Grounding monitoring system and motor

By designing a grounding monitoring system in the motor, the switching unit and prompt unit are used to visually display the live status and grounding status of the metal shell, the live and grounding problems of the metal shell in the equipment are solved, the safety and maintenance efficiency are improved, and operation is reduced cost.

CN118980965APending Publication Date: 2024-11-19BEIJING ENFI ENVIRONMENTAL TECH CO LTD
View PDF 0 Cites 1 Cited by

Patent Information

Application Number
CN202411064587.2
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-05
Publication Date
2024-11-19

AI Technical Summary

Technical Problem

In the operation of motors and other equipment, the activation of the metal shell leads to safety problems, and it is impossible to intuitively display whether the metal shell is charged and whether the grounding end is effectively grounded, which affects the safety and maintenance efficiency of the equipment.

Method used

A grounding monitoring system is designed, including a switching unit, an operation monitoring device and a test monitoring device. Through switching of the switching unit, the live state of the metal shell and the grounding of the grounding terminal are visually displayed using prompt units (such as buzzers and indicators). to ensure that the operator can accurately judge and perform effective maintenance.

Benefits of technology

It improves the safety and maintenance efficiency of equipment operations, reduces operating costs, and does not affect the normal operation of equipment. It can be inspected during equipment operation.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118980965A_ABST
    Figure CN118980965A_ABST
Patent Text Reader

Abstract

The invention provides a grounding monitoring system, which comprises a switching unit, the third end of the switching unit is connected with the grounding end of equipment, the first end and the third end of the switching unit are conducted, or the second end and the third end of the switching unit are conducted; the operation monitoring device comprises a first prompting unit, and the first prompting unit is connected in series between the metal shell of the equipment and the first end of the switching unit; and the test monitoring device comprises a test power supply and a second prompting unit, and the second prompting unit is connected in series between the test power supply and the second end of the switching unit. According to the grounding monitoring system disclosed by the invention, an operator can accurately and efficiently judge whether the metal shell is electrified or not and whether the grounding end is effectively grounded or not in daily maintenance, so that the safety of equipment operation is improved, and the cost of equipment operation is reduced.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present disclosure relates to the technical field of grounding monitoring, and in particular to a grounding monitoring system and a motor. Background Art

[0002] During the operation of equipment such as motors, once the metal shell becomes charged due to a fault, it will cause damage to the operators and equipment, leading to more serious safety problems. Therefore, the metal shell of the equipment needs to be grounded through the grounding terminal of the equipment. However, since the charge of the metal shell and the effective grounding of the grounding terminal cannot be displayed intuitively, the operators cannot accurately and efficiently judge whether the metal shell is charged and whether the grounding terminal is effectively grounded during daily maintenance, which leads to lower safety and higher cost of equipment operation. Summary of the invention

[0003] The present disclosure aims to solve one of the technical problems in the related art at least to some extent.

[0004] To this end, an object of the present disclosure is to provide a ground monitoring system and a motor.

[0005] To achieve the above-mentioned purpose, the first aspect of the present disclosure provides a grounding monitoring system, comprising: a switching unit, the third end of the switching unit is connected to the grounding end of the device, wherein the first end and the third end of the switching unit are conductive, or the second end and the third end are conductive; an operation monitoring device, the operation monitoring device comprising: a first prompt unit, the first prompt unit is connected in series between the metal shell of the device and the first end of the switching unit, and the first prompt unit is used to issue a first prompt message when power is supplied; a test monitoring device, the test monitoring device comprising: a test power supply and a second prompt unit, the second prompt unit is connected in series between the test power supply and the second end of the switching unit, and the second prompt unit is used to issue a second prompt message when power is supplied.

[0006] Optionally, the operation monitoring device also includes: a counting unit, which is connected in series between the metal shell and the first end of the switching unit, and the counting unit and the first prompt unit are connected in parallel, the first end of the counting unit is connected to the metal shell, the second end of the counting unit is connected to the first end of the switching unit, and the counting unit is used to record the number of power-on times.

[0007] Optionally, the operation monitoring device also includes: a first voltage conversion unit, which is connected in series between the metal shell and the first prompt unit, and the first end of the first voltage conversion unit is connected to the metal shell, and the second end of the first voltage conversion unit is connected to the first end of the first prompt unit, and the first voltage conversion unit is used to convert the voltage of the metal shell into a stable first voltage.

[0008] Optionally, the first prompt unit includes: a buzzer, which is connected in series between the metal shell and the first end of the switching unit, and the first end of the buzzer is connected to the metal shell, and the second end of the buzzer is connected to the first end of the switching unit, and the buzzer is used to emit sound information when power is supplied; and / or a first indicator light, which is connected in series between the metal shell and the first end of the switching unit, and the first end of the first indicator light is connected to the metal shell, and the second end of the first indicator light is connected to the first end of the switching unit, and the first indicator light is used to emit first light information when power is supplied.

[0009] Optionally, the test monitoring device also includes: a second voltage conversion unit, the second voltage conversion unit is connected in series between the test power supply and the second prompt unit, and the first end of the second voltage conversion unit is connected to the test power supply, the second end of the second voltage conversion unit is connected to the first end of the second prompt unit, and the second voltage conversion unit is used to convert the voltage of the test power supply into a stable second voltage.

[0010] Optionally, the test monitoring device further includes: a voltage detection unit, a detection end of the voltage detection unit is connected to the test power supply, and the voltage detection unit is used to detect and display the voltage of the test power supply.

[0011] Optionally, the second prompt unit includes: a second indicator light, the second indicator light is connected in series between the test power supply and the second end of the switching unit, and the first end of the second indicator light is connected to the test power supply, and the second end of the second indicator light is connected to the second end of the switching unit, and the second indicator light is used to emit a second light information when power is supplied.

[0012] Optionally, the grounding monitoring system also includes: an encapsulation shell, which is arranged on the metal shell, and the switching unit, the operation monitoring device and the test monitoring device are respectively arranged inside the encapsulation shell, and the operating end of the switching unit, the prompt end of the first prompt unit and the prompt end of the second prompt unit respectively extend to the outer surface of the encapsulation shell.

[0013] Optionally, the grounding monitoring system also includes: a first terminal, which is arranged on the outer surface of the encapsulation shell and is connected in series between the metal shell and the first prompt unit, the first end of the first terminal is connected to the metal shell, and the second end of the first terminal is connected to the first end of the first prompt unit; and / or a second terminal, which is arranged on the outer surface of the encapsulation shell and is connected in series between the third end of the switching unit and the grounding terminal of the device, the first end of the second terminal is connected to the grounding terminal of the device, and the second end of the second terminal is connected to the third end of the switching unit.

[0014] A second aspect of the present disclosure provides a motor, comprising: a grounding monitoring system as provided in the first aspect of the present disclosure, wherein the third end of a switching unit of the grounding monitoring system is connected to a grounding end of the motor, and a first prompt unit of the grounding monitoring system is connected in series between a metal shell of the motor and a first end of the switching unit.

[0015] The technical solution provided by the present disclosure may have the following beneficial effects:

[0016] When the switching unit is switched, the charged state of the metal shell of the equipment and the grounding state of the grounding terminal of the equipment can be displayed intuitively, so that the operating personnel can accurately and efficiently judge whether the metal shell is charged and whether the grounding terminal is effectively grounded during daily maintenance, thereby improving the safety of equipment operation and reducing the cost of equipment operation.

[0017] Additional aspects and advantages of the present disclosure will be given in part in the following description and in part will be obvious from the following description or learned through practice of the present disclosure. BRIEF DESCRIPTION OF THE DRAWINGS

[0018] The above and / or additional aspects and advantages of the present disclosure will become apparent and easily understood from the following description of the embodiments in conjunction with the accompanying drawings, in which:

[0019] Figure 1 is a circuit diagram of a ground monitoring system proposed in an embodiment of the present disclosure;

[0020] Figure 2 is a circuit diagram of a ground monitoring system proposed in an embodiment of the present disclosure;

[0021] As shown in the figure: 1. Operation monitoring device;

[0022] 11. a first prompting unit, 111. a buzzer, 112. a first indicator light;

[0023] 12. a counting unit, 13. a first voltage conversion unit;

[0024] 2. Test monitoring device;

[0025] 21. Test power supply;

[0026] 22. a second prompting unit, 221. a second indicator light;

[0027] 23. A second voltage conversion unit, 24. A voltage detection unit;

[0028] 3. a switching unit, 4. a packaging shell, 5. a first wiring terminal, 6. a second wiring terminal;

[0029] 100. Metal shell, 200. Ground terminal. DETAILED DESCRIPTION

[0030] Embodiments of the present disclosure are described in detail below, examples of which are shown in the accompanying drawings, wherein the same or similar reference numerals throughout represent the same or similar elements or elements having the same or similar functions. The embodiments described below with reference to the accompanying drawings are exemplary and are only used to explain the present disclosure, and are not to be construed as limitations of the present disclosure. On the contrary, the embodiments of the present disclosure include all changes, modifications, and equivalents that fall within the spirit and connotation of the appended claims.

[0031] like Figure 1 and Figure 2 As shown, an embodiment of the present disclosure proposes a grounding monitoring system, including: a switching unit 3, an operation monitoring device 1 and a test monitoring device 2, wherein the third end of the switching unit 3 is connected to the grounding end 200 of the device, wherein the first end and the third end of the switching unit 3 are conductive, or the second end and the third end are conductive, the operation monitoring device 1 includes: a first prompt unit 11, the first prompt unit 11 is connected in series between the metal shell 100 of the device and the first end of the switching unit 3, and the first prompt unit 11 is used to send a first prompt message when powered on, the test monitoring device 2 includes: a test power supply 21 and a second prompt unit 22, the second prompt unit 22 is connected in series between the test power supply 21 and the second end of the switching unit 3, and the second prompt unit 22 is used to send a second prompt message when powered on.

[0032] It can be understood that when the first end and the third end of the switching unit 3 are turned on, since the first prompt unit 11 is connected in series between the metal shell 100 of the device and the first end of the switching unit 3, and the third end of the switching unit 3 is connected to the ground terminal 200 of the device, the metal shell 100 of the device and the ground terminal 200 constitute a power supply circuit for the first prompt unit 11. If the metal shell 100 is energized, the first prompt unit 11 can be energized. Therefore, the first prompt information issued by the first prompt unit 11 can be used to intuitively display the charged state of the metal shell 100 of the device.

[0033] When the second end and the third end of the switching unit 3 are turned on, since the second prompt unit 22 is connected in series between the test power supply 21 and the second end of the switching unit 3, and the third end of the switching unit 3 is connected to the ground terminal 200 of the device, the test power supply 21 and the ground terminal 200 of the device constitute a power supply circuit for the second prompt unit 22. If the ground terminal 200 of the device is effectively grounded, the second prompt unit 22 can be powered. Therefore, the second prompt information issued by the second prompt unit 22 can be used to intuitively display the grounding status of the device ground terminal 200.

[0034] Therefore, when the switching unit 3 is switched, the charged state of the metal shell 100 of the device can be intuitively displayed, and the grounded state of the grounding terminal 200 of the device can be intuitively displayed, so that the operating personnel can accurately and efficiently judge whether the metal shell 100 is charged and whether the grounding terminal 200 is effectively grounded during daily maintenance, thereby improving the safety of equipment operation and reducing the cost of equipment operation.

[0035] It should be noted that the switching unit 3 is used for switching the passage. Specifically, the first end and the third end of the switching unit 3 are connected, which can realize the conduction of the passage between the metal shell 100 and the grounding terminal 200 of the equipment, so that the operation monitoring of the metal shell 100 of the equipment is realized by using the first prompt unit 11; the second end and the third end of the switching unit 3 are connected, which can realize the conduction of the passage between the test power supply 21 and the equipment grounding terminal 200, so that the test monitoring of the equipment grounding terminal 200 is realized by using the second prompt unit 22. The specific type of the switching unit 3 can be set according to actual needs, and there is no limitation to this. For example, the switching unit 3 can be a switching switch controlled by a button, and the button action drives the passage switching of the switching switch.

[0036] The grounding monitoring of the equipment can be performed by switching unit 3 in any inspection cycle, and the operation can be performed when the equipment is running, without the need to stop the equipment for inspection, thus reducing the impact on the normal operation of the equipment.

[0037] The operation monitoring device 1 is used for operation monitoring of the metal shell 100 of the equipment, wherein the first prompt unit 11 is used to send a first prompt message when powered on. The specific type of the first prompt unit 11 can be set according to actual needs and is not limited to this.

[0038] The test monitoring device 2 is used for test monitoring of the equipment grounding terminal 200, wherein the test power supply 21 is used to cooperate with the equipment grounding terminal 200 to form a power supply circuit for the second prompt unit 22. Specifically, the positive side of the test power supply 21 and the equipment grounding terminal 200 constitute the power supply circuit for the second prompt unit 22, while the negative side of the test power supply 21 is connected to the equipotential terminal of the grounding terminal 200. The specific type of the test power supply 21 can be set according to actual needs and is not limited to this. For example, the test power supply 21 can be a rechargeable battery. When the voltage is insufficient, the test power supply 21 is charged by an external power supply; the test power supply 21 can be a non-rechargeable battery. When the voltage is insufficient, the test power supply 21 is replaced.

[0039] The second prompt unit 22 is used to send out a second prompt message when power is supplied. The specific type of the second prompt unit 22 can be set according to actual needs and is not limited thereto.

[0040] The first prompt information and the second prompt information are used to intuitively prompt the operating personnel. The specific types of the first prompt information and the second prompt information can be set according to actual needs and are not limited to this. For example, the first prompt information and the second prompt information can be lighting information, sound information, sound-light information, etc.

[0041] like Figure 2 As shown, in some embodiments, the operation monitoring device 1 also includes: a counting unit 12, the counting unit 12 is connected in series between the metal shell 100 and the first end of the switching unit 3, and the counting unit 12 and the first prompt unit 11 are connected in parallel, the first end of the counting unit 12 is connected to the metal shell 100, and the second end of the counting unit 12 is connected to the first end of the switching unit 3, and the counting unit 12 is used to record the number of power-on times.

[0042] It can be understood that since the counting unit 12 is connected in series between the metal shell 100 and the first end of the switching unit 3, and the counting unit 12 and the first prompt unit 11 are connected in parallel, when the first end and the third end of the switching unit 3 are turned on, the metal shell 100 of the device and the grounding terminal 200 constitute a power supply circuit of the counting unit 12. If the metal shell 100 is energized, the counting unit 12 can be energized. Therefore, the counting of the counting unit 12 can be used to monitor the energized state of the metal shell 100 of the device. At the same time, when the first prompt unit 11 fails or the leakage of the metal shell 100 disappears, it can be determined by the number of times recorded by the counting unit 12 whether the metal shell 100 has leaked electricity. Therefore, with the cooperation of the counting unit 12 and the first prompt unit 11, the double insurance monitoring function is realized, thereby improving the monitoring stability and accuracy of the operation monitoring device 1.

[0043] It should be noted that the counting unit 12 is used to record the number of times it has been powered on. The specific type of the counting unit 12 can be set according to actual needs and is not limited to this. For example, the counting unit 12 can be a counter with a display function. When the counter is powered on, the recorded number increases by one.

[0044] The counting unit 12 can monitor and record intermittent grounding failures caused by abnormal vibrations, thereby reminding operators to pay attention to the grounding problem and repair it.

[0045] like Figure 2 As shown, in some embodiments, the operation monitoring device 1 also includes: a first voltage conversion unit 13, the first voltage conversion unit 13 is connected in series between the metal shell 100 and the first prompt unit 11, and the first end of the first voltage conversion unit 13 is connected to the metal shell 100, and the second end of the first voltage conversion unit 13 is connected to the first end of the first prompt unit 11, and the first voltage conversion unit 13 is used to convert the voltage of the metal shell 100 into a stable first voltage.

[0046] It can be understood that since the first voltage conversion unit 13 is connected in series between the metal shell 100 and the first prompt unit 11, when the first end and the third end of the switching unit 3 are turned on and the metal shell 100 of the device is energized, the electric energy output by the metal shell 100 and the grounding terminal 200 of the device can provide stable power supply to the first prompt unit 11 under the conversion of the first voltage conversion unit 13, so that the first prompt unit 11 can stably send out the first prompt information, thereby realizing stable and accurate monitoring of the operation monitoring device 1.

[0047] It should be noted that since the metal shell 100 is energized due to a device failure, the specific energized voltage is unstable, and the first voltage conversion unit 13 converts the voltage of the metal shell 100 into a stable first voltage, which can ensure that the first prompt unit 11 is stably powered. The specific type of the first voltage conversion unit 13 can be set according to actual needs and is not limited to this. For example, the first voltage conversion unit 13 can be a voltage stabilizer.

[0048] like Figure 2 As shown, in some embodiments, the first prompt unit 11 includes: a buzzer 111, the buzzer 111 is connected in series between the metal shell 100 and the first end of the switching unit 3, and the first end of the buzzer 111 is connected to the metal shell 100, and the second end of the buzzer 111 is connected to the first end of the switching unit 3, and the buzzer 111 is used to emit sound information when power is supplied.

[0049] It can be understood that when the first end and the third end of the switching unit 3 are turned on, since the buzzer 111 is connected in series between the metal shell 100 and the first end of the switching unit 3, and the third end of the switching unit 3 is connected to the ground terminal 200 of the device, the metal shell 100 of the device and the ground terminal 200 constitute a power supply circuit for the buzzer 111. If the metal shell 100 is charged, the buzzer 111 can be powered. Therefore, the sound information emitted by the buzzer 111 can be used to intuitively display the charged state of the metal shell 100 of the device.

[0050] It should be noted that the buzzer 111 is used to emit sound information when powered, so as to utilize the sound information to realize the power monitoring of the metal shell 100 of the equipment. The specific type of the buzzer 111 can be set according to actual needs and is not limited to this.

[0051] like Figure 2 As shown, in some embodiments, the first prompt unit 11 includes: a first indicator light 112, the first indicator light 112 is connected in series between the metal shell 100 and the first end of the switching unit 3, and the first end of the first indicator light 112 is connected to the metal shell 100, and the second end of the first indicator light 112 is connected to the first end of the switching unit 3, and the first indicator light 112 is used to emit a first light information when power is supplied.

[0052] It can be understood that when the first end and the third end of the switching unit 3 are turned on, since the first indicator light 112 is connected in series between the metal shell 100 and the first end of the switching unit 3, and the third end of the switching unit 3 is connected to the ground terminal 200 of the device, the metal shell 100 of the device and the ground terminal 200 constitute a power supply circuit for the first indicator light 112. If the metal shell 100 is energized, the first indicator light 112 can be energized. Therefore, the first light information emitted by the first indicator light 112 can be used to intuitively display the charged state of the metal shell 100 of the device.

[0053] It should be noted that the first indicator light 112 is used to emit a first light information when powered on, so as to utilize the light information to realize the power monitoring of the metal shell 100 of the equipment. The specific type of the first indicator light 112 can be set according to actual needs and is not limited to this.

[0054] like Figure 2 As shown, in some embodiments, the test monitoring device 2 also includes: a second voltage conversion unit 23, the second voltage conversion unit 23 is connected in series between the test power supply 21 and the second prompt unit 22, and the first end of the second voltage conversion unit 23 is connected to the test power supply 21, and the second end of the second voltage conversion unit 23 is connected to the first end of the second prompt unit 22, and the second voltage conversion unit 23 is used to convert the voltage of the test power supply 21 into a stable second voltage.

[0055] It can be understood that since the second voltage conversion unit 23 is connected in series between the test power supply 21 and the second prompt unit 22, when the second end and the third end of the switching unit 3 are turned on and the ground terminal 200 of the equipment is effectively grounded, the electric energy output by the test power supply 21 and the equipment ground terminal 200 can provide stable power supply to the second prompt unit 22 under the conversion of the second voltage conversion unit 23, so that the second prompt unit 22 can stably send out the second prompt information, thereby realizing stable and accurate monitoring of the test monitoring device 2.

[0056] It should be noted that the second voltage conversion unit 23 is used to convert the voltage of the test power supply 21 into a stable second voltage. The specific type of the second voltage conversion unit 23 can be set according to actual needs and is not limited to this. By way of example, the second voltage conversion unit 23 can be an integrated boost module, a boost chip, etc.

[0057] The specific types of the first voltage and the second voltage can be set according to actual needs, and there is no limitation on this. For example, the first voltage and the second voltage can both be 48V.

[0058] like Figure 2 As shown, in some embodiments, the test monitoring device 2 further includes: a voltage detection unit 24 , a detection end of the voltage detection unit 24 is connected to the test power supply 21 , and the voltage detection unit 24 is used to detect and display the voltage of the test power supply 21 .

[0059] It can be understood that since the detection end of the voltage detection unit 24 is connected to the test power supply 21, the voltage detection unit 24 can detect and display the voltage of the test power supply 21, so that the operator can intuitively obtain the voltage status of the test power supply 21. Therefore, when the voltage of the test power supply 21 is insufficient, the operator can replace the test power supply 21 or replenish the electric energy of the test power supply 21 in time, thereby ensuring the stable monitoring of the test monitoring device 2.

[0060] It should be noted that the voltage detection unit 24 is used to detect and display the voltage of the test power supply 21. The specific type of the voltage detection unit 24 can be set according to actual needs and is not limited to this. For example, the voltage detection unit 24 can be a voltmeter, and the positive pole of the voltage detection unit 24 is connected to the positive pole of the test power supply 21, and the negative pole of the voltage detection unit 24 is connected to the negative pole of the test power supply 21.

[0061] like Figure 2As shown, in some embodiments, the second prompt unit 22 includes: a second indicator light 221, the second indicator light 221 is connected in series between the test power supply 21 and the second end of the switching unit 3, and the first end of the second indicator light 221 is connected to the test power supply 21, and the second end of the second indicator light 221 is connected to the second end of the switching unit 3, and the second indicator light 221 is used to emit a second light information when power is supplied.

[0062] It can be understood that when the second end and the third end of the switching unit 3 are turned on, since the second indicator light 221 is connected in series between the test power supply 21 and the second end of the switching unit 3, and the third end of the switching unit 3 is connected to the ground terminal 200 of the device, the test power supply 21 and the ground terminal 200 of the device constitute a power supply circuit for the second indicator light 221. If the ground terminal 200 of the device is effectively grounded, the second indicator light 221 can be energized. Therefore, the second light information emitted by the second indicator light 221 can be used to intuitively display the grounding status of the ground terminal 200 of the device.

[0063] It should be noted that the second indicator light 221 is used to emit a second light information when powered, so as to utilize the light information to realize grounding monitoring of the equipment grounding terminal 200. The specific type of the second indicator light 221 can be set according to actual needs and is not limited to this.

[0064] like Figure 2 As shown, in some embodiments, the grounding monitoring system also includes: an encapsulation shell 4, which is arranged on a metal shell 100, and the switching unit 3, the operation monitoring device 1 and the test monitoring device 2 are respectively arranged inside the encapsulation shell 4, and the operation end of the switching unit 3, the prompt end of the first prompt unit 11 and the prompt end of the second prompt unit 22 extend to the outer surface of the encapsulation shell 4 respectively.

[0065] It can be understood that since the encapsulation shell 4 is arranged on the metal shell 100, and the switching unit 3, the operation monitoring device 1 and the test monitoring device 2 are respectively arranged inside the encapsulation shell 4, the operation end of the switching unit 3, the prompt end of the first prompt unit 11 and the prompt end of the second prompt unit 22 respectively extend to the outer surface of the encapsulation shell 4, so that the grounding monitoring system can use the encapsulation shell 4 to be integrated on the equipment, and can also use the encapsulation shell 4 to achieve effective protection of the switching unit 3, the operation monitoring device 1 and the test monitoring device 2, and will not affect the operation of the switching unit 3, and the prompts of the first prompt unit 11 and the second prompt unit 22, thereby making the use of the grounding monitoring system more convenient and the operation more stable.

[0066] It should be noted that the encapsulation shell 4 is used to encapsulate the carrying switching unit 3, the operation monitoring device 1 and the test monitoring device 2. The specific type of the encapsulation shell 4 can be set according to actual needs and is not limited to this. For example, the encapsulation shell 4 can be a plastic shell.

[0067] like Figure 2 As shown, in some embodiments, the ground monitoring system further includes: a first wiring terminal 5, the first wiring terminal 5 is arranged on the outer surface of the encapsulation shell 4, and the first wiring terminal 5 is connected in series between the metal shell 100 and the first prompt unit 11, the first end of the first wiring terminal 5 is connected to the metal shell 100, and the second end of the first wiring terminal 5 is connected to the first end of the first prompt unit 11;

[0068] It can be understood that since the first terminal 5 is arranged on the outer surface of the packaging shell 4, and the first terminal 5 is connected in series between the metal shell 100 and the first prompt unit 11, the metal shell 100 and the first prompt unit 11 can be electrically connected by using the first terminal 5, and at the same time, it is convenient for the disassembly and assembly of the grounding monitoring system, making the use of the grounding monitoring system more flexible and convenient.

[0069] It should be noted that the first terminal 5 is used to connect the metal shell 100 to achieve electrical connection between the metal shell 100 and the first prompt unit 11. The specific type of the first terminal 5 can be set according to actual needs and is not limited to this.

[0070] like Figure 2 As shown, in some embodiments, the grounding monitoring system also includes: a second terminal 6, the second terminal 6 is arranged on the outer surface of the encapsulation shell 4, and the second terminal 6 is connected in series between the third end of the switching unit 3 and the grounding terminal 200 of the device, the first end of the second terminal 6 is connected to the grounding terminal 200 of the device, and the second end of the second terminal 6 is connected to the third end of the switching unit 3.

[0071] It can be understood that since the second terminal 6 is arranged on the outer surface of the encapsulating shell 4, and the second terminal 6 is connected in series between the third end of the switching unit 3 and the grounding terminal 200 of the device, the second terminal 6 can be used to achieve electrical connection between the third end of the switching unit 3 and the grounding terminal 200 of the device, and at the same time, it is convenient for the disassembly and assembly of the grounding monitoring system, making the use of the grounding monitoring system more flexible and convenient.

[0072] It should be noted that the second terminal 6 is used to connect the ground terminal 200 of the device to achieve electrical connection between the third end of the switching unit 3 and the device ground terminal 200. The specific type of the second terminal 6 can be set according to actual needs and is not limited to this.

[0073] The embodiment of the present disclosure also proposes a motor, including: a grounding monitoring system as in the embodiment of the present disclosure, wherein the third end of the switching unit 3 of the grounding monitoring system is connected to the grounding terminal 200 of the motor, and the first prompt unit 11 of the grounding monitoring system is connected in series between the metal shell 100 of the motor and the first end of the switching unit 3.

[0074] It can be understood that when the first end and the third end of the switching unit 3 are turned on, since the first prompt unit 11 is connected in series between the metal shell 100 of the motor and the first end of the switching unit 3, and the third end of the switching unit 3 is connected to the ground terminal 200 of the motor, the metal shell 100 of the motor and the ground terminal 200 constitute a power supply circuit of the first prompt unit 11. If the metal shell 100 is energized, the first prompt unit 11 can be energized. Therefore, the first prompt information issued by the first prompt unit 11 can be used to intuitively display the charged state of the metal shell 100 of the motor.

[0075] When the second end and the third end of the switching unit 3 are turned on, since the second prompt unit 22 is connected in series between the test power supply 21 and the second end of the switching unit 3, and the third end of the switching unit 3 is connected to the ground terminal 200 of the motor, the test power supply 21 and the ground terminal 200 of the motor constitute a power supply circuit for the second prompt unit 22. If the ground terminal 200 of the motor is effectively grounded, the second prompt unit 22 can be powered. Therefore, the second prompt information issued by the second prompt unit 22 can be used to intuitively display the grounding status of the motor ground terminal 200.

[0076] Therefore, when the switching unit 3 is switched, the charged state of the motor metal shell 100 and the grounded state of the motor grounding terminal 200 can be intuitively displayed, so that the operator can accurately and efficiently judge whether the metal shell 100 is charged and whether the grounding terminal 200 is effectively grounded during daily maintenance, thereby improving the safety of the motor operation and reducing the cost of the motor operation.

[0077] It should be noted that, in the relevant embodiment, the metal housing 100 of the motor is grounded in the following two ways.

[0078] On-site grounding: The independently laid protection line will greatly increase the phase protection reactance of the distribution line, and it is impossible to calculate it, so that the fault current cannot be calculated. Therefore, it cannot accurately meet the requirements of the protection device to cut off the fault circuit within the specified time.

[0079] Grounding inside the junction box: Although it can meet the grounding requirements, it is impossible to intuitively judge the reliability of the grounding. It is necessary to open the motor's junction box and check the wiring terminals and protective wires therein, which increases the workload and working time of the staff.

[0080] The grounding monitoring system of this embodiment can be directly installed on the metal shell 100 of the motor, and can intuitively monitor the grounding of the motor at all times. Once a grounding problem occurs, the grounding monitoring system can not only issue an audible and visual alarm, but also record the number of alarms. When the operator performs daily maintenance on the motor, the grounding monitoring system can be used to directly detect the integrity of the motor grounding to avoid safety accidents caused by grounding disconnection. At the same time, it also reduces the labor intensity of the operator and shortens the operation time. The grounding monitoring system of this embodiment is more efficient and convenient.

[0081] In the description of the present disclosure, the terms "first", "second", etc. are used for descriptive purposes only and cannot be understood as indicating or implying relative importance. In addition, in the description of the present disclosure, unless otherwise specified, "plurality" means two or more.

[0082] Any process or method description in a flowchart or otherwise described herein may be understood to represent a module, segment or portion of code that includes one or more executable instructions for implementing the steps of a specific logical function or process, and the scope of the preferred embodiments of the present disclosure includes alternative implementations in which functions may not be performed in the order shown or discussed, including performing functions in a substantially simultaneous manner or in the reverse order depending on the functions involved, which should be understood by those skilled in the art to which the embodiments of the present disclosure belong.

[0083] In the description of this specification, the description with reference to the terms "one embodiment", "some embodiments", "example", "specific example", or "some examples" means that the specific features, structures, materials or characteristics described in conjunction with the embodiment or example are included in at least one embodiment or example of the present disclosure. In this specification, the schematic representation of the above terms does not necessarily refer to the same embodiment or example. Moreover, the specific features, structures, materials or characteristics described may be combined in any one or more embodiments or examples in a suitable manner.

[0084] Although the embodiments of the present disclosure have been shown and described above, it is to be understood that the above embodiments are exemplary and are not to be construed as limitations of the present disclosure. A person skilled in the art may change, modify, replace and vary the above embodiments within the scope of the present disclosure.

Claims

1. A ground monitoring system, It is characterized in that include: A switching unit, wherein the third end of the switching unit is connected to the ground end of the device, wherein the first end and the third end of the switching unit are conductive, or the second end and the third end of the switching unit are conductive; An operation monitoring device, the operation monitoring device comprising: a first prompt unit, the first prompt unit is connected in series between the metal shell of the device and the first end of the switching unit, and the first prompt unit is used to send a first prompt message when power is supplied; A test monitoring device, the test monitoring device comprises: a test power supply and a second prompt unit, the second prompt unit is connected in series between the test power supply and the second end of the switching unit, and the second prompt unit is used to send out a second prompt information when power is supplied.

2. The ground monitoring system according to claim 1, It is characterized in that The operation monitoring device also includes: A counting unit, wherein the counting unit is connected in series between the metal shell and the first end of the switching unit, and the counting unit and the first prompt unit are connected in parallel, the first end of the counting unit is connected to the metal shell, the second end of the counting unit is connected to the first end of the switching unit, and the counting unit is used to record the number of times power is supplied.

3. The ground monitoring system according to claim 1, It is characterized in that The operation monitoring device also includes: A first voltage conversion unit, wherein the first voltage conversion unit is connected in series between the metal shell and the first prompt unit, and a first end of the first voltage conversion unit is connected to the metal shell, a second end of the first voltage conversion unit is connected to a first end of the first prompt unit, and the first voltage conversion unit is used to convert the voltage of the metal shell into a stable first voltage.

4. The ground monitoring system according to claim 1, It is characterized in that The first prompting unit comprises: A buzzer, the buzzer is connected in series between the metal shell and the first end of the switching unit, the first end of the buzzer is connected to the metal shell, the second end of the buzzer is connected to the first end of the switching unit, and the buzzer is used to emit sound information when powered; and / or A first indicator light is connected in series between the metal shell and the first end of the switching unit, and the first end of the first indicator light is connected to the metal shell, and the second end of the first indicator light is connected to the first end of the switching unit, and the first indicator light is used to emit a first light information when power is supplied.

5. The ground monitoring system according to claim 1, It is characterized in that The test monitoring device also includes: A second voltage conversion unit, the second voltage conversion unit is connected in series between the test power supply and the second prompt unit, and the first end of the second voltage conversion unit is connected to the test power supply, the second end of the second voltage conversion unit is connected to the first end of the second prompt unit, and the second voltage conversion unit is used to convert the voltage of the test power supply into a stable second voltage.

6. The ground monitoring system according to claim 1, It is characterized in that The test monitoring device also includes: A voltage detection unit, wherein a detection end of the voltage detection unit is connected to the test power supply, and the voltage detection unit is used to detect and display the voltage of the test power supply.

7. The ground monitoring system according to claim 1, It is characterized in that The second prompting unit comprises: A second indicator light, the second indicator light is connected in series between the test power supply and the second end of the switching unit, and the first end of the second indicator light is connected to the test power supply, the second end of the second indicator light is connected to the second end of the switching unit, and the second indicator light is used to emit a second light information when power is supplied.

8. The ground monitoring system according to any one of claims 1 to 7, It is characterized in that The ground monitoring system further comprises: An encapsulation shell, wherein the encapsulation shell is arranged on the metal shell, and the switching unit, the operation monitoring device and the test monitoring device are respectively arranged inside the encapsulation shell, and the operation end of the switching unit, the prompt end of the first prompt unit and the prompt end of the second prompt unit respectively extend to the outer surface of the encapsulation shell.

9. The ground monitoring system according to claim 8, It is characterized in that The ground monitoring system further comprises: A first terminal, which is disposed on the outer surface of the encapsulation shell and is connected in series between the metal shell and the first prompt unit, wherein a first end of the first terminal is connected to the metal shell, and a second end of the first terminal is connected to a first end of the first prompt unit; and / or A second terminal, the second terminal is arranged on the outer surface of the packaging shell, and the second terminal is connected in series between the third end of the switching unit and the ground terminal of the device, the first end of the second terminal is connected to the ground terminal of the device, and the second end of the second terminal is connected to the third end of the switching unit.

10. A motor, It is characterized in that include: According to the grounding monitoring system as described in any one of claims 1-9, the third end of the switching unit of the grounding monitoring system is connected to the grounding terminal of the motor, and the first prompt unit of the grounding monitoring system is connected in series between the metal shell of the motor and the first end of the switching unit.

Citation Information

Cited By

  • Electrical control cabinet with anti-creeping function

    CN120511574A