Dam body adopting aeolian sand for damming and construction method
By using clay soil shell and geogrid structure in the dam construction of the dam, the strength and stiffness of the dam are improved, the construction difficulties and quality problems of the dam are solved, and the efficient construction of solid waste landfills is achieved. .
Patent Information
- Application Number
- CN202411340397.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-24
- Publication Date
- 2024-11-22
- Estimated Expiration
- 2044-09-24
AI Technical Summary
The mechanical properties of wind-stacked sand are poor and the shear resistance is insufficient, which leads to difficulty in construction during the dam construction process, inability to pass through machinery, and the dam body is prone to loosening and collapse, making it difficult to ensure the quality of the dam construction.
The structure of a clay shell combined with a three-way geogrid and a two-way geogrid is adopted. Through the design of a multi-layer sub-shell and top guard, the moisture content and crush strength of the wind-abundant sand are ensured, and the overall strength and rigidity of the dam body are improved. , ensure the smooth progress of construction.
Effectively solve the problems of construction difficulties and difficult to ensure quality of the wind-accumulated sand dam body, save the construction cost of solid waste landfills, and reduce the demand for clay soil and mineral resources, providing a new landfill for the central and western regions. Construction plan.
Smart Images

Figure CN118997068A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of dam construction, and in particular to a dam body constructed using aeolian sand and a construction method. Background Art
[0002] my country's central and western regions are rich in aeolian sand resources. As a major industrial and energy production region in northern my country, this region generates large quantities of solid waste during production, necessitating the construction of numerous landfills to dispose of this waste. Because the region lacks clayey soil reserves but possesses abundant aeolian sand reserves, using aeolian sand as the primary damming material for landfill construction is the optimal solution.
[0003] However, the mechanical properties of aeolian sand are poor. In its natural state, aeolian sand is loose, its cohesion is close to 0kPa, and its shear resistance is poor. When conventional vibration rolling is used to compact aeolian sand, excessive vibration intensity will cause shear damage to the aeolian sand. If the vibration intensity is too low, the relative density required for the dam body cannot be achieved, and engineering vehicles cannot pass smoothly on the aeolian sand dam body. Therefore, the use of aeolian sand to build dams is difficult and the quality is difficult to guarantee. Summary of the Invention
[0004] In view of the shortcomings of the existing technology, the present invention proposes a dam body and a construction method for building a dam using aeolian sand, which makes it feasible to build a dam using aeolian sand and can ensure the quality of the dam.
[0005] The dam body constructed with aeolian sand according to the present invention comprises: a clay shell with a trapezoidal cross-section of the outer contour and aeolian sand filled in the clay shell, the clay shell comprising a plurality of sub-shells with top openings arranged in sequence from bottom to top and a top protective shell for sealing the top opening of the sub-shell located at the top, the cross-section of the inner contour of each layer of sub-shell being an inverted trapezoid, wherein the sub-shells and the top protective shells are both constructed of clay or modified materials with equivalent cohesion and permeability coefficient, the interior of each sub-shell is paved with a plurality of layers of three-dimensional geogrids arranged in parallel along its height direction, each layer of three-dimensional geogrid is paved along the entire length direction and the width direction of the sub-shell, at least one layer of bidirectional geogrid is further provided between adjacent layers of three-dimensional geogrids, the bidirectional geogrid being paved along the entire length direction and the entire width direction of the cross-section of the sub-shell.
[0006] Furthermore, the spacing between each layer of the three-dimensional geogrid and the adjacent layer of the two-dimensional geogrid is equal.
[0007] Furthermore, the moisture content of the aeolian sand filled inside each layer of the sub-shell is 9%-10%, and under this moisture content condition, the preset relative density of the aeolian sand is achieved through rolling to ensure the overall strength of the aeolian sand after rolling.
[0008] Furthermore, at least one layer of bidirectional geogrid is laid in the top protective shell, and the bidirectional geogrid is laid along the entire length direction of the top protective shell and the entire width direction of the cross section of the top protective shell.
[0009] Furthermore, at least one layer of three-dimensional geogrid is laid in the top protective shell, and the three-dimensional geogrid is laid along the entire length direction of the top protective shell and the entire width direction of the cross section of the top protective shell.
[0010] The construction method for building a dam using aeolian sand according to the present invention is used to construct the dam body using aeolian sand, comprising the following steps: Step 1: clearing the dam foundation, removing loose aeolian sand on the surface, and digging down to the dam foundation bearing layer;
[0011] Step 2: Use clay or modified materials with equivalent cohesion and permeability to build the first sub-shell on the dam foundation bearing layer, and lay multiple layers of three-dimensional geogrids in parallel in the height direction within the first sub-shell, as well as at least one layer of two-way geogrid between adjacent layers of three-dimensional geogrids;
[0012] Step 3: Filling the first sub-shell with aeolian sand of a preset thickness, leveling the sand while filling, and dividing the sand into grids of equal size while leveling, with ridges formed between adjacent grids;
[0013] Step 4: Water each grid and let it stand until the moisture content of the aeolian sand reaches 9%-10%, then compact the aeolian sand.
[0014] Step 5: Test the compaction results of step 4 to obtain the relative density of the current layer of aeolian sand after compaction. If the relative density meets the design requirements, start the construction of the next layer of sub-shell. If not, continue to increase the number of compaction passes.
[0015] Step 6: Continue to build the Nth (N≥2)th layer of sub-shell upwards on top of the first layer of sub-shell until the clay shell reaches the preset elevation. The construction method of the Nth (N≥2)th layer of sub-shell is the same as the construction method of the first layer of sub-shell in steps 2 to 5.
[0016] Step 7: On the compacted aeolian sand in the uppermost sub-shell, a top protective shell is constructed using clay or a modified material with equivalent cohesion and permeability.
[0017] Furthermore, in step 2, each layer of bidirectional geogrid is laid along the entire length direction of the sub-shell and the entire width direction of the cross section of the sub-shell, and each layer of tridirectional geogrid is laid along the entire length direction of the sub-shell and the entire width direction of the sub-shell.
[0018] Furthermore, in step three, the size of the grid is 5.0m×8.0m, and the ridge height is greater than the virtual paving thickness.
[0019] Furthermore, in step 4, a road roller is used to compact the aeolian sand, and the compaction direction is from the outside to the inside of the clay shell in the length direction of the clay shell; the number of compaction times is determined according to the loose thickness of the aeolian sand.
[0020] Furthermore, in step seven, at least one layer of bidirectional geogrid is laid in the top protective shell, and the bidirectional geogrid is laid along the entire length direction of the top protective shell and the entire width direction of the cross section of the top protective shell.
[0021] The dam body and construction method using aeolian sand for dam construction of the present invention solve the problem that aeolian sand cannot be used as a building material for earth-rock dam construction due to its poor mechanical properties. By combining the clay soil shell with the use of three-way geogrid and two-way geogrid, the unfavorable factors such as construction difficulties, impediment of machinery passage, and easy loosening and collapse of the dam body during the construction of the aeolian sand dam body are solved. The invention adopts local conditions and uses local materials, greatly saving the construction cost of solid waste landfills, while saving mineral resources such as clay soil, sand and gravel, and providing a new solution for the construction of solid waste landfills in central and western my country. BRIEF DESCRIPTION OF THE DRAWINGS
[0022] Figure 1 A schematic structural diagram of a dam body constructed using aeolian sand according to an embodiment of the present invention;
[0023] Figure 2 is a schematic diagram of the grid structure;
[0024] Figure 3 This is a curve showing the relationship between the relative density of aeolian sand and the number of compaction times at the optimal moisture content. DETAILED DESCRIPTION
[0025] In order to better understand the purpose, structure and function of the present invention, the present invention is further described in detail below with reference to the accompanying drawings.
[0026] Figure 1 FIG. 1 shows the structure of a dam body 100 constructed using aeolian sand according to an embodiment of the present invention. Figure 1As shown, the dam body 100 using aeolian sand to build the dam may include: a clay shell 1 with a trapezoidal cross-section of the outer contour and aeolian sand 2 filled in the clay shell 1. The clay shell 1 may include multiple layers of sub-shells 11 with top openings arranged in sequence from bottom to top and a top protective shell 12 for closing the top opening of the sub-shell 11 located at the top. The cross-section of the inner contour of each layer of sub-shell 11 is inverted trapezoidal. The sub-shells 11 and the top protective shell 12 are both constructed of clay or modified materials with equivalent cohesion and permeability coefficient. The interior of each sub-shell 11 is paved with multiple layers of three-dimensional geogrids 3 ( Figure 1 Each layer of three-dimensional geogrid 3 is along the entire length direction of the sub-shell 11 (ie, the direction perpendicular to the inside and outside of the paper) and the width direction of the sub-shell 11 (ie, the direction perpendicular to the inside and outside of the paper). Figure 1 At least one layer of bidirectional geogrid 4 is provided between adjacent layers of three-way geogrid 3 ( Figure 1 The bidirectional geogrid 4 is arranged along the entire length direction of the sub-shell 11 (ie, perpendicular to the inside and outside of the paper) and the entire width direction of the cross section of the sub-shell (ie, perpendicular to the inside and outside of the paper). Figure 1 length from left to right as shown).
[0027] The dam body 100 using aeolian sand for damming according to the embodiment of the present invention is composed of a plurality of sub-shells 11 by providing a clay shell 1, and the cross section of the outer contour of the clay shell 1 is trapezoidal, and the cross section of the inner contour of each layer of the sub-shell 11 is inverted trapezoidal, so that the structure of the clay shell 1 itself is more stable; by laying a three-dimensional geogrid 3 in the sub-shell 11, the overall performance of the sub-shell 11 structure can be further improved, and the sub-shell 11 can be prevented from loosening and collapsing during water injection and rolling during the subsequent filling of aeolian sand; and in the entire length direction of the sub-shell 11 and the entire width direction of the cross section of the sub-shell 11 (i.e. Figure 1 The bidirectional geogrid 4 laid along the length from left to right as shown in the figure can form a pulling effect on the dam body, which can effectively prevent the displacement of the sub-shell 11 when the aeolian sand is rolled during the subsequent filling process of aeolian sand, thereby further improving the structural strength of the sub-shell 11. In the embodiment of the present invention, the sub-shells 11 of each layer of the dam body 100 using aeolian sand for dam construction are added with bidirectional geogrids 4 and three-dimensional geogrids 3 on the basis of clay or modified materials with equivalent cohesion and permeability coefficient, which greatly improves the strength and rigidity of the dam body and ensures the passage of vehicles when construction is carried out on the sub-shell 11. Such a setting makes full use of aeolian sand, making it feasible to use aeolian sand for dam construction in areas where clay reserves are scarce but aeolian sand reserves are abundant, and can ensure the quality of dam construction, thereby providing a better solution for the construction of solid waste landfills in the region.
[0028] In such Figure 1In the preferred embodiment shown, in order to further improve the structural strength of the sub-shell 11, the spacing between each layer of triaxial geogrid 3 and the adjacent layer of biaxial geogrid 4 can be made equal, preferably 1 m.
[0029] According to the present invention, the moisture content of the aeolian sand 2 filled in each layer of the sub-shell 11 is 9%-10%, and under this moisture content condition, the preset relative density of the aeolian sand is achieved through rolling to ensure the overall strength of the aeolian sand 2 after rolling.
[0030] In a preferred embodiment, at least one layer of bidirectional geogrid 4 may be laid within the top retaining shell 12. The bidirectional geogrid 4 may be laid along the entire length of the top retaining shell 12 and the entire width of the top retaining shell's cross section. This arrangement creates a tensioning effect on the top retaining shell 12, effectively preventing displacement of the top retaining shell 12 when driven over by a vehicle, thereby helping to improve the structural strength of the top retaining shell 12.
[0031] Preferably, at least one layer of triaxial geogrid 3 may be laid within the top retaining shell 12. The triaxial geogrid 3 may be laid along the entire length of the top retaining shell 12 and across the entire width of the cross-section of the top retaining shell 12. This configuration significantly improves the strength and rigidity of the top retaining shell 12 by adding the biaxial geogrid 4 and triaxial geogrid 3 to the top retaining shell 12, while maintaining cohesive soil or a modified material with equivalent cohesion and permeability. This further ensures the passage of vehicles on the top retaining shell 12 during construction.
[0032] Table 1 below shows the technical specifications of the three-dimensional geogrid 3 used in the present invention:
[0033] Table 1
[0034]
[0035] Furthermore, the construction method for building a dam using aeolian sand according to an embodiment of the present invention is used to construct the dam body 100 using aeolian sand, and may include the following steps:
[0036] Step 1: Clear the dam foundation, remove loose wind-blown sand on the surface, and dig down to the dam foundation bearing layer;
[0037] Step 2: If Figure 1 As shown, a first layer of sub-shell 11 is constructed on the dam foundation bearing layer using clay or modified materials with equivalent cohesion and permeability coefficient, and multiple layers of three-dimensional geogrids 3 and at least one layer of two-way geogrid 4 located between adjacent layers of three-dimensional geogrids 3 are laid parallel in the height direction within the first layer of sub-shell 11;
[0038] Step 3: Fill the first layer of sub-shell 11 with a preset thickness of wind-blown sand 2 (the thickness of the wind-blown sand is usually controlled at 30cm to 50cm), and level the wind-blown sand 2 by filling and leveling. Figure 2 As shown, the aeolian sand 2 is divided into grids while being leveled to obtain a plurality of grids 21 of equal size, and ridges 22 are formed between adjacent grids 21;
[0039] Step 4: watering each grid 21 and allowing the aeolian sand to stand until the moisture content is 9%-10%, and then rolling the aeolian sand;
[0040] Step 5: Testing the compaction results of step 4 to obtain the relative density of the current layer of aeolian sand after compaction. If the relative density meets the design requirements, construction of the next layer of sub-shell 11 is started. If it does not meet the requirements, the number of compaction passes is increased.
[0041] Step 6: Continue to build the Nth (N≥2)th layer of sub-shell 11 upwards on the first layer of sub-shell 11 until the clay shell 1 reaches the preset elevation. The construction method of the Nth (N≥2)th layer of sub-shell 11 is the same as the construction method of the first layer of sub-shell 11 in steps 2 to 5.
[0042] Step 7: On the compacted aeolian sand 2 in the uppermost sub-shell 11 , a top protective shell 12 is constructed using clay or a modified material with equivalent cohesion and permeability.
[0043] The construction method of using aeolian sand to build a dam in an embodiment of the present invention solves the problem that aeolian sand cannot be used as a building material for earth-rock dam construction due to its poor mechanical properties through the above steps. By combining the clay shell 1 with the three-way geogrid 3 and the two-way geogrid 4, the unfavorable factors such as construction difficulties, inability of machinery to pass, and easy loosening and collapse of the dam body during the construction of the aeolian sand dam body are solved. It is adapted to local conditions and uses local materials, which greatly saves the construction cost of solid waste landfills. At the same time, it saves mineral resources such as clay, sand and gravel, and provides a new solution for the construction of solid waste landfills in central and western my country.
[0044] In a preferred embodiment, the upper surface of the top protective shell 12 is flush with the top surface of the uppermost sub-shell 11, so that the clay shell 1 as a whole meets the preset elevation while having stronger structural stability.
[0045] According to the present invention, in step 2, each layer of bidirectional geogrid 4 can be laid along the entire length direction of the sub-shell 11 and the entire width direction of the cross section of the sub-shell 11, and each layer of tridirectional geogrid 3 can be laid along the entire length direction of the sub-shell 11 and the entire width direction of the cross section of the sub-shell 11.
[0046] Furthermore, in step three, the dimensions of the grid 21 can be 5.0m x 8.0m, with the ridge height 22 greater than the void thickness. By compartmentalizing the aeolian sand, it is easier to subsequently water the grids 21 to ensure the optimal moisture content of the aeolian sand within each grid 21, thereby ensuring the optimal moisture content of each layer of aeolian sand as a whole. When the void thickness is 30cm, the ridge height 22 is greater than 30cm.
[0047] Furthermore, in step 4, a roller can be used to compact the aeolian sand. The compaction direction is from the outside to the inside of the clay shell 1 along the length direction of the clay shell 1. The number of compaction times can be determined according to the thickness of the aeolian sand. In this step, a 16t single-smooth-wheel vibrating roller can be used to compact the aeolian sand (static pressure). Figure 1 As shown, the 16t single-smooth-wheel vibratory roller can run from the leftmost starting point in the sub-housing 11 in the direction of the paper inward to the direction of the paper outward, and then circle back to the distance of 1 / 2 wheel rail from the starting point (to achieve more comprehensive rolling of aeolian sand) and run from the direction of the paper inward to the direction of the paper outward, until it circles back to the center area of the sub-housing 11, the roller circles back to the rightmost starting point in the sub-housing 11 again and runs from the direction of the paper inward to the direction of the paper outward, and then circle back to the distance of 1 / 2 wheel rail from the starting point and run from the direction of the paper inward to the direction of the paper outward, until it circles back to the center area of the sub-housing 11, thereby completing one round of rolling of aeolian sand. By repeating the above steps, multiple rounds of rolling of aeolian sand can be achieved.
[0048] Preferably, in this step, the number of rolling passes can be determined according to the virtual paving thickness, such as Figure 3 From the relationship curve between the relative density of aeolian sand and the number of rolling times under the optimal moisture content shown, it can be seen that the number of rolling times is preferably 4-6 times.
[0049] Furthermore, in step seven, at least one layer of bidirectional geogrid 4 may be laid within the top protective shell 12. The bidirectional geogrid 4 may be laid along the entire length of the top protective shell 12 and the entire width of the cross-section of the top protective shell 12. This arrangement creates a tensioning effect on the top protective shell 12, effectively preventing displacement of the top protective shell 12 when a vehicle runs over it, thereby helping to improve the structural strength of the top protective shell 12.
[0050] Preferably, at least one layer of triaxial geogrid 3 may be laid within the top retaining shell 12. The triaxial geogrid 3 may be laid along the entire length of the top retaining shell 12 and across the entire width of the cross-section of the top retaining shell 12. This configuration significantly improves the strength and rigidity of the top retaining shell 12 by adding the biaxial geogrid 4 and triaxial geogrid 3 to the top retaining shell 12, while maintaining cohesive soil or a modified material with equivalent cohesion and permeability. This further ensures the passage of vehicles on the top retaining shell 12 during construction.
[0051] Finally, it should be noted that the above embodiments are only used to illustrate the technical solutions of the present invention, rather than to limit them. Although the present invention has been described in detail with reference to the aforementioned embodiments, those skilled in the art should understand that they can still modify the technical solutions described in the aforementioned embodiments, or make equivalent replacements for some or all of the technical features therein. These modifications or replacements do not deviate the essence of the corresponding technical solutions from the scope of the technical solutions of the embodiments of the present invention, and they should all be included in the scope of the claims and description of the present invention. In particular, as long as there is no structural conflict, the various technical features mentioned in the various embodiments can be combined in any way. The present invention is not limited to the specific embodiments disclosed herein, but includes all technical solutions that fall within the scope of the claims.
Claims
1. A dam body built with aeolian sand. It is characterized in that include: A clay shell with a trapezoidal cross-section of the outer contour and aeolian sand filled in the clay shell, the clay shell comprising a plurality of sub-shells with top openings arranged in sequence from bottom to top and a top protective shell for closing the top opening of the sub-shell located at the top, the cross-section of the inner contour of each layer of the sub-shell is an inverted trapezoid, wherein the sub-shells and the top protective shells are constructed of clay or modified materials with equivalent cohesion and permeability coefficient, the interior of each sub-shell is paved with a plurality of three-dimensional geogrids arranged in parallel along its height direction, each layer of the three-dimensional geogrid is laid along the entire length direction of the sub-shell and the width direction of the sub-shell, at least one layer of bidirectional geogrid is further arranged between adjacent layers of the three-dimensional geogrids, the bidirectional geogrid is laid along the entire length direction of the sub-shell and the entire width direction of the cross-section of the sub-shell.
2. The dam body constructed by using aeolian sand according to claim 1, It is characterized in that The spacing between each layer of the three-dimensional geogrid and the adjacent layer of the two-dimensional geogrid is equal.
3. The dam body constructed by using aeolian sand according to claim 1 or 2, It is characterized in that The moisture content of the aeolian sand filled inside each layer of the sub-shell is 9%-10%, and under the moisture content condition, the preset relative density of the aeolian sand is achieved through rolling to ensure the overall strength of the aeolian sand after rolling.
4. The dam body constructed by using aeolian sand according to claim 1 or 2, It is characterized in that At least one layer of bidirectional geogrid is laid in the top protective shell, and the bidirectional geogrid is laid along the entire length direction of the top protective shell and the entire width direction of the cross section of the top protective shell.
5. The dam body constructed by using aeolian sand according to claim 4, It is characterized in that At least one layer of three-dimensional geogrid is also laid in the top protective shell. The three-dimensional geogrid is laid along the entire length direction of the top protective shell and the entire width direction of the cross section of the top protective shell.
6. A construction method for building a dam using aeolian sand, used for constructing a dam body using aeolian sand according to any one of claims 1 to 5, It is characterized in that The following steps are involved: Step 1: Clear the dam foundation, remove the loose wind-blown sand on the surface, and dig down to the bearing layer of the dam foundation; Step 2: Using clay or modified materials with equivalent cohesion and permeability coefficient to construct the first layer of the sub-shell on the dam foundation bearing layer, and laying multiple layers of three-dimensional geogrids and at least one layer of two-way geogrids between adjacent layers of the three-dimensional geogrids in parallel in the height direction inside the first layer of the sub-shell; Step 3: Filling the first layer of the sub-shell with a preset virtual thickness of aeolian sand, leveling the virtual aeolian sand by filling and leveling, and dividing the aeolian sand into grids to obtain a plurality of grids of equal size, and forming ridges between adjacent grids; Step 4: watering each of the grids, and leaving the grids to stand until the water content of the aeolian sand reaches 9%-10%, and then rolling the aeolian sand; Step 5: Testing the rolling result of step 4 to obtain the relative density of the current layer of aeolian sand after rolling. If the relative density meets the design requirements, the construction of the next layer of the sub-shell is started. If it does not meet the requirements, the number of rolling times is continued to increase; Step 6: Continue to build the Nth (N≥2)th layer of sub-shells upwards on the first layer of sub-shells until the clay shell reaches a preset elevation, wherein the construction method of the Nth (N≥2)th layer of sub-shells is the same as the construction method of the first layer of sub-shells described in steps 2 to 5; Step 7: On the compacted aeolian sand in the uppermost sub-shell, the top protective shell is constructed using clay or a modified material having equivalent cohesion and permeability coefficient.
7. The construction method of using aeolian sand to build a dam according to claim 6, It is characterized in that In step 2, each layer of the bidirectional geogrid is laid along the entire length direction of the sub-shell and the entire width direction of the cross section of the sub-shell, and each layer of the tridirectional geogrid is laid along the entire length direction of the sub-shell and the width direction of the sub-shell.
8. The construction method of using aeolian sand to build a dam according to claim 6 or 7, It is characterized in that In step three, the size of the grid is 5.0m×8.0m, and the ridge height is greater than the virtual paving thickness.
9. The construction method of using aeolian sand to build a dam according to claim 6 or 7, It is characterized in that In the step 4, the aeolian sand is rolled by a road roller, and the rolling direction is to roll the clay shell from the outside to the inside in the length direction of the clay shell; the number of rolling times is determined according to the virtual thickness of the aeolian sand.
10. The construction method of using aeolian sand to build a dam according to claim 6 or 7, It is characterized in that In the step seven, at least one layer of bidirectional geogrid is laid in the top protective shell, and the bidirectional geogrid is laid along the entire length direction of the top protective shell and the entire width direction of the cross section of the top protective shell.
Citation Information
Patent Citations
Earthquake-resistant measures and construction methods for high earth-rock dams
CN102261053A
Sediment storage dam covered with geogrid reinforced cement modified soil and construction method of sediment storage dam
CN106917388A
Earth dam filling construction method
CN111851428A
Large sediment storage dam structure suitable for dispersive civil engineering dam
CN119021188A
Novel pumped storage upper reservoir dam body anti-seepage structure
CN218712655U