Steel bar manufacturing cost accounting control method based on BIM three-dimensional model
Through the cost accounting and control method of the BIM three-dimensional model of steel bar production, the problems of steel bar consumption and cost control are solved, accurate accounting and resource saving are achieved, and production efficiency and cost management are improved.
Patent Information
- Application Number
- CN202411134598.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-19
- Publication Date
- 2024-11-22
AI Technical Summary
The existing technology lacks effective cost accounting and control methods for steel bar production, resulting in increased consumption of steel bars, rising costs, and uncontrollable consumption of the environment and resources.
Using the cost accounting and control method of steel bar production based on BIM three-dimensional model, by creating BIM three-dimensional model, it conducts collision inspection, deepens design, generates batching sheets, statistics material consumption and accounting profit and loss management, combines APP for lightweight processing, and monitors costs in real time. And formulate targeted management measures.
Accurate accounting and control of steel bar production costs has been achieved, material waste has been reduced, resources have been saved, and production efficiency and cost control capabilities have been improved.
Smart Images

Figure CN119006028A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the field of steel bar production cost control, and specifically to a steel bar production cost accounting control method based on a BIM three-dimensional model. Background Art
[0002] The cost of steel bar production accounts for a large proportion of the total construction project cost, and the consumption of steel bars is a non-renewable resource. The processing and excessive use of steel bars will not only lead to rising costs but will also further increase the consumption of raw materials such as cement, sand and gravel. Therefore, how to control the production cost of steel bars is particularly important. At the same time, saving resources is also necessary for environmental protection and social sustainable development. At present, there is a lack of cost accounting and control methods for steel bar production. Summary of the invention
[0003] Therefore, in order to solve the above-mentioned shortcomings, the present invention provides a steel bar production cost accounting and control method based on the BIM three-dimensional model, which achieves the purpose of accounting and controlling the steel bar production cost through the BIM three-dimensional model.
[0004] The present invention is implemented by constructing a steel bar production cost accounting and control method based on a BIM three-dimensional model; comprising the following operations; S1. Create a BIM 3D model based on the approved construction phase design drawings, including the geometric dimensions of the concrete structure and the dimensions of the steel bars; and verify the engineering quantities with the design drawings; S2. Conduct in-depth design of the steel bar model; S3. A material list is formed according to the construction schedule issued, and pushed to the automatic unloading machine to complete the cutting of raw materials. The CNC automatic machine automatically completes the processing according to the in-depth design model drawing; the material is transported to the stacking area, and the installation team picks up the material; S4. Count the consumption of raw materials for steel bars produced, compare with the purchase quantity, inventory quantity (including semi-finished products and raw materials in stock), and waste material disposal quantity, and calculate the profit and loss management of steel bar materials in the entire production process; S5. Compress the BIM model for lightweight processing, and make it into an APP to view various data at any time through the mobile phone, so as to timely grasp the cost control of steel bar production, and compare and analyze the cost accounting results of the three links. If there is any deviation from the predetermined target, formulate targeted management measures.
[0005] According to the method for cost accounting and control of steel bar production based on BIM three-dimensional model described in the present invention; the specific operation of S1 is: S1-1. After creating the BIM 3D model, conduct a collision check. If there are conflicts and collisions in the geometric dimensions and elevations of the concrete structure, the settings of the steel bars and steel strands, timely feedback shall be given to the design unit, and the model shall be corrected with the drawings adjusted by the design; S1-2. When creating a steel bar model, set a list code for the steel bars that are not measured separately to identify them separately; the list number is unified with the measurement rules and the capital letters of the first Chinese pinyin letters of the types of steel bars that are not measured are added (FB-wall protection, DW-positioning, LJ-connection); in this way, statistics can be quickly performed according to the list number later, and the project quantity can also be counted according to the type of steel bars that are not measured separately; the measurement rules of each industry have different requirements for the list number of steel bars that are not measured separately, and the code for the separate identification can be adjusted according to the requirements of the industry; S1-3. When creating a BIM 3D model, it is necessary to set the stages so that the quantity and cost of different stages can be quickly compared during cost accounting. The three stages can be set as modeling stage, detailed design stage, and production accounting stage.
[0006] According to the method for cost accounting and control of steel bar production based on BIM three-dimensional model described in the present invention; the specific operation of S2 is: S2-1. Convert the designed center straight length of the steel bar in the drawing into the actual arc length; The dimension given in the design is the length of the center straight line of the steel bar, such as the straight line BC+CE in the partial enlarged figure. In actual production, the BE segment is an arc. To calculate the arc length BE, is π(D+d / 2) / 4, Where D≥2.5d, d is the steel bar diameter, and D is the steel bar bending diameter; If D=2.5d, the arc length BE is 0.75πd=2.356d; Straight line BC+CE=(D / 2+d / 2)*2=3d; 3d-2.356d=0.644d. That is, when D=2.5d, the cutting length should be reduced by 0.644d for each 90° bending of the steel bar. When the bending diameter (such as 3d, 5d) and bending angle (such as 30°, 60°, 75°, 135°, 180°) are different, the cutting length should be reduced by different lengths. Through the BIM model, the number of bends in the whole project, the reduction of bends and other data are counted, and then the difference in the number of steel bars between the straight line and the arc is summarized; S2-2. Create a database of straight line and arc difference values for steel bars and a BIM model library. When conducting in-depth design of later projects, the database can be directly called to save time in creating models; S2-3. Create a material list in the model based on the steel bar lap form and lap length required by the specifications, construction progress and the length of the steel bar raw materials.
[0007] According to the steel bar production cost accounting and control method based on BIM three-dimensional model described in the present invention; the specific operation of S3 is: S3-1. Input the incoming information of raw materials into the model, including basic information such as quantity, unit price, invoice, and stacking location. The quantity is different from the theoretical measurement quantity and the weighing quantity. If there is a difference between the two, the theoretical measurement quantity shall prevail. S3-2. According to the construction progress requirements, the cutting list is configured according to the steel bar model with in-depth design of the structural parts, and then the materials are cut and made and sent to the installation team.
[0008] According to the method for cost accounting and control of steel bar production based on BIM three-dimensional model described in the present invention; S4 also includes: The quantity information of semi-finished steel bars consumed in the installation process (including structural parts, steel bar models and numbers) is loaded into the BIM model; further, compared with the engineering quantities in the design drawings (including the number of listed steel bars that are measured separately and not separately), the profit and loss management of the production link and the design engineering quantities is calculated; and cost accounting data for comparative analysis of the three links is formed (the three links are the production link, the installation link, and the design drawings).
[0009] The present invention has the following advantages: The present invention provides a method for calculating and controlling the cost of steel bar production based on the BIM three-dimensional model, which achieves the purpose of calculating and controlling the cost of steel bar production by means of the BIM three-dimensional model. BRIEF DESCRIPTION OF THE DRAWINGS
[0010] Figure 1 The dimension given in the design is a schematic diagram of the straight length of the center of the steel bar; Figure 2 This is a schematic diagram of the staggered arrangement of lashing joints; Figure 3 Schematic diagram of staggered arrangement of connection joints of stressed steel bars. DETAILED DESCRIPTION
[0011] The following will be combined with the attached Figure 1-Figure 3 The present invention is described in detail, and the technical solutions in the embodiments of the present invention are clearly and completely described. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0012] The present invention provides a method for cost accounting and control of steel bar production based on BIM three-dimensional model, which is specifically implemented in the following manner; including the following operations: S1. Create a BIM 3D model based on the approved construction phase design drawings, including the geometric dimensions of the concrete structure and the dimensions of the steel bars; and verify the engineering quantities with the design drawings.
[0013] S1-1. After creating the BIM 3D model, a collision check is performed. If there are conflicts and collisions in the geometric dimensions and elevations of the concrete structure, or in the settings of the steel bars and steel strands, feedback is promptly provided to the design unit, and the model is corrected using the drawings adjusted by the design.
[0014] S1-2. When creating a steel bar model, set a list code for the steel bars that are not separately measured according to the "Measurement Rules for Bill of Quantities of Highway Engineering Standard Construction Bidding Documents Chapter 8 - 2018 Edition" to mark them separately, such as the wall reinforcement of the anti-slide pile in List 214-3, the positioning frame reinforcement in List 403, and the longitudinal connection reinforcement of the steel frame in List 503-2. It is recommended to set the list code to 214-3-FB, 403-DW, 503-2-LJ, and unify the list number with the measurement rules and add the capital letters of the first Chinese pinyin of the type of steel bars that are not measured (FB-wall, DW-positioning, LJ-connection); in this way, statistics can be quickly performed according to the list number later, and the project quantity can also be counted according to the type of steel bars that are not measured. The measurement rules of each industry have different requirements for the list number of steel bars that are not separately measured, and the separately marked code can be adjusted according to the requirements of the industry.
[0015] S1-3. When creating a BIM 3D model, you need to set the stages so that you can quickly compare the quantities and costs of different stages during cost accounting. You can set the stages to three stages: modeling stage, detailed design stage, and production accounting stage.
[0016] S2. Conduct in-depth design of the steel bar model: S2-1. Convert the designed center straight length of the steel bar in the drawing into the actual arc length. Figure 1 As shown; The design dimension is the length of the center straight line of the steel bar, such as the straight line BC+CE in the partial enlarged figure. When it is actually made, the BE segment is an arc. The arc length BE is calculated as π(D+d / 2) / 4, where D≥2.5d, d is the diameter of the steel bar, and D is the bending diameter of the steel bar; if D=2.5d, the arc length BE is 0.75πd=2.356d. Straight line BC+CE=(D / 2+d / 2)*2=3d; 3d-2.356d=0.644d. That is, when D=2.5d, the cutting length should be reduced by 0.644d for each 90° steel bar bending. When the bending diameter (such as 3d, 5d) and bending angle (such as 30°, 60°, 75°, 135°, 180°) are different, the cutting length should be reduced by different lengths. Through the BIM model, the number of bends in the entire project, the reduction of bends and other data are counted, and then the number of steel bar differences between the straight line and the arc are summarized.
[0017] Article 4.2.5 of the Technical Specifications for Highway Bridge and Culvert Construction (JTG / T 3650-2020) stipulates that the ends of the stirrups should be hooked, and the shape of the hooks should comply with the design requirements. The bending diameter of the hooks should be larger than the diameter of the main reinforcement being hooped, and the HPB300 steel bar should be no less than 2.5 times the diameter of the stirrups, and the HRB400 steel bar should be no less than 5 times the diameter of the stirrups.
[0018] This calculation is based on the premise that the centerline length of the steel bar remains unchanged after bending, which is consistent with the mechanical properties of the steel bar in the elastic deformation stage. In other words, the centerline length of the steel bar remains unchanged after bending, while the outer edge becomes longer and the inner edge shortens.
[0019] S2-2. Create a database and BIM model library for the difference between straight lines and arcs of steel bars. When conducting in-depth design of later projects, the database can be directly called to save time in creating models.
[0020] S2-3. Create a material list in the model based on the steel bar lap form and lap length required by the specifications, construction progress and the length of the steel bar raw materials.
[0021] Section 4.3.2 of the Technical Specifications for Highway Bridge and Culvert Construction (JTG / T 3650-2020) stipulates that the connection joints of the stressed steel bars should be set in sections with smaller internal forces and should be staggered. For welded joints and mechanical connection joints, there shall not be two joints on the same steel bar within the joint length section; for tied joints, the distance between the two joints shall not be less than 1.3 times the lap length. For the stressed steel bars arranged within the joint length section, the percentage of the cross-sectional area of the joint to the total cross-sectional area shall comply with the provisions of Table 1.
[0022] Table 1 shows the maximum percentage of the joint area of the stressed steel bars within the joint length section. Figure 2 This is a schematic diagram of the staggered arrangement of binding joints. Figure 3 Schematic diagram of staggered arrangement of connection joints of stressed steel bars.
[0023] In addition to round and spiral coils, the production size of steel bars is generally 9m and 12m long. Therefore, when mixing materials, it is necessary to count the types of steel bars that need to be produced in a similar time according to the production schedule; then configure according to various types of steel bars to save materials to the greatest extent.
[0024] The BIM model results of the in-depth design must also comply with the relevant provisions of the "Standard for In-depth Design of Steel Structure Engineering (T / CECS606-2019)".
[0025] S3. A material list is formed according to the issued construction schedule and pushed to the automatic unloading machine to complete the cutting of raw materials. The CNC automatic machinery automatically completes the processing according to the in-depth design model drawing; the materials are transported to the stacking area and the installation team picks up the materials.
[0026] S3-1. Enter the raw material storage information into the model, including quantity, unit price, invoice, stacking location and other basic information. The quantity is different from the theoretical measurement quantity and the weighing quantity. If there is a difference between the two, the theoretical measurement shall prevail. S3-2. According to the construction progress requirements, the steel bar model with in-depth design of the structural parts is configured with a material cutting list, and then the materials are cut and made and sent to the installation team.
[0027] S4. Count the consumption of raw materials for manufactured steel bars, compare with the purchase quantity, inventory quantity (including semi-finished products and raw materials in stock), and waste material disposal quantity, and calculate the profit and loss management of steel bar materials in the entire manufacturing process; at the same time, load the quantity information of semi-finished steel bars consumed in the installation process (including structural parts, models and numbers of steel bars) into the BIM model; further, compare with the engineering quantity of the design drawings (including the number of listed steel bars that are measured separately and not measured separately), calculate the profit and loss management of the manufacturing link and the design engineering quantity; form cost accounting data for comparative analysis of the three links (the three links are manufacturing link, installation link, and design drawings).
[0028] S5. Compress the BIM model for lightweight processing, and make it into an APP to view various data at any time through the mobile phone, so as to timely grasp the cost control of steel bar production, and compare and analyze the cost accounting results of the three links. If there is any deviation from the predetermined target, formulate targeted management measures.
[0029] The above description of the disclosed embodiments enables one skilled in the art to implement or use the present invention. Various modifications to these embodiments will be apparent to one skilled in the art, and the general principles defined herein may be implemented in other embodiments without departing from the spirit or scope of the present invention. Therefore, the present invention will not be limited to the embodiments shown herein, but rather to the widest scope consistent with the principles and novel features disclosed herein.
Claims
1. A method for cost accounting and control of steel bar production based on BIM three-dimensional model, characterized in that; Including the following operations: S1. Create a BIM 3D model based on the approved construction phase design drawings, including the geometric dimensions of the concrete structure and the dimensions of the steel bars; and verify the engineering quantities with the design drawings; S2. Conduct in-depth design of the steel bar model; S3. A material list is formed according to the construction schedule issued, and pushed to the automatic unloading machine to complete the cutting of raw materials. The CNC automatic machine automatically completes the processing according to the in-depth design model drawing; the material is transported to the stacking area, and the installation team picks up the material; S4. Count the consumption of raw materials for steel bars produced, compare with the purchase quantity, inventory quantity (including semi-finished products and raw materials in stock), and waste material disposal quantity, and calculate the profit and loss management of steel bar materials in the entire production process; S5. Compress the BIM model for lightweight processing, and make it into an APP to view various data at any time through the mobile phone, so as to timely grasp the cost control of steel bar production, and compare and analyze the cost accounting results of the three links. If there is any deviation from the predetermined target, formulate targeted management measures.
2. According to the method for cost accounting and control of steel bar production based on BIM three-dimensional model as described in claim 1, it is characterized in that; The specific operations of S1 are: S1-1. After creating the BIM 3D model, conduct a collision check. If there are conflicts and collisions in the geometric dimensions and elevations of the concrete structure, the settings of the steel bars and steel strands, timely feedback shall be given to the design unit, and the model shall be corrected with the drawings adjusted by the design; S1-2. When creating a steel bar model, set a list code for the steel bars that are not measured separately to identify them separately; the list number is unified with the measurement rules and the capital letters of the first Chinese pinyin letters of the types of steel bars that are not measured are added (FB-wall protection, DW-positioning, LJ-connection); in this way, statistics can be quickly performed according to the list number later, and the project quantity can also be counted according to the type of steel bars that are not measured separately; the measurement rules of each industry have different requirements for the list number of steel bars that are not measured separately, and the code for the separate identification can be adjusted according to the requirements of the industry; S1-3. When creating a BIM 3D model, it is necessary to set the stages so that the quantity and cost of different stages can be quickly compared during cost accounting. The three stages can be set as modeling stage, detailed design stage, and production accounting stage.
3. According to the method for cost accounting and control of steel bar production based on BIM three-dimensional model in claim 1, it is characterized in that; The specific operations of S2 are: S2-1. Convert the designed center straight length of the steel bar in the drawing into the actual arc length; The dimension given in the design is the length of the center straight line of the steel bar, such as the straight line BC+CE in the partial enlarged figure. In actual production, the BE segment is an arc. Calculate the arc length BE, is π(D+d / 2) / 4, Where D≥2.5d, d is the steel bar diameter, and D is the steel bar bending diameter; If D=2.5d, the arc length BE is 0.75πd=2.356d; Line BC+CE=(D / 2+d / 2)*2=3d; 3d-2.356d=0.644d; That is, when D=2.5d, the cutting length should be reduced by 0.644d for each 90° bending of the steel bar; When the bending diameter (such as 3d, 5d) and bending angle (such as 30°, 60°, 75°, 135°, 180°) are different, the cutting length should be reduced by different lengths. Through the BIM model, the number of bends in the whole project, the reduction of bends and other data are counted, and then the difference in the number of steel bars between the straight line and the arc is summarized; S2-2. Create a database of straight line and arc difference values for steel bars and a BIM model library. When conducting in-depth design of later projects, the database can be directly called to save time in creating models; S2-3. Create a material list in the model based on the steel bar lap form and lap length required by the specifications, construction progress and the length of the steel bar raw materials.
4. According to the method for cost accounting and control of steel bar production based on BIM three-dimensional model in claim 1, it is characterized in that; The specific operations of S3 are: S3-1. Input the incoming information of raw materials into the model, including basic information such as quantity, unit price, invoice, and stacking location. The quantity is different from the theoretical measurement quantity and the weighing quantity. If there is a difference between the two, the theoretical measurement quantity shall prevail. S3-2. According to the construction progress requirements, the cutting list is configured according to the steel bar model with in-depth design of the structural parts, and then the materials are cut and made and sent to the installation team.
5. According to the method for cost accounting and control of steel bar production based on BIM three-dimensional model as described in claim 1, it is characterized in that; S4 also includes; The quantity information of semi-finished steel bars consumed in the installation process (including structural parts, steel bar models and numbers) is loaded into the BIM model; further, compared with the engineering quantities in the design drawings (including the number of listed steel bars that are measured separately and not separately), the profit and loss management of the production link and the design engineering quantities is calculated; and cost accounting data for comparative analysis of the three links is formed (the three links are the production link, the installation link, and the design drawings).