Tower inspection line automatic correction and planning method and device based on image key point identification

Through image key point recognition technology, the tower inspection routes are automatically corrected and planned, and the inefficiency problem caused by artificial dependence in the existing technology is solved, and rapid adaptation to complex environments and improved system operation efficiency is achieved.

CN118941856APending Publication Date: 2024-11-12GOLMUD JINGNENG NEW ENERGY CO LTD
View PDF 10 Cites 0 Cited by

Patent Information

Application Number
CN202410985896.7
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-07-23
Publication Date
2024-11-12

AI Technical Summary

Technical Problem

In the prior art, line correction and planning methods rely on manual collection and processing of information, and cannot quickly adapt to complex environments, resulting in inefficient system operation.

Method used

Using the method based on image key point recognition, the key point image data is obtained by obtaining the original image data and key point recognition parameters, and inputting it into the correction planning model to output correction and planning results, and verifying it to improve the automatic correction of the system. and planning capabilities.

Benefits of technology

It realizes all-round rapid tower inspection, correction and optimization planning for complex environments, improves the operating efficiency of the system, and reduces the dependence of manual intervention.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118941856A_ABST
    Figure CN118941856A_ABST
Patent Text Reader

Abstract

The invention discloses a tower inspection line automatic correction and planning method and device based on image key point identification. The method comprises the following steps: acquiring original image data and key point identification parameters; processing the original image data according to the key point identification parameters to obtain key point image data; inputting the key point image data and the inspection line data into a correction planning model, and outputting a correction result and a planning result; and verifying the correction result and the planning result to obtain a verification result. According to the invention, the technical problem that the operation efficiency of the whole system is reduced due to the fact that the line correction and planning method in the prior art only obtains a final judgment result through manual information acquisition and processing and cannot carry out comprehensive and rapid tower inspection correction and optimization planning work for a complex environment is solved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the field of line inspection and intelligent planning measures, and in particular to a method and a device for automatic correction and planning of a tower inspection line based on image key point recognition. Background Art

[0002] With the continuous development of intelligent technology, people are using more and more intelligent devices in their lives, work and study. The use of intelligent technology has improved the quality of people's lives and increased the efficiency of their study and work.

[0003] At present, the correction and optimization of the tower inspection line is usually done by manual repair. The maintenance personnel judge the line condition, combine the equipment operation condition and line aging condition, and comprehensively judge the line correction strategy, so as to carry out subsequent planning and improvement work. However, the line correction and planning method in the prior art is only the final judgment result obtained by manually collecting and processing information, and it is impossible to carry out comprehensive and rapid tower inspection correction and optimization planning work in complex environments, which reduces the operation efficiency of the entire system.

[0004] To address the above-mentioned problems, no effective solution has been proposed yet. Summary of the invention

[0005] The embodiment of the present invention provides a method and device for automatic correction and planning of pole tower inspection lines based on image key point recognition, so as to at least solve the technical problem that the line correction and planning methods in the prior art only obtain the final judgment results through manual information collection and processing, and cannot perform comprehensive and rapid pole tower inspection correction and optimization planning work in complex environments, thereby reducing the operating efficiency of the entire system.

[0006] According to one aspect of an embodiment of the present invention, there is provided a method for automatic correction and planning of a tower inspection route based on image key point recognition, comprising: acquiring original image data and key point recognition parameters; processing the original image data according to the key point recognition parameters to obtain key point image data; inputting the key point image data and the inspection route data into a correction planning model, and outputting correction results and planning results; and verifying the correction results and the planning results to obtain verification results.

[0007] Optionally, before processing the original image data according to the key point recognition parameters to obtain the key point image data, the method further includes: marking areas in the original image data related to the key point recognition parameters for key point recognition processing.

[0008] Optionally, the inputting of the key point image data and the inspection route data into the revised planning model, and outputting the correction result and the planning result include: training the revised planning model through historical data of key image recognition; inputting the key point image data into the correction layer in the revised planning model to obtain the correction result; inputting the key point image data and the inspection route data into the planning layer in the revised planning model together to obtain the planning result.

[0009] Optionally, verifying the correction result and the planning result to obtain the verification result includes: comparing the correction result and the planning result with a correction planning threshold in a verification matrix to obtain a comparison result; and generating the verification result based on the comparison result.

[0010] According to another aspect of an embodiment of the present invention, there is also provided a device for automatic correction and planning of pole tower inspection lines based on image key point recognition, comprising: an acquisition module for acquiring original image data and key point recognition parameters; a processing module for processing the original image data according to the key point recognition parameters to obtain key point image data; an input module for inputting the key point image data and inspection line data into a correction planning model, and outputting correction results and planning results; and a verification module for verifying the correction results and the planning results to obtain verification results.

[0011] Optionally, the device further includes: marking an area in the original image data related to the key point recognition parameter for key point recognition processing.

[0012] Optionally, the input module includes: a training unit, used to train the revised planning model through historical data of key image recognition; an input unit, used to input the key point image data into the correction layer in the revised planning model to obtain the correction result; the input unit is also used to input the key point image data and the inspection route data into the planning layer in the revised planning model to obtain the planning result.

[0013] Optionally, the verification module includes: a comparison unit, used to compare the correction result and the planning result with the correction planning threshold in the verification matrix to obtain a comparison result; and a generation unit, used to generate the verification result according to the comparison result.

[0014] According to another aspect of an embodiment of the present invention, a non-volatile storage medium is also provided, wherein the non-volatile storage medium includes a stored program, wherein when the program is running, the device where the non-volatile storage medium is located is controlled to execute a method for automatic correction and planning of tower inspection routes based on image key point recognition.

[0015] According to another aspect of an embodiment of the present invention, an electronic device is also provided, comprising a processor and a memory; the memory stores computer-readable instructions, and the processor is used to run the computer-readable instructions, wherein when the computer-readable instructions are run, a method for automatic correction and planning of tower inspection routes based on image key point recognition is executed.

[0016] In an embodiment of the present invention, the original image data and key point recognition parameters are obtained; the original image data is processed according to the key point recognition parameters to obtain key point image data; the key point image data and inspection line data are input into a correction planning model, and correction results and planning results are output; the correction results and planning results are verified to obtain verification results. This solves the technical problem that the line correction and planning methods in the prior art are only the final judgment results obtained by manually collecting and processing information, and cannot perform comprehensive and rapid tower inspection correction and optimization planning work in complex environments, thereby reducing the operating efficiency of the entire system. BRIEF DESCRIPTION OF THE DRAWINGS

[0017] The drawings described herein are used to provide a further understanding of the present invention and constitute a part of this application. The exemplary embodiments of the present invention and their descriptions are used to explain the present invention and do not constitute an improper limitation of the present invention. In the drawings:

[0018] Figure 1 is a flow chart of a method for automatic correction and planning of tower inspection routes based on image key point recognition according to an embodiment of the present invention;

[0019] Figure 2 It is a structural block diagram of a tower inspection line automatic correction and planning device based on image key point recognition according to an embodiment of the present invention;

[0020] Figure 3 is a block diagram of a terminal device for executing a method according to an embodiment of the present invention;

[0021] Figure 4 It is a storage unit for holding or carrying a program code for implementing a method according to an embodiment of the present invention. DETAILED DESCRIPTION

[0022] In order to enable those skilled in the art to better understand the scheme of the present invention, the technical scheme in the embodiments of the present invention will be clearly and completely described below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work should fall within the scope of protection of the present invention.

[0023] It should be noted that the terms "first", "second", etc. in the specification and claims of the present invention and the above-mentioned drawings are used to distinguish similar objects, and are not necessarily used to describe a specific order or sequence. It should be understood that the data used in this way can be interchanged where appropriate, so that the embodiments of the present invention described herein can be implemented in an order other than those illustrated or described herein. In addition, the terms "including" and "having" and any variations thereof are intended to cover non-exclusive inclusions, for example, a process, method, system, product or device that includes a series of steps or units is not necessarily limited to those steps or units that are clearly listed, but may include other steps or units that are not clearly listed or inherent to these processes, methods, products or devices.

[0024] According to an embodiment of the present invention, a method embodiment of a method for automatic correction and planning of a tower inspection route based on image key point recognition is provided. It should be noted that the steps shown in the flowchart of the accompanying drawings can be executed in a computer system such as a set of computer executable instructions, and although a logical order is shown in the flowchart, in some cases, the steps shown or described can be executed in an order different from that shown here.

[0025] Embodiment 1

[0026] Figure 1 is a flow chart of a method for automatic correction and planning of tower inspection routes based on image key point recognition according to an embodiment of the present invention, such as Figure 1 As shown, the method comprises the following steps:

[0027] Step S102, obtaining original image data and key point recognition parameters.

[0028] Step S104: Process the original image data according to the key point recognition parameters to obtain key point image data.

[0029] Step S106, inputting the key point image data and the inspection route data into the correction planning model, and outputting the correction result and the planning result.

[0030] Step S108, verifying the correction result and the planning result to obtain a verification result.

[0031] Optionally, before processing the original image data according to the key point recognition parameters to obtain the key point image data, the method further includes: marking areas in the original image data related to the key point recognition parameters for key point recognition processing.

[0032] Optionally, the inputting of the key point image data and the inspection route data into the revised planning model, and outputting the correction result and the planning result include: training the revised planning model through historical data of key image recognition; inputting the key point image data into the correction layer in the revised planning model to obtain the correction result; inputting the key point image data and the inspection route data into the planning layer in the revised planning model together to obtain the planning result.

[0033] Optionally, verifying the correction result and the planning result to obtain the verification result includes: comparing the correction result and the planning result with a correction planning threshold in a verification matrix to obtain a comparison result; and generating the verification result based on the comparison result.

[0034] Through the above embodiments, the technical problem that the line correction and planning methods in the prior art only obtain the final judgment results through manual information collection and processing, cannot perform comprehensive and rapid tower inspection correction and optimization planning work in complex environments, and reduces the operating efficiency of the entire system is solved.

[0035] Embodiment 2

[0036] Figure 2 is a structural block diagram of a tower inspection line automatic correction and planning device based on image key point recognition according to an embodiment of the present invention, such as Figure 2 As shown, the device comprises:

[0037] The acquisition module 20 is used to acquire original image data and key point recognition parameters.

[0038] The processing module 22 is used to process the original image data according to the key point recognition parameters to obtain key point image data.

[0039] The input module 24 is used to input the key point image data and the inspection route data into the correction planning model, and output the correction result and the planning result.

[0040] The verification module 26 is used to verify the correction result and the planning result to obtain a verification result.

[0041] Optionally, the device further includes: marking an area in the original image data related to the key point recognition parameter for key point recognition processing.

[0042] Optionally, the input module includes: a training unit, used to train the revised planning model through historical data of key image recognition; an input unit, used to input the key point image data into the correction layer in the revised planning model to obtain the correction result; the input unit is also used to input the key point image data and the inspection route data into the planning layer in the revised planning model to obtain the planning result.

[0043] Optionally, the verification module includes: a comparison unit, used to compare the correction result and the planning result with the correction planning threshold in the verification matrix to obtain a comparison result; and a generation unit, used to generate the verification result according to the comparison result.

[0044] According to another aspect of an embodiment of the present invention, a non-volatile storage medium is also provided, wherein the non-volatile storage medium includes a stored program, wherein when the program is running, the device where the non-volatile storage medium is located is controlled to execute a method for automatic correction and planning of tower inspection routes based on image key point recognition.

[0045] Specifically, the above method includes: obtaining original image data and key point recognition parameters; processing the original image data according to the key point recognition parameters to obtain key point image data; inputting the key point image data and the inspection line data into the revised planning model, outputting the revision result and the planning result; verifying the revision result and the planning result to obtain the verification result. Optionally, before processing the original image data according to the key point recognition parameters to obtain the key point image data, the method also includes: marking the area related to the key point recognition parameters in the original image data for key point recognition processing. Optionally, inputting the key point image data and the inspection line data into the revised planning model, outputting the revision result and the planning result includes: training the revised planning model with historical data of key image recognition; inputting the key point image data into the revision layer in the revised planning model to obtain the revision result; inputting the key point image data and the inspection line data into the planning layer in the revised planning model together to obtain the planning result. Optionally, verifying the correction result and the planning result to obtain the verification result includes: comparing the correction result and the planning result with a correction planning threshold in a verification matrix to obtain a comparison result; and generating the verification result based on the comparison result.

[0046] According to another aspect of an embodiment of the present invention, an electronic device is also provided, comprising a processor and a memory; the memory stores computer-readable instructions, and the processor is used to run the computer-readable instructions, wherein when the computer-readable instructions are run, a method for automatic correction and planning of tower inspection routes based on image key point recognition is executed.

[0047] Specifically, the above method includes: obtaining original image data and key point recognition parameters; processing the original image data according to the key point recognition parameters to obtain key point image data; inputting the key point image data and the inspection line data into the revised planning model, outputting the revision result and the planning result; verifying the revision result and the planning result to obtain the verification result. Optionally, before processing the original image data according to the key point recognition parameters to obtain the key point image data, the method also includes: marking the area related to the key point recognition parameters in the original image data for key point recognition processing. Optionally, inputting the key point image data and the inspection line data into the revised planning model, outputting the revision result and the planning result includes: training the revised planning model with historical data of key image recognition; inputting the key point image data into the revision layer in the revised planning model to obtain the revision result; inputting the key point image data and the inspection line data into the planning layer in the revised planning model together to obtain the planning result. Optionally, verifying the correction result and the planning result to obtain the verification result includes: comparing the correction result and the planning result with a correction planning threshold in a verification matrix to obtain a comparison result; and generating the verification result based on the comparison result.

[0048] The serial numbers of the above embodiments of the present invention are only for description and do not represent the advantages or disadvantages of the embodiments.

[0049] In the above embodiments of the present invention, the description of each embodiment has its own emphasis. For parts that are not described in detail in a certain embodiment, reference can be made to the relevant descriptions of other embodiments.

[0050] In the several embodiments provided in this application, it should be understood that the disclosed technical content can be implemented in other ways. Among them, the device embodiments described above are only schematic. For example, the division of the units can be a logical function division. There may be other division methods in actual implementation. For example, multiple units or components can be combined or integrated into another system, or some features can be ignored or not executed. Another point is that the mutual coupling or direct coupling or communication connection shown or discussed can be through some interfaces, indirect coupling or communication connection of units or modules, which can be electrical or other forms.

[0051] The units described as separate components may or may not be physically separated, and the components shown as units may or may not be physical units, that is, they may be located in one place or distributed on multiple units. Some or all of the units may be selected according to actual needs to achieve the purpose of the present embodiment.

[0052] in addition, Figure 3 This is a schematic diagram of the hardware structure of a terminal device provided in one embodiment of the present application. Figure 3 As shown, the terminal device may include an input device 30, a processor 31, an output device 32, a memory 33 and at least one communication bus 34. The communication bus 34 is used to realize the communication connection between the components. The memory 33 may include a high-speed RAM memory, and may also include a non-volatile storage NVM, such as at least one disk memory. Various programs can be stored in the memory 33 to complete various processing functions and implement the method steps of this embodiment.

[0053] Optionally, the processor 31 may be implemented as a central processing unit (CPU), an application-specific integrated circuit (ASIC), a digital signal processor (DSP), a digital signal processing device (DSPD), a programmable logic device (PLD), a field programmable gate array (FPGA), a controller, a microcontroller, a microprocessor or other electronic components, and the processor 31 is coupled to the input device 30 and the output device 32 via a wired or wireless connection.

[0054] Optionally, the input device 30 may include multiple input devices, for example, it may include at least one of a user interface for users, a device interface for devices, a programmable interface for software, a camera, and a sensor. Optionally, the device interface for devices may be a wired interface for data transmission between devices, or a hardware insertion interface for data transmission between devices (such as a USB interface, a serial port, etc.); Optionally, the user interface for users may be, for example, a control button for users, a voice input device for receiving voice input, and a touch sensing device for users to receive user touch input (such as a touch screen with a touch sensing function, a touch pad, etc.); Optionally, the programmable interface for the software may be, for example, an entry for users to edit or modify programs, such as an input pin interface or an input interface of a chip; Optionally, the transceiver may be a radio frequency transceiver chip with communication function, a baseband processing chip, and a transceiver antenna, etc. Audio input devices such as microphones may receive voice data. The output device 32 may include output devices such as displays and speakers.

[0055] In this embodiment, the processor of the terminal device includes functions for executing each module of the data processing device in each device. The specific functions and technical effects can be referred to the above embodiments and will not be repeated here.

[0056] Figure 4 A schematic diagram of the hardware structure of a terminal device provided in another embodiment of the present application. Figure 4 Yes Figure 3 A specific embodiment in the implementation process. Figure 4 As shown, the terminal device of this embodiment includes a processor 41 and a memory 42.

[0057] The processor 41 executes the computer program code stored in the memory 42 to implement the method in the above embodiment.

[0058] The memory 42 is configured to store various types of data to support operations on the terminal device. Examples of such data include instructions for any application or method used to operate on the terminal device, such as messages, pictures, videos, etc. The memory 42 may include a random access memory (RAM) and may also include a non-volatile memory, such as at least one disk storage.

[0059] Optionally, the processor 41 is provided in the processing component 40. The terminal device may further include: a communication component 43, a power component 44, a multimedia component 45, an audio component 46, an input / output interface 47 and / or a sensor component 48. The specific components included in the terminal device are set according to actual needs, and this embodiment does not limit this.

[0060] The processing component 40 generally controls the overall operation of the terminal device. The processing component 40 may include one or more processors 41 to execute instructions to complete all or part of the steps of the above method. In addition, the processing component 40 may include one or more modules to facilitate the interaction between the processing component 40 and other components. For example, the processing component 40 may include a multimedia module to facilitate the interaction between the multimedia component 45 and the processing component 40.

[0061] The power supply component 44 provides power to various components of the terminal device. The power supply component 44 may include a power management system, one or more power supplies, and other components associated with generating, managing, and distributing power to the terminal device.

[0062] The multimedia component 45 includes a display screen that provides an output interface between the terminal device and the user. In some embodiments, the display screen may include a liquid crystal display (LCD) and a touch panel (TP). If the display screen includes a touch panel, the display screen may be implemented as a touch screen to receive input signals from the user. The touch panel includes one or more touch sensors to sense touch, slide, and gestures on the touch panel. The touch sensor may not only sense the boundaries of a touch or slide action, but also detect the duration and pressure associated with the touch or slide operation.

[0063] The audio component 46 is configured to output and / or input audio signals. For example, the audio component 46 includes a microphone (MIC), and when the terminal device is in an operating mode, such as a speech recognition mode, the microphone is configured to receive an external audio signal. The received audio signal can be further stored in the memory 42 or sent via the communication component 43. In some embodiments, the audio component 46 also includes a speaker for outputting audio signals.

[0064] The input / output interface 47 provides an interface between the processing component 40 and the peripheral interface modules, which may be click wheels, buttons, etc. These buttons may include but are not limited to: volume buttons, start buttons, and lock buttons.

[0065] The sensor assembly 48 includes one or more sensors for providing various aspects of status assessment for the terminal device. For example, the sensor assembly 48 can detect the open / closed state of the terminal device, the relative positioning of the components, and the presence or absence of contact between the user and the terminal device. The sensor assembly 48 may include a proximity sensor configured to detect the presence of nearby objects without any physical contact, including detecting the distance between the user and the terminal device. In some embodiments, the sensor assembly 48 may also include a camera, etc.

[0066] The communication component 43 is configured to facilitate wired or wireless communication between the terminal device and other devices. The terminal device can access a wireless network based on a communication standard, such as WiFi, 2G or 3G, or a combination thereof. In one embodiment, the terminal device may include a SIM card slot for inserting a SIM card, so that the terminal device can log in to the GPRS network and establish communication with the service end through the Internet.

[0067] From the above, we can see that Figure 4 The communication component 43, the audio component 46, the input / output interface 47, and the sensor component 48 involved in the embodiment can all be used as Figure 3 Implementation method of the input device in the embodiment.

[0068] In the several embodiments provided in this application, it should be understood that the disclosed technical content can be implemented in other ways. Among them, the device embodiments described above are only schematic. For example, the division of the units can be a logical function division. There may be other division methods in actual implementation. For example, multiple units or components can be combined or integrated into another system, or some features can be ignored or not executed. Another point is that the mutual coupling or direct coupling or communication connection shown or discussed can be through some interfaces, indirect coupling or communication connection of units or modules, which can be electrical or other forms.

[0069] The units described as separate components may or may not be physically separated, and the components shown as units may or may not be physical units, that is, they may be located in one place or distributed on multiple units. Some or all of the units may be selected according to actual needs to achieve the purpose of the present embodiment.

[0070] In addition, each functional unit in each embodiment of the present invention may be integrated into one processing unit, or each unit may exist physically separately, or two or more units may be integrated into one unit. The above-mentioned integrated unit may be implemented in the form of hardware or in the form of software functional units.

[0071] If the integrated unit is implemented in the form of a software functional unit and sold or used as an independent product, it can be stored in a computer-readable storage medium. Based on this understanding, the technical solution of the present invention, in essence, or the part that contributes to the prior art, or all or part of the technical solution can be embodied in the form of a software product, and the computer software product is stored in a storage medium, including a number of instructions for a computer device (which can be a personal computer, a server or a network device, etc.) to perform all or part of the steps of the method described in each embodiment of the present invention. The aforementioned storage medium includes: U disk, read-only memory (ROM, Read-Only Memory), random access memory (RAM, Random Access Memory), mobile hard disk, magnetic disk or optical disk and other media that can store program codes.

[0072] The above is only a preferred embodiment of the present invention. It should be pointed out that for ordinary technicians in this technical field, several improvements and modifications can be made without departing from the principle of the present invention. These improvements and modifications should also be regarded as the scope of protection of the present invention.

Claims

1. A method for automatic correction and planning of tower inspection routes based on image key point recognition, characterized in that: include: Obtain original image data and key point recognition parameters; Processing the original image data according to the key point recognition parameters to obtain key point image data; Inputting the key point image data and the inspection route data into the correction planning model, and outputting the correction result and the planning result; The correction result and the planning result are verified to obtain a verification result.

2. The method according to claim 1, characterized in that Before processing the original image data according to the key point recognition parameters to obtain key point image data, the method further includes: The area in the original image data related to the key point recognition parameter is marked for key point recognition processing.

3. The method according to claim 1, characterized in that: The inputting of the key point image data and the inspection route data into the correction planning model and the outputting of the correction result and the planning result comprises: Training the revised planning model through historical data of key image recognition; Inputting the key point image data into the correction layer in the correction planning model to obtain the correction result; The key point image data and the inspection route data are input into the planning layer in the revised planning model to obtain the planning result.

4. The method according to claim 1, characterized in that: The verification of the correction result and the planning result to obtain the verification result includes: Comparing the correction result and the planning result with the correction planning threshold in the verification matrix to obtain a comparison result; The verification result is generated according to the comparison result.

5. A tower inspection route automatic correction and planning device based on image key point recognition, characterized in that: include: An acquisition module, used to acquire original image data and key point recognition parameters; A processing module, used for processing the original image data according to the key point recognition parameters to obtain key point image data; An input module, used to input the key point image data and inspection route data into the correction planning model, and output the correction result and planning result; The verification module is used to verify the correction result and the planning result to obtain a verification result.

6. The device according to claim 5, characterized in that The device also includes: The area in the original image data related to the key point recognition parameter is marked for key point recognition processing.

7. The device according to claim 5, characterized in that The input module comprises: A training unit, used for training the revised planning model through historical data of key image recognition; An input unit, used for inputting the key point image data into the correction layer in the correction planning model to obtain the correction result; The input unit is also used to input the key point image data and the inspection route data into the planning layer in the revised planning model to obtain the planning result.

8. The device according to claim 5, characterized in that The verification module comprises: A comparison unit, used for comparing the correction result and the planning result with the correction planning threshold in the verification matrix to obtain a comparison result; A generating unit is used to generate the verification result according to the comparison result.

9. A non-volatile storage medium, characterized in that: The non-volatile storage medium includes a stored program, wherein the program controls the device where the non-volatile storage medium is located to execute the method according to any one of claims 1 to 4 when the program is executed.

10. An electronic device, characterized in that: It comprises a processor and a memory; the memory stores computer-readable instructions, and the processor is used to execute the computer-readable instructions, wherein the computer-readable instructions execute the method described in any one of claims 1 to 4 when executed.

Citation Information

Patent Citations

  • Electric power tower unmanned aerial vehicle inspection route planning method and system

    CN113238578A

  • Marine unmanned aerial vehicle inspection flight path generation method and device and unmanned aerial vehicle

    CN113485453A

  • Method and device for automatically correcting route of unmanned aerial vehicle

    CN114677859A

  • Cruise path correction method and system based on historical faults of photovoltaic module

    CN114924590A

  • Power transformation equipment inspection robot path planning method, equipment and storage medium

    CN115933637A