own limit and N-1 safety requirements, C o,j,t represents the available capacity of the jth line in time period t when only the line limit is considered, C T It represents the open capacity limit of feeder N-1 safety requirement, U represents the voltage level of the distribution network, and I r,j represents the rated current carrying capacity of the jth intelligent switch, I m,j,t Represents the maximum current of the jth smart switch in time period t.
[0038] Furthermore, the above topological structure indicators include transfer capacity and grid connectivity, among which:
[0039] The specific transfer capacity is:
[0040]
[0041] Where P N-1 Indicates the load that other lines transfer to this line when a fault occurs; P all It indicates the load carried by the line during normal operation, and TC indicates the transfer capacity of the grid to transfer the load carried by the faulty line;
[0042] The grid connectivity is specifically:
[0043]
[0044] In the formula, NC represents the connectivity status of each node in the distribution network. The larger the NC is, the higher the grid connectivity of the distribution network is, and the less impact the distribution network is affected by the N-1 fault. B Represents the total number of nodes, represents the grid connectivity of the x-th type of node, represents the number of nodes of the xth type, x represents the node type, x=1 represents a terminal node, x=2 represents a general node, and x=3 represents a cross node.
[0045] Furthermore, the weight of the second indicator is specifically:
[0046] in:
[0047]
[0048] Where W j represents the second indicator weight of the jth indicator, E j represents the entropy of the jth index, P ij represents the numerical weight of the i-th item in the j-th indicator, x ij It represents the score of the i-th item in the j-th indicator, n represents the number of items in each indicator, and m represents the number of indicators.
[0049] In a second aspect, the present application provides a distribution network topology structure evaluation system adapted to access of multiple distributed resources, which is applied to a distribution network topology structure evaluation method adapted to access of multiple distributed resources in any one of the first aspects, including:
[0050] The first module is used to obtain distribution network data of the distribution network topology to be evaluated, and calculate the evaluation index according to the distribution network data, the evaluation index includes a first index and a second index, the first index includes a reliability index and an economic index, and the second index includes a controllability index, an open capacity index and a topology index;
[0051] The second module is used to weight each secondary indicator in each first indicator and each secondary indicator in each second indicator based on the entropy weight method to obtain the second indicator weight of each secondary indicator;
[0052] The third module is used to weight each first indicator and each second indicator based on the hierarchical analysis method to obtain the first indicator weight of each first indicator and each second indicator;
[0053] The fourth module is used to calculate the comprehensive score of the distribution network topology structure by using the weights of each first indicator and each second indicator, and evaluate the distribution network topology structure based on the comprehensive score.
[0054] In a third aspect, the present application provides an electronic device comprising a memory, a processor, and a computer program stored in the memory and executable on the processor, wherein the processor implements any one of the methods in the first aspect when executing the computer program.
[0055] In a fourth aspect, the present application provides a non-transitory computer-readable storage medium, which stores computer instructions, and the computer instructions enable a computer to execute any one of the methods in the first aspect.
[0056] Compared with the prior art, the present invention has at least the following beneficial effects:
[0057] In the present application, firstly, the second indicator weight of each secondary indicator in the first indicator and the second indicator is quantitatively calculated, and then the entropy weight method is used to weight each secondary indicator to obtain the second indicator weight of each secondary indicator, and the hierarchical analysis method is used to weight each first indicator and each second indicator to obtain the first indicator weight of each first indicator and each second indicator; finally, according to the first indicator weight and each second indicator weight, the comprehensive score of the distribution network topology structure is calculated, and the distribution network topology structure is evaluated based on the comprehensive score; thereby adapting to the evaluation of the distribution network topology structure connected to "hydro-solar-charging-storage", on the basis of traditional reliability and economic evaluation indicators, as well as newly added topological structure, open capacity and controllability indicators, a new distribution network topology structure multi-attribute evaluation index system is established, and the entropy weight method and hierarchical analysis method are used to calculate each indicator under various distribution network scenarios, and the optimization of the new distribution network topology structure containing multiple distributed resources of "hydro-solar-charging-storage" is realized. BRIEF DESCRIPTION OF THE DRAWINGS
[0058] The drawings described herein are used to provide a further understanding of the embodiments of the present invention, constitute a part of this application, and do not constitute a limitation of the embodiments of the present invention. In the drawings:
[0059] Figure 1 A method flow chart of an evaluation method in an embodiment of the present invention;
[0060] Figure 2 is a system diagram of various evaluation indicators in the embodiment of the present invention;
[0061] Figure 3 is a schematic diagram of comprehensive scores of various distribution network topology structures obtained by the evaluation method in an embodiment of the present invention;
[0062] Figure 4 A schematic diagram of a radial distribution network topology structure in an embodiment of the present invention;
[0063] Figure 5 A schematic diagram of a multi-segment multi-connection type distribution network topology structure according to an embodiment of the present invention;
[0064] Figure 6 A schematic diagram of a ring distribution network topology structure in an embodiment of the present invention;
[0065] Figure 7 A schematic diagram of a typical hydraulic output power in an embodiment of the present invention;
[0066] Figure 8 A schematic diagram of a typical photovoltaic output power in an embodiment of the present invention;
[0067] Fig. 9 Schematic diagram of a typical load of a charging station in an embodiment of the present invention;
[0068] Fig.10 A schematic diagram of the index scores of the radial distribution network topology structure in an embodiment of the present invention;
[0069] Fig.11 A schematic diagram of the index scores of the multi-segment multi-connection type distribution network topology structure according to an embodiment of the present invention;
[0070] Fig.12 It is a schematic diagram of the index score of the ring network type distribution network topology structure in an embodiment of the present invention. DETAILED DESCRIPTION
[0071] In order to make the purpose, technical solutions and advantages of the embodiments of the present invention clearer, the technical solutions in the embodiments of the present invention will be clearly and completely described below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are part of the embodiments of the present invention, not all of the embodiments. Generally, the components of the embodiments of the present invention described and shown in the drawings here can be arranged and designed in various different configurations.
[0072] Therefore, the following detailed description of the embodiments of the present invention provided in the accompanying drawings is not intended to limit the scope of the invention claimed for protection, but merely represents selected embodiments of the present invention. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0073] It should be noted that similar reference numerals and letters denote similar items in the following drawings, and therefore, once an item is defined in one drawing, further definition and explanation thereof is not required in subsequent drawings.
[0074] In the description of the embodiments of the present invention, "plurality" means at least 2.
[0075] Embodiment 1: In order to adapt to the evaluation of the distribution network topology structure connected to "hydro-solar-charging-storage", a new distribution network topology structure multi-attribute evaluation index system can be established on the basis of traditional reliability and economic evaluation indicators, as well as newly added topology structure, open capacity and controllability indicators, and the entropy weight method and hierarchical analysis method are used to calculate each indicator under various distribution network scenarios, thereby realizing the optimization of the new distribution network topology structure containing multiple distributed resources of "hydro-solar-charging-storage"; this embodiment provides a distribution network topology structure evaluation method that is adapted to the access of multiple distributed resources, such as Figure 1 As shown, the following specific steps may be included:
[0076] S1, obtaining distribution network data of the distribution network topology structure to be evaluated, and calculating evaluation indicators based on the distribution network data, the evaluation indicators include a first indicator and a second indicator, the first indicator includes a reliability indicator and an economic indicator, and the second indicator includes a controllability indicator, an open capacity indicator and a topology structure indicator.
[0077] Optionally, the above reliability indicators include system average power outage frequency, system average power outage time, power supply availability and load loss, such as Figure 2 As shown, where:
[0078] The average power outage frequency of the system is as follows:
[0079]
[0080] Furthermore, the average power outage time of the system is specifically:
[0081]
[0082] Furthermore, the power supply can be considered specifically as follows:
[0083]
[0084] Furthermore, the load loss is specifically:
[0085]
[0086] In the above formulas, N LP represents the set of all nodes in the distribution network topology, α x represents the annual average power outage frequency of load point x; U x N represents the average annual power outage time of node x; x represents the number of users of node x, P x is the load of node x; SAIFI represents the average power outage frequency of the system, SAIDI represents the average power outage time of the system, ASAI represents the power supply can be considered, and ENS represents the load loss.
[0087] Optionally, the above economic indicators include total investment cost, power outage loss cost and unit load cost, such as Figure 2 As shown, where:
[0088] The total investment cost is as follows:
[0089] F IC =Z+F OC -F DC ,in, F OC =λ 1 Z, F DC =λ 2 Z;
[0090] In the formula, F IC represents the total investment cost, Z represents the line cost and equipment cost, and F OC represents the operation and maintenance cost, F DC represents cost recovery, Z line represents the unit investment cost of the line, l I Indicates the line length, represents the investment cost of equipment J, λ 1 , 2 Indicates the multiple of experience value.
[0091] Furthermore, the power outage loss cost is specifically:
[0092]
[0093] In the formula, F SC represents the power outage loss cost for one year, ρ D Represents the local electricity price; K P Indicates the ratio of power outage loss cost to electricity price; U i represents the voltage at node i, P i represents the load of node i.
[0094] Furthermore, the unit load cost is specifically:
[0095]
[0096] In the formula, C UC represents the unit load cost, P L Indicates the total system load, F IC represents the total investment cost, F SC Represents the cost of power outage losses in one year.
[0097] Optionally, the above open capacity indicators include the minimum time-series open capacity and the open capacity, see Figure 2 ,in:
[0098] The minimum time-sequential open capacity is as follows:
[0099] C n,j,t =min(C o,j,t ,C T ),t=1,2,…,N.
[0100] Furthermore, the open capacity is as follows:
[0101]
[0102] In the above formula, C n,j,t It represents the minimum sequentially open capacity of the line considering the component's own limit and N-1 safety requirements, Co,j,t represents the available capacity of the jth line in time period t when only the line limit is considered, C T It represents the open capacity limit of feeder N-1 safety requirement, U represents the voltage level of the distribution network, and I r,j represents the rated current carrying capacity of the jth intelligent switch, I m,j,t Represents the maximum current of the jth smart switch in time period t.
[0103] Optionally, the above topological structure indicators include transfer capacity and grid connectivity, such as Figure 2 As shown, where:
[0104] The specific transfer capacity is:
[0105]
[0106] Where P N-1 Indicates the load that other lines transfer to this line when a fault occurs; P all It indicates the load carried by the line during normal operation, and TC indicates the grid's transfer capacity to the load carried by the faulty line.
[0107] The grid connectivity is specifically:
[0108]
[0109] In the formula, NC represents the connectivity status of each node in the distribution network. The larger the NC is, the higher the grid connectivity of the distribution network is, and the less impact the distribution network is affected by the N-1 fault. B Represents the total number of nodes, represents the grid connectivity of the x-th type of node, represents the number of nodes of the xth type, x represents the node type, x=1 represents a terminal node, x=2 represents a general node, and x=3 represents a cross node.
[0110] Specifically, when evaluating the topology of a distribution network, controllability is a crucial aspect, which directly affects the operating efficiency and flexibility of the distribution network. This embodiment selects two key controllability indicators: Figure 2As shown in the figure, they are remote monitoring capability and intelligent dispatching capability; among them, remote monitoring capability refers to the ability of the distribution network to achieve remote real-time monitoring and diagnosis of key parameters such as equipment, lines and loads. This capability can help operation and maintenance personnel to discover and solve problems in a timely manner, improve fault handling efficiency, reduce operation risks, and ensure power supply reliability; intelligent dispatching capability refers to the ability of the distribution network to achieve intelligent dispatch and optimized management of the power system through intelligent algorithms and technologies in the face of load changes and energy supply fluctuations. This capability can effectively balance the relationship between supply and demand, improve energy utilization, reduce operating costs, and promote the economy and sustainable development of the power system. Both remote monitoring capability and intelligent dispatching capability are obtained through manual experience.
[0111] Among them, comprehensive consideration of the two indicators of remote monitoring capability and intelligent dispatching capability can comprehensively evaluate the controllability level of the distribution network during operation, and provide an important reference for optimizing the topology, improving operating efficiency and improving service quality. The improvement of these controllability indicators will help the distribution network to achieve intelligent, information-based and efficient operation, and adapt to the ever-changing power demand and environmental conditions.
[0112] S2, weighting each secondary indicator in each first indicator and each secondary indicator in each second indicator based on the entropy weight method to obtain the second indicator weight of each secondary indicator.
[0113] Optionally, the second indicator weight is specifically:
[0114] in:
[0115]
[0116] Where W j represents the second indicator weight of the jth indicator, E j represents the entropy of the jth index, P ij represents the numerical weight of the i-th item in the j-th indicator, x ij It represents the score of the i-th item in the j-th indicator, n represents the number of items in each indicator, and m represents the number of indicators.
[0117] S3, weighting each first indicator and each second indicator based on the hierarchical analysis method to obtain the first indicator weight of each first indicator and each second indicator.
[0118] Among them, when using the hierarchical analysis method to build a model to solve practical decision-making problems, it can be carried out in the following four steps:
[0119] (1) Establish a comparison matrix: Assume that there are n indicators to be evaluated at each level, and construct a comparison matrix A = (a ij )n×n The following form:
[0120]
[0121] Among them, a ij is the relative importance of index i to j, satisfying a ij >0,a ij =1(i=j), a ij =1(i≠j).
[0122] (2) Calculate the hierarchical single ranking: solve the characteristic equation of A Aω = λω, solve the characteristic vector ω and normalize it to obtain the weight ω of each factor at the same level ai .
[0123] (3)—Consistency test: Perform consistency test on the calculated weight vector to ensure the rationality of the evaluation. The consistency test is mainly performed by calculating the consistency index (CI) and the consistency ratio (CR); the calculation formulas for the consistency index CI and the consistency ratio CR are:
[0124]
[0125] Among them, λ max is the maximum eigenvalue of the judgment matrix, n is the order of the judgment matrix; RI is the random consistency index, which is obtained by looking up the table according to the number of criteria. If CR is less than 0.1, the consistency of the judgment matrix is considered acceptable, otherwise the judgment matrix needs to be readjusted. Since n = 5, the random one-time index RI = 1.12 (look up the table).
[0126] (4) Hierarchical sorting and composite weight: Sort each criterion in the criterion layer according to the calculated weight vector to determine the relative importance of each criterion. Calculate the composite weight of the indicator layer to the criterion layer, that is, consider the weight of the previous layer and calculate the relative importance of each factor in the indicator layer to the criterion layer; through the composite weight, the comprehensive influence of each factor in the indicator layer on the overall goal can be determined.
[0127] S4, using each first indicator weight and each second indicator weight, calculate a comprehensive score of the distribution network topology structure, and evaluate the distribution network topology structure based on the comprehensive score.
[0128] The comprehensive score of the distribution network topology structure is calculated using the weights of each first indicator and each second indicator, which is also performed using the hierarchical analysis method. The steps are the same as those in S3 and will not be repeated here.
[0129] Example 2: With the rapid development of renewable energy and the continuous improvement of smart grids, "hydro-photovoltaic charging and storage" as a new distribution network scenario integrating hydropower, photovoltaics, energy storage and charging loads has received increasing attention; it is of great significance in improving energy efficiency, reducing carbon emissions, and improving power system operation. However, the access of "hydro-photovoltaic charging and storage" technology requires not only technical support, but also a suitable distribution network topology to maximize its utilization. Therefore, it is particularly important to scientifically evaluate and optimize the distribution network topology. The evaluation of the distribution network topology of "hydro-photovoltaic charging and storage" in this embodiment includes the following steps:
[0130] S1, discuss reliability indicators, economic indicators, open capacity indicators, topology indicators and controllability indicators, and build a five-dimensional comprehensive evaluation system to guide the optimization of the distribution network topology structure suitable for "hydro-solar-charging-storage" access. The indicator system structure is as follows Figure 2 shown.
[0131] S2, quantitatively calculate the secondary indicators in the distribution network topology: The reliability indicators of the distribution network are the basis for quantitatively evaluating the reliability of the distribution network. They can objectively reflect the power outages and service quality in the operation of the distribution network. In order to systematically evaluate the reliability of the distribution network, this embodiment selects four key indicators based on the IEEE distribution network reliability evaluation indicator standard:
[0132] (1) System Average Outage Frequency (SAIFI): It indicates the average number of power outages per user in the system in a year. The calculation formula is:
[0133]
[0134] Among them, N LP is the set of all nodes in the distribution network topology; α x is the annual average power outage frequency of load point x; N x is the number of users of node x.
[0135] (2) System Average Power Outage Duration (SAIDI): It indicates the average power outage duration of each user in the system within one year. The calculation formula is:
[0136]
[0137] Among them, U x is the annual average power outage time of node x.
[0138] (3) Power supply reliability index (ASAI): It refers to the ratio of the number of effective power supply hours to the total time per unit time. The calculation formula is:
[0139]
[0140] (4) Load loss (ENS): refers to the load loss caused by faults in the line within one year. The calculation formula is:
[0141]
[0142] Among them, P x is the load of node x.
[0143] Furthermore, economic evaluation indicators play an important role in evaluating the selection and optimization of distribution network topology. In addition to considering the equipment and labor costs required in the initial stage of distribution network construction, it is also necessary to comprehensively consider the operating economy after commissioning and the cost of recycling equipment when it is scrapped; such comprehensive consideration can more comprehensively evaluate the economic performance of the distribution network and provide stronger support for decision-making. This embodiment selects three key indicators:
[0144] (1) Total investment cost (F IC ): This indicator includes the direct costs such as equipment, labor, and land required for the construction of the distribution network, as well as indirect costs related to the construction, such as design fees, approval fees, etc. The total investment cost can reflect the investment scale and capital requirements during the construction phase of the distribution network. The specific calculation formula is as follows:
[0145] F IC =Z+F OC -F DC ,in, F OC =λ 1 Z, F DC =λ 2 Z;
[0146] Among them, Z mainly includes line cost and equipment cost; L, E s Respectively represent the collection of lines and equipment; Z line , l I They represent the unit investment cost and line length of the line respectively; is the investment cost of equipment J; F OC 、F DC They represent operation and maintenance costs and cost recovery respectively, and their values are often taken as λ of the investment cost Z based on actual experience. 1 , 2 times.
[0147] (2) Power outage loss cost (F SC ): This indicator refers to the loss costs caused by failures or power outages during the operation of the distribution network, including power outage losses to users, production interruption losses, etc. The power outage loss cost is directly related to the reliability and stability of the distribution network operation and is crucial to the economic evaluation.
[0148]
[0149] Among them, F SC is the annual power outage loss; D is the local electricity price; K P is the ratio of power outage loss to electricity price; U i is the node voltage.
[0150] (3) Unit load cost (C UC ): This indicator refers to the cost per unit load, including power supply cost, equipment maintenance cost, etc. It reflects the economy of the distribution network during operation. Comparing the unit load costs of different topologies can evaluate their operating efficiency and cost-effectiveness.
[0151]
[0152] Among them, P L is the total system load.
[0153] Furthermore, considering that the load of the distribution network has a time sequence, and the time sequence of the charging station load, the hydropower output, and the energy storage charging and discharging needs to be considered at the same time, an indicator that can comprehensively consider these factors is needed to evaluate the open capacity of the distribution network; in this embodiment, the minimum value of the open capacity with time sequence fluctuations under different distribution network topologies is studied as one of the important indicators. This indicator can reflect the minimum load that the distribution network can supply in different time periods, and then evaluate its adaptability and stability to load changes; the specific expression is as follows:
[0154]
[0155] Among them, C o,j,t is the available capacity of the jth line in time period t when only the line limit is considered; U is the voltage level of the distribution network; I r,j is the rated current carrying capacity of the jth intelligent switch; I m,j,t is the maximum current of the jth smart switch in time period t.
[0156] Among them, the minimum value of the open capacity of the distribution network considering the timing characteristics is:
[0157] C n,j,t =min(C o,j,t ,C T ),t=1,2,…,N.
[0158] Among them, C n,j,t The capacity of the line that can be opened to take into account the component's own limitations and N-1 safety requirements; C T It is the open capacity limit required for the safety of feeder N-1.
[0159] Furthermore, based on the analysis of the structure of the distribution network itself, this embodiment selects transfer capacity (TC) and network connectivity (NC) as indicators for evaluating the grid topology.
[0160] (1) TC reflects the difference in the transfer capacity of different grid structures when a fault occurs. The larger the TC value, the less long-term power outage load the grid can bear in the event of a fault, and the stronger its overall load-carrying capacity. Therefore, in topological structure analysis, TC is an important indicator that evaluates the grid's ability to transfer the load carried by the faulty line. The calculation formula is:
[0161]
[0162] Among them, P N-1 When a fault occurs, the load carried by this line is transferred to other lines; P all The load carried by the road during normal operation.
[0163] (2) NC represents the connectivity status of each node in the distribution network. The larger the NC is, the higher the connectivity of the distribution network is, and the less the distribution network is affected by the N-1 fault. The calculation formula of NC is:
[0164]
[0165] Where x is the node type, x=1 represents a terminal node, x=2 represents a general node, and x=3 represents a cross node; is the connectivity of the x-th type of node; is the number of nodes of the xth type; N B is the total number of nodes.
[0166] Furthermore, when evaluating the topology of a distribution network, controllability is a crucial aspect, which directly affects the operating efficiency and flexibility of the distribution network. This embodiment selects two key controllability indicators: remote monitoring capability and intelligent dispatching capability.
[0167] (1) Remote monitoring capability refers to the ability of the distribution network to remotely monitor and diagnose key parameters such as equipment, lines, and loads in real time. This capability can help operation and maintenance personnel to promptly discover and solve problems, improve fault handling efficiency, reduce operational risks, and ensure power supply reliability.
[0168] (2) Intelligent dispatch capability refers to the ability of the distribution network to achieve intelligent dispatch and optimized management of the power system through intelligent algorithms and technologies in the face of load changes, energy supply fluctuations, etc. This capability can effectively balance the supply and demand relationship, improve energy utilization, reduce operating costs, and promote the economic and sustainable development of the power system.
[0169] Among them, comprehensive consideration of the two indicators of remote monitoring capability and intelligent dispatching capability can comprehensively evaluate the controllability level of the distribution network during operation, providing an important reference for optimizing the topology, improving operation efficiency and improving service quality. The improvement of these controllability indicators will help the distribution network to achieve intelligent, information-based and efficient operation, and adapt to the ever-changing power demand and environmental conditions.
[0170] S3, entropy weight method to determine the weight of evaluation indicators: Entropy weight method is a commonly used weighting method. According to the impact of the numerical changes of each indicator on the whole, the entropy value of the indicator is calculated to determine the weight. The specific calculation formula is as follows:
[0171] in:
[0172]
[0173] Where W j represents the second indicator weight of the jth indicator, E j represents the entropy of the jth index, P ij represents the numerical weight of the i-th item in the j-th indicator, x ij It represents the score of the i-th item in the j-th indicator, n represents the number of items in each indicator, and m represents the number of indicators.
[0174] Specifically, the entropy weight method can determine the weight of each secondary indicator of distribution network evaluation by calculating the information entropy, and then make a comprehensive evaluation of the indicator. This method can effectively deal with the complex relationship within the indicator and provide an objective basis for comprehensive evaluation.
[0175] S4, use the hierarchical analysis method to weight the indicators of the five dimensions. The hierarchical analysis method can help us determine the weight of each indicator according to the relative importance of the indicators, so as to make a comprehensive evaluation of the whole. This method takes into account the hierarchical structure and relative importance of different indicators, making the evaluation results more accurate and reliable; among them, when using the hierarchical analysis method to build a model to solve practical decision-making problems, it can be carried out in the following four steps:
[0176] (1) Establish a comparison matrix: Assume that there are n indicators to be evaluated at each level, and construct a comparison matrix A = (a ij ) n×n The following form:
[0177]
[0178] Among them, a ij is the relative importance of index i to j, satisfying a ij >0,aij =1(i=j), a ij =1(i≠j).
[0179] (2) Calculate the hierarchical single ranking: solve the characteristic equation of A Aω = λω, solve the characteristic vector ω and normalize it to obtain the weight ω of each factor at the same level ai .
[0180] (3)—Consistency test: Perform consistency test on the calculated weight vector to ensure the rationality of the evaluation. The consistency test is mainly performed by calculating the consistency index (CI) and the consistency ratio (CR); the calculation formulas for the consistency index CI and the consistency ratio CR are:
[0181]
[0182] Among them, λ max is the maximum eigenvalue of the judgment matrix, n is the order of the judgment matrix; RI is the random consistency index, which is obtained by looking up the table according to the number of criteria. If CR is less than 0.1, the consistency of the judgment matrix is considered acceptable, otherwise the judgment matrix needs to be readjusted. Since n = 5, the random one-time index RI = 1.12 (look up the table).
[0183] (4) Hierarchical sorting and composite weight: Sort each criterion in the criterion layer according to the calculated weight vector to determine the relative importance of each criterion. Calculate the composite weight of the indicator layer to the criterion layer, that is, consider the weight of the previous layer and calculate the relative importance of each factor in the indicator layer to the criterion layer; through the composite weight, the comprehensive impact of each factor in the indicator layer on the overall goal can be determined; among them, the criterion layer is the evaluation object (that is, the final comprehensive score obtained by different topological structures), and each indicator layer is each first-level indicator.
[0184] S5, topology optimization based on comprehensive score: the entropy weight method is used to weight the small indicators of the above five types of distribution network evaluation indicators to obtain the scores of the five-dimensional comprehensive evaluation indicators of the distribution network. The hierarchical analysis method is used to calculate the comprehensive weights of the five indicators, and the weighted comprehensive scores of each distribution network are calculated. The results are as follows: Figure 3 As shown in the figure, the results show that the scores of the ring distribution network and the multi-segment multi-connection distribution network are higher, and the score of the radial distribution network is lower. For distribution networks with different topological structures, the score of only introducing energy storage is the highest, indicating that the introduction of energy storage into the distribution network will improve the distribution network indicators. The optimal distribution network structure is the ring distribution network with the introduction of energy storage, and its score is 0.90117.
[0185] Specifically, this embodiment uses a calculation example for analysis. The calculation example selects an active medium-voltage distribution network in a certain area, including a single radial network. The network structure is as follows: Figure 4As shown; multi-segment multi-connection network, the network structure is as follows Figure 5 As shown; Ring network, the network structure is as follows Figure 6 The network load information is shown in Table 1.
[0186] Table 1 Load information of each node in the distribution network
[0187]
[0188] Specifically, there is a strong correlation between the change in hydropower output and the month, which usually reflects the impact of seasonal changes, rainfall changes, reservoir scheduling and other factors on hydropower generation. In order to more accurately evaluate the topological structure of the distribution network, this embodiment adopts a method based on historical data, that is, the hydropower output data of 12 months in a year is counted and the average is calculated, and the obtained average is used as the typical hydropower output value. Figure 7 The typical hydroelectric output power curve shown can intuitively reflect the average level and fluctuation of hydroelectric power generation in different months, which is crucial for evaluating the reliability and stability of distribution networks under different seasons and load conditions.
[0189] Among them, the typical photovoltaic output power has a strong correlation with the change of charging station load and hour, and both have obvious daily change rules; this embodiment uses the typical photovoltaic output power and charging station load data for 24 hours a day in a year and performs average processing. The typical photovoltaic output power is as follows Figure 8 As shown in Figure 2, the charging station load is Fig. 9 As shown; specifically, the capacity of the energy storage is configured to be 1MWh, the state of charge is between 0 and 1, initially 0.5, the unit power investment cost of the energy storage is 600 yuan / kW, and the unit capacity investment cost is 1000 yuan / (MWh).
[0190] Specifically, the calculation results show that the reliability of the ring network distribution network is the highest, and its power supply reliability rate (ASAI) is: 0.999872003; followed by the multi-segment multi-connection distribution network, and its power supply reliability rate (ASAI) is: 0.999743931; the reliability of the radial distribution network is the worst, and its power supply reliability rate (ASAI) is: 0.999458049. The reason is that the radial distribution network and the multi-segment multi-connection distribution network are mostly overhead lines, while the ring network distribution network is mostly underground cables, and the reliability of underground cables is higher than that of overhead lines. Secondly, when a fault occurs in the ring network distribution network, only fault isolation is required to supply power to all loads normally; when an N-1 fault occurs in the multi-segment multi-connection distribution network, the switching operation can be performed to transfer the affected loads and restore power supply; while the radial distribution network does not have the transfer capacity, after a fault occurs, the affected loads cannot be powered, resulting in an increase in the amount of load loss in the distribution network and a decrease in the reliability of the distribution network.
[0191] Furthermore, the calculation results show that the unit load cost of the multi-connection and multi-section distribution network is the lowest, which is 0.135404424 million yuan / kW, followed by the radial distribution network, with a unit load cost of 0.148601796 million yuan / kW, and the ring distribution network has the highest unit load cost of 0.534148469 million yuan / kW. Among them, the ring distribution network has the highest construction cost, resulting in the worst economy of the ring distribution network. Although the radial distribution network has the lowest construction cost, due to its low reliability and the highest load loss, the unit load cost is slightly higher than the multi-segment multi-connection distribution network. The multi-segment multi-connection distribution network takes into account both low construction cost and high reliability, and has the best economy.
[0192] Furthermore, when calculating the available capacity, the time sequence characteristics of the distribution network load need to be considered. This embodiment simultaneously considers the minimum value and fluctuation of the available capacity of the distribution network under the time sequence characteristics. The minimum value of the available capacity of the ring network distribution network under the time sequence characteristics is up to 24.6804MW, and the minimum time sequence fluctuation of the available capacity is 1.232MW, which is better than the radial distribution network and the multi-segment multi-connection distribution network.
[0193] Furthermore, the radial distribution network has the worst transfer capacity. Since there is no interconnection line, the transfer capacity is 0. When an N-1 fault occurs in the multi-segment and multi-interconnection distribution network, full load transfer can be achieved. However, when the load increases, load loss will occur. The calculated value of the distribution network's transfer capacity is 0.8333. The ring distribution network has the strongest transfer capacity of 0.8912.
[0194] Furthermore, the controllability indicators of the distribution network are mainly the remote monitoring capability and intelligent dispatching capability of the distribution network. The radial distribution network has the worst controllability due to its low load dispatching capability, while the ring network and multi-segment and multi-connection distribution network have stronger controllability.
[0195] Specifically, the entropy weight method is used to weight the small indicators of the above five types of distribution network evaluation indicators to obtain the scores of the five-dimensional comprehensive evaluation indicators of the distribution network. At the same time, the scores of the three distribution network structures with different "water-solar-charging-storage" ratios are calculated. The results are as follows: Fig.10 , Fig.11 , Fig.12 As shown in the figure, the results show that the scores of the ring distribution network and the multi-segment multi-connection distribution network are higher, and the score of the radial distribution network is lower. For distribution networks with different topological structures, the score of only introducing energy storage is the highest, indicating that the introduction of energy storage into the distribution network will improve the distribution network indicators. The optimal distribution network structure is the ring distribution network with the introduction of energy storage, and its score is 0.90117.
[0196] Embodiment 3: The present application provides a distribution network topology structure evaluation system adapted to access of multiple distributed resources, which is applied to a distribution network topology structure evaluation method adapted to access of multiple distributed resources in any one of Embodiment 1 or Embodiment 2, including:
[0197] The first module is used to obtain the distribution network data of the distribution network topology structure to be evaluated, and calculate the evaluation index based on the distribution network data. The evaluation index includes a first index and a second index. The first index includes a reliability index and an economic index. The second index includes a controllability index, an open capacity index and a topology structure index.
[0198] The second module is used to weight each secondary indicator in each first indicator and each secondary indicator in each second indicator based on the entropy weight method to obtain the second indicator weight of each secondary indicator.
[0199] The third module is used to weight each first indicator and each second indicator based on the hierarchical analysis method to obtain the first indicator weight of each first indicator and each second indicator.
[0200] The fourth module is used to calculate the comprehensive score of the distribution network topology structure by using the weights of each first indicator and each second indicator, and evaluate the distribution network topology structure based on the comprehensive score.
[0201] This embodiment also provides an electronic device, including a memory, a processor, and a computer program stored in the memory and executable on the processor, wherein the processor implements any one of the methods in Embodiment 1 or Embodiment 2 when executing the computer program.
[0202] This embodiment also provides a non-transitory computer-readable storage medium, which stores computer instructions, and the computer instructions enable a computer to execute any method in Embodiment 1 or Embodiment 2.
[0203] The specific implementation methods described above further illustrate the objectives, technical solutions and beneficial effects of the present invention in detail. It should be understood that the above description is only a specific implementation method of the present invention and is not intended to limit the scope of protection of the present invention. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the present invention should be included in the scope of protection of the present invention.
Claims
1. A distribution network topology evaluation method adapted to multiple distributed resource accesses, characterized in that: The specific steps include: Acquire distribution network data of the distribution network topology to be evaluated, and calculate evaluation indicators based on the distribution network data, wherein the evaluation indicators include a first indicator and a second indicator, the first indicator includes a reliability indicator and an economic indicator, and the second indicator includes a controllability indicator, an open capacity indicator, and a topology structure indicator; Based on the entropy weight method, weight each secondary indicator in each of the first indicators, and each secondary indicator in each of the second indicators, to obtain a second indicator weight of each of the secondary indicators; Based on the hierarchical analysis method, each of the first indicators and each of the second indicators is weighted to obtain a first indicator weight of each first indicator and each of the second indicators; The comprehensive score of the distribution network topology structure is calculated by using each of the first indicator weights and each of the second indicator weights, and the distribution network topology structure is evaluated based on the comprehensive score.
2. A distribution network topology evaluation method adapted to access of multiple distributed resources according to claim 1, characterized in that: The reliability indicators include the average power outage frequency of the system, the average power outage time of the system, the power supply capacity and the load loss, among which: The average power outage frequency of the system is specifically: The average power outage time of the system is specifically: The power supply may be specifically considered to be: The load loss is specifically: In the above formula, N LP represents the set of all nodes in the distribution network topology, α x represents the annual average power outage frequency of load point x; U x N represents the average annual power outage time of node x; x represents the number of users of node x, P x is the load of node x; SAIFI represents the average power outage frequency of the system, SAIDI represents the average power outage time of the system, ASAI represents the power supply can be considered, and ENS represents the load loss.
3. A distribution network topology evaluation method adapted to access of multiple distributed resources according to claim 1, characterized in that: The economic indicators include total investment cost, power outage loss cost and unit load cost, among which: The total investment cost is specifically: F IC =Z+F OC -F DC ,in, F OC =λ1Z,F DC =λ2Z; In the formula, F IC represents the total investment cost, Z represents the line cost and equipment cost, and F OC represents the operation and maintenance cost, F DC represents cost recovery, Z line represents the unit investment cost of the line, l I Indicates the line length, represents the investment cost of equipment J, λ1 and λ2 represent the multiple empirical values respectively; The power outage loss costs are specifically: In the formula, F SC represents the power outage loss cost for one year, ρ D Represents the local electricity price; K P Indicates the ratio of power outage loss cost to electricity price; U i represents the voltage at node i, P i represents the load of node i; The unit load costs are specifically: In the formula, C UC represents the unit load cost, P L Indicates the total system load, F IC represents the total investment cost, F SC Represents the cost of power outage losses in one year.
4. A distribution network topology evaluation method adapted to access of multiple distributed resources according to claim 1, characterized in that: The openable capacity indicator includes the minimum time-series openable capacity and the openable capacity, where: The minimum time-sequentially openable capacity is specifically: C n,j,t =min(C o,j,t ,C T ),t=1,2,…,N: The openable capacity is specifically: In the above formula, C n,j,t It represents the minimum sequentially open capacity of the line considering the component's own limit and N-1 safety requirements, C o,j,t represents the available capacity of the jth line in time period t when only the line limit is considered, C T It represents the open capacity limit of feeder N-1 safety requirement, U represents the voltage level of the distribution network, and I r,j represents the rated current carrying capacity of the jth intelligent switch, I m,j,t Represents the maximum current of the jth smart switch in time period t.
5. A distribution network topology evaluation method adapted to access of multiple distributed resources according to claim 1, characterized in that: The topological structure indicators include the transfer capacity and grid connectivity, among which: The transfer capacity is specifically: Where P N-1 Indicates the load that other lines transfer to this line when a fault occurs; P all It indicates the load carried by the line during normal operation, and TC indicates the transfer capacity of the grid to transfer the load carried by the faulty line; The grid connectivity is specifically: In the formula, NC represents the connectivity status of each node in the distribution network. The larger the NC is, the higher the grid connectivity of the distribution network is, and the less impact the distribution network is affected by the N-1 fault. B Represents the total number of nodes, represents the grid connectivity of the x-th type of node, represents the number of nodes of the xth type, x represents the node type, x=1 represents a terminal node, x=2 represents a general node, and x=3 represents a cross node.
6. A distribution network topology evaluation method adapted to access of multiple distributed resources according to claim 1, characterized in that: The second indicator weight is specifically: in: Where W j represents the second indicator weight of the jth indicator, E j represents the entropy of the jth index, P ij represents the numerical weight of the i-th item in the j-th indicator, x ij It represents the score of the i-th item in the j-th indicator, n represents the number of items in each indicator, and m represents the number of indicators.
7. A distribution network topology evaluation method adapted to access of multiple distributed resources according to claim 1, characterized in that: 。 8. A distribution network topology structure evaluation system adapted to access of multiple distributed resources, applied to a distribution network topology structure evaluation method adapted to access of multiple distributed resources as claimed in any one of claims 1 to 7, characterized in that: include: The first module is used to obtain distribution network data of the distribution network topology structure to be evaluated, and calculate the evaluation index according to the distribution network data, wherein the evaluation index includes a first index and a second index, the first index includes a reliability index and an economic index, and the second index includes a controllability index, an open capacity index and a topology structure index; The second module is used to weight each secondary indicator in each of the first indicators and each secondary indicator in each of the second indicators based on the entropy weight method to obtain the second indicator weight of each of the secondary indicators; The third module is used to weight each of the first indicators and each of the second indicators based on the hierarchical analysis method to obtain the first indicator weight of each of the first indicators and each of the second indicators; The fourth module is used to calculate the comprehensive score of the distribution network topology structure by using the weights of each of the first indicators and the weights of each of the second indicators, and evaluate the distribution network topology structure based on the comprehensive score.
9. An electronic device, characterized in that: The method comprises a memory, a processor and a computer program stored in the memory and executable on the processor, wherein the method according to any one of claims 1 to 7 is implemented when the processor executes the computer program.
10. A non-transitory computer-readable storage medium, characterized in that: The non-transitory computer-readable storage medium stores computer instructions, which enable a computer to execute the method of any one of claims 1-7.