Internet of Things access platform system
Through the IoT access platform system, real-time collection and analysis of cable production line data, generation of schedule decision-making suggestions, solving problems that are difficult to detect in time in cable manufacturing, improving production efficiency and quality control, and realizing intelligent management of cable production lines .
Patent Information
- Application Number
- CN202410998847.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-24
- Publication Date
- 2024-11-19
AI Technical Summary
Due to the reliance on manual monitoring during the existing cable manufacturing process, quality problems are difficult to detect in a timely manner, resulting in waste of resources and low production efficiency, and lagging monitoring time, affecting power supply reliability.
Design an IoT access platform system to collect environmental and equipment data in real time through sensor groups deployed on cable production lines, and generate scheduled decision suggestions in combination with preset model algorithms to achieve smart decision-making, including finished product detection, cost monitoring, and image Functions such as analysis and safety management to improve production efficiency and quality control.
Real-time monitoring and decision-making of cable production lines has been achieved, the efficiency of product control in various processes in the production area has been improved, potential problems have been discovered in a timely manner, costs have been reduced, cable quality and production efficiency have been ensured, and power supply reliability has been enhanced.
Smart Images

Figure CN118982339A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of cable manufacturing, and in particular to an Internet of Things access platform system. Background Art
[0002] Cables are important basic products in network construction. As the degree of urban cabling becomes higher and higher, their quality has received more and more attention. Power grid failures caused by cable quality problems occur frequently, seriously affecting power supply reliability.
[0003] In order to improve the quality of cables, a combination of on-site supervision and random inspection is adopted to carry out quality control. During the production stage, important line cables are supervised and factory accepted. After the cables arrive, cables of all voltage levels are randomly sampled and inspected. However, if quality problems occur after the cable is manufactured, the cables that have been produced will be wasted, and production resources will be wasted. If the production equipment is monitored manually in the factory, there will be a certain lag in the monitoring time, and potential problems cannot be discovered in time, which not only increases the burden on operators, but also easily leads to operational errors, affecting production efficiency and output quality. Therefore, an Internet of Things access platform system is proposed. Summary of the invention
[0004] The present invention provides an Internet of Things access platform system, which can timely discover the production conditions of various cable production lines in a production area and make intelligent decisions.
[0005] The basic solution provided by the present invention is: an Internet of Things access platform system, including an Internet of Things acquisition unit and a processing decision unit;
[0006] The IoT collection unit is used to collect IoT data of the sensor group deployed in the cable processing production line in real time. The IoT collection unit includes a sensor unit and a device collection unit;
[0007] The sensor unit is used to obtain the environmental data and material input information in the cable processing process in real time; the environmental data includes temperature, humidity, and task volume information, and the material input information includes material input speed and material input specification value;
[0008] An equipment collection unit, used to collect output data of each process of each production line and operation data of cable production equipment; the output data includes the output of semi-finished products or finished products;
[0009] Also included is a data recording unit for receiving and storing output data and operation data;
[0010] The processing decision unit is used to combine the real-time environmental data of cables on each production line, material input information, and operating data of cable production equipment through a preset model algorithm, generate scheduling decision suggestions for the cables produced in real time on each production line, and send the scheduling decision suggestions to the administrator's smart terminal.
[0011] The principle of the present invention is that the cable production line includes different cable processing equipment, and different cable processing equipment is responsible for different processes, such as the cable drawing device that reduces the diameter of the metal wire in the cable, the cable stranding device that twists multiple single wires or conductors into one strand, and the winding device, co-extrusion molding equipment, cable wrapping device, cable sheath extrusion device, cable degassing device and other equipment. By obtaining the environmental data and material input information of different equipment working during the cable processing process in the production area, the cable production situation in different processes is determined and visualized on the management terminal, and cable scheduling decision suggestions are generated, which is convenient for administrators to schedule or make decisions on urgent delivery dates through suggestions. For example, if the current equipment operation data can be formed and enter the next equipment according to the current material input speed, there is no need to adjust the parameters. If the production of this batch of cables cannot be completed at the synchronous speed, other production lines are enabled for production.
[0012] Compared with the existing technology, sensors are deployed on each production line in the production area to collect data, and real-time cable production data of each process is obtained to make intelligent decisions. Cable production scheduling decision suggestions are given for different batches of cable production, thereby improving the quality control efficiency of each process in the cable production in the production area.
[0013] Further, it also includes a finished product detection unit;
[0014] The finished product detection unit is used to detect the finished product indicators of the produced finished cables according to the process parameter indicators, and send the finished product indicators and process parameter indicators to the administrator's smart terminal.
[0015] Test the indicators of the finished cable to see if they meet the requirements of the finished product, and send the finished product indicators to the administrator.
[0016] Furthermore, the data recording unit is also used to package the production line, environmental data, and material input information of a single batch of cable production into production records and store them;
[0017] The processing decision unit is also used to learn the changing patterns of the production records stored within the cycle and adjust the scheduling decision suggestions based on the learning results.
[0018] The production line, production environment data, material input information, etc. of each batch of cable products are recorded, and the regularity of the data recorded within the cycle is studied. According to the learning results, historical parameter records are formed, which can be referred to in the next production.
[0019] Further, it includes a cable cost monitoring unit;
[0020] A cost monitoring unit, used to obtain cost data of each batch of cable shutdown maintenance, the cost data including delayed production time, component consumption, and rework and repair material quantity;
[0021] The data recording unit is also used to generate a cost threshold according to the cables in a cycle. When the cost data in the cycle is higher than the cost threshold, the cost data in the cycle is analyzed and cost control suggestions are generated.
[0022] The maintenance cost of each batch of cable production is managed. The maintenance cost includes both time cost and component replacement cost. When the actual cost is within the cost threshold, it means that the cost control is normal. If it is outside the cost threshold, it means that the cost control is insufficient. By identifying and analyzing the actual cost of each batch of cable production, abnormal situations can be judged, which is beneficial to cost control.
[0023] Furthermore, it also includes an image analysis unit, and the Internet of Things acquisition unit also includes a speed infrared imaging acquisition unit;
[0024] The infrared imaging acquisition unit is used to acquire infrared imaging of the cable surface in real time during the cable processing to obtain a surface image, and to acquire a radiographic image of the inside of the cable through an X-ray visual sensor to obtain a cross-sectional image;
[0025] An image analysis unit is used to identify and analyze the cross-sectional image and the surface image through an image recognition algorithm to determine whether there are cracks on the cable surface, whether the diameter width of the cable inner core reaches a preset value, and whether there are defects in the cable inner core;
[0026] The finished product early warning unit is used to send defect information to the administrator's smart terminal when any of the following defect information occurs: cracks, diameter width less than a preset value, or cable core defects.
[0027] In the continuous production process, the finished product is accompanied by dynamic changes in various parameters. Controlling each parameter within a certain range can ensure qualified or excellent products. If cracks appear on the cable sheath, it is easy to accelerate the aging of the sheath or even break. If the inner core diameter of the cable is too small or the inner core of the cable is defective, the resistance value and heat generation of a certain cable will be affected, affecting the normal signal transmission stability of the cable. Therefore, by acquiring images of the cable surface and internal cross-section, an alarm will be issued when a defect occurs in the cable.
[0028] Furthermore, it also includes a park security management unit, which includes a video monitoring unit, a video recognition unit and a time warning unit;
[0029] Video monitoring unit, used to collect monitoring images of various monitoring points in the production area;
[0030] The video recognition unit is used to identify and analyze the surveillance images through the video recognition algorithm to determine whether there is a security incident;
[0031] The event warning unit is used to send security events to the administrator's smart terminal when there are security events.
[0032] Monitor the production area and identify incidents with potential safety hazards through video surveillance, such as illegal operations, prolonged stay in dangerous areas, entry of non-production personnel, etc., so as to conduct early warning management.
[0033] Further, it also includes a maintenance record unit and an equipment analysis unit;
[0034] Maintenance record unit, used to record and store daily maintenance information and repair information of cable production equipment;
[0035] The equipment analysis unit is used to analyze the equipment health status based on the recorded and stored equipment daily maintenance information and repair information, and send the cable production equipment that does not meet the equipment health requirements to the administrator's smart terminal according to the preset equipment health requirements.
[0036] By recording the daily maintenance and repair data of the equipment, the health status of the equipment is judged periodically. When the equipment does not meet the equipment health requirements, the corresponding equipment will be sent to the administrator for replacement. Automatic health management of the equipment is achieved. BRIEF DESCRIPTION OF THE DRAWINGS
[0037] Figure 1 Schematic diagram of an embodiment of the present invention. DETAILED DESCRIPTION
[0038] The following is further described in detail through specific implementation methods:
[0039] The embodiment is basically as shown in the attached Figure 1 As shown:
[0040] The Internet of Things access platform system includes a sensor unit, an equipment collection unit, a processing decision unit, a finished product detection unit, a data recording unit, a cable cost monitoring unit, an image analysis unit, an infrared imaging collection unit, a finished product early warning unit, a video monitoring unit, a video recognition unit, and a time early warning unit.
[0041] Cable production equipment includes cable wire drawing equipment, cable stranding equipment, coiling equipment, co-extrusion equipment, cable wrapping equipment, cable sheath extrusion equipment, and cable degassing equipment.
[0042] The IoT collection unit is used to collect IoT data of the sensor group deployed in the cable processing production line in real time. The IoT collection unit includes a sensor unit and a device collection unit;
[0043] The sensor unit is used to obtain the environmental data and material input information in the cable processing process in real time; the environmental data includes temperature, humidity, and task volume information, and the material input information includes material input speed and material input specification value;
[0044] Equipment collection unit, used to collect output data of each process of each production line and operation data of cable production equipment; output data includes the output of semi-finished products or finished products;
[0045] Specifically, on the one hand, the equipment collection unit can collect the output of semi-finished products or finished products of each process of each production line in real time, and on the other hand, the equipment collection unit automatically collects the operation data of the cable production equipment.
[0046] The data recording unit is used to receive and store output data and operation data. The output of semi-finished products or finished products and equipment operation data are automatically uploaded and stored.
[0047] The processing decision unit is used to generate scheduling decision suggestions for the cables produced in real time on each production line by combining the real-time environmental data of the cables on each production line, material input information, and operating data of the cable production equipment through a pre-made model algorithm, and send the scheduling decision suggestions to the administrator's smart terminal.
[0048] Specifically, the processing decision unit has built-in multiple model algorithms, which can receive, store, organize and input data sent by the equipment collection unit, perform model prediction based on the real-time environmental data of the cable on each production line, material input information, and the operating data of the cable production equipment, and obtain decision suggestions for scheduling or responding to urgent delivery dates. The scheduling decision suggestions are sent to the administrator's smart terminal, which can visualize the data for the administrator to monitor and predict.
[0049] The cable production line includes different cable processing equipment, and different cable processing equipment is responsible for different processes. For example, the cable drawing device reduces the diameter of the metal wire in the cable, the cable stranding device twists multiple single wires or conductors into one strand, and there are many types of equipment such as coiling devices, co-extrusion molding equipment, cable wrapping devices, cable sheath extrusion devices, cable degassing devices, etc. By obtaining the environmental data and material input information of different equipment working during the cable processing process in the production area, the cable production situation in different processes is determined, and cable production scheduling decision recommendations are generated. For example, if the current equipment operation data can be formed and enter the next equipment according to the current material input speed, there is no need to adjust the parameters. If the batch of cable production cannot be completed at the synchronous speed, other production lines are enabled for production.
[0050] Compared with the existing technology, sensors are deployed on each production line in the production area to collect data, and real-time cable production data of each process is obtained to make intelligent decisions. Cable production scheduling decision suggestions are given for different batches of cable production, thereby improving the quality control efficiency of each process in the cable production in the production area.
[0051] The finished product detection unit is used to detect the finished product indicators of the cables produced by the production line and send the finished product indicators to the administrator's smart terminal.
[0052] Specifically, the indicators of the finished cables are tested according to the process parameters, and the finished product test indicators and the process parameter indicators can be sent together to the administrator's smart terminal.
[0053] Common cable electrical performance detectors include insulation resistance testers, conductor resistance testers, withstand voltage partial discharge devices, and bubble detection devices. Test the indicators of finished cables to see if the cable indicators meet the requirements of finished products, and send the finished product indicators to the administrator.
[0054] Data recording unit, used to package the production line, environmental data, and material input information of a single batch of cable production into production records and store them;
[0055] The processing decision unit is also used to learn the changing patterns of the production records stored within the cycle and adjust the scheduling decision suggestions according to the learning results.
[0056] The production line, production environment data, material input information, etc. of each batch of cable products are recorded, and the regularity of the data recorded within the cycle is studied. According to the learning results, historical parameter records are formed, which can be referred to in the next production.
[0057] Cable cost monitoring unit;
[0058] Cost monitoring unit, used to obtain cost data of each batch of cable shutdown maintenance, including delayed production time, component consumption, and rework and repair material quantity;
[0059] The data recording unit is also used to generate a cost threshold according to the cables in a cycle. When the cost data in the cycle is higher than the cost threshold, the cost data in the cycle is analyzed and cost control suggestions are generated.
[0060] The maintenance cost of each batch of cable production is managed. The maintenance cost includes both time cost and component replacement cost. When the actual cost is within the cost threshold, it means that the cost control is normal. If it is outside the cost threshold, it means that the cost control is insufficient. By identifying and analyzing the actual cost of each batch of cable production, abnormal situations can be judged, which is beneficial to cost control.
[0061] It also includes an image analysis unit, and the Internet of Things acquisition unit also includes a speed infrared imaging acquisition unit;
[0062] The infrared imaging acquisition unit is used to collect infrared imaging of the cable surface in real time during the cable processing to obtain the surface image, and to collect the radiographic imaging of the inside of the cable through the X-ray visual sensor to obtain the cross-sectional image;
[0063] An image analysis unit is used to identify and analyze the cross-sectional image and the surface image through an image recognition algorithm to determine whether there are cracks on the cable surface, whether the diameter width of the cable inner core reaches a preset value, and whether there are defects in the cable inner core;
[0064] The finished product early warning unit is used to send defect information to the administrator's smart terminal when any of the following defect information occurs: cracks, diameter width less than a preset value, or cable core defects.
[0065] In the continuous production process, the finished product is accompanied by dynamic changes in various parameters. Controlling each parameter within a certain range can ensure qualified or excellent products. If cracks appear on the cable sheath, it is easy to accelerate the aging of the sheath or even break. If the inner core diameter of the cable is too small or the inner core of the cable is defective, the resistance value and heat generation of a certain cable will be affected, affecting the normal signal transmission stability of the cable. Therefore, by acquiring images of the cable surface and internal cross-section, an alarm will be issued when a defect occurs in the cable.
[0066] The park security management unit includes a video monitoring unit, a video recognition unit, and a time warning unit;
[0067] Video monitoring unit, used to collect monitoring images of various monitoring points in the production area;
[0068] The video recognition unit is used to identify and analyze the surveillance images through the video recognition algorithm to determine whether there is a security incident;
[0069] The event warning unit is used to send security events to the administrator's smart terminal when there are security events.
[0070] Monitor the production area and identify incidents with potential safety hazards through video surveillance, such as illegal operations, prolonged stay in dangerous areas, entry of non-production personnel, etc., so as to conduct early warning management.
[0071] Maintenance record unit, used to record and store daily maintenance information and repair information of cable production equipment;
[0072] The equipment analysis unit is used to analyze the equipment health status based on the recorded and stored equipment daily maintenance information and repair information, and send the cable production equipment that does not meet the equipment health requirements to the administrator's smart terminal according to the preset equipment health requirements.
[0073] By recording the daily maintenance and repair data of the equipment, the health status of the equipment is judged periodically. When the equipment does not meet the equipment health requirements, the corresponding equipment will be sent to the administrator for replacement. Automatic health management of the equipment is achieved.
[0074] The above are only embodiments of the present invention, and the common knowledge such as the known specific structures and characteristics in the scheme are not described in detail here. It should be pointed out that for those skilled in the art, several deformations and improvements can be made without departing from the structure of the present invention, which should also be regarded as the protection scope of the present invention, and these will not affect the effect of the implementation of the present invention and the practicality of the patent. The scope of protection required by this application shall be based on the content of its claims, and the specific implementation methods and other records in the specification can be used to interpret the content of the claims.
Claims
1. An Internet of Things access platform system, characterized by: It includes IoT collection unit and processing decision unit; The Internet of Things acquisition unit is used to collect Internet of Things data of the sensor group deployed in the cable processing production line in real time, and the Internet of Things acquisition unit includes a sensor unit and a device acquisition unit; The sensor unit is used to obtain the environmental data and material input information in the cable processing process in real time; the environmental data includes temperature, humidity, and task volume information, and the material input information includes material input speed and material input specification value; An equipment collection unit, used to collect output data of each process of each production line and operation data of cable production equipment; the output data includes the output of semi-finished products or finished products; Also included is a data recording unit for receiving and storing output data and operation data; The processing decision unit is used to combine the real-time environmental data of cables, material input information, and operating data of cable production equipment on each production line through a preset model algorithm, generate scheduling decision suggestions for the cables produced in real time on each production line, and send the scheduling decision suggestions to the administrator's smart terminal.
2. The Internet of Things access platform system according to claim 1, characterized in that: It also includes a finished product inspection unit; The finished product detection unit is used to detect the finished product indicators of the produced finished cables according to the process parameter indicators, and send the finished product indicators and process parameter indicators to the administrator's smart terminal.
3. The Internet of Things access platform system according to claim 2, characterized in that: The data recording unit is also used to package the production line, environmental data, and material input information of a single batch of cable production into production records and store them; The processing decision unit is also used to learn the changing patterns of the production records stored within the cycle and adjust the scheduling decision suggestions based on the learning results.
4. The Internet of Things access platform system according to claim 3, characterized in that: Also included is a cable cost monitoring unit; A cost monitoring unit, used to obtain cost data of each batch of cable shutdown maintenance, the cost data including delayed production time, component consumption, and rework and repair material quantity; The data recording unit is also used to generate a cost threshold according to the cable production volume within a period. When the cost data within the period is higher than the cost threshold, the cost data within the period is analyzed and cost control suggestions are generated.
5. The Internet of Things access platform system according to claim 1, characterized in that: It also includes an image analysis unit, and the Internet of Things acquisition unit also includes a speed infrared imaging acquisition unit; The infrared imaging acquisition unit is used to acquire infrared imaging of the cable surface in real time during the cable processing to obtain a surface image, and to acquire a radiographic image of the inside of the cable through an X-ray visual sensor to obtain a cross-sectional image; An image analysis unit is used to identify and analyze the cross-sectional image and the surface image through an image recognition algorithm to determine whether there are cracks on the cable surface, whether the diameter width of the cable inner core reaches a preset value, and whether there are defects in the cable inner core; The finished product early warning unit is used to send defect information to the administrator's smart terminal when any of the following defect information occurs: cracks, diameter width less than a preset value, or cable core defects.
6. The Internet of Things access platform system according to claim 1, characterized in that: It also includes a park security management unit, which includes a video monitoring unit, a video recognition unit, and a time warning unit; Video monitoring unit, used to collect monitoring images of various monitoring points in the production area; The video recognition unit is used to identify and analyze the surveillance images through the video recognition algorithm to determine whether there is a security incident; The event warning unit is used to send security events to the administrator's smart terminal when there are security events.
7. The Internet of Things access platform system according to claim 6, characterized in that: It also includes a maintenance record unit and an equipment analysis unit; Maintenance record unit, used to record and store daily maintenance information and repair information of cable production equipment; The equipment analysis unit is used to analyze the equipment health status based on the recorded and stored equipment daily maintenance information and repair information, and send the cable production equipment that does not meet the equipment health requirements to the administrator's smart terminal according to the preset equipment health requirements.
Citation Information
Cited By
Insulating layer coating process and device for high-voltage cable
CN120527092A