Method and device for configuring broadband oscillation multi-damping controller
By establishing impedance network models and optimization models for power systems and coordinating the design of multi-damped controller parameters, the problem that single-machine equivalent models in power systems cannot accurately characterize dynamic behavior and multi-machine system oscillations is solved, thus achieving system stability and equipment safety.
Patent Information
- Application Number
- CN202411129872.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-16
- Publication Date
- 2024-11-15
AI Technical Summary
In existing technologies, single-machine equivalent models cannot accurately characterize the dynamic behavior of a system. In multi-machine systems, if a coordinated design method is not adopted, new oscillation problems will arise, leading to damage to power system equipment and instability hazards.
By collecting target parameters of the power system, an impedance network model is established, and a first and second optimization model of the multi-damped controller is constructed. The control parameters are designed in a coordinated manner to generate configuration parameters of the multi-damped controller that meet the preset conditions, thereby ensuring the global stabilization of the oscillation mode.
It effectively suppresses broadband oscillations in large-scale power systems, ensuring the safety and stability of system equipment, and solves the problem that single-machine equivalent models cannot accurately characterize the dynamic behavior of the system and the oscillation problem in multi-machine systems.
Smart Images

Figure CN118970940A_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the technical field of power system operation and stability control, and in particular to a configuration method and device for a broadband oscillation multi-damping controller. Background Art
[0002] With the increasingly prominent "double high" characteristics in the development of power systems, converter-based power supplies or converter interface power supplies, various AC and DC transmission systems that rely on power electronic equipment to achieve energy conversion, and new loads represented by electric vehicles, distributed power sources, and microgrids are profoundly changing the stability mechanism and dynamic characteristics of new power systems from different perspectives of source-grid-load. Massively distributed and widely accessed power electronic equipment and their interaction with AC and DC power grids can cause broadband oscillation problems with a wide frequency range, multiple dominant modes, and large-range time-varying frequencies. Broadband oscillations can cause equipment damage or unit disconnection in the power system, seriously endangering equipment safety and system stability.
[0003] In the related art, broadband oscillation suppression measures can be divided into grid-side measures and unit-side measures. Grid-side measures are usually based on flexible AC transmission system equipment or dedicated suppression converters, while unit-side measures include adjusting control parameters, replacing control structures, additional damping control or embedded blocking filtering, etc.
[0004] However, in related technologies, centralized control is mostly performed on a single device. In actual large-scale systems, due to the access of massive heterogeneous converter devices and the complex grid structure and form, the single-machine equivalent model cannot accurately characterize the dynamic behavior of the system. In addition, if the control parameters of the multi-power system stabilizer are not designed in a coordinated manner in a multi-machine system, the interaction between them may induce new oscillations, which urgently needs to be improved. Summary of the invention
[0005] The present application provides a configuration method and device for a broadband oscillation multi-damping controller to solve the defects in the related technology that the single-machine equivalent model cannot accurately characterize the dynamic behavior of the system, and the new oscillation problem induced by the interaction in the multi-machine system if the coordinated design method is not adopted.
[0006] The first aspect of the present application provides a configuration method for a wide-band oscillation multi-damping controller, comprising the following steps: collecting target parameters of a power system, and establishing an impedance network model of the power system based on the target parameters; establishing a first optimization model of the multi-damping controller based on the impedance network model; establishing a second optimization model of the multi-damping controller by combining the impedance network model and the first optimization model, and obtaining the expected parameters of the multi-damping controller based on the first optimization model and the second optimization model, so as to generate configuration parameters of the multi-damping controller that meet preset realistic conditions and / or target scenarios based on the expected parameters.
[0007] Optionally, in one embodiment of the present application, establishing a first optimization model of a multi-damping controller based on the impedance network model includes: obtaining at least one wide-band oscillation mode of the power system based on the impedance network model; and establishing the first optimization model of the multi-damping controller based on the at least one wide-band oscillation mode.
[0008] Optionally, in one embodiment of the present application, the first optimization model may be, but is not limited to, expressed as:
[0009]
[0010] Among them, the column vector x represents the installation point, M p is the evaluation function, C ad is the cost vector, C1 to C5 respectively represent the relationship constraint between the participation factor index and the given threshold, the capacity constraint of the point controller to be installed, the theoretical additional capacity constraint of the point controller to be installed, the actual additional capacity constraint of the point controller to be installed, and the unit cost constraint.
[0011] Optionally, in one embodiment of the present application, the second optimization model of the multi-damping controller is established by combining the impedance network model and the first optimization model, including: determining an equivalent circuit of the multi-damping controller based on the impedance network model; obtaining at least one constraint condition of the second optimization model based on the equivalent circuit; and establishing the second optimization model of the multi-damping controller based on the at least one constraint condition and the first optimization model.
[0012] Optionally, in one embodiment of the present application, the second optimization model may be, but is not limited to, expressed as:
[0013]
[0014] Among them, α n represents the real part of the eigenvalue corresponding to the oscillation mode n, and the constraints C1 to C5 respectively represent the relationship constraint between the control gain and the converter output capacity, the gain upper limit constraint, the impedance phase angle constraint, the oscillation mode frequency constraint, and the oscillation stability constraint.
[0015] Optionally, in one embodiment of the present application, the expected parameters of the multi-damping controller are obtained according to the first optimization model and the second optimization model, so as to generate configuration parameters of the multi-damping controller that meet preset realistic conditions and / or target scenarios based on the expected parameters, including: determining the initial expected parameters of the multi-damping controller based on the first optimization model; obtaining the expected parameters of the multi-damping controller according to the initial expected parameters and the second optimization model; judging whether the expected parameters meet preset realistic conditions and / or target scenarios; if the expected parameters meet the preset realistic conditions and / or target scenarios, generating the configuration parameters based on the expected parameters, otherwise adjusting the expected parameters based on target parameters that meet the preset realistic conditions and / or target scenarios, and generating the configuration parameters based on the expected parameters.
[0016] The second aspect of the present application provides a configuration device for a wide-band oscillation multi-damping controller, including: an acquisition module, used to acquire target parameters of an electric power system and establish an impedance network model of the electric power system based on the target parameters; an establishment module, used to establish a first optimization model of the multi-damping controller based on the impedance network model; a configuration module, used to establish a second optimization model of the multi-damping controller in combination with the impedance network model and the first optimization model, and obtain the expected parameters of the multi-damping controller based on the first optimization model and the second optimization model, so as to generate configuration parameters of the multi-damping controller that meet preset realistic conditions and / or target scenarios based on the expected parameters.
[0017] Optionally, in one embodiment of the present application, the establishment module includes: a first generation unit, used to obtain at least one wide-frequency oscillation mode of the power system based on the impedance network model; a first establishment unit, used to establish a first optimization model of the multi-damping controller based on the at least one wide-frequency oscillation mode.
[0018] Optionally, in one embodiment of the present application, the first optimization model may be, but is not limited to, expressed as:
[0019]
[0020] Among them, the column vector x represents the installation point, M p is the evaluation function, C ad is the cost vector, C1 to C5 respectively represent the relationship constraint between the participation factor index and the given threshold, the capacity constraint of the point controller to be installed, the theoretical additional capacity constraint of the point controller to be installed, the actual additional capacity constraint of the point controller to be installed, and the unit cost constraint.
[0021] Optionally, in one embodiment of the present application, the configuration module includes: a first determination unit, used to determine the equivalent circuit of the multi-damping controller based on the impedance network model; an acquisition unit, used to acquire at least one constraint condition of the second optimization model based on the equivalent circuit; and a second establishment unit, used to establish the second optimization model of the multi-damping controller based on the at least one constraint condition and the first optimization model.
[0022] Optionally, in one embodiment of the present application, the second optimization model may be, but is not limited to, expressed as:
[0023]
[0024] Among them, α n represents the real part of the eigenvalue corresponding to the oscillation mode n, and the constraints C1 to C5 respectively represent the relationship constraint between the control gain and the converter output capacity, the gain upper limit constraint, the impedance phase angle constraint, the oscillation mode frequency constraint, and the oscillation stability constraint.
[0025] Optionally, in one embodiment of the present application, the configuration module includes: a second determination unit, used to determine the initial expected parameters of the multi-damping controller based on the first optimization model; a second generation unit, used to obtain the expected parameters of the multi-damping controller according to the initial expected parameters and the second optimization model; a judgment unit, used to judge whether the expected parameters meet preset realistic conditions and / or target scenarios; a configuration unit, used to generate the configuration parameters based on the expected parameters when the expected parameters meet the preset realistic conditions and / or the target scenarios, otherwise adjust the expected parameters based on the target parameters that meet the preset realistic conditions and / or the target scenarios, and generate the configuration parameters based on the expected parameters.
[0026] The third aspect of the present application provides an electronic device, comprising: a memory, a processor, and a computer program stored in the memory and executable on the processor, wherein the processor executes the program to implement a configuration method of a wide-band oscillation multi-damping controller as described in the above embodiment.
[0027] The fourth aspect of the present application provides a computer-readable storage medium, which stores a computer program. When the program is executed by a processor, it implements the configuration method of the broadband oscillation multi-damping controller as described above.
[0028] The fifth aspect of the present application provides a computer program product, including a computer program, which, when executed, implements the configuration method of the broadband oscillation multi-damping controller as described above.
[0029] The embodiment of the present application can establish the first optimization model and the second optimization model of the multi-damping controller according to the target parameters and the impedance network model, and obtain the configuration parameters of the multi-damping controller that meets certain realistic conditions and / or target scenarios by solving the above optimization models. By designing the control capacity and layout strategy with full operating condition coverage and optimal capacity cost, the problem of coordinated combination of different controller parameters is solved to ensure the global stabilization of the oscillation mode. Thus, the defects of the related technology that the single-machine equivalent model cannot accurately describe the dynamic behavior of the system, and the new oscillation problems induced by the interaction in the multi-machine system if the coordinated design method is not adopted are solved.
[0030] Additional aspects and advantages of the present application will be given in part in the description below, and in part will become apparent from the description below, or will be learned through the practice of the present application. BRIEF DESCRIPTION OF THE DRAWINGS
[0031] The above and / or additional aspects and advantages of the present application will become apparent and easily understood from the following description of the embodiments in conjunction with the accompanying drawings, in which:
[0032] Figure 1 A flowchart of a configuration method of a broadband oscillation multi-damping controller provided according to an embodiment of the present application;
[0033] Figure 2 A block diagram of a multi-wind farm and a coordinated control system thereof provided according to an embodiment of the present application;
[0034] Figure 3 A block diagram of output currents of different wind farm controllers provided according to an embodiment of the present application;
[0035] Figure 4 A block diagram showing a comparison between centralized control and collaborative control provided according to an embodiment of the present application;
[0036] Figure 5 A block diagram of a multi-controller parameter coordination optimization method provided according to an embodiment of the present application;
[0037] Figure 6 A flowchart of the working principle of a configuration method of a broadband oscillation multi-damping controller provided according to an embodiment of the present application;
[0038] Figure 7 A block diagram of a configuration device of a broadband oscillation multi-damping controller provided according to an embodiment of the present application;
[0039] Figure 8 It is a schematic diagram of the structure of an electronic device provided according to an embodiment of the present application. DETAILED DESCRIPTION
[0040] The embodiments of the present application are described in detail below, and examples of the embodiments are shown in the accompanying drawings, wherein the same or similar reference numerals throughout represent the same or similar elements or elements having the same or similar functions. The embodiments described below with reference to the accompanying drawings are exemplary and are intended to be used to explain the present application, and should not be construed as limiting the present application.
[0041] The following describes the configuration method and device of the broadband oscillation multi-damping controller of the embodiment of the present application with reference to the accompanying drawings. In view of the defects mentioned in the above background technology that the single-machine equivalent model cannot accurately describe the dynamic behavior of the system, and the new oscillation problems induced by the interaction if the coordinated design method is not adopted in the multi-machine system, the present application provides a configuration method of a broadband oscillation multi-damping controller. In this method, the first optimization model and the second optimization model of the multi-damping controller can be established according to the target parameters and the impedance network model, and the configuration parameters of the multi-damping controller that meet certain realistic conditions and / or target scenarios are obtained by solving the above optimization models. By designing the control capacity and layout strategy with full operating condition coverage and optimal capacity cost, the problem of coordinated combination of different controller parameters is solved to ensure the global stabilization of the oscillation mode. As a result, the defects in the related technology that the single-machine equivalent model cannot accurately describe the dynamic behavior of the system, and the new oscillation problems induced by the interaction if the coordinated design method is not adopted in the multi-machine system are solved.
[0042] Specifically, Figure 1 The present invention is a flowchart of a method for configuring a broadband oscillation multi-damping controller according to an embodiment of the present application.
[0043] like Figure 1 As shown, the configuration method of the broadband oscillation multi-damping controller includes the following steps:
[0044] In step S101 , target parameters of the power system are collected, and an impedance network model of the power system is established based on the target parameters.
[0045] It will be understood by those skilled in the art that the embodiments of the present application may collect target parameters according to the actual situation of the power system with broadband oscillation risk, which may include but are not limited to equivalent parameters of units, stations, lines, substations and power grids, and the present application does not impose specific limitations.
[0046] Furthermore, the embodiment of the present application can establish an impedance network model of the power system based on the collected target parameters.
[0047] For example, the embodiment of the present application can be established as follows Figure 2The three-wind turbine group system shown includes two types of direct-drive and doubly-fed types. Each wind farm is connected to a 500kV substation through lines of different lengths. A grid-side damping controller is configured at the grid connection point. Measurement points are arranged at each node in the system. The damping controller and the measurement points upload the identified broadband oscillation characteristics to the collaborative controller. The collaborative controller performs online impedance network analysis and parameter coordination optimization, and then sends the control parameters to the damping controller.
[0048] Specifically, the operating conditions of the embodiment of the present application can be set to 0.11pu output of the doubly-fed wind turbine group, 0.23pu output of the direct-drive wind turbine group, 200 units in the doubly-fed wind farm 1#, 50 units in the doubly-fed wind farm 2#, and 100 units in the direct-drive wind farm. When the series compensation is not put into use, the units are all operating normally. After the series compensation is put into use, a divergent 9Hz oscillation phenomenon is generated. The oscillation components in the two doubly-fed wind farms are relatively large relative to the fundamental amplitude, while the oscillation components in the direct-drive wind farm are small; the doubly-fed wind turbine group exhibits negative resistance and inductance characteristics at the oscillation frequency, and the direct-drive wind turbine group exhibits positive resistance and inductance characteristics at the oscillation frequency.
[0049] In step S102, a first optimization model of a multi-damping controller is established based on the impedance network model.
[0050] As a possible implementation method, the embodiment of the present application can perform oscillation mode analysis and stability assessment based on the impedance network model, screen out risky oscillation modes, and then establish a first optimization model of the multi-damping controller based on different oscillation modes, that is, involving the layout and capacity optimization problem of the multi-damping controller, and then solve the configuration capacity and installation location of the wide-band oscillation multi-damping controller in the power system.
[0051] In addition, in the embodiment of the present application, if the scale of the power system is relatively large and there are many installation locations to be selected, resulting in low solution efficiency of the first optimization model, the installation locations can also be preliminarily screened according to the following principles to appropriately reduce the complexity of the optimization calculation while ensuring the control performance:
[0052] Principle 1: In different oscillation modes of the embodiments of the present application, the distance between the installation position and the oscillation source affects the suppression performance. For example, for a determined single oscillation path, assuming that the installation position of the controller moves, the capacitance and inductance values on both sides of the oscillation equivalent circuit will change. In addition, for the oscillation risk in the double-fed-series compensation system of the embodiments of the present application, connecting the controller at a position far away from the unit can make the oscillation component converge faster; and for the direct-drive-weak AC power grid system, connecting the controller at a position close to the unit can make the oscillation component converge faster.
[0053] Principle 2: The embodiments of the present application have the greatest demand for control capacity under severe fault conditions (such as three-phase short circuit, which is not specifically limited in this application), and should be given priority when selecting fault sets. Specifically, the oscillation amplitude of the embodiments of the present application will usually increase as the degree of disturbance increases, and the damping controller requires a larger output to achieve the same suppression effect. Therefore, when designing the capacity of the suppression converter in the embodiments of the present application, in addition to covering the suppression of all non-fault conditions, it is also necessary to consider whether the controller can achieve a suppression effect under the most severe fault conditions.
[0054] Optionally, in one embodiment of the present application, based on the impedance network model, a first optimization model of the multi-damping controller is established, including: based on the impedance network model, obtaining at least one broadband oscillation mode of the power system; based on the at least one broadband oscillation mode, establishing the first optimization model of the multi-damping controller. The first optimization model can be, but is not limited to, expressed as:
[0055]
[0056] Among them, the column vector x represents the installation point, M p is the evaluation function, C ad is the cost vector, C1 to C5 respectively represent the relationship constraint between the participation factor index and the given threshold, the capacity constraint of the point controller to be installed, the theoretical additional capacity constraint of the point controller to be installed, the actual additional capacity constraint of the point controller to be installed, and the unit cost constraint.
[0057] It can be understood that the embodiments of the present application can perform oscillation stability analysis on power systems, such as large-scale renewable energy grid-connected systems, based on impedance network models, quickly locate dominant oscillation modes that require attention, and determine the observability and controllability of the oscillation modes of each node in the power system based on the dominant oscillation mode, thereby comprehensively obtaining the node participation factor.
[0058] Among them, in the embodiment of the present application, the node participation factor is obtained by multiplying the observability index and the controllability index of the power system, which can reflect the sensitivity of the eigenvalue change and is used to screen the points and signals where the controller is installed. In short, the node participation factor of the embodiment of the present application can be obtained by the zero eigenvalue of the node admittance matrix in the power system and the corresponding left and right eigenvectors.
[0059] Specifically, the optimization of the layout and capacity of the multi-damping controller in the embodiment of the present application can be as follows: the embodiment of the present application numbers the locations in the power system that have the conditions for installing the controller 1 to n. p , number the oscillation modes 1 to n m , using the node participation factor obtained by the above calculation method as the evaluation index, the evaluation function at node k is defined, which can be expressed as but not limited to:
[0060]
[0061] Among them, G ik represents the participation factor of node k in the i-th oscillation mode, ε i Indicates the probability of the current oscillating operating condition occurring, where the probability can be estimated based on historical operating data or set to a typical value.
[0062] Further, in the embodiment of the present application, the installation point is represented as a column vector x, and the element value is fixed to 0 or 1, where 1 indicates that the controller is installed and 0 indicates that the controller is not installed. The expression of the column vector can be, but is not limited to, represented as:
[0063]
[0064] The evaluation function vector can be expressed as, but not limited to:
[0065]
[0066] The node participation factor matrix can be expressed as, but not limited to:
[0067]
[0068] Furthermore, the embodiment of the present application can determine the first constraint condition based on the node participation factor index, that is, the sum of the participation factors of all installed control nodes in a single oscillation mode is greater than a certain threshold. In other words, the embodiment of the present application can ensure that all oscillation modes have corresponding damping control, wherein the certain threshold can be set by technical personnel in this field according to actual conditions, and the present application does not impose any specific restrictions.
[0069] In addition, the first constraint condition of the embodiment of the present application can be expressed as, but not limited to:
[0070]
[0071] Furthermore, the embodiment of the present application provides a typical set F of fault and disturbance conditions (wherein the set F contains n g Working condition), the maximum demand for control capacity under the typical working condition set is determined by electromagnetic transient simulation. In addition, the embodiment of the present application considers that the increase of capacity in practice is limited by cost and implementation difficulty, and is set to increase in a step-by-step manner. When the capacity increase is less than the step capacity, it will not increase. Furthermore, the embodiment of the present application sets a second constraint condition according to the relationship between the capacities, wherein the second constraint condition can be, but is not limited to, expressed as:
[0072]
[0073] C3:S kb =S k -Ska , (7)
[0074]
[0075] Among them, S k Defined as the capacity of point k determined by set F, S ka Indicates that the point has controllable capacity, S kb represents the theoretical additional capacity, S kc Indicates the actual newly added capacity, S ad Indicates the step capacity.
[0076] The cost vector can be expressed as, but is not limited to:
[0077]
[0078] Calculate the cost C based on capacity kad The expression of can be, but is not limited to, expressed as:
[0079]
[0080] Among them, C adc represents the cost of adding a controller, C g represents the fixed cost of adding converter equipment, C s Represents the unit cost of increasing the converter capacity.
[0081] In summary, the objective function of the first optimization model in the embodiment of the present application, that is, the controller layout optimization problem, can be expressed as but not limited to:
[0082]
[0083] Among them, the column vector x represents the installation point, M p is the evaluation function, C ad is the cost vector, C1 to C5 respectively represent the relationship constraint between the participation factor index and the given threshold, the capacity constraint of the point controller to be installed, the theoretical additional capacity constraint of the point controller to be installed, the actual additional capacity constraint of the point controller to be installed, and the unit cost constraint.
[0084] Furthermore, the embodiment of the present application can use the first optimization model of formula (11) to optimize the control position and capacity cost at the same time, and the result obtained is the optimal boundary. Further, a more appropriate combination of values can be comprehensively selected according to cost constraints and actual needs.
[0085] In step S103, the impedance network model and the first optimization model are combined to establish a second optimization model of the multi-damping controller, and the desired parameters of the multi-damping controller are obtained based on the first optimization model and the second optimization model, so as to generate configuration parameters of the multi-damping controller that meet preset realistic conditions and / or target scenarios based on the desired parameters.
[0086] In the actual implementation process, the embodiment of the present application can obtain the desired parameters of the multi-damping controller according to the first optimization model, such as the configuration capacity and the installation position, etc., and the present application does not make specific restrictions. Further, the embodiment of the present application combines the impedance network model and the first optimization model to establish a second optimization model of the multi-damping controller, and obtains the desired parameters of the multi-damping controller by solving the second optimization model, such as the equivalent impedance amplitude and the phase angle parameters, etc., and the present application does not make specific restrictions. Then, the embodiment of the present application can generate the configuration parameters of the multi-damping controller that meets certain realistic conditions and target scenarios based on the expected parameters. Among them, the certain realistic conditions and target scenarios can be set by technicians in this field according to actual conditions, and the present application does not make specific restrictions.
[0087] For example, the embodiment of the present application can design the configuration parameters of the damping controller of the 9 Hz oscillation mode. After the three dispersed damping controllers are put into use, the oscillation is effectively suppressed. The output current of the controller is respectively as follows: Figure 3 As shown, the magnitude of the controlled output current at different positions is proportional to the magnitude of the original oscillating current, and the output current converges rapidly, which further illustrates that the embodiment of the present application can give full play to the role of controllers at different points.
[0088] In addition, the embodiment of the present application simultaneously connects the common busbars of the three wind farms, namely Figure 2 At the leftmost measurement point in the figure, a damping controller is connected (the centralized control method is used as a control, and this application does not make specific restrictions), and the suppression effects of single centralized control and multiple coordinated control are compared. The results are as follows Figure 4 As shown. Figure 4 It can be seen that although the single controller connected to a common point in the embodiment of the present application can effectively suppress oscillations, the output current peak is significantly larger than the sum of the current peaks of multiple controllers in the collaborative control in the figure; and the active power waveform delivered by the busbar shows that the oscillation component converges slightly faster than a single controller when collaborative control is adopted.
[0089] Therefore, the embodiments of the present application can make more effective use of system control resources in some scenarios, which is beneficial to the global stabilization of broadband oscillations.
[0090] Optionally, in one embodiment of the present application, the impedance network model and the first optimization model are combined to establish a second optimization model of the multi-damping controller, including: determining an equivalent circuit of the multi-damping controller based on the impedance network model; obtaining at least one constraint of the second optimization model based on the equivalent circuit; and establishing the second optimization model of the multi-damping controller based on at least one constraint and the first optimization model. The second optimization model can be, but is not limited to, expressed as:
[0091]
[0092] Among them, α n represents the real part of the eigenvalue corresponding to the oscillation mode n, and the constraints C1 to C5 respectively represent the relationship constraint between the control gain and the converter output capacity, the gain upper limit constraint, the impedance phase angle constraint, the oscillation mode frequency constraint, and the oscillation stability constraint.
[0093] As a possible implementation method, the embodiment of the present application can determine the equivalent circuit of the multi-damping controller based on the impedance network model, thereby obtaining at least one constraint condition of the second optimization model, and then establishing the second optimization model of the multi-damping controller.
[0094] Specifically, in a system with sufficient measurement conditions, the embodiment of the present application can obtain the equivalent circuit network of the system in each oscillation mode through an online construction method of the impedance network model, and convert the coordinated optimization problem of the control parameters into the amplitude and phase parameters of the impedance at the configuration part of the nodes, so that all oscillation modes are effectively stabilized.
[0095] That is to say, the embodiments of the present application can Figure 5 Assume that there are N m Oscillation modes and N c controllers, and the constraint condition of the control gain in the nth oscillation mode of the ith controller can be expressed as but not limited to:
[0096]
[0097] Among them, S in represents the output capacity of the controlled device i in the corresponding frequency band of oscillation mode n, f ca Indicates the conversion relationship between capacity and control channel limit.
[0098] Further, in the embodiment of the present application, the node voltage is taken as an input signal as an example, and the impedance amplitude of the branch connected to the node i in the oscillation mode n can be constrained according to the gain upper limit constraint to establish a constraint formula, and the constraint formula can be but is not limited to being expressed as:
[0099]
[0100] Furthermore, the constraints on the impedance phase angle and the oscillation mode frequency in the embodiment of the present application can be expressed as, but not limited to:
[0101]
[0102] C4:|ω cn -ω n |<ω lim , (15)
[0103] Among them, ω cn represents the oscillation frequency when considering control, ω n represents the oscillation frequency without control, ω lim Indicates frequency limit.
[0104] Furthermore, the stability constraints of all oscillation modes in the embodiment of the present application can be expressed as, but not limited to:
[0105]
[0106] Among them, α n represents the real part of the eigenvalue of the corresponding oscillation mode.
[0107] Furthermore, the optimization target of the embodiment of the present application is to maximize the mode damping under the worst condition, and establish a second optimization model of the multi-damping controller, whose objective function can be, but is not limited to, expressed as:
[0108]
[0109] Furthermore, the embodiment of the present application can obtain the equivalent impedance amplitude and phase parameters of each controller to be configured by solving the second optimization model shown in equation (17).
[0110] Optionally, in one embodiment of the present application, expected parameters of the multi-damping controller are obtained according to the first optimization model and the second optimization model, so as to generate configuration parameters of the multi-damping controller that meet preset realistic conditions and / or target scenarios based on the expected parameters, including: determining initial expected parameters of the multi-damping controller based on the first optimization model; obtaining expected parameters of the multi-damping controller according to the initial expected parameters and the second optimization model; judging whether the expected parameters meet preset realistic conditions and / or target scenarios; if the expected parameters meet the preset realistic conditions and / or target scenarios, generating configuration parameters based on the expected parameters, otherwise adjusting the expected parameters based on target parameters that meet the preset realistic conditions and / or target scenarios, and generating configuration parameters based on the expected parameters.
[0111] As a possible implementation method, the embodiment of the present application can obtain the initial expected parameters of the multi-damping controller by solving the first optimization model, and obtain the expected parameters through the initial expected parameters and the second optimization model.
[0112] Furthermore, in some embodiments, the embodiments of the present application can determine whether the expected parameters meet certain realistic conditions and target scenarios, and generate configuration parameters if the expected parameters meet certain realistic conditions and target scenarios; otherwise, the expected parameters are adjusted based on the target parameters that meet certain realistic conditions and target scenarios, and then the configuration parameters are generated.
[0113] Furthermore, in some embodiments, the embodiments of the present application can determine whether the expected parameters meet certain realistic conditions, and generate configuration parameters if the expected parameters meet certain realistic conditions; otherwise, the expected parameters are adjusted based on the target parameters that meet certain realistic conditions, and then the configuration parameters are generated.
[0114] For example, the embodiments of the present application can verify and check the planned capacity and installation nodes obtained by the first optimization model and the various control parameters obtained by the second optimization model to ensure compliance with actual conditions and target scenarios; if any discrepancies occur, the causes should be found and certain calculation parameters should be appropriately corrected.
[0115] like Figure 6 As shown, the working principle of the configuration method of the broadband oscillation multi-damping controller proposed in the embodiment of the present application is introduced in detail with a specific embodiment below.
[0116] Step S601: Collect target parameters and establish an impedance network model.
[0117] It can be understood that the target parameters collected in the embodiment of the present application may include, but are not limited to, equivalent parameters of units, stations, lines, substations and power grids, and the present application does not impose specific restrictions, and then the impedance network model of the power system is established based on the collected target parameters. Figure 2 As shown, the embodiment of the present application can establish a three-wind turbine group system including two types of direct drive and double-fed.
[0118] Step S602: performing oscillation mode analysis and stability assessment based on the impedance network model.
[0119] It can be understood that the embodiments of the present application can perform oscillation mode analysis and stability assessment based on the impedance network model, screen out risky oscillation modes, and then establish a first optimization model of the multi-damping controller based on different oscillation modes, that is, it involves the layout and capacity optimization problems of the multi-damping controller, and then solve the configuration capacity and installation location of the wide-band oscillation multi-damping controller in the power system.
[0120] Step S603: Establish a first optimization model.
[0121] It can be understood that the first optimization model established in the embodiment of the present application may include but is not limited to objective functions and constraints, wherein the objective function may include but is not limited to maximizing the evaluation function, minimizing the configuration cost, etc., and the constraints may include but are not limited to all oscillation modes being controlled, capacity restrictions, etc. The present application does not make specific restrictions, and its expressions are shown in Formula (5)-Formula (11), and no unnecessary details are given here.
[0122] Step S604: Solve the first optimization model to obtain controller configuration nodes and capacity.
[0123] It can be understood that the embodiment of the present application can obtain the configuration nodes and capacity of the controller by solving the first optimization model.
[0124] Step S605: Establish a second optimization model.
[0125] It can be understood that the second optimization model established in the embodiment of the present application may include but is not limited to objective functions and constraints, wherein the objective function may include but is not limited to maximizing the worst case mode damping, etc., and the constraints may include but are not limited to the upper limit of gain, frequency range, stability of each mode, etc. The present application does not make specific restrictions, and its expression is shown in Formula (12)-Formula (17), which will not be elaborated here.
[0126] Step S606: Solve the second optimization model to obtain the controller equivalent impedance amplitude and phase angle.
[0127] It can be understood that the embodiment of the present application can obtain the equivalent impedance amplitude and phase angle of the controller by solving the second optimization model.
[0128] Step S607: Data verification.
[0129] It can be understood that the embodiment of the present application verifies and checks the planned capacity and installation nodes obtained by the first optimization model and the various control parameters obtained by the second optimization model to ensure compliance with actual conditions and target scenarios; if any discrepancies occur, the causes should be found and certain calculation parameters should be appropriately corrected.
[0130] Step S608: Complete the parameter configuration of the controller.
[0131] It can be understood that, in the embodiment of the present application, the parameter configuration of the controller is completed when the data is verified.
[0132] Step S609: Parameter adjustment and correction.
[0133] It can be understood that the embodiment of the present application performs parameter adjustment and correction when the data has not been verified.
[0134] According to the configuration method of the broadband oscillation multi-damping controller proposed in the embodiment of the present application, the first optimization model and the second optimization model of the multi-damping controller can be established according to the target parameters and the impedance network model, and by solving the above optimization model, the configuration parameters of the multi-damping controller that meet certain realistic conditions and / or target scenarios are obtained. By designing the control capacity and point distribution strategy with full operating condition coverage and optimal capacity cost, the problem of coordinated combination of different controller parameters is solved to ensure the global stabilization of the oscillation mode. In this way, the defects of the related technology that the single-machine equivalent model cannot accurately characterize the dynamic behavior of the system, and the new oscillation problems induced by the interaction in the multi-machine system if the coordinated design method is not adopted are solved.
[0135] Next, a configuration device of a broadband oscillation multi-damping controller proposed in an embodiment of the present application is described with reference to the accompanying drawings.
[0136] Figure 7 It is a block diagram of a configuration device of a broadband oscillation multi-damping controller provided according to an embodiment of the present application.
[0137] like Figure 7 As shown, the configuration device 10 of the broadband oscillation multi-damping controller includes: a collection module 100 , a creation module 200 and a configuration module 300 .
[0138] The acquisition module 100 is used to acquire target parameters of the power system and establish an impedance network model of the power system based on the target parameters.
[0139] The building module 200 is used to build a first optimization model of the multi-damping controller based on the impedance network model.
[0140] The configuration module 300 is used to combine the impedance network model and the first optimization model to establish a second optimization model of the multi-damping controller, and obtain the desired parameters of the multi-damping controller based on the first optimization model and the second optimization model, so as to generate configuration parameters of the multi-damping controller that meet preset realistic conditions and / or target scenarios based on the desired parameters.
[0141] Optionally, in one embodiment of the present application, the establishment module 200 includes: a first generating unit and a first establishing unit.
[0142] Wherein, the first generating unit is used to obtain at least one broadband oscillation mode of the power system based on the impedance network model.
[0143] The first establishing unit is used to establish a first optimization model of the multi-damping controller based on at least one broadband oscillation mode.
[0144] Optionally, in one embodiment of the present application, the first optimization model may be, but is not limited to, expressed as:
[0145]
[0146] Among them, the column vector x represents the installation point, M p is the evaluation function, C ad is the cost vector, C1 to C5 respectively represent the relationship constraint between the participation factor index and the given threshold, the capacity constraint of the point controller to be installed, the theoretical additional capacity constraint of the point controller to be installed, the actual additional capacity constraint of the point controller to be installed, and the unit cost constraint.
[0147] Optionally, in one embodiment of the present application, the configuration module 300 includes: a first determining unit, an acquiring unit and a second establishing unit.
[0148] Wherein, the first determination unit is used to determine the equivalent circuit of the multi-damping controller based on the impedance network model.
[0149] An acquisition unit is used to acquire at least one constraint condition of the second optimization model based on the equivalent circuit.
[0150] The second establishing unit is used to establish a second optimization model of the multi-damping controller based on at least one constraint condition and the first optimization model.
[0151] Optionally, in one embodiment of the present application, the second optimization model may be, but is not limited to, expressed as:
[0152]
[0153] Among them, α n represents the real part of the eigenvalue corresponding to the oscillation mode n, and the constraints C1 to C5 respectively represent the relationship constraint between the control gain and the converter output capacity, the gain upper limit constraint, the impedance phase angle constraint, the oscillation mode frequency constraint, and the oscillation stability constraint.
[0154] Optionally, in one embodiment of the present application, the configuration module 300 includes: a second determination unit, a second generation unit, a judgment unit and a configuration unit.
[0155] The second determination unit is used to determine the initial desired parameters of the multi-damping controller based on the first optimization model.
[0156] The second generating unit is used to obtain the expected parameters of the multi-damping controller according to the initial expected parameters and the second optimization model.
[0157] The judgment unit is used to judge whether the expected parameters meet the preset realistic conditions and / or target scenarios.
[0158] The configuration unit is used to generate configuration parameters based on the expected parameters when the expected parameters meet preset realistic conditions and / or target scenarios, otherwise adjust the expected parameters based on target parameters that meet preset realistic conditions and / or target scenarios, and generate configuration parameters based on the expected parameters.
[0159] It should be noted that the above explanation of the configuration method embodiment of the broadband oscillation multi-damping controller is also applicable to the configuration device of the broadband oscillation multi-damping controller of this embodiment, and will not be repeated here.
[0160] According to the configuration device of the broadband oscillation multi-damping controller proposed in the embodiment of the present application, the first optimization model and the second optimization model of the multi-damping controller can be established according to the target parameters and the impedance network model, and the configuration parameters of the multi-damping controller that meet certain realistic conditions and / or target scenarios are obtained by solving the above optimization models. By designing the control capacity and layout strategy with full operating condition coverage and optimal capacity cost, the problem of coordinated combination of different controller parameters is solved to ensure the global stabilization of the oscillation mode. In this way, the defects of the related art that the single-machine equivalent model cannot accurately characterize the dynamic behavior of the system, and the new oscillation problems induced by the interaction in the multi-machine system if the coordinated design method is not adopted are solved.
[0161] Figure 8 This is a schematic diagram of the structure of an electronic device provided according to an embodiment of the present application. The electronic device may include:
[0162] A memory 801 , a processor 802 , and a computer program stored in the memory 801 and executable on the processor 802 .
[0163] When the processor 802 executes the program, the configuration method of the wide-band oscillation multi-damping controller provided in the above embodiment is implemented.
[0164] Furthermore, the electronic device further comprises:
[0165] The communication interface 803 is used for communication between the memory 801 and the processor 802 .
[0166] The memory 801 is used to store computer programs that can be executed on the processor 802 .
[0167] The memory 801 may include a high-speed RAM memory, and may also include a non-volatile memory (non-volatile memory), such as at least one disk memory.
[0168] If the memory 801, the processor 802 and the communication interface 803 are implemented independently, the communication interface 803, the memory 801 and the processor 802 can be connected to each other through a bus and communicate with each other. The bus can be an Industry Standard Architecture (ISA) bus, a Peripheral Component Interconnect (PCI) bus or an Extended Industry Standard Architecture (EISA) bus. The bus can be divided into an address bus, a data bus, a control bus, etc. For ease of representation, Figure 8 Only one thick line is used in the diagram, but this does not mean that there is only one bus or only one type of bus.
[0169] Optionally, in a specific implementation, if the memory 801, the processor 802 and the communication interface 803 are integrated on a chip, the memory 801, the processor 802 and the communication interface 803 can communicate with each other through an internal interface.
[0170] The processor 802 may be a central processing unit (CPU), or an application specific integrated circuit (ASIC), or one or more integrated circuits configured to implement the embodiments of the present application.
[0171] An embodiment of the present application also provides a computer-readable storage medium having a computer program stored thereon, which, when executed by a processor, implements the configuration method of the broadband oscillation multi-damping controller as described above.
[0172] An embodiment of the present application also provides a computer program product, including a computer program, which, when executed, implements the configuration method of the broadband oscillation multi-damping controller as described above.
[0173] In the description of this specification, the description with reference to the terms "one embodiment", "some embodiments", "example", "specific example", or "some examples" etc. means that the specific features, structures, materials or characteristics described in conjunction with the embodiment or example are included in at least one embodiment or example of the present application. In this specification, the schematic representations of the above terms do not necessarily refer to the same embodiment or example. Moreover, the specific features, structures, materials or characteristics described may be combined in any one or N embodiments or examples in a suitable manner. In addition, those skilled in the art may combine and combine the different embodiments or examples described in this specification and the features of the different embodiments or examples, without contradiction.
[0174] In addition, the terms "first" and "second" are used for descriptive purposes only and should not be understood as indicating or implying relative importance or implicitly indicating the number of technical features indicated. Therefore, a feature defined as "first" or "second" may explicitly or implicitly include at least one of the features. In the description of this application, "N" means at least two, such as two, three, etc., unless otherwise clearly and specifically defined.
[0175] Any process or method description in a flowchart or otherwise described herein may be understood to represent a module, fragment or portion of code comprising one or N executable instructions for implementing the steps of a custom logical function or process, and the scope of the preferred embodiments of the present application includes alternative implementations in which functions may not be performed in the order shown or discussed, including performing functions in a substantially simultaneous manner or in reverse order depending on the functions involved, which should be understood by technicians in the technical field to which the embodiments of the present application belong.
[0176] The logic and / or steps represented in the flowchart or otherwise described herein, for example, can be considered as an ordered list of executable instructions for implementing logical functions, and can be embodied in any computer-readable medium for use by an instruction execution system, device or apparatus (such as a computer-based system, a system including a processor, or other system that can fetch instructions from an instruction execution system, device or apparatus and execute instructions), or in combination with these instruction execution systems, devices or apparatuses. For the purpose of this specification, "computer-readable medium" can be any device that can contain, store, communicate, propagate or transmit a program for use by an instruction execution system, device or apparatus, or in combination with these instruction execution systems, devices or apparatuses. More specific examples of computer-readable media (a non-exhaustive list) include the following: an electrical connection with one or N wirings (electronic devices), a portable computer disk box (magnetic device), a random access memory (RAM), a read-only memory (ROM), an erasable and programmable read-only memory (EPROM or flash memory), a fiber optic device, and a portable compact disk read-only memory (CDROM). In addition, the computer-readable medium may even be paper or other suitable medium on which the program is printed, since the program may be obtained electronically by optically scanning the paper or other medium and then editing, interpreting or processing in other suitable ways as necessary and then storing it in a computer memory.
[0177] It should be understood that the various parts of the present application can be implemented by hardware, software, firmware or a combination thereof. In the above embodiment, the N steps or methods can be implemented by software or firmware stored in a memory and executed by a suitable instruction execution system. If implemented by hardware, as in another embodiment, it can be implemented by any one or a combination of multiple of the following technologies known in the art: a discrete logic circuit having a logic gate circuit for implementing a logic function for a data signal, a dedicated integrated circuit having a suitable combination of logic gate circuits, a programmable gate array (PGA), a field programmable gate array (FPGA), etc.
[0178] A person skilled in the art may understand that all or part of the steps in the method for implementing the above-mentioned embodiment may be completed by instructing related hardware through a program, and the program may be stored in a computer-readable storage medium, which, when executed, includes one or a combination of the steps of the method embodiment.
[0179] In addition, each functional unit in each embodiment of the present application may be integrated into a processing module, or each unit may exist physically separately, or two or more units may be integrated into one module. The above-mentioned integrated module may be implemented in the form of hardware or in the form of a software functional module. If the integrated module is implemented in the form of a software functional module and sold or used as an independent product, it may also be stored in a computer-readable storage medium.
[0180] The storage medium mentioned above may be a read-only memory, a disk or an optical disk, etc. Although the embodiments of the present application have been shown and described above, it can be understood that the above embodiments are exemplary and cannot be understood as limiting the present application. A person of ordinary skill in the art may change, modify, replace and modify the above embodiments within the scope of the present application.
Claims
1. A configuration method for a broadband oscillation multi-damping controller, characterized in that: The following steps are involved: Collecting target parameters of the power system, and establishing an impedance network model of the power system based on the target parameters; Based on the impedance network model, establishing a first optimization model of a multi-damping controller; In combination with the impedance network model and the first optimization model, a second optimization model of the multi-damping controller is established, and the desired parameters of the multi-damping controller are obtained based on the first optimization model and the second optimization model, so as to generate configuration parameters of the multi-damping controller that meet preset realistic conditions and / or target scenarios based on the desired parameters.
2. The configuration method of the broadband oscillation multi-damping controller according to claim 1, characterized in that: The step of establishing a first optimization model of a multi-damping controller based on the impedance network model comprises: Based on the impedance network model, obtaining at least one broadband oscillation mode of the power system; Based on the at least one broadband oscillation mode, a first optimization model of the multi-damping controller is established.
3. The configuration method of the broadband oscillation multi-damping controller according to claim 2, characterized in that: in, The first optimization model is expressed as: maxf v ={M p x,-C ad x} stC1,C2,C3,C4,C5, The objective function of the first optimization model is to jointly optimize the control location and capacity cost to obtain the optimal boundary; the column vector x represents the installation point, M p is the evaluation function, C ad is the cost vector, C1 to C5 respectively represent the relationship constraint between the participation factor index and the given threshold, the capacity constraint of the point controller to be installed, the theoretical additional capacity constraint of the point controller to be installed, the actual additional capacity constraint of the point controller to be installed, and the unit cost constraint.
4. The configuration method of the broadband oscillation multi-damping controller according to claim 1, characterized in that: The step of combining the impedance network model and the first optimization model to establish a second optimization model of the multi-damping controller includes: Based on the impedance network model, determining an equivalent circuit network of the multi-damping controller; Based on the equivalent circuit, obtaining at least one constraint condition of the second optimization model; Based on the at least one constraint condition and the first optimization model, a second optimization model of the multi-damping controller is established.
5. The configuration method of the broadband oscillation multi-damping controller according to claim 4, characterized in that: in, The second optimization model is expressed as: stC1,C2,C3,C4,C5, Among them, the objective function of the second optimization model is to maximize the mode damping under the worst case; α n That is, it represents the real part of the eigenvalue corresponding to the oscillation mode n. The constraints C1 to C5 respectively represent the relationship constraint between the control gain and the converter output capacity, the gain upper limit constraint, the impedance phase angle constraint, the oscillation mode frequency constraint, and the oscillation stability constraint.
6. The configuration method of the broadband oscillation multi-damping controller according to claim 1, characterized in that: Obtaining the desired parameters of the multi-damping controller according to the first optimization model and the second optimization model, so as to generate configuration parameters of the multi-damping controller that meet preset realistic conditions and / or target scenarios based on the desired parameters, comprises: Based on the first optimization model, determining initial desired parameters of the multi-damping controller; Obtaining desired parameters of the multi-damping controller according to the initial desired parameters and the second optimization model; Determining whether the expected parameters meet preset realistic conditions and / or target scenarios; If the expected parameters satisfy the preset realistic conditions and / or the target scenario, the configuration parameters are generated based on the expected parameters; otherwise, the expected parameters are adjusted based on the target parameters satisfying the preset realistic conditions and / or the target scenario, and the configuration parameters are generated based on the expected parameters.
7. A configuration device for a broadband oscillation multi-damping controller, characterized in that: include: A collection module, used for collecting target parameters of the power system and establishing an impedance network model of the power system based on the target parameters; An establishing module, used for establishing a first optimization model of a multi-damping controller based on the impedance network model; A configuration module is used to combine the impedance network model and the first optimization model to establish a second optimization model of the multi-damping controller, and obtain the desired parameters of the multi-damping controller according to the first optimization model and the second optimization model, so as to generate configuration parameters of the multi-damping controller that meet preset realistic conditions and / or target scenarios based on the desired parameters.
8. An electronic device, characterized in that: include: A memory, a processor, and a computer program stored in the memory and executable on the processor, wherein the processor executes the program to implement the configuration method of the broadband oscillation multi-damping controller as described in any one of claims 1 to 6.
9. A computer-readable storage medium having a computer program stored thereon, characterized in that: The program is executed by a processor to implement the configuration method of the broadband oscillation multi-damping controller as described in any one of claims 1-6.
10. A computer program product, characterized in that It comprises a computer program, which, when executed, is used to implement the configuration method of the broadband oscillation multi-damping controller as described in any one of claims 1-6.