In-service fan electric quantity evaluation and correction method and system based on incoming flow wind speed correction

By correcting the CFD simulated wind speed and combining with the fan SCADA data, the power generation evaluation deviation caused by the complex terrain of the wind farm is solved, and the evaluation accuracy is improved. It is suitable for post-wind farm evaluation and technical transformation projects.

CN119005047APending Publication Date: 2024-11-22CENT SOUTHERN CHINA ELECTRIC POWER DESIGN INST CHINA POWER ENG CONSULTING GROUP CORP
View PDF 0 Cites 6 Cited by

Patent Information

Application Number
CN202411029736.1
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-07-30
Publication Date
2024-11-22

AI Technical Summary

Technical Problem

The deviation in power generation evaluation caused by complex terrain in service wind farms has failed to make full use of the wind measurement data and operation data of existing units, resulting in inaccurate evaluation results. It is difficult for conventional CFD algorithms to truly simulate flow field distribution. Numerical simulation calculations are expensive and difficult to apply.

Method used

By obtaining the wind parameter data at the wind measurement tower, simulated the wind parameter data at the computer location, obtain the fan output characteristic curve, correct the simulated wind speed, calculate the overall correction coefficient, correct the simulated wind parameter data, obtain the theoretical annual power generation, and cooperate with the actual operation. Comparison of annual power generation, the software calculation comprehensive correction coefficient was obtained, which was used for wind farm power evaluation and reduce CFD simulation error.

Benefits of technology

It improves the accuracy of wind farm power evaluation, makes up for the insufficient representativeness of the wind measuring tower and the CFD simulation error, and realizes refined resource evaluation, which is suitable for post-evaluation and technical transformation projects of "large instead of small".

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119005047A_ABST
    Figure CN119005047A_ABST
Patent Text Reader

Abstract

The invention discloses an in-service fan electric quantity evaluation and correction method and system based on incoming flow wind speed correction, and relates to the technical field of wind power plant post-evaluation and technical improvement. The method comprises the following steps: processing and obtaining simulated wind parameter data at a machine site through wind power plant evaluation software; the actual output power is projected to the output characteristic curve of the corresponding type to obtain the overall correction coefficient of the fan, and the simulated wind parameter data is corrected; and obtaining corrected simulation wind parameter data at each machine location point, obtaining theoretical annual energy production of the wind power plant through software calculation, comparing the theoretical annual energy production with actual operation annual energy production, and obtaining a software calculation comprehensive correction coefficient as a reduction coefficient for electric quantity analysis of the wind power plant. According to the method, the defects that the representativeness of the anemometer tower is insufficient under the complex terrain of the wind field and errors exist in CFD simulation are overcome, refined assessment of resources in the field is achieved by combining fan SCADA data, and the method can be used for guiding projects such as post-assessment of the wind field and technical improvement of replacing small with large.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of post-evaluation and technical transformation of wind farms, and in particular to a method and system for evaluating and correcting the power consumption of in-service wind turbines based on correction of incoming wind speed. Background Art

[0002] In the process of wind farm development, the power generation of the unit is the most important resource and economic evaluation parameter, which determines the development feasibility of the unit site and even the entire site. The power generation is closely related to the project investment payback period, power generation cost and profit margin, so the accuracy of power evaluation is particularly important.

[0003] However, it is often found that the power generation of the units is significantly different from that of the previous assessment during operation. Excluding power restrictions, operation and maintenance and other human operations, the main reason is the simulation error of the wind flow field caused by complex terrain. The current wind resource-related specifications mainly include "NB / T31147-2018 Technical Specifications for Measurement and Assessment of Wind Energy Resources in Wind Farm Projects" and "GB / T18710-2002 Wind Energy Resource Assessment Methods for Wind Farms". These specifications cannot cover the wind resource assessment of in-service wind farms. At present, the wind resource assessment of in-service and technical transformation project wind farms is still implemented according to the standards and processes for the assessment of new wind farms. The wind measurement data and operation data of existing units are not fully utilized, resulting in inaccurate assessment results.

[0004] With reference to the current wind farm resource assessment specifications, the power generation assessment of the unit only uses the data of the wind tower as the input condition. However, for the complex mountainous environment, on the one hand, there are terrain differences between the unit site and the wind tower, and there is uncertainty in the spatial extrapolation of the wind tower. On the other hand, the special terrain at the unit site makes it impossible for the conventional computational fluid dynamics (CFD) algorithm (transient incompressible Reynolds-averaged equations RANS) to truly simulate the flow field distribution. Although direct numerical simulation (DNS) or large eddy simulation (LES) can partially capture the flow field change characteristics, the solution consumes a lot of time and computing resources, and the computational overhead increases exponentially with the Reynolds number, which makes it difficult to apply in engineering. Summary of the invention

[0005] In view of the deficiencies in the prior art, the purpose of the present invention is to provide a method and system for correcting the power generation assessment of in-service wind turbines based on the correction of the incoming wind speed, so as to solve the problem of power generation assessment deviation caused by the influence of terrain in in-service wind farms, and to compensate for the distortion of the model flow field by correcting the incoming wind speed of CFD fitting. It can be used to guide the refined assessment of resources in the site, and can be used as an input for the power generation assessment of the "large-replacing-small" unit transformation.

[0006] To achieve the above purpose, the technical solution adopted by the present invention is as follows:

[0007] A method for evaluating and correcting the power consumption of an in-service wind turbine based on incoming wind speed correction comprises the following steps:

[0008] Step 1) obtaining wind parameter data at a wind tower and using it as a boundary condition, and obtaining simulated wind parameter data at a machine site through software processing; the simulated wind parameter data includes a time series and simulated wind speed at each moment;

[0009] Step 2) obtaining an output characteristic curve of the wind turbine at the machine site, counting the actual output power of the wind turbine at the machine site at each moment in a set period of time in the time series, and obtaining the theoretical wind speed at each moment in the same period of time through the output characteristic curve;

[0010] Step 3) based on the theoretical wind speed and the simulated wind speed at the corresponding moment, an overall correction coefficient of the simulated wind parameter data at the station site is obtained, and the simulated wind parameter data at each moment at the station site in step 1) is corrected to obtain the corrected simulated wind parameter data at the station site;

[0011] Step 4) obtaining the corrected simulated wind parameter data at all machine sites in the wind farm through steps 1) to 3), inputting the data into the software for processing to obtain the theoretical annual power generation of the wind farm, and comparing the theoretical annual power generation with the actual annual power generation to obtain the comprehensive correction coefficient calculated by the software;

[0012] Step 5) The comprehensive correction coefficient calculated by the software is used as a reduction coefficient for the wind farm electricity evaluation of the software.

[0013] Preferably, in step 1), the wind parameter data at the wind tower includes the actual average wind speed and wind direction at the wind tower.

[0014] Preferably, in step 1), the software is wind farm assessment software, and the wind farm assessment software uses a CFD algorithm to calculate the distribution of wind resources in the wind farm and the power generation of the wind farm.

[0015] Preferably, in step 1), the software includes any one of Meteodyn WT software, WindSim software, WindFarmer software, WAsP software, and WindPRO software.

[0016] Preferably, in step 1), the data interval of the time series is 1 hour.

[0017] Preferably, in step 2), the wind turbine is of variable pitch type, and within the set time period, it is advisable to count the actual output power point when the actual average wind speed of the wind turbine is 4-9 m / s.

[0018] Preferably, in step 3), the overall correction coefficient Calculated by the following formula:

[0019]

[0020] In the formula, K t1 , K t2 , K t3 ,……,K tn is the wind speed correction coefficient at each moment; n is the total number of moments;

[0021] The corrected simulated wind parameter data is obtained by correcting the simulated wind speed in the simulated wind parameter data. The calculation method of the corrected simulated wind speed is as follows:

[0022]

[0023] Preferably, the wind speed correction factor K tn Calculated by the following formula:

[0024]

[0025] Where V tn is the theoretical wind speed at each moment; v n is the simulated wind speed at each moment.

[0026] Preferably, the step 3) further comprises: based on the corrected simulated wind parameter data, obtaining representative annual wind speed data at the machine site after performing representative annual analysis according to long-term observation stations or mesoscale sources.

[0027] Preferably, in step 4), the wind farm software calculates the comprehensive correction coefficient C f It is calculated by the following formula:

[0028] C f = Actual annual power generation of wind farm / theoretical annual power generation.

[0029] A system for evaluating and correcting the power of an in-service wind turbine based on correction of incoming wind speed, comprising:

[0030] A data acquisition module is used to obtain wind parameter data at the wind tower, simulated wind parameter data at each machine site in the wind farm, and actual output power and output characteristic curve of the wind turbine at each machine site;

[0031] A data processing module processes the data obtained by the data acquisition module to obtain an overall correction coefficient of the simulated wind parameter data and a software-calculated comprehensive correction coefficient for power generation calculation;

[0032] The data output module calculates the comprehensive correction coefficient through the software to correct the power generation calculation, and then outputs the corrected wind farm assessment power.

[0033] Compared with the prior art, the present invention has the following beneficial effects:

[0034] The present invention provides a method for correcting the electricity consumption assessment of in-service wind turbines based on the correction of incoming wind speed, which makes up for the shortcomings of insufficient representativeness of wind towers under complex terrain of wind farms and errors in CFD simulations, and realizes refined assessment of resources within the farm area by combining wind turbine SCADA data. It can be used to guide post-evaluation of wind farms and technical transformation projects such as "replacing small with large", improves the accuracy of electricity consumption assessment of wind farms, and has the advantage of a simple calculation method.

[0035] The method of the present invention processes historical simulated wind speed and theoretical wind speed to obtain a wind speed correction coefficient, and corrects the simulated wind speed to obtain a more accurate simulated wind speed, thereby solving the problem of insufficient representativeness of wind tower data and avoiding the problem of low accuracy of simulated wind speed. The method of the present invention calculates the comprehensive correction coefficient through software, reduces CFD simulation errors, and can obtain highly reliable power generation evaluation data. BRIEF DESCRIPTION OF THE DRAWINGS

[0036] Figure 1 A schematic diagram of calculating the theoretical wind speed of a wind turbine in a specific embodiment of the present invention;

[0037] Figure 2 This is an example diagram of the statistical power generation of a wind farm unit using existing technology;

[0038] Figure 3 This is an example diagram of the statistical power generation situation of a wind farm unit after adopting the method of the present invention, in which units T1, T3, T5, and T6 are corrected. DETAILED DESCRIPTION

[0039] The following is a detailed description of the implementation of the present invention in conjunction with the accompanying drawings, but they do not constitute a limitation of the present invention and are only given as examples. At the same time, the advantages of the present invention will become clearer and easier to understand through the description.

[0040] Example 1

[0041] This embodiment takes the wind farm assessment software Meteodyn WT as an example to illustrate the in-service wind turbine power assessment correction method based on incoming wind speed correction of the present invention.

[0042] The specific steps are as follows:

[0043] Step 1) Using the wind parameter data at the wind tower in a certain year in history as the boundary condition, the Meteodyn WT software is used to calculate the distribution of wind resources in the entire field, and the time series output is selected for a certain existing machine site in the wind farm to obtain the simulated wind parameter data at the machine site.

[0044] The wind parameter data at the wind tower includes the actual average wind speed and wind direction at the wind tower; the simulated wind parameter data includes the time series and the simulated wind speed at each moment in the corresponding period. The data interval of the time series is 1 hour.

[0045] Step 2) Corresponding to the above time series, considering that the wind turbines are all variable pitch type, the time period when the actual average wind speed of the wind turbine at the machine site is within the range of 4 to 9 m / s is selected for analysis, and the actual output power P of the wind turbine at the point at each time in the time period is counted. n The actual wind speed v obtained from the SCADA data of the wind turbine sn , forming a series of scattered points (v s1 ,P1)、(v s2 ,P2)、(v s3 , P3),……,(v sn , P n ).

[0046] When the wind turbine is of variable pitch type, when the time period when the actual average wind speed is in the range of 4 to 9 m / s is selected for analysis, the sample size is large, the data obtained is stable and highly reliable, and the accuracy of the evaluation results can be improved.

[0047] Get the output characteristic curve of the fan at this point, such as Figure 1 As shown, the above series of scattered points are projected onto the output characteristic curve of the model, and the theoretical wind speed V at each moment in the same period is obtained. t1 、V t2 、V t3 ,……,V tn .

[0048] Because the cabin anemometer is located in the wake area of ​​the wind turbine blades, its wind speed will be smaller than the natural flow wind speed in front of the impeller. In order to perform wind speed regression, the actual wind speed obtained from the moment-by-moment statistical SCADA data is projected onto the power curve of the corresponding model to obtain the theoretical wind speed. Figure 1 Taking three types of machines as examples, each statistical point is projected onto the output characteristic curve of the corresponding machine type.

[0049] Step 3) Compare the theoretical wind speed and the simulated wind speed at each time in the same period as the theoretical wind speed to obtain the average wind speed correction coefficient K corresponding to each time t1 , K t2 , K t3 ,……,K tn ;

[0050]

[0051] In the formula, v n For V tn The simulated wind speed corresponding to each time.

[0052] Take the mean As an overall correction coefficient, the simulated wind parameter data is corrected by using the overall correction coefficient to form a set of corrected simulated wind parameter data, and the representative annual wind speed data at the machine site can be obtained after a representative year analysis based on a long-term observation station or a mesoscale source;

[0053] The corrected simulated wind parameter data is obtained by correcting the simulated wind speed in the simulated wind parameter data. The calculation method of the corrected simulated wind speed is as follows:

[0054]

[0055] The representative annual wind speed data can be used as an input condition for calculating the amount of electricity in the wind farm operation period. The representative annual wind speed data obtained based on the corrected simulated wind speed of the present invention is also more accurate and reliable.

[0056] This step can eliminate the errors caused by terrain in the CFD algorithm.

[0057] Step 4) Obtain the corrected simulated wind parameter data at all machine sites in the wind farm through the above steps 1) to 3), bring the corrected simulated wind parameter data into the Meteodyn WT software to calculate the theoretical annual power generation of the wind farm, and compare the obtained theoretical annual power generation with the actual operating annual power generation to obtain the software calculated comprehensive correction coefficient C f , the software calculates the comprehensive correction coefficient C f Used as a reduction factor to analyze the power generation of wind farms using the comprehensive reduction method;

[0058] Among them C f = Actual annual power generation of wind farm / theoretical annual power generation;

[0059] Step 5) The software calculates the comprehensive correction coefficient C f It is considered as a comprehensive reduction item for power generation and is used to analyze and evaluate wind farm power generation through Meteodyn WT software, which can eliminate software calculation errors.

[0060] If it is necessary to evaluate the resource situation of the station and the surrounding areas with the same conditions, the above overall correction coefficients shall be considered in the wind parameter data input and power generation calculation. And software calculates the comprehensive correction coefficient C f , that is, we can get a more accurate distribution of resources in the area.

[0061] The following will apply the method of evaluating the power generation of a unit through CFD software simulation in the prior art and the method of evaluating the power generation after correcting the wind parameter data and power generation simulated by CFD software in the present invention to evaluate the power generation of each unit site of a wind farm unit, so as to further illustrate the advantages of the present invention.

[0062] The wind farm's generator locations T1, T3, T5, and T6 are located near cliffs. The specific assessment results are as follows: Figure 2 and Figure 3 shown.

[0063] like Figure 2 As shown in FIG. 1 , when the wind speed is not corrected by the method of the present invention and the CFD software is directly used for simulation, for the cliff area, that is, Figure 2 At the middle unit locations T1, T3, T5, and T6, the software cannot simulate the separation phenomenon of the actual airflow, resulting in wind speeds and power generation hours that are higher than the actual operation of the units, and the deviation is large.

[0064] like Figure 3 As shown, after the wind speed is corrected by the method of the present invention and the comprehensive reduction of the wind farm is taken into account, the simulation results are in good agreement with the actual operation of the unit.

[0065] The above method can be used to guide post-evaluation of wind farms and technical transformation projects such as "replacing small with large" to accurately evaluate the power generation of wind farms in the area where wind turbines are located.

[0066] Different from the wind power development stage, the in-service wind farms have real statistical values ​​of unit power generation, which are often used for power assessment, grid access plan declaration, etc. The present invention combines the CFD method with the actual output characteristics of the unit, compares the difference between numerical simulation and actual power, and corrects the software simulation wind speed sequence to make it close to the actual nacelle inflow wind speed level.

[0067] Because the cabin anemometer is located in the impeller wake field area, the wind speed level in the statistical parameters of the wind farm unit operation data acquisition and monitoring control system (SCADA system) is significantly different from the natural flow wind speed in front of the cabin, which cannot represent the resource distribution at this point and cannot be used as an effective input condition for flow field calculation. After correcting the CFD simulation time series, the present invention is close to the wind speed level in front of the machine position wake, and can establish a virtual tower at this point to conduct resource assessment at the point or surrounding area.

[0068] Example 2

[0069] An in-service wind turbine power evaluation and correction system for implementing the in-service wind turbine power evaluation and correction method in Example 1 comprises:

[0070] A data acquisition module is used to obtain wind parameter data at the wind tower, simulated wind measurement data at each machine site in the wind farm, and actual output power and output characteristic curve of the wind turbine at each machine site;

[0071] A data processing module processes the data obtained by the data acquisition module to obtain an overall correction coefficient of the simulated wind parameter data and a software-calculated comprehensive correction coefficient for power generation calculation;

[0072] The data processing module can specifically implement the following contents in the above method: obtain the theoretical wind speed at each moment in the same period by projecting the actual output power onto the output characteristic curve; calculate and process the theoretical wind speed and the simulated wind speed at the corresponding moment to obtain the wind speed correction coefficient, and obtain the overall correction coefficient of the wind turbine at each machine site through the wind speed correction coefficient; correct the simulated wind parameter data of the wind turbine at each machine site through the overall correction coefficient to obtain the corrected simulated wind parameter data; calculate and process the corrected simulated wind parameter data of all machine sites to obtain the theoretical annual power generation of the wind farm, and calculate and process the theoretical annual power generation and the actual annual power generation to obtain the software calculated comprehensive correction coefficient. The specific processing method is shown in each step of Example 1, which will not be repeated here.

[0073] The data output module calculates the comprehensive correction coefficient through the software to correct the power generation calculation, and then outputs the corrected wind farm assessment power.

[0074] Obviously, the above embodiments are merely examples for the purpose of clear explanation, and are not intended to limit the implementation methods. For those skilled in the art, other different forms of changes or modifications can be made based on the above description. It is not necessary and impossible to list all the implementation methods here. The obvious changes or modifications derived therefrom are still within the scope of protection of the invention.

[0075] Other parts not described belong to the prior art.

Claims

1. A method for evaluating and correcting the power consumption of in-service wind turbines based on wind speed correction, characterized in that: The following steps are involved: Step 1) obtaining wind parameter data at a wind tower and using it as a boundary condition, and obtaining simulated wind parameter data at a machine site through software processing; the simulated wind parameter data includes a time series and simulated wind speed at each moment; Step 2) obtaining an output characteristic curve of the wind turbine at the machine site, counting the actual output power of the wind turbine at the machine site at each moment in a set period of time in the time series, and obtaining the theoretical wind speed at each moment in the same period of time through the output characteristic curve; Step 3) based on the theoretical wind speed and the simulated wind speed at the corresponding moment, an overall correction coefficient of the simulated wind parameter data at the machine site is obtained, and the simulated wind parameter data in step 1) is corrected to obtain the corrected simulated wind parameter data; Step 4) obtaining the corrected simulated wind parameter data at all machine sites in the wind farm through steps 1) to 3), and inputting the corrected simulated wind parameter data into the software for processing to obtain the theoretical annual power generation of the wind farm, comparing the theoretical annual power generation with the actual annual power generation, and obtaining the comprehensive correction coefficient calculated by the software; Step 5) The comprehensive correction coefficient calculated by the software is used as a reduction coefficient for the wind farm electricity evaluation of the software.

2. The method for evaluating and correcting the power consumption of in-service wind turbines based on the correction of incoming wind speed according to claim 1 is characterized in that: In the step 1), the wind parameter data at the wind tower includes the actual average wind speed and wind direction at the wind tower.

3. The method for evaluating and correcting the power consumption of in-service wind turbines based on the correction of incoming wind speed according to claim 1 is characterized in that: In the step 1), the software is a wind farm assessment software, and the wind farm assessment software uses a CFD algorithm to calculate the wind resource distribution and wind farm power generation of the wind farm.

4. The method for evaluating and correcting the power consumption of in-service wind turbines based on the correction of incoming wind speed according to claim 3 is characterized in that: In the step 1), the software includes any one of Meteodyn WT software, WindSim software, WindFarmer software, WAsP software, and WindPRO software.

5. The method for evaluating and correcting the power consumption of in-service wind turbines based on the correction of incoming wind speed according to claim 1 is characterized in that: In the step 2), the wind turbine is of variable pitch type, and within the set time period, the valid data points of the actual output power statistics of the wind turbine should correspond to an average wind speed of 4 to 9 m / s.

6. The method for evaluating and correcting the power consumption of in-service wind turbines based on the correction of incoming wind speed according to claim 1 is characterized in that: In step 3), the overall correction coefficient Calculated by the following formula: In the formula, K t1 , K t2 , K t3 ,……,K tn is the wind speed correction coefficient at each moment; n is the total number of moments; The corrected simulated wind parameter data is obtained by correcting the simulated wind speed in the simulated wind parameter data. The calculation method of the corrected simulated wind speed is as follows:

7. The method for evaluating and correcting the power consumption of in-service wind turbines based on the correction of incoming wind speed according to claim 6 is characterized in that: The wind speed correction factor K tn Calculated by the following formula: Where V tn is the theoretical wind speed at each moment; v n is the simulated wind speed at each moment.

8. The method for evaluating and correcting the power consumption of in-service wind turbines based on the correction of incoming wind speed according to claim 1 is characterized in that: The step 3) also includes: based on the corrected simulated wind parameter data, obtaining the representative annual wind speed data at the machine site after performing a representative year analysis according to long-term observation stations or mesoscale sources.

9. The method for evaluating and correcting the power consumption of in-service wind turbines based on the correction of incoming wind speed according to any one of claims 1 to 8, characterized in that: In step 4), the wind farm software calculates the comprehensive correction coefficient C f It is calculated by the following formula: C f = Actual annual power generation of wind farm / theoretical annual power generation.

10. A system for evaluating and correcting the power consumption of in-service wind turbines based on wind speed correction, characterized in that: include: A data acquisition module is used to obtain wind parameter data at the wind tower, simulated wind parameter data at each machine site in the wind farm, and actual output power and output characteristic curve of the wind turbine at each machine site; A data processing module processes the data obtained by the data acquisition module to obtain an overall correction coefficient of the simulated wind parameter data and a software-calculated comprehensive correction coefficient for power generation calculation; The data output module calculates the comprehensive correction coefficient through the software to correct the power generation calculation, and then outputs the corrected wind farm assessment power.

Citation Information

Cited By

  • Wind power plant output calculation method considering reduction, storage medium and electronic equipment

    CN119294159A

  • Wind power output reduction method and system based on time sequence point-by-point correction

    CN119538801A

  • A method and system for reducing wind power output based on point-by-point correction of time series

    CN119538801B

  • Wind resource evaluation system for transformation of wind power plant by changing large wind power plant into small wind power plant

    CN121189885A

  • Wind power plant wind speed time sequence prediction method based on SCADA data correction and CFD modeling

    CN121562489A