Highway carbonaceous soft rock high-performance roadbed structure and construction method thereof
By setting up a waterproof area and a water sealing layer in the carbon soft rock roadbed, combining composite geotextile and New Jersey guardrail, the disintegration problem of the carbon soft rock roadbed when encountering water is solved, and the stability and strength of the roadbed humidity are achieved. Improvement avoids the occurrence of road surface diseases.
Patent Information
- Application Number
- CN202411376477.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-30
- Publication Date
- 2024-11-19
AI Technical Summary
Carbon-based soft rock roadbeds are prone to disintegration when exposed to water, resulting in reduced strength of the roadbed and deterioration. There is a lack of effective edge wrapping materials and uniform mixing technology, resulting in cracking and collapse of the roadbed slope, making it difficult to maintain stable humidity.
The isolation layer, carbon soft rock filling area, anti-seepage area, upper embankment, roadbed and pavement structure are arranged from bottom to top, and the anti-seepage layer is formed by using composite geotextiles and geogrids, combining New Jersey guardrails and anti-filtration Geotextile is sealed to ensure stable roadbed humidity.
Effectively utilize carbon soft rock filler to prevent moisture infiltration and slope settlement, ensure stable humidity of the roadbed, avoid cracking and collapse of the roadbed, reduce engineering costs, and improve the overall strength and stability of the roadbed.
Smart Images

Figure CN118979417A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of road construction, and in particular to a high-performance carbonaceous soft rock roadbed structure for an expressway and a construction method thereof. Background Art
[0002] Carbonaceous soft rock is mainly distributed in Guizhou, Hunan, Guangxi and other places in my country. In today's highway construction, green and environmental protection are the bottom line, and "less borrowing and less waste" is the basic requirement for roadbed filling. Under the construction concept of "safe and century-old quality engineering", how to scientifically and reasonably use special filler carbonaceous soft rock to fill the roadbed and ensure the quality of the project is a technical problem that needs to be solved.
[0003] Carbonaceous soft rock has the engineering property of easy disintegration and mudification and rapid reduction of strength when it comes into contact with water. The effect of water will reduce the overall strength of the roadbed and increase the settlement deformation, thus causing roadbed and pavement diseases. Therefore, it is key to do a good job in the water-proof design of carbonaceous soft rock roadbed and ensure its humidity stability. Rainfall mainly infiltrates through the roadbed slope and the central dividing strip, part of the rainwater infiltrates through the pavement structure layer, and the capillary water rise of the base affects the stability of the roadbed humidity. Related studies have shown that the depth of rainfall on the humidity state of granular roadbed does not exceed 3m; the lateral diffusion of the central dividing strip seepage affects the range of more than 3m, and the vertical diffusion affects the depth of 2-4m; the capillary water rise height of coarse sand, gravel, etc. is 0.2-0.4m. Then the structural type of high-performance roadbed of carbonaceous soft rock should be determined comprehensively based on factors affecting roadbed humidity, various parts of the roadbed, roadbed fillers and other factors. At present, carbonaceous soft rock roadbeds often use water-blocking materials such as clay, lime soil or cement soil for interlayer filling and covering to maintain the stability of the roadbed humidity field. However, in actual projects, there is often a lack of available edging clay soil around the carbonaceous soft rock roadbed of mountain roads, which involves long-distance transportation, thereby increasing the cost of the project; and it is difficult to fully mix lime soil or cement soil. At the same time, whether it is edging clay soil, lime soil or cement soil, they are all fillers of different properties from carbonaceous soft rock. The roadbed is prone to lateral differential settlement due to the difference in fillers, resulting in cracks and collapse on the surface of the roadbed slope, and even cracks in the road surface. Summary of the invention
[0004] The purpose of the present invention is to solve the defects in the prior art and to propose a high-performance highway carbonaceous soft rock roadbed structure and a construction method thereof.
[0005] In order to achieve the above object, the present invention adopts the following technical solutions:
[0006] A high-performance carbonaceous soft rock roadbed structure for a highway, characterized in that it comprises an isolation layer, a carbonaceous soft rock filling area, an upper embankment, a roadbed and a road surface arranged in sequence from bottom to top;
[0007] The carbonaceous soft rock filling area is provided with anti-seepage areas on both sides, and the anti-seepage areas are provided with anti-seepage layers distributed in sequence;
[0008] A groove is opened on the road surface, a sleeper is arranged in the groove, two sets of New Jersey guardrails are arranged above the sleeper, and a concrete cushion layer, a sand filling layer and a planting soil layer are sandwiched between the two New Jersey guardrails from bottom to top.
[0009] Furthermore, the anti-seepage layer includes composite geotextile and geogrid, the anti-seepage layer is coated with carbonaceous soft rock, and each layer of the anti-seepage layer is connected by U-shaped nails.
[0010] Furthermore, the road surface includes a graded crushed stone base layer, a cement stabilized crushed stone base layer and a surface layer, and the grooves are opened on the cement stabilized crushed stone base layer and the surface layer.
[0011] Furthermore, a drainage hole is provided on the New Jersey guardrail, the height of the drainage hole is higher than the height of the upper end surface of the groove, the aperture of the drainage hole is 2 cm, and the slope is 2%.
[0012] A method for constructing a high-performance carbonaceous soft rock roadbed for a highway comprises the following steps:
[0013] S1: Geogrids and composite geotextiles are laid on the isolation layer at the bottom of the embankment in sequence, and carbonaceous soft rock is filled on top of the composite geotextiles. After the carbonaceous soft rock is filled with a thickness of 1 to 2 meters, the geogrids and composite geotextiles on the upper part of the bottom isolation layer are reversed to the top surface of the carbonaceous soft rock to form a carbonaceous soft rock filling area;
[0014] S2: geogrid, composite geotextile and 1-2m thick carbonaceous soft rock are laid on the left and right sides of the carbonaceous soft rock filling area in turn, and the geogrid and composite geotextile in this step are used to wrap the carbonaceous soft rock, and the operation is repeated to form an anti-seepage area until the anti-seepage area is flush with the top surface of the carbonaceous soft rock filling area, and the anti-seepage area and the carbonaceous soft rock filling area form a lower embankment;
[0015] S3: Geogrid and composite geotextile are laid on the top surface of the lower embankment in sequence, and then the upper embankment and roadbed are filled in sequence and compacted;
[0016] S4: The road surface is laid on the roadbed. The road surface is laid in sequence according to the graded crushed stone base, cement stabilized crushed stone base and surface layer. The cement stabilized crushed stone base is constructed in two layers, and the first layer is paved in the entire width;
[0017] S5: After the first layer of cement-stabilized crushed stone base is paved, cast-in-place concrete pillows are placed on top of it, and the second layer of cement-stabilized crushed stone base on the left and right sides is paved halfway, with the pillows flush with the top surfaces of the second layer of cement-stabilized crushed stone base;
[0018] S6: After the sleeper beam reaches the design strength, install the New Jersey guardrail and lay the concrete cushion between the New Jersey guardrails. After the concrete cushion reaches the design strength, lay the anti-filter geotextile on top and fill the sand layer. Cover the sand layer with anti-filter geotextile and finally backfill the sand layer with planting soil.
[0019] Furthermore, in step S1, the carbonaceous soft rock is laid in layers in sequence and compacted by a heavy roller. During the filling process, the cross slope of the top surface of the embankment is ≥4%, and the intersections of the sections should overlap and be compacted with each other, with a longitudinal overlap length of more than 2m.
[0020] Further, in step S2, after filling the 1-2 m thick carbonaceous soft rock, the roadbed slope is repaired according to the designed slope, and then the reversed geogrid section and composite geotextile section of the previous layer are reversed upward along the repaired slope, and a new geogrid is laid at the same time; the reversed geogrid end, the composite geotextile end and the newly laid geogrid are straightened and leveled, and after tensioning, they are fixed on the carbonaceous soft rock below with U-shaped nails every 1 m, and then a new composite geotextile is laid;
[0021] The width of the anti-seepage zone c ≥ 3m, and the width of the reverse package b ≥ 1m; the geogrid uses a bidirectional steel-plastic geogrid, and the composite geotextile is a composite geomembrane with two cloths and one membrane.
[0022] Furthermore, in step S3, the upper embankment and the roadbed are both filled with hard graded crushed stone and gravel fillers, the maximum particle size of the upper embankment filling stone is less than or equal to 15 cm, and the maximum particle size of the roadbed filling stone is less than or equal to 10 cm; the compacted thickness of the upper embankment is less than or equal to 40 cm, and the compacted thickness of the roadbed is less than or equal to 30 cm.
[0023] Furthermore, in step S4, the thickness of the mid-graded crushed stone subbase of the road surface is 15-25 cm, the thickness of the cement stabilized crushed stone base is 35-40 cm, and the surface layer includes a lower layer, a middle layer and an upper layer, the thickness of the lower layer is 5-10 cm, the thickness of the middle layer is 5-8 cm, and the thickness of the upper layer is 3-5 cm.
[0024] Furthermore, in step S5, the thickness of the bolster is 18 to 25 cm. After the bolster reaches more than 75% of the design strength, the second layer of cement-stabilized crushed stone base on the left and right sides is half-paved.
[0025] Beneficial Effects
[0026] Compared with the prior art, the beneficial effect of the present invention lies in that: through the arrangement of the present invention, the carbonaceous soft rock excavated along the line can be fully utilized as roadbed filler, and the disadvantages of no available edging clay soil and chemical improvement pollution environment in the surrounding area can be compensated, and the reinforcement and waterproofing effects of geogrids and composite geotextiles, the water-isolating effect of the isolation layer at the bottom of the embankment, and the water-sealing effect of the separated New Jersey guardrail in the central dividing strip can be fully utilized to jointly ensure the stability of the roadbed humidity field, thereby keeping the engineering properties of the carbonaceous soft rock filler stable. BRIEF DESCRIPTION OF THE DRAWINGS
[0027] The accompanying drawings are used to provide further understanding of the present invention and constitute a part of the specification. They are used to explain the present invention together with the embodiments of the present invention and do not constitute a limitation of the present invention.
[0028] Figure 1 It is a schematic diagram of the overall structure of the roadbed structure.
[0029] Figure 2 This is a schematic diagram of the structure of the anti-seepage area on one side of the roadbed structure.
[0030] Figure 3 A schematic diagram of the structure of the central dividing strip.
[0031] In the figure: 1-isolation layer at the bottom of embankment, 2-carbonaceous soft rock filling area, 3-anti-seepage area, 4-upper embankment, 5-roadbed, 6-pavement, 7-central dividing strip, 8-geogrid, 9-composite geotextile, 10-U-nail, 11-foundation, 12-graded crushed stone subbase, 13-cement stabilized crushed stone base, 14-surface layer, 15-cord, 16-New Jersey guardrail, 17-sluice hole, 18-concrete cushion, 19-anti-filtration geotextile, 20-sand fill layer, 21-planting soil. DETAILED DESCRIPTION
[0032] The technical solutions in the embodiments of the present invention will be described clearly and completely below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, rather than all the embodiments.
[0033] In the description of the present invention, it is necessary to understand that the terms "upper", "lower", "front", "back", "left", "right", "top", "bottom", "inside", "outside", etc., indicating the orientation or position relationship are based on the orientation or position relationship shown in the drawings, and are only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as a limitation on the present invention.
[0034] Reference Figure 1 - Figure 3 ,
[0035] The carbonaceous soft rock high-performance roadbed structure includes an isolation layer, a carbonaceous soft rock filling area, an upper embankment, a roadbed and a road surface arranged in sequence from bottom to top;
[0036] 1. Isolation layer 1 at the bottom of the embankment: located above the foundation 11, used to prevent the migration of water caused by the rise of groundwater level or capillary water action to the carbonaceous soft rock filling area 2.
[0037] 2. Carbonaceous soft rock filling area 2: located above the isolation layer 1 at the bottom of the embankment, it is filled with carbonaceous soft rock in layers, and the carbonaceous soft rock filling position is the lower embankment. Geogrids 8 and composite geotextiles 9 are fully spread on the top surface of the lower embankment.
[0038] 3. Anti-seepage area 3: Located on the left and right sides of the carbonaceous soft rock filling area 2, each time the carbonaceous soft rock of preset thickness is filled, the left and right sides of the carbonaceous soft rock filling area 2 are wrapped inside by using geogrids 8 and composite geotextiles 9 to prevent rainfall and slope runoff from infiltrating the carbonaceous soft rock filling area 2 through the slopes on both sides.
[0039] 4. Upper embankment 4 and roadbed 5: The upper embankment 4 is located above the carbonaceous soft rock filling area 2 and the anti-seepage area 3. The roadbed 5 is located above the upper embankment 4.
[0040] 5. Pavement 6: Pavement 6 is designed with a conventional graded crushed stone subbase 12 of 20 cm thickness, a cement stabilized crushed stone base 13 of 38 cm thickness, and a surface layer 14 with a lower layer, a middle layer, and an upper layer of 8 cm, 6 cm, and 4 cm thickness respectively, wherein the cement stabilized crushed stone base 13 is constructed in two layers.
[0041] VI. Central median strip 7: A cast-in-place concrete corbel 15 is provided at the bottom of the central median strip 7. The corbel 15 is 20 cm thick and is located in the cement stabilized gravel base 13. The top surface of the corbel 15 is flush with the top surface of the cement stabilized gravel base 13. A 20 cm thick concrete cushion 18 is provided on the corbel 15. Separate concrete New Jersey guardrails 16 are provided on both sides of the concrete cushion 18. The concrete cushion 18 is flush with the bottom surface of the New Jersey guardrail 16 and are located on the corbel 15 together.
[0042] A filter geotextile 19 is laid on top of the concrete cushion 18, and the sand filling layer 20 inside is wrapped around it; then the planting soil 21 is backfilled on top of it for planting anti-glare trees and green plants. A drainage hole 17 is set at the bottom of the New Jersey guardrail 16 to drain the water inside the central dividing strip 7.
[0043] A method for constructing a high-performance carbonaceous soft rock roadbed for a highway comprises sequentially constructing an isolation layer at the bottom of an embankment, a lower embankment, an upper embankment, a roadbed, a road surface and a central dividing strip.
[0044] The specific construction method is:
[0045] 1. Isolation layer at the bottom of the embankment 1
[0046] An important characteristic of carbonaceous soft rock is that it disintegrates and turns into mud when exposed to water, and its strength is greatly reduced. Therefore, preventing carbonaceous soft rock from being soaked by water is an important aspect of improving the stability of the roadbed. On the basis of doing a good job of foundation treatment and ensuring the overall stability of the roadbed, the present invention clearly proposes that the isolation layer 1 at the bottom of the embankment is made of hard and medium-hard permeable materials with good water stability such as gravel and slag.
[0047] The isolation layer 1 at the bottom of the embankment is filled horizontally in layers from the lowest point, with each layer thickness not exceeding 50cm. It must be filled horizontally along the transverse direction of the roadbed to ensure that the thickness a of the thinnest part of the isolation layer 1 at the bottom of the embankment is ≥ 0.5m. When the longitudinal terrain of the roadbed changes greatly and the bottom isolation layer cannot be filled at the same level in the longitudinal direction, steps must be set for overlap. The height of each step shall not exceed 0.5m, and the step length and overlap length shall be greater than or equal to 3m.
[0048] 2. Lower Embankment
[0049] 1. Geogrid 8 and composite geotextile 9 are laid on the upper part of the isolation layer 1 at the bottom of the embankment in sequence and fixed with U-shaped nails 10, and then the carbonaceous soft rock is filled on the top of the composite geotextile 9. After the carbonaceous soft rock with a thickness of 1 to 2 meters is filled, the geogrid 8 and composite geotextile 9 on the upper part of the bottom isolation layer 1 are reversed upward to the top surface of the carbonaceous soft rock, and the reverse width b is ≥ 1m.
[0050] Then, geogrid 8 and composite geotextile 9 are laid on the left and right sides of the top surface of the soft carbonaceous rock in sequence, with a laying width of c ≥ 3m, and fixed with U-shaped nails 10. Then, 1-2m thick soft carbonaceous rock is filled on top of the composite geotextile 9, and the geogrid 8 and composite geotextile 9 laid last time are reversed, with a reversed width of b ≥ 1m. Then, geogrid 8 and composite geotextile 9 are laid on the left and right sides of the top surface of the soft soft rock in sequence again, with a laying width of c ≥ 3m. Repeat the above steps until the lower embankment is completed, and the lower embankment soft carbonaceous rock filling area 2 and the anti-seepage areas 3 on its left and right sides are formed.
[0051] 2. Carbonaceous soft rock filler particle size and loose layer thickness
[0052] Carbonaceous soft rock can generally be excavated by cold excavation with an excavator. When direct excavation is difficult, blasting can be used. The maximum particle size of carbonaceous soft rock filler should be controlled within 30cm. The compaction layer thickness should not exceed 40cm. When loading in the material yard, the coarse and fine materials of each car should be consciously mixed to ensure uniform filling and a certain gradation.
[0053] 3. Paving and rolling
[0054] (1) When loading the first layer of carbonaceous soft rock, the heavy-loaded vehicle should adopt the backward loading method, and the bulldozer should flatten the material in time. The heavy-loaded vehicle should drive on the flattened carbonaceous soft rock layer to avoid the heavy-loaded vehicle driving and rolling directly on the composite geotextile 9.
[0055] (2) During the filling process, the cross slope of the top surface of the embankment shall be ≥ 4% to ensure the lateral drainage capacity of the top surface of the embankment.
[0056] (3) Use a heavy roller with a deadweight of ≥26t for rolling. Adhere to the principle of static rolling first and then vibration, and first the two sides and then the middle. The number of rolling times is determined by the test road. Generally, 3 to 4 times are sufficient, and one round trip is considered one time.
[0057] (4) Pay attention to the control of overlap length and width when filling transition sections and segmented filling. The joints of each section should overlap and be compacted, and the longitudinal overlap length should be more than 2m.
[0058] 4. Compaction standards and quality control
[0059] The maximum particle size of carbonaceous soft rock filler is generally tens of centimeters, and the filler is mainly coarse particles. The maximum particle size of the compaction test is 40mm. Obviously, the proportion of fillers with a particle size less than 40mm in the carbonaceous soft rock is not high. Therefore, the compaction test results cannot fully reflect the compaction characteristics of carbonaceous soft rock fillers. If the maximum dry density determined by the compaction test results is used as the standard dry density, the compaction degree obtained by the sand filling method is likely to exceed 100, which loses the meaning of judgment. Therefore, it is not appropriate to use compaction index control for carbonaceous soft rock roadbed.
[0060] For the large particle size of carbonaceous soft rock, it is reasonable to refer to the quality control method of stone-filled roadbed. That is, the compaction standard of carbonaceous soft rock is determined by the test road, including: compaction layer thickness, maximum particle size, rolling machinery and number of rolling times. Quality control is mainly based on construction process control, combined with compaction settlement difference control. Under normal circumstances, the compaction settlement difference of the last two times should be ≤3mm.
[0061] 5. Anti-seepage area
[0062] (1) After filling the 1-2m thick carbonaceous soft rock, the roadbed slope is repaired according to the designed slope, and then the reserved reverse geogrid section and composite geotextile section of the previous layer are reversed upward along the repaired slope, and a new geogrid 8 is laid at the same time. The ends of the reversed geogrid, the ends of the composite geotextile and the newly laid geogrid 8 are straightened and leveled, and after tensioning, they are fixed to the carbonaceous soft rock below with U-shaped nails 10 every 1m. Then a new composite geotextile 9 is laid.
[0063] (2) The width of the anti-seepage zone 3 is c ≥ 3 m, and the width of the reverse package is b ≥ 1 m.
[0064] (3) The geogrid 8 is a bidirectional steel-plastic geogrid, and the composite geotextile 9 is a composite geomembrane with two fabrics and one membrane.
[0065] (4) The maximum particle size of the filler within 30 cm from the geosynthetics, i.e., geogrid 8 and composite geotextile 9, should not be greater than 10 cm, and the filler should be carbonaceous soft rock. When the first layer of filler is spread on the composite geotextile 9 in the anti-seepage area 3, the truck should use the backward loading method and should not roll directly on the composite geotextile 9.
[0066] (5) Within two days after the geogrid 8 and composite geotextile 9 are laid, the roadbed slope should be covered with rooting soil to avoid exposure to the sun. The rooting soil grass seeds of the slope can be plants suitable for local climatic conditions.
[0067] (6) Filling speed
[0068] Carbonaceous soft rock roadbed should be quickly filled and constructed, and the construction should be completed before the rainy season to provide it with a longer natural settlement time.
[0069] 3. Embankment and roadbed
[0070] After the lower embankment is completed, the geogrid 8 and the composite geotextile 9 are laid on the top surface in sequence, and then the upper embankment 4 and the roadbed 5 are filled.
[0071] In general, the CBR value of carbonaceous soft rock is between 8 and 10, which just meets the minimum requirements of the specification for fillers. However, as the connection between the roadbed and the pavement, the strength standard of using carbonaceous soft rock as roadbed filler is undoubtedly low, which is not conducive to the stress distribution and transmission between the pavement and the roadbed. On the other hand, when using carbonaceous soft rock as the roadbed, the bending index is difficult to meet the design requirements during the roadbed inspection. The rebound modulus of the roadbed mainly depends on the roadbed and the upper embankment, and the rebound modulus has a good positive correlation with the filler CBR. Therefore, in order to ensure the rebound modulus of the roadbed, the CBR value of the roadbed and the upper embankment filler is increased. The lower embankment mainly plays a filling role and has little effect on the roadbed rebound modulus, so the CBR of the carbonaceous soft rock filler of the lower embankment is not adjusted.
[0072] Based on the above considerations, in order to ensure the high performance of the carbonaceous soft rock filler roadbed, it is proposed that for expressways and first-class highways, the upper embankment 4 and the roadbed 5 1.5m below the top surface of the roadbed should be filled with hard graded crushed stone, gravel and other fillers with good water stability and high strength, and the minimum bearing ratio CBR of the upper embankment 4 filler is ≥5, and the minimum bearing ratio CBR of the roadbed 5 filler is ≥10. This is higher than the relevant provisions of the "Highway Roadbed Design Code" JTGD30-2015 "For expressways and first-class highways, the minimum bearing ratio CBR of the upper roadbed filler is ≥8, the minimum bearing ratio CBR of the lower roadbed filler is ≥5, and the minimum bearing ratio CBR of the upper embankment filler is ≥4".
[0073] The maximum particle size of the upper embankment 4 stone filling shall not exceed 15cm, and that of the roadbed 5 shall not exceed 10cm. The filler shall have a certain gradation, and there shall be no obvious concentration of coarse particles when observed with the naked eye. The deadweight of the vibratory roller shall be greater than or equal to 30t, and the number of rolling passes shall be no less than 6 times, with no wheel marks on the surface. The compaction thickness of the upper embankment 4 shall not exceed 40cm, and that of the roadbed 5 shall not exceed 30cm, and the compaction thickness of the last layer on the top surface of the roadbed 5 shall not be less than 10cm. The pores on the top surface of the roadbed 5 shall be filled and leveled with hard and medium-hard stone chips, and shall not be leveled with fine-grained soil. The compaction quality of the upper embankment 4 and the roadbed 5 is jointly controlled by construction process parameters and compaction settlement difference, and the compaction settlement difference of the last two passes shall be ≤2mm.
[0074] 4. Road surface
[0075] A road surface 6 is laid on top of the roadbed 5. The road surface 6 is designed according to a conventional graded crushed stone base layer 12 with a thickness of 20 cm, a cement stabilized crushed stone base layer 13 with a thickness of 38 cm, and a surface layer 14 with a lower layer, a middle layer, and an upper layer with thicknesses of 8 cm, 6 cm, and 4 cm respectively. The cement stabilized crushed stone base layer 13 is paved in its entirety and constructed in two layers.
[0076] 5. Central Divider
[0077] When the central dividing strip 7 adopts conventional corrugated beam guardrail, longitudinal drainage seepage ditch, anti-seepage layer, water collection tank, anti-seepage geotextile, etc. are arranged inside, and the casing is usually pre-buried and installed by drilling. The drilling depth varies, and the drilling penetrates the surface layer, and even penetrates the base layer and sub-base layer to the roadbed. In this way, rainwater can easily seep down along the pipe, through the roadbed and the upper embankment to the lower embankment, and then soften the carbonaceous soft rock filling material of the lower embankment. For this reason, it is proposed that the central dividing strip 7 adopts a separated prefabricated New Jersey guardrail 16 to completely seal the central dividing strip 7 and prevent rainwater from seeping in.
[0078] The cement stabilized gravel base 13 is paved in full width and constructed in two layers. When the first layer of the cement stabilized gravel base 13 is paved, a concrete corbel 15 is cast on top of it. The corbel is 20 cm thick and the concrete grade is C20. When the corbel 15 reaches 75% of the design strength, the second layer of cement stabilized gravel base 13 on the left and right sides is paved halfway, and the corbel 15 is flush with the top surface of the second layer of cement stabilized gravel base 13.
[0079] After the bolster 15 reaches the design strength, the separate prefabricated New Jersey guardrail 16 is installed. A drainage hole with a hole diameter of 2 cm and a slope of 2% is reserved at the bottom of the New Jersey guardrail 16 to ensure that the accumulated water inside the central dividing strip 7 can be drained.
[0080] After the New Jersey guardrail 16 is installed, a concrete cushion layer 18 is constructed between the New Jersey guardrails 16 and above the sleeper beam 15. The cushion layer is 20 cm thick and the concrete grade is C20.
[0081] After the concrete cushion layer 18 reaches the designed strength, the anti-filter geotextile 19 is laid on top of it, and then the sand filling layer 20 is filled with a thickness of 30 to 40 cm. After compaction, the anti-filter geotextile 19 should wrap around the sand filling layer 20 inside it.
[0082] Then, the planting soil 21 is backfilled on the top of the anti-filtration geotextile 19 for planting anti-glare trees and green plants.
[0083] 6. Roadbed settlement monitoring
[0084] During the roadbed filling period, a settlement monitoring system for high-performance carbonaceous soft rock roadbed should be constructed to monitor the surface settlement of the roadbed. Observation points can be arranged in the center and on the left and right sides of the roadbed to track the settlement and stability of the roadbed in real time, and provide reliable data support for the time nodes of road paving.
[0085] The above description is only a preferred specific implementation manner of the present invention, but the protection scope of the present invention is not limited thereto. Any technician familiar with the technical field can make equivalent replacements or changes according to the technical scheme and inventive concept of the present invention within the technical scope disclosed by the present invention, which should be covered by the protection scope of the present invention.
Claims
1. A high-performance carbonaceous soft rock roadbed structure for a highway, characterized in that: It includes the isolation layer, carbonaceous soft rock filling area, upper embankment, roadbed and road surface arranged in sequence from bottom to top; The carbonaceous soft rock filling area is provided with anti-seepage areas on both sides, and the anti-seepage areas are provided with anti-seepage layers distributed in sequence; A groove is opened on the road surface, a sleeper is arranged in the groove, two sets of New Jersey guardrails are arranged above the sleeper, and a concrete cushion layer, a sand filling layer and a planting soil layer are sandwiched between the two New Jersey guardrails from bottom to top.
2. The high-performance carbonaceous soft rock roadbed structure for a highway according to claim 1 is characterized in that: The anti-seepage layer comprises a composite geotextile and a geogrid, the anti-seepage layer is coated with carbonaceous soft rock, and each layer of the anti-seepage layer is connected by U-shaped nails.
3. The high-performance carbonaceous soft rock roadbed structure for a highway according to claim 1 is characterized in that: The road surface comprises a graded crushed stone base layer, a cement stabilized crushed stone base layer and a surface layer, and the grooves are arranged on the cement stabilized crushed stone base layer and the surface layer.
4. The high-performance carbonaceous soft rock roadbed structure for a highway according to claim 1 is characterized in that: A drainage hole is provided on the New Jersey guardrail, the height of the drainage hole is higher than the height of the upper end surface of the groove, the hole diameter of the drainage hole is 2 cm, and the slope is 2%.
5. A high-performance highway carbonaceous soft rock roadbed construction method, characterized in that: The following steps are involved: S1: Geogrids and composite geotextiles are laid on the isolation layer at the bottom of the embankment in sequence, and carbonaceous soft rock is filled on top of the composite geotextiles. After the carbonaceous soft rock is filled with a thickness of 1 to 2 meters, the geogrids and composite geotextiles on the upper part of the bottom isolation layer are reversed to the top surface of the carbonaceous soft rock to form a carbonaceous soft rock filling area; S2: geogrid, composite geotextile and 1-2m thick carbonaceous soft rock are laid on the left and right sides of the carbonaceous soft rock filling area in turn, and the geogrid and composite geotextile in this step are used to wrap the carbonaceous soft rock, and the operation is repeated to form an anti-seepage area until the anti-seepage area is flush with the top surface of the carbonaceous soft rock filling area, and the anti-seepage area and the carbonaceous soft rock filling area form a lower embankment; S3: Geogrid and composite geotextile are laid on the top surface of the lower embankment in sequence, and then the upper embankment and roadbed are filled in sequence and compacted; S4: The road surface is laid on the roadbed. The road surface is laid in sequence according to the graded crushed stone base, cement stabilized crushed stone base and surface layer. The cement stabilized crushed stone base is constructed in two layers, and the first layer is paved in the entire width; S5: After the first layer of cement-stabilized crushed stone base is paved, cast-in-place concrete pillows are placed on top of it, and the second layer of cement-stabilized crushed stone base on the left and right sides is paved halfway, with the pillows flush with the top surfaces of the second layer of cement-stabilized crushed stone base; S6: After the sleeper beam reaches the design strength, install the New Jersey guardrail and lay the concrete cushion between the New Jersey guardrails. After the concrete cushion reaches the design strength, lay the anti-filter geotextile on top and fill the sand layer. Cover the sand layer with anti-filter geotextile and finally backfill the sand layer with planting soil.
6. A method for constructing a high-performance highway carbonaceous soft rock roadbed according to claim 5, characterized in that: In step S1, the carbonaceous soft rock is laid in layers in sequence and compacted by a heavy roller. During the filling process, the cross slope of the top surface of the embankment is ≥4%, and the intersections of the sections should overlap and be compacted with each other, with a longitudinal overlap length of more than 2m.
7. The method for constructing a high-performance highway carbonaceous soft rock roadbed according to claim 5, characterized in that: In step S2, after filling the 1-2 m thick carbonaceous soft rock, the roadbed slope is repaired according to the designed slope, and then the reversed geogrid section and composite geotextile section of the previous layer are reversed upward along the repaired slope, and a new geogrid is laid at the same time; the reversed geogrid end, the composite geotextile end and the newly laid geogrid are straightened and leveled, and after tensioning, they are fixed on the carbonaceous soft rock below with U-shaped nails every 1 m, and then a new composite geotextile is laid; The width of the anti-seepage zone c ≥ 3m, and the width of the reverse package b ≥ 1m; the geogrid uses a bidirectional steel-plastic geogrid, and the composite geotextile is a composite geomembrane with two cloths and one membrane.
8. The method for constructing a high-performance carbonaceous soft rock roadbed for a highway according to claim 5, characterized in that: In step S3, the upper embankment and roadbed are both filled with hard graded crushed stone and gravel fillers, the maximum particle size of the upper embankment filling stone is less than or equal to 15 cm, and the maximum particle size of the roadbed filling stone is less than or equal to 10 cm; the compacted thickness of the upper embankment is less than or equal to 40 cm, and the compacted thickness of the roadbed is less than or equal to 30 cm.
9. The method for constructing a high-performance highway carbonaceous soft rock roadbed according to claim 5, characterized in that: In step S4, the thickness of the medium-graded crushed stone subbase of the road surface is 15-25 cm, the thickness of the cement-stabilized crushed stone base is 35-40 cm, and the surface layer includes a lower layer, a middle layer and an upper layer, the thickness of the lower layer is 5-10 cm, the thickness of the middle layer is 5-8 cm, and the thickness of the upper layer is 3-5 cm.
10. The method for constructing a high-performance highway carbonaceous soft rock roadbed according to claim 5, characterized in that: In step S5, the thickness of the bolster is 18-25 cm. After the bolster reaches more than 75% of the design strength, the second layer of cement-stabilized crushed stone base on the left and right sides is half-paved.
Citation Information
Patent Citations
Carbonaceous soft rock-geosynthetic material composite roadbed structure
CN111441211A
Drainage design and construction method for interior and edge of long-service-life flexible structure pavement
CN115506197A
Central dividing strip capable of keeping humidity of soil body
CN220284675U
Highway carbon soft rock high-performance roadbed structure
CN223150956U
Telescopic device and construction method for draining high level road
JP2000144614A