Construction method for replacing middle section of blast furnace shell
By using the support structure of reinforced truss and cow legs in the blast furnace, the furnace shell is gradually cut and adjusted, and the rapid replacement of the middle section of the blast furnace is achieved, which solves the stability and safety problems during the furnace shell replacement process, improves construction efficiency and reduces cost.
Patent Information
- Application Number
- CN202411171699.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-26
- Publication Date
- 2024-11-22
AI Technical Summary
During the blast furnace iron smelting process, the furnace shell is prone to deformation or burning through due to high temperature and gas, which requires frequent replacement. In the replacement process of the prior art, it is difficult to ensure the stability and safety of the overall structure during the replacement process, and the efficiency of the segment replacement is Low, high cost.
A construction method for replacing the middle section of the blast furnace shell is adopted. By installing reinforced trusses and cow legs, the furnace shell structure is gradually cut and adjusted, the overall replacement of the middle section is realized, and the position of the upper section of the furnace shell is adjusted through the jack to ensure the welding quality and structure. stability.
It realizes rapid replacement of the furnace shell in the middle section, improves construction efficiency and safety, saves construction period and costs, and ensures the stability and safety of the overall structure.
Smart Images

Figure CN118996028A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of blast furnace repair, in particular to a construction method for replacing a middle section of a blast furnace shell. Background Art
[0002] Blast furnaces are widely used in ironmaking production. During the ironmaking process, high temperature, coal gas and material discharge may cause varying degrees of damage to the furnace shell. The furnace shell may be deformed or even burned through during long-term production, which will affect production and require the furnace to be shut down for maintenance and replacement of the blast furnace shell. Usually, the wall thickness of the blast furnace body shell is smaller than that of the furnace bottom, and the temperature is higher than that of the furnace top. Therefore, the damage to the furnace bottom is more serious than that of the furnace top. Considering the use and cost, it is more practical to only replace the middle section of the furnace shell. The blast furnace itself is a self-supporting cylindrical structure, which is not affected by the blast furnace frame structure. Therefore, only the middle section of the furnace shell needs to be cut and removed, and the upper furnace shell structure needs to be reinforced to ensure the safety and stability of the entire structure. To this end, a construction method for replacing the middle section of the blast furnace shell is proposed. Summary of the invention
[0003] The present invention aims to solve the above-mentioned problem, thereby providing a construction method for replacing the middle section of a blast furnace shell.
[0004] The present invention solves the above-mentioned problem by adopting the following technical solution: A construction method for replacing the middle section of a blast furnace shell is carried out according to the following steps: Step 1: Install the reinforcement truss; there are multiple reinforcement trusses, which are arranged on the outer periphery of the furnace shell, one end of which is welded and fixed to the main frame column, and the other end is close to the outer wall of the furnace shell and is not connected yet; Step 2: Weld brackets at the upper and lower bands of the seam to be cut between the middle section furnace shell that needs to be replaced and the upper section furnace shell that does not need to be replaced, set up jacks between the two brackets that are opposite to each other, and evenly set the brackets around the furnace shell; Step 3: Cut the middle furnace shell that needs to be replaced and the upper furnace shell that does not need to be replaced. After cutting, use a jack to adjust the upper furnace shell that does not need to be replaced to make it higher than the designed elevation. Step 4: Weld the upper furnace shell that is not replaced to the end of the reinforcement truss, and make the weld seam fully welded; Step 5: Cut the middle section of the furnace shell that needs to be replaced, and replace and install it as a whole; the middle section of the furnace shell is divided into multiple annular belts, which are installed and welded upward one by one; Step 6: After the installation of the last furnace shell of the middle section is completed, the bracket is installed on the newly installed middle section furnace shell. The newly installed bracket is opposite to the bracket on the upper section furnace shell that has not been replaced, and a jack is set between the two opposite brackets. The top surface of the jack is pressed tightly against the bracket on the upper section furnace shell; Step 7: Disconnect the connection node between the reinforcement truss and the upper furnace shell, adjust the upper furnace shell by jack, lower it to the design elevation, and the horizontality must meet the specification requirements, finally weld the upper furnace shell to the newly replaced middle furnace shell to complete the replacement of the middle furnace shell.
[0005] Compared with the prior art, the present invention adopting the above technical solution has the following outstanding features: The method of the present invention can realize the replacement of only the middle section of the furnace shell without affecting the structural performance of the upper and lower parts of the furnace shell; the stability and safety of the overall structure during the furnace shell replacement process are guaranteed. Compared with the original piecewise replacement of the furnace shell, the middle section of the furnace shell can be replaced as a whole, and the construction speed is faster. Overall, the construction efficiency is improved, the construction period is saved, and the construction cost is saved.
[0006] Preferably, a further technical solution of the present invention is: The reinforcement truss comprises a horizontal support rod, an inclined support rod and a reinforcing rod, wherein the inclined support rod is located above the horizontal support rod, and the reinforcing rod is vertically placed between the horizontal support rod and the inclined support rod, and the reinforcement truss is in a triangular shape as a whole; the triangular support structure is more stable.
[0007] The bracket includes a horizontal plate and a rib plate located above the horizontal plate. The rib plate is vertically fixed to the horizontal plate, and the side of the rib plate close to the furnace shell is a beveled side, and the inclination angle is adapted to the inclination angle of the outer wall of the furnace shell; ensuring that the upper and lower supporting surfaces of the jack are horizontal and parallel. BRIEF DESCRIPTION OF THE DRAWINGS
[0008] Figure 1 A schematic diagram of the construction state structure of an embodiment of the present invention; Figure 2 It is a schematic diagram of the top view of the structure of the reinforcement truss according to an embodiment of the present invention; Figure 3 This is a schematic diagram of the bracket arrangement structure of an embodiment of the present invention; Figure 4 It is a schematic diagram of the matching structure of the bracket and the jack according to an embodiment of the present invention; Marked in the figure are: reinforcement truss 1, main frame column 2, furnace shell 3, corbel 4, jack 5, cutting seam 6, horizontal support rod 11, inclined support rod 12, reinforcing rod 13, upper furnace shell 31, middle furnace shell 32. DETAILED DESCRIPTION
[0009] The present invention will be further described below in conjunction with embodiments, the purpose of which is only to provide a better understanding of the content of the present invention. Therefore, the examples given do not limit the protection scope of the present invention.
[0010] See also Figure 1-Figure 4 A construction method for replacing the middle section of a blast furnace shell is characterized by following the steps: Step 1: Install the reinforcement truss 1; there are multiple reinforcement trusses 1, which are arranged on the outer periphery of the furnace shell 3, one end of which is welded and fixed to the main frame column 2, and the other end is close to the outer wall of the furnace shell 3, and is not connected yet; Step 2: Weld the brackets 4 at the upper and lower bands of the to-be-cut seam 6 of the middle furnace shell 32 to be replaced and the upper furnace shell 31 to be replaced, and set up the jacks 5 between the two brackets 4 in the upper and lower positions, and the brackets 4 are evenly arranged around the furnace shell 3; Step 3: Cut the middle furnace shell 32 that needs to be replaced and the upper furnace shell 31 whose top is not replaced. After cutting, adjust the upper furnace shell 31 whose top is not replaced by the jack 5 to make it higher than the designed elevation. Step 4: Weld the upper furnace shell 31 that does not need to be replaced to the end of the reinforcement truss 1, and fully weld the weld; Step 5: Cut the middle section furnace shell 32 that needs to be replaced, and replace and install it as a whole; the middle section furnace shell 32 is divided into multiple annular bands, which are installed and welded upward one by one; Step 6: After the last band of the middle furnace shell 32 is installed, the bracket 4 is installed on the newly installed middle furnace shell 32. The newly installed bracket 4 is opposite to the bracket 4 on the upper furnace shell 31 whose top is not replaced, and a jack 5 is set between the two opposite brackets 4. The top surface of the jack 5 is pressed tightly against the bracket 4 on the upper furnace shell; Step 7: Disconnect the connection node between the reinforcement truss 1 and the upper furnace shell 31, adjust the upper furnace shell 31 through the jack 5, lower the upper furnace shell 31 to the designed elevation, and the horizontality must meet the specification requirements, and finally weld the upper furnace shell 31 to the newly replaced middle furnace shell 32 to complete the replacement of the middle furnace shell 32.
[0011] The reinforcement truss 1 comprises a horizontal support rod 11, an inclined support rod 12 and a reinforcing rod 13. The inclined support rod 12 is located above the horizontal support rod 11, and the reinforcing rod 13 is vertically placed between the horizontal support rod 11 and the inclined support rod 12. The reinforcement truss 1 is triangular in shape as a whole; the triangular support structure is more stable.
[0012] The bracket 4 includes a horizontal plate and a rib plate located above the horizontal plate. The rib plate is vertically fixed to the horizontal plate, and the side of the rib plate close to the furnace shell 3 is a beveled side, and the inclination angle is adapted to the inclination angle of the outer wall of the furnace shell 3; ensuring that the upper and lower supporting surfaces of the jack are horizontal and parallel.
[0013] The reinforcement truss 1 must meet the overall load requirements of the upper furnace shell 31. The impact of the removal and installation of the internal cooling wall or throat steel brick structure on the load change is considered according to the maximum load. The reinforcement truss 1 can be set to a single layer or multiple layers according to the actual load size.
[0014] The welding nodes between the reinforcement truss 1 and the main frame column 2 and the furnace shell 3 must be fully welded and meet the weld strength requirements.
[0015] The load borne by the support of the frame platform may not be considered when performing strength verification of the reinforcement truss 1, and it is fixed to the main beam structure of the platform during installation.
[0016] Taking into account the elastic deformation of the steel structure, the upper furnace shell 31 should be slightly higher than the design elevation when it is adjusted for the first time, and the influence of its possible sinking on the installation of the middle furnace shell of the blast furnace must be considered.
[0017] During the construction process, it is necessary to strengthen the inspection of the upper furnace shell 31 elevation and the blast furnace frame structure. When serious deformation occurs, which affects the construction and structural safety, the construction must be stopped immediately and further reinforcement measures must be taken.
[0018] The method of the present invention can realize the replacement of only the middle section of the furnace shell without affecting the structural performance of the upper and lower parts of the furnace shell; the stability and safety of the overall structure during the furnace shell replacement process are guaranteed. Compared with the original piecewise replacement of the furnace shell, the middle section of the furnace shell can be replaced as a whole, and the construction speed is faster. Overall, the construction efficiency is improved, the construction period is saved, and the construction cost is saved.
[0019] The above description is only a preferred feasible embodiment of the present invention, and does not limit the scope of rights of the present invention. All equivalent changes made using the contents of the present specification and its drawings are included in the scope of rights of the present invention.
Claims
1. A construction method for replacing the middle section of a blast furnace shell, It is characterized in that Follow these steps: Step 1: installing the reinforcement trusses (1); a plurality of reinforcement trusses (1) are provided, which are arranged respectively on the outer periphery of the furnace shell (3), one end of which is welded and fixed to the main frame column (2), and the other end of which is close to the outer wall of the furnace shell (3) and is not connected yet; Step 2: Welding brackets (4) at the upper and lower bands of the seam between the middle section furnace shell that needs to be replaced and the upper section furnace shell that does not need to be replaced, and setting a jack (5) between the two brackets (4) at upper and lower positions facing each other, and the brackets (4) are evenly arranged around the furnace shell (3); Step 3: Cut the middle furnace shell that needs to be replaced and the upper furnace shell that does not need to be replaced. After cutting, adjust the upper furnace shell that does not need to be replaced by using a jack (5) to make it higher than the designed elevation. Step 4: Weld the upper furnace shell that is not replaced to the end of the reinforcement truss (1) to ensure that the weld is fully welded; Step 5: Cut the middle section of the furnace shell that needs to be replaced, and replace and install it as a whole; the middle section of the furnace shell is divided into multiple annular belts, which are installed and welded upward one by one; Step 6: After the installation of the last furnace shell (3) of the middle furnace shell is completed, a bracket (4) is installed on the newly installed middle furnace shell. The newly installed bracket (4) is opposite to the bracket (4) on the upper furnace shell that has not been replaced, and a jack (5) is set between the two opposite brackets (4). The top surface of the jack (5) is pressed tightly against the bracket (4) on the upper furnace shell. Step 7: Disconnect the connection node between the reinforcement truss (1) and the upper furnace shell, adjust the upper furnace shell by the jack (5), lower the upper furnace shell to the design elevation, and the horizontality must meet the requirements of the specification, and finally weld the upper furnace shell to the newly replaced middle furnace shell to complete the replacement of the middle furnace shell.
2. A construction method for replacing the middle section of a blast furnace shell according to claim 1, Features: The reinforcement truss (1) comprises a horizontal support rod, an inclined support rod and a reinforcing rod, wherein the inclined support rod is located above the horizontal support rod, and the reinforcing rod is vertically arranged between the horizontal support rod and the inclined support rod, and the reinforcement truss (1) is in a triangular shape as a whole.
3. A construction method for replacing the middle section of a blast furnace shell according to claim 1, Features: The corbel (4) comprises a horizontal plate and a rib plate located above the horizontal plate, the rib plate is vertically fixed to the horizontal plate, and the side of the rib plate close to the furnace shell is a beveled side, and the inclination angle is adapted to the inclination angle of the outer wall of the furnace shell.