Method for shortening overhaul period of nuclear power plant and storage medium

Through the analysis of the overhaul data of nuclear power plant overhaul situation and the optimization of accident analysis, SSC availability requirements are reduced, and the overhaul plan is re-formulated, which solves the problem of shortening the overhaul construction period in the existing technology, and effectively shortens the overhaul construction period and improves the flexibility of unit operation. .

CN118967092APending Publication Date: 2024-11-15SUZHOU NUCLEAR POWER RES INST CO LTD +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202410972298.6
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-07-19
Publication Date
2024-11-15

AI Technical Summary

Technical Problem

The existing technology is difficult to effectively shorten the overhaul period of nuclear power plants, and it mainly focuses on project identification and optimization, resource planning and time management, and lacks the optimization methods for accident analysis.

Method used

By analyzing the overhaul situation data, we can select optimized projects, optimize accident analysis, reduce SSC availability requirements, and re-formulate an overhaul plan to shorten the construction period.

Benefits of technology

The overhaul period has been shortened, and the accident analysis that can be optimized through logical correlation traceability optimization affects the time and arrangement of project, improving the flexibility and efficiency of unit overhaul.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118967092A_ABST
    Figure CN118967092A_ABST
Patent Text Reader

Abstract

The invention discloses a method for shortening the overhaul period of a nuclear power plant and a storage medium. The method for shortening the overhaul period of the nuclear power plant comprises the following steps of S1, analyzing according to existing overhaul condition data to obtain an optimizable project of a target nuclear power unit; s2, analyzing and acquiring accident analysis corresponding to the optimizable project; and S3, judging whether the accident analysis meets a rationality requirement or not, if not, optimizing the accident analysis, and optimizing an overhaul plan of the target nuclear power unit according to the optimized accident analysis so as to shorten the overhaul period. The method comprises the following steps: obtaining an optimizable project, carrying out corresponding analysis to obtain corresponding rationality suspected accident analysis, optimizing accident analysis influencing the time consumption and arrangement of the optimizable project through tracing of logic association, determining a more reasonable overhaul limiting condition according to the optimized accident analysis, and further optimizing an overhaul plan. Therefore, the purpose of shortening the unit overhaul period is achieved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the field of nuclear power, and in particular to a method and a storage medium for shortening the overhaul period of a nuclear power plant. Background Art

[0002] Regular overhaul is essential for operating nuclear power plants. The overhaul plan is a plan that carefully arranges all the work and activities that need to be implemented around the various goals set for the overhaul, and guides and coordinates the activities of personnel to ensure that the established overhaul goals are completed with high quality. The quality of the overhaul plan is the key to overhaul period control, so continuously optimizing the overhaul plan to shorten the overhaul period is one of the important tasks of overhaul management.

[0003] Normally, nuclear power plant overhaul planning engineers formulate and optimize overhaul plans according to established processes and control the overhaul period.

[0004] Currently, the research and practice on shortening the overhaul period of nuclear power plants mainly focuses on the three major links of project identification and optimization, resource planning and time management, and realizes overhaul optimization and shortening of construction period from the perspectives of overhaul planning, resource allocation and overhaul technology. Summary of the invention

[0005] The technical problem to be solved by the present invention is to provide a method and a storage medium for shortening the overhaul period of a nuclear power plant.

[0006] The technical solution adopted by the present invention to solve the technical problem is: construct a method for shortening the overhaul period of a nuclear power plant, which is applied to a target nuclear power unit to be optimized, comprising the following steps:

[0007] S1. Analyzing the existing overhaul data to obtain the optimizable items of the target nuclear power unit;

[0008] S2. Analyze and obtain the accident analysis corresponding to the optimizable project;

[0009] S3. Determine whether the accident analysis meets the rationality requirement. If not, optimize the accident analysis, and optimize the overhaul plan of the target nuclear power unit according to the optimized accident analysis to shorten the overhaul period.

[0010] Preferably, in the method for shortening the overhaul period of a nuclear power plant constructed by the present invention, before executing step S1, the following steps are further performed:

[0011] S0. Obtaining the existing overhaul situation data;

[0012] Step S0 is specifically as follows: S01, obtaining historical overhaul data of the target nuclear power unit;

[0013] Step S1 corresponds to: selecting at least one of the projects that occupy too many critical paths and the projects that have no substantial work from the historical overhaul situation data to obtain the optimizable project.

[0014] Preferably, in the method for shortening the overhaul period of a nuclear power plant constructed by the present invention, before executing step S1, the following steps are further performed:

[0015] S0. Obtaining the existing overhaul situation data;

[0016] Step S0 is specifically as follows: S02, obtaining historical overhaul data of the target nuclear power unit, and obtaining overhaul comparison data of other nuclear power units;

[0017] Step S1 corresponds to: comparing the historical overhaul situation data with the overhaul situation control data, and screening out the projects that take too long from the historical overhaul situation data to obtain the optimizable projects.

[0018] Preferably, in the method for shortening the overhaul period of a nuclear power plant constructed by the present invention, step S2 comprises:

[0019] S21, analyzing the optimizable items to obtain corresponding restriction conditions;

[0020] S22. Analyze the specific requirements and sources of the restriction conditions to obtain an accident analysis corresponding to the optimizable project.

[0021] Preferably, in the method for shortening the overhaul period of a nuclear power plant constructed by the present invention, step S22 is specifically:

[0022] Determine the correspondence between the restriction conditions and the accident analysis according to the technical specifications, and analyze the specific requirements and sources of the restriction conditions;

[0023] The accident analyses satisfying the restriction conditions are screened out according to the corresponding relationship and recorded as the accident analyses corresponding to the optimizable items.

[0024] Preferably, in the method for shortening the overhaul period of a nuclear power plant constructed by the present invention, in step S3, the judgment of whether the accident analysis meets the rationality requirement is specifically:

[0025] Calculate the occurrence frequency of the initiating event corresponding to the accident analysis, and if the occurrence frequency is lower than a preset frequency, determine that the accident analysis does not meet the rationality requirement; or,

[0026] Obtain the accident analysis difference between the target nuclear power unit and other nuclear power units, and if the accident analysis difference is greater than a preset difference, determine that the accident analysis does not meet the rationality requirement.

[0027] Preferably, in the method for shortening the overhaul period of a nuclear power plant constructed by the present invention, in step S3, the optimizing the accident analysis is specifically:

[0028] Obtaining analysis elements corresponding to the accident analysis;

[0029] On the premise of meeting nuclear safety requirements and operational safety conditions, the specific requirements of the analysis elements should be reasonably lowered.

[0030] Preferably, in the method for shortening the overhaul period of a nuclear power plant constructed in the present invention, the accident analysis elements include: at least one of: operating condition classification, initial state, basic assumptions, functional assumptions and acceptance criteria.

[0031] Preferably, in the method for shortening the overhaul period of a nuclear power plant constructed by the present invention, in step S3, the overhaul plan of the target nuclear power unit is optimized according to the optimized accident analysis, specifically:

[0032] According to the optimized accident analysis, the unit status requirement or SSC availability requirement is re-proposed as the new constraint condition;

[0033] The overhaul plan is optimized according to the new limiting conditions.

[0034] The present invention also constructs a storage medium in which a computer program is stored. When the computer program is executed by a processor, the steps of any of the above methods for shortening the overhaul period of a nuclear power plant are implemented.

[0035] By implementing the present invention, the following beneficial effects are achieved:

[0036] The method for shortening the overhaul period of a nuclear power plant disclosed in the present invention comprises the following steps: S1, obtaining the optimizable items of the target nuclear power unit according to the existing overhaul situation data analysis; S2, analyzing and obtaining the accident analysis corresponding to the optimizable items; S3, judging whether the accident analysis meets the rationality requirements, if not, optimizing the accident analysis, and optimizing the overhaul plan of the target nuclear power unit according to the optimized accident analysis, so as to shorten the overhaul period. By obtaining the optimizable items, the corresponding analysis of the accident analysis with questionable rationality is obtained, and by tracing the logical association, the accident analysis that affects the time and arrangement of the optimizable items is optimized, thereby shortening the overhaul period of the unit. BRIEF DESCRIPTION OF THE DRAWINGS

[0037] The present invention will be further described below with reference to the accompanying drawings and embodiments, in which:

[0038] Figure 1 It is a schematic diagram of the process of optimizing the overhaul period in the prior art;

[0039] Figure 2 It is a schematic diagram of the overall process of optimizing the overhaul period of the present invention;

[0040] Figure 3 It is a flow chart of the method for shortening the overhaul period of a nuclear power plant in the first embodiment of the present invention. DETAILED DESCRIPTION

[0041] In order to have a clearer understanding of the technical features, purposes and effects of the present invention, specific embodiments of the present invention are now described in detail with reference to the accompanying drawings.

[0042] It should be noted that the flowcharts shown in the accompanying drawings are only exemplary and do not necessarily include all the contents and operations / steps, nor do they have to be executed in the order described. For example, some operations / steps can be decomposed, while some operations / steps can be combined or partially combined, so the actual execution order may change according to actual conditions.

[0043] The block diagrams shown in the accompanying drawings are only functional entities and do not necessarily correspond to physically independent entities. That is, these functional entities can be implemented in software form, or in one or more hardware modules or integrated circuits, or in different networks and / or processor devices and / or microcontroller devices.

[0044] At present, relevant research and practice mainly focus on Figure 1 The second, third and fourth links (project identification and optimization, resource planning, and time management) in the project can achieve overhaul optimization and shorten the construction period from the perspective of overhaul planning and resource allocation.

[0045] The data collection and analysis phase includes: collecting regulations or requirements in nuclear safety regulations and nuclear power plant technical specifications to ensure nuclear safety; collecting and reviewing historical overhaul reports, operation records, maintenance records, and defect handling in previous cycles; determining required maintenance activities based on the equipment operation cycle, such as fuel replacement, equipment inspection, preventive replacement, etc.

[0046] The project identification and optimization phase includes: determining the periodic maintenance projects that need to be carried out, including routine inspections, preventive maintenance, improvement projects, etc.; conducting risk assessments on each project, optimizing the operation sequence, and improving efficiency.

[0047] The resource planning phase includes: estimating the required human, material (spare parts, tools, etc.) and time resources; arranging sufficient staff, including internal employees and external contractors; preparing necessary spare parts and materials to ensure adequate supply.

[0048] The time management process includes: developing a detailed overhaul schedule, considering the possibility of cross-operation to shorten the construction period; and rationally arranging the work on the critical path to ensure that it will not cause delays to the entire project.

[0049] The communication and coordination phase includes: communicating with relevant departments (such as operations, safety, technical support, etc.) to ensure that the overhaul plan is coordinated with other operational activities; maintaining communication with regulatory agencies to ensure that all regulatory requirements are met.

[0050] The tracking and adjustment phase includes: real-time tracking of progress during the overhaul process, and making adjustments when necessary to cope with changes in actual conditions; timely updating relevant parties on progress and any changes to ensure that the project is completed on time.

[0051] The evaluation and feedback phase includes: conducting a summary evaluation after the overhaul is completed, recording the actual problems encountered and their solutions; collecting feedback information to provide lessons learned for the planning of the next overhaul cycle.

[0052] See also Figure 1 and Figure 2 The present invention starts from the currently neglected data collection and analysis link, optimizes accident analysis, and reasonably reduces the availability requirements of SSC (i.e., nuclear power plant structures, systems and equipment) to give overhaul arrangements greater flexibility, ultimately achieving the purpose of shortening the unit overhaul period.

[0053] SSC availability requirement is one of the important inputs for formulating maintenance strategies, which will directly affect the overhaul period. Take a certain unit as an example. The unit is equipped with four safety injection systems, each of which can guarantee 100% functional requirements. Each safety injection system includes a medium-pressure injection pump, a low-pressure injection pump, a heat exchanger and an injection tank covered by nitrogen. If the technical specification requires three columns to be available, the maintenance of the safety injection system can only be carried out column by column. Assuming that the maintenance period of one safety injection system is T, the maintenance period for completing the four safety injection systems is 4T. However, if the technical specification requirements are lowered and it is set to be available for two columns, then the parallel maintenance of the two safety injection systems can be achieved, and the total maintenance period is shortened from 4T to 2T.

[0054] In the existing forward design process of overhaul plans, the availability requirements of equipment are determined through accident analysis. Deterministic safety analysis is the basis for the design, construction and operation of nuclear power plants at this stage. It screens representative initiating events to cover accidents that may occur during the life of the unit, and then uses deterministic methods to conservatively prove that the unit's protection and mitigation measures are capable of coping with such conditions, and that the consequences of the accident can meet the acceptance criteria. During the unit operation phase, the initial operating condition assumptions and functional assumptions made in the accident analysis are converted into requirements for unit status and SSC availability in the operating technical specifications.

[0055] Therefore, this invention proposes a method for shortening the overhaul period of a nuclear power plant by optimizing accident analysis, see Figure 2 and Figure 3 The first embodiment of the present invention discloses a method for shortening the overhaul period of a nuclear power plant, which is applied to a target nuclear power unit to be optimized, and includes the following steps:

[0056] Collecting potential optimization projects: S1. Obtaining optimizable projects of the target nuclear power unit based on existing overhaul situation data analysis. Optimizable projects are potential optimization projects in the overhaul plan. To determine whether to optimize potential optimization projects, it is necessary to analyze the recorded overhaul situation data.

[0057] Clarify the restriction conditions and identify the relevant accident analysis: S2. Analyze and obtain the accident analysis corresponding to the optimizable project.

[0058] Relaxing restrictions and optimizing overhaul plans: S3. Determine whether the accident analysis meets the rationality requirements. If not, optimize the accident analysis, and optimize the overhaul plan of the target nuclear power unit based on the optimized accident analysis to shorten the overhaul period.

[0059] Among them, according to the nuclear safety guideline "Management of Modifications in Nuclear Power Plants", before implementing the optimized overhaul plan, there is also a license application step. It is necessary to determine whether the optimization of the accident analysis and restriction conditions is a safety-critical modification. If it is a safety-critical modification, a corresponding application should be made and implemented after approval.

[0060] Furthermore, by analyzing the overhaul history of the target nuclear power unit, it is possible to identify the shortcomings and pain points in the overhaul plan and find out where there is "waste" in the overhaul period. Therefore, in the method for shortening the overhaul period of a nuclear power plant constructed by the present invention, before executing step S1, the following steps are also performed: S0, obtaining the existing overhaul situation data; step S0 is specifically: S01, obtaining the historical overhaul situation data of the target nuclear power unit; step S1 corresponds to: screening out at least one of the projects that occupy too many critical paths and the projects without substantive work from the historical overhaul situation data to obtain the optimizable project.

[0061] For example, with the continuous improvement of the overhaul management level of nuclear power plants, the completion time of the pre-unloading preparation process of a nuclear power plant during the overhaul is constantly advanced, while the decay cooling time of the post-subcritical fuel assembly specified in the technical specification remains unchanged. This will lead to the situation where the overhaul unloading affects the overhaul critical path due to waiting for the decay cooling time of the post-subcritical fuel assembly to meet the requirements. Therefore, the decay cooling time requirement of the post-subcritical fuel assembly becomes an important factor limiting the shortening of the overhaul period, and shortening the decay cooling time requirement of the post-subcritical fuel assembly can be regarded as an optimizable project.

[0062] Furthermore, it is also possible to identify the overhaul links of the target nuclear power unit that take significantly longer time than other nuclear power units during the overhaul period by making a horizontal comparison with the overhaul conditions of other nuclear power units. If the reasons of insufficient resources or unreasonable plans can be ruled out, and it is determined that the overhaul plan is subject to restrictions on the unit status or SSC availability in the technical specifications on which the overhaul plan is based, then this link can be used as a potential optimization project. Therefore, in the method for shortening the overhaul period of a nuclear power plant constructed by the present invention, before executing step S1, the following steps are also performed: S0, obtaining the existing overhaul situation data; step S0 is specifically: S02, obtaining the historical overhaul situation data of the target nuclear power unit, and obtaining the overhaul situation comparison data of other nuclear power units; step S1 corresponds to: comparing the historical overhaul situation data with the overhaul situation comparison data, and filtering out the projects that take too long from the historical overhaul situation data to obtain the optimizable projects. The aforementioned other nuclear power units can be either units of the same model or units of the same type. In some other embodiments, the overhaul processes of the same type may be used for horizontal comparison, with the goal of indicating where there may be room for optimization, thereby playing a role in discovering clues and guiding the direction of optimization.

[0063] In other embodiments, after identifying the overhaul phase of the target nuclear power unit that takes significantly longer than that of other units, it is necessary to judge these overhaul phases against the technical specifications, and screen out the overhaul phases that take too long due to limitations in the technical specifications regarding the unit status or SSC availability, and then record these overhaul phases as optimizable projects.

[0064] For example, compared with a certain type of nuclear power unit A and another type of nuclear power unit B, which only have two safety injection systems, the target nuclear power unit C has four safety injection systems, which has higher redundancy in design, but lower flexibility in overhaul arrangements, and only allows preventive maintenance of one of the trains in state E. If it is proved through optimized accident analysis that only two trains are available to meet the requirements, then the remaining two trains can be repaired at the same time. In this way, the total overhaul period of the target nuclear power unit C can be shortened from 4T to 2T. Therefore, in this example, the determined optimizable item is the available quantity requirement of the safety injection system.

[0065] Further, in order to obtain the accident analysis corresponding to the optimizable project, it is necessary to determine the constraints of the optimizable project, and then derive the accident analysis associated with the logical upstream from the specific requirements of these constraints and the relevant sources of these constraints. Therefore, in the method for shortening the overhaul period of a nuclear power plant constructed by the present invention, step S2 includes: S21, analyzing the optimizable project to obtain the corresponding constraints; S22, analyzing the specific requirements and sources of the constraints to obtain the accident analysis corresponding to the optimizable project. The source of the constraints of the overhaul project corresponding to the optimizable project can be the operating technical specification, the technical specification or the final safety analysis report. For example, through analysis, it can be clarified that the restrictive factors of the safety injection system of the target nuclear power unit in preventive maintenance come from the operating technical specification, because the operating technical specification stipulates that the four-row medium-pressure safety injection system must be available when the unit is in the reactor power operation mode, the steam generator cooling normal shutdown mode, the RIS (Reactor Injection System)-RHR (Residual Heat Removal System) cooling normal shutdown mode and the maintenance shutdown mode.

[0066] Further, in the method for shortening the overhaul period of a nuclear power plant constructed by the present invention, step S22 is specifically as follows: establishing a technical specification to determine the corresponding relationship between the restriction condition and the accident analysis; screening out the accident analysis that satisfies the restriction condition according to the corresponding relationship, and recording it as the accident analysis corresponding to the optimizable project. For example, through analysis, it can be clarified that the safety injection system is used to mitigate breach accidents under the shutdown condition of the target nuclear power unit, and such accidents put forward corresponding requirements for the availability of the safety injection system.

[0067] In other embodiments, in order to obtain the accident analysis corresponding to the optimizable project, the specific restrictions given in the technical specification are identified based on the optimizable project and the pre-sorted "Summary Table of Unit Status and SSC Availability Requirements in Technical Specifications", and then the relevant accident analysis is identified based on the restrictions and the pre-sorted "Summary Table of Safety Analysis Applicable to Technical Specifications", and it is clarified which accident analysis requirements these restrictions are proposed to meet.

[0068] Furthermore, in the method for shortening the overhaul period of a nuclear power plant constructed by the present invention, in step S3, the judgment of whether the accident analysis meets the rationality requirement is specifically: calculating the occurrence frequency of the initiating event corresponding to the accident analysis, and if the occurrence frequency is lower than a preset frequency, then judging that the accident analysis does not meet the rationality requirement. The preset frequency may be the lower limit of the occurrence frequency of the design reference condition corresponding to the accident.

[0069] Alternatively, the judgment of whether the accident analysis meets the rationality requirement is specifically as follows: obtaining the difference in accident analysis between the target nuclear power unit and other nuclear power units, and if the difference in accident analysis is greater than a preset difference, determining that the accident analysis does not meet the rationality requirement. Such a difference in accident analysis may be that the accident analysis of the target nuclear power unit is significantly more stringent than that of other nuclear power units, and in this case, the requirements for the accident analysis should be relaxed to make it more reasonable.

[0070] Since the equipment cannot be used during maintenance, the number of columns that can be repaired at the same time is reduced when the SSC availability requirements are high. For example, based on the assumption that four columns are available for the target nuclear power unit, if there are a total of four columns in the safety injection system, according to the design basis accident analysis, it is necessary to consider one column pipeline rupture (assuming a rupture accident), one column failure, one column just under maintenance, and the last column normal operation to mitigate the accident. In order to meet the SSC availability requirements, these four target nuclear power units can only be repaired one by one, and the maintenance time will be prolonged. If it is not considered as a design basis accident, there is no need to assume that one column is faulty when the accident occurs, so that two columns can be repaired at the same time, and thus, the overhaul period can be optimized from this point.

[0071] Furthermore, when it is found that there is indeed an unreasonable accident analysis in the overhaul plan, it is necessary to optimize the corresponding accident analysis and restrictions, and simultaneously involve the update of relevant nuclear power plant documents, which include but are not limited to the final safety analysis report, technical specifications and maintenance outlines. In order to shorten the overhaul period of nuclear power plants, it is necessary to relax the corresponding restrictions on the corresponding unreasonable accident analysis. In the method for shortening the overhaul period of nuclear power plants constructed by the present invention, in step S3, the optimization of the accident analysis is specifically: obtaining the analysis elements corresponding to the accident analysis; on the premise of meeting nuclear safety requirements and operating safety conditions, reasonably reducing the specific requirements of the analysis elements. For example, by analyzing and demonstrating that the coolant loss accident of a target nuclear power unit in low mode is managed as a special operating condition, a more realistic accident analysis hypothesis can be adopted, thereby optimizing the relevant management requirements in the unit operation technical specifications, allowing two injection systems to be repaired at the same time, which is conducive to shortening the unit overhaul period.

[0072] A breach accident can be regarded as an extreme case of a coolant loss accident. The frequency of breach accidents in low mode is very low and can be regarded as not a design basis accident. Therefore, the analysis of breach accidents in low mode can be less conservative than the design basis accident analysis, that is, there is no need to consider the superposition of various unfavorable factors. Therefore, the reliability requirements of the response measures do not need to be set too high, that is, there is no need to set that only one of the trains can be repaired while the other three trains must remain in a state of being ready for use at any time. Assuming that the breach happens to occur on the injection pipeline of one of the trains, the other train can alleviate the accident. Therefore, two trains can remain in a state of being ready for use, and the remaining two trains can be repaired at the same time, which is conducive to shortening the overhaul period of the unit.

[0073] Furthermore, in the method for shortening the overhaul period of a nuclear power plant constructed by the present invention, the accident analysis elements include: at least one of the operating condition classification, initial state, basic assumptions, functional assumptions and acceptance criteria. If there are overly conservative or unreasonable situations, it is possible to consider carrying out accident analysis optimization work on the premise of meeting the requirements of relevant nuclear safety regulations and ensuring the safety of unit operation. Among them, the basic assumptions include: whether to consider the single fault criterion and whether to consider the superposition of the loss of external power supply, etc.

[0074] Whether a hypothetical accident is considered as a design basis accident will affect the requirements of relevant measures for mitigating the accident. For example, through horizontal comparison with multiple other nuclear power units, it is found that the target nuclear power unit is the only unit in the current mainstream pressurized water reactor power plant that uses small rupture accidents of low-state primary circuits and their connected pipelines as design basis accidents in safety analysis. The requirements of the target nuclear power unit on this overhaul project are more stringent than those of other nuclear power units. The single failure criterion must be considered in the design basis accident analysis, that is, in the design basis accident analysis, it must be assumed that when the accident occurs, one of the most effective devices for mitigating the accident just fails. This increases the availability requirements of the injection system of the target nuclear power unit in the shutdown state and reduces the overhaul flexibility of the target nuclear power unit. Therefore, it is necessary to consider relaxing the requirements for the availability of the injection system of the target nuclear power unit to shorten the overhaul period under the premise of safety.

[0075] Furthermore, in the method for shortening the overhaul period of a nuclear power plant constructed by the present invention, in step S3, the overhaul plan of the target nuclear power unit is optimized according to the optimized accident analysis, specifically: according to the optimized accident analysis, the unit status requirements or SSC availability requirements are re-proposed as the new constraints; the overhaul plan is optimized according to the new constraints. By implementing the present invention, the SSC availability requirements are systematically, logically and based on evidence. In this way, equipment outside the requirements can be flexibly arranged for maintenance, shortening the total overhaul period.

[0076] For operating nuclear power plants, reasonably determining the redundancy requirements of key dedicated safety facilities under the premise of ensuring unit safety, and allowing multiple trains to be repaired in parallel while meeting the redundancy requirements are effective measures to shorten the overhaul period.

[0077] According to the requirements of the nuclear safety guideline "Management of Nuclear Power Plant Modifications", nuclear power plant modifications that are determined to be important to safety should be submitted to the National Nuclear Safety Administration for approval. If the modification is not important to safety, the nuclear power plant can manage it on its own.

[0078] A second embodiment of the present invention discloses a storage medium storing a computer program, which, when executed by a processor, implements the steps of the method for shortening the overhaul period of a nuclear power plant in any of the above embodiments.

[0079] By implementing the present invention, the following beneficial effects are achieved:

[0080] In the method for shortening the overhaul period of a nuclear power plant disclosed in the present invention, potential optimization items with optimization space in the overhaul of a unit are screened rationally and with basis, optimizable items are obtained, specific restrictive conditions and their sources are clarified, operating conditions and initiating events that have a significant impact on the overhaul period are identified, and the rationality of appropriately reducing the availability requirements of dedicated safety facilities is demonstrated through analysis and evaluation of various elements of accident analysis, providing a basis for optimizing the technical specification, and ultimately achieving the purpose of optimizing the overhaul plan and shortening the overhaul period.

[0081] It can be understood that the above embodiments only express the preferred implementation modes of the present invention, and the description thereof is relatively specific and detailed, but it cannot be understood as limiting the patent scope of the present invention. It should be pointed out that, for ordinary technicians in this field, without departing from the concept of the present invention, the above embodiments or technical features can be freely combined, and several deformations and improvements can be made, which all belong to the protection scope of the present invention, that is, the embodiments described in "some embodiments" can be freely combined with any of the above and below embodiments. Therefore, all equivalent changes and modifications made to the scope of the claims of the present invention should fall within the scope of the claims of the present invention.

Claims

1. A method for shortening the overhaul period of a nuclear power plant, applied to a target nuclear power unit to be optimized, characterized in that: The following steps are involved: S1. Analyzing the existing overhaul data to obtain the optimizable items of the target nuclear power unit; S2. Analyze and obtain the accident analysis corresponding to the optimizable project; S3. Determine whether the accident analysis meets the rationality requirement. If not, optimize the accident analysis, and optimize the overhaul plan of the target nuclear power unit according to the optimized accident analysis to shorten the overhaul period.

2. The method for shortening the overhaul period of a nuclear power plant according to claim 1, characterized in that: Before executing step S1, the following steps are also performed: S0. Obtaining the existing overhaul situation data; Step S0 is specifically as follows: S01, obtaining historical overhaul data of the target nuclear power unit; Step S1 corresponds to: selecting at least one of the projects that occupy too many critical paths and the projects that have no substantial work from the historical overhaul situation data to obtain the optimizable project.

3. The method for shortening the overhaul period of a nuclear power plant according to claim 1, characterized in that: Before executing step S1, the following steps are also performed: S0. Obtaining the existing overhaul situation data; Step S0 is specifically as follows: S02, obtaining historical overhaul data of the target nuclear power unit, and obtaining overhaul comparison data of other nuclear power units; Step S1 corresponds to: comparing the historical overhaul situation data with the overhaul situation control data, and screening out the projects that take too long from the historical overhaul situation data to obtain the optimizable projects.

4. The method for shortening the overhaul period of a nuclear power plant according to claim 1, characterized in that: Step S2 includes: S21, analyzing the optimizable items to obtain corresponding restriction conditions; S22. Analyze the specific requirements and sources of the restriction conditions to obtain an accident analysis corresponding to the optimizable project.

5. The method for shortening the overhaul period of a nuclear power plant according to claim 4, characterized in that: Step S22 is specifically as follows: Determine the correspondence between the restriction conditions and the accident analysis according to the technical specifications, and analyze the specific requirements and sources of the restriction conditions; The accident analyses satisfying the restriction conditions are screened out according to the corresponding relationship and recorded as the accident analyses corresponding to the optimizable items.

6. The method for shortening the overhaul period of a nuclear power plant according to claim 1, characterized in that: In step S3, the judgment of whether the accident analysis meets the rationality requirement is specifically as follows: Calculate the occurrence frequency of the initiating event corresponding to the accident analysis, and if the occurrence frequency is lower than a preset frequency, determine that the accident analysis does not meet the rationality requirement; or, Obtain the accident analysis difference between the target nuclear power unit and other nuclear power units, and if the accident analysis difference is greater than a preset difference, determine that the accident analysis does not meet the rationality requirement.

7. The method for shortening the overhaul period of a nuclear power plant according to claim 1, characterized in that: In step S3, the optimization of the accident analysis is specifically as follows: Obtaining analysis elements corresponding to the accident analysis; On the premise of meeting nuclear safety requirements and operational safety conditions, the specific requirements of the analysis elements should be reasonably lowered.

8. The method for shortening the overhaul period of a nuclear power plant according to claim 7, characterized in that: The accident analysis elements include: at least one of: operating condition classification, initial state, basic assumptions, functional assumptions and acceptance criteria.

9. The method for shortening the overhaul period of a nuclear power plant according to claim 4, characterized in that: In step S3, the overhaul plan of the target nuclear power unit is optimized according to the optimized accident analysis, specifically: According to the optimized accident analysis, the unit status requirement or SSC availability requirement is re-proposed as the new constraint condition; The overhaul plan is optimized according to the new limiting conditions.

10. A storage medium storing a computer program, characterized in that: The computer program implements the steps of the method for shortening the overhaul period of a nuclear power plant according to any one of claims 1 to 9 when executed by a processor.