Tie-back well cementation device and tie-back well cementation method for oil well

By using a back-connect cementing device in the oil well, the cementing mud is discharged using annular channels and high-pressure fluid, the problem of bending deformation of the casing due to cement plugs is solved, and the effect of reducing costs and improving oil production efficiency is achieved.

CN119021630APending Publication Date: 2024-11-26CHINA PETROLEUM & CHEMICAL CORP +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202310603836.X
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2023-05-26
Publication Date
2024-11-26

AI Technical Summary

Technical Problem

During the oil production process of oil wells, the casing forms a cement plug due to solidification of the cementing mud, which leads to hindering the pressure transfer, the casing bends and deforms, affecting the oil production operation, and the method of improving the extrusion resistance is expensive and not practical.

Method used

A back-connection cementing device for oil wells is designed, including a back-connection barrel, an outer tube body, a back-connection plug and an inner tube body. By forming an annular channel and a void in the wellbore, cementing mud is injected and used to use high-pressure fluid to The residue after it solidifies is discharged to prevent the formation of cement plugs.

Benefits of technology

Effectively prevent casing from bending and deforming, ensure normal use of casing, reduce cementing costs, and improve the efficiency and safety of cementing operations.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119021630A_ABST
    Figure CN119021630A_ABST
Patent Text Reader

Abstract

The invention relates to a tie-back well cementation device for an oil well. The tie-back well cementation device comprises a tie-back cylinder arranged in a shaft. The outer pipe body can be inserted into a shaft, an outer annulus is formed between the outer pipe body and the shaft, the tie-back plug is arranged below the outer pipe body, the tie-back plug can sit on a tie-back barrel so as to cut off communication between the tie-back barrel and the outer annulus, and a connecting hole for communicating the outer pipe body with the tie-back barrel is formed in the tie-back plug. And the inner pipe body can be inserted into the outer pipe body, so that an inner annulus can be formed between the inner pipe body and the outer pipe body. The outer diameter of the inner pipe body is set to be smaller than the diameter of the connecting hole, so that the inner pipe body can penetrate through the connecting hole, and an annular channel which is communicated with the tie-back barrel and the inner annulus and allows fluid to flow is formed between the connecting hole and the inner pipe body.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to a tie-back cementing device for an oil well and a tie-back cementing method. Background Art

[0002] In the process of oil production, tieback cementing is one of the commonly used cementing methods, which can effectively maintain oil wells and reduce production operation costs.

[0003] However, after the cementing operation was completed, as the oil production process progressed, the operators found that the casing in some oil layers in the oil well had deformed, which seriously affected the normal oil production operation. After analysis, it was determined that some residual cementing mud was attached to the casing after the cementing operation. After solidification, these attached cementing muds would form cement plugs in the casing. After solidification, the cement plugs would interfere with or block the fluid flow on the upper and lower sides of the casing, so that the pressure of the liquid column on the upper part of the casing could not be normally transmitted to the lower part of the cement plug. In this way, the pressure trapped in the lower part of the cement plug would be lost during the solidification process or after solidification, resulting in a pressure difference between the inside and outside of the casing. When this pressure difference exceeds the anti-extrusion strength of the casing, the casing will bend and deform, affecting the normal use of the casing.

[0004] Unlimited improvement of the casing collapse resistance of the oil layer will result in the diameter not being able to meet the requirements of the later completion operations and a huge increase in costs, making it difficult to solve the problem of casing bending and deformation. Summary of the invention

[0005] In view of the above technical problems, the present invention aims to provide a tie-back cementing device for oil wells. The tie-back cementing device for oil wells of the present invention can effectively prevent the downhole casing from bending and deforming, thereby affecting the normal use of the casing.

[0006] According to a first aspect of the present invention, there is provided a tie-back cementing device for an oil well, comprising a tie-back barrel arranged in a wellbore; an outer tube body capable of being inserted into the wellbore, an outer annulus being formed between the outer tube body and the wellbore, and a tie-back plug arranged below the outer tube body, the tie-back plug being capable of sitting on the tie-back barrel to cut off the connection between the tie-back barrel and the outer annulus, and a connecting hole connecting the outer tube body and the tie-back barrel being provided in the tie-back plug.

[0007] The inner tube body is also included, and the inner tube body can be inserted into the outer tube body so as to form an inner annulus between the inner tube body and the outer tube body. The outer diameter of the inner tube body is set to be smaller than the diameter of the connecting hole, so that the inner tube body can pass through the connecting hole and form an annular channel between the connecting hole and the inner tube body to connect the return tube and the inner annulus and allow fluid to flow.

[0008] In a preferred embodiment, an anti-overflow cylinder is further provided at the upper end of the shaft, and the anti-overflow cylinder is cylindrical and is arranged to be higher than the ground.

[0009] In a preferred embodiment, an anti-overflow umbrella is further provided at the upper end of the anti-overflow cylinder. The anti-overflow umbrella is configured to be conical so that the size of the lower end connected to the anti-overflow cylinder is smaller than the size of the upper end.

[0010] In a preferred embodiment, a flow guide pipe connected to the anti-overflow cylinder is further provided outside the anti-overflow cylinder, and a vibrating screen is further provided at the free end of the flow guide pipe.

[0011] In a preferred embodiment, a first connecting hole is provided on the side wall of the overflow prevention tube, and a second connecting hole is provided on the side wall of the outer tube body at the same height as the first connecting hole.

[0012] One end of the flow guide pipe away from the vibrating screen is arranged to be in communication with the first connecting hole, so that the flow guide pipe is connected to the side wall of the overflow prevention cylinder.

[0013] In a preferred embodiment, a blowout preventer is further provided between the overflow prevention tube and the outer tube body, and the blowout preventer is provided at the lower side of the first connecting hole.

[0014] In a preferred embodiment, it also includes a carrier arranged on the upper side of the anti-overflow cylinder, and a hanger is also arranged on the carrier.

[0015] According to a second aspect of the present invention, a tie-back cementing method is provided, which is performed using any one of the tie-back cementing devices for oil wells described above, and the method comprises:

[0016] Step 1: Connect the tie-back plug to the lower end of the outer tube body, and lower the tie-back plug into the wellbore together with the outer tube body until the tie-back plug sits on the tie-back tube;

[0017] Step 2: lift the outer tube body by a certain distance, so that a gap connecting the tie-back tube and the outer annulus is formed between the tie-back plug and the tie-back tube in the vertical direction;

[0018] Step 3: inject cementing mud into the outer tube body, and the cementing mud will flow to the outer annulus through the outer tube body, the connecting hole, the tie-back tube and the gap in sequence, and then return to the wellhead through the outer annulus. At this time, the outer annulus is filled with cementing mud;

[0019] Step 4: Building a platform and a hanger on the upper side of the wellhead, and setting an overflow prevention tube at the wellhead, and then connecting a flow guide pipe and a vibrating screen to the overflow prevention tube and the side wall of the outer tube body;

[0020] Step 5: inserting the inner tube into the outer tube until the inner tube is inserted into the return tube;

[0021] Step 6: lower the outer tube body until the tie-back plug is seated on the tie-back tube again, cutting off the connection between the tie-back tube and the outer annulus;

[0022] Step 7: close the blowout preventer and inject drilling fluid into the inner pipe body until all the cementing mud in the outer pipe body and the inner pipe body is discharged from the inner annulus and the guide pipe;

[0023] Step 8: The inner tube body is lifted out of the outer tube body, and the cementing mud in the outer annulus is waited to solidify.

[0024] In a preferred embodiment, after the reconnection plug is seated in the reconnection tube, gas is introduced into the outer tube body to perform seal verification.

[0025] In a preferred embodiment, the outer tube is lifted up by a distance of 20-40 cm. BRIEF DESCRIPTION OF THE DRAWINGS

[0026] The present invention will be described below with reference to the accompanying drawings.

[0027] Figure 1 A schematic diagram of a tie-back cementing device for an oil well according to an embodiment of the present invention is shown.

[0028] In the present application, all drawings are schematic drawings, which are only used to illustrate the principles of the present invention and are not drawn according to the actual scale. DETAILED DESCRIPTION

[0029] The present invention will be described below with reference to the accompanying drawings.

[0030] Figure 1 FIG. 1 is a schematic diagram of a tie-back cementing device 100 for an oil well according to an embodiment of the present invention. Figure 1 As shown, the tie-back cementing device 100 for oil wells comprises a tie-back tube 10. The tie-back tube 10 is cylindrical and reserved in a wellbore 11.

[0031] Meanwhile, the tie-back cementing device 100 for oil wells further comprises an outer tube body 20 , which may be a casing, for example. The outer tube body 20 can be inserted into the wellbore 10 , so that an outer annulus 22 can be formed between the outer tube body 20 and the wellbore 11 .

[0032] like Figure 1As shown, a tie-back plug 30 is also provided below the outer tube body 20. When the tie-back plug 30 is lowered into the oil well together with the outer tube body 20, the tie-back plug 30 can sit on the tie-back tube 10, thereby cutting off the connection between the tie-back tube 10 and the outer annulus 22. At the same time, a connecting hole 32 is provided in the tie-back plug 30. In this way, when the tie-back plug 30 is connected to the tie-back tube 10, the tie-back tube 10 and the outer tube body 20 can be connected through the connecting hole 32.

[0033] Therefore, when a tie-back cementing operation is required, the operator can lower the tie-back plug 30 together with the outer pipe body 20 into the wellbore 11 until the tie-back plug 30 is seated on the tie-back tube 10 , thereby completing the positioning of the tie-back plug 30 .

[0034] Then the operator can lift the outer tube body 10 for a certain distance, so that the tie-back plug 30 is separated from the tie-back tube 10, and a gap 35 is formed between the tie-back plug 30 and the tie-back tube 10 in the vertical direction to connect the tie-back tube 10 and the outer annulus 22. Thus, the operator can inject cementing mud from the wellhead into the outer tube body 20. Then the cementing mud will flow into the tie-back tube 10 through the connecting hole 32.

[0035] When the tie-back tube 10 is filled with cementing mud, cementing mud is continuously injected. At this time, the cementing mud flows into the outer annulus 22 along the gap 35 under the action of pressure, and is discharged back to the wellhead along the outer annulus 22 .

[0036] When the cementing mud is returned to the wellhead along the outer annulus 35, the outer annulus 22 will be filled with cementing mud. When the cementing mud solidifies, the purpose of cementing can be achieved.

[0037] In a preferred embodiment, the lifting distance of the outer tube 20 is set to 20 cm-40 cm. Multiple field experiments have shown that when the lifting distance of the outer tube 20 is within this size range, the cementing mud has a good return pressure and return speed.

[0038] However, after the cementing operation is completed, the inventors of the present invention have found that residual cementing mud will inevitably remain in the outer tube body 20. The residual cementing mud will solidify and adhere to the inner wall of the outer tube body 20, forming a cement plug (not shown). The formed cement plug will affect the pressure transmission on the upper and lower sides of the outer tube body 20. In severe cases, the cement plug will block the outer tube body 20, thereby cutting off the hydraulic transmission on the upper and lower sides of the outer tube body 20.

[0039] At this time, the pressure trapped under the cement plug will lose pressure during or after solidification, resulting in a pressure difference between the inside and outside of the outer tube 20. When this pressure difference exceeds the collapse strength of the outer tube 20, the outer tube 20 will deform, thereby affecting the normal oil production operation of the oil well.

[0040] To solve this problem, the tie-back cementing device 100 for oil wells of the present invention further includes an inner tube body 40 that can be inserted into the outer tube body 20. The inner tube body 40 can be, for example, an oil pipe or a drill pipe. The diameter of the inner tube body 40 is set to be smaller than the inner diameter of the outer tube body 20, so that when the inner tube body 40 is inserted into the outer tube body 20, an inner annulus 42 is formed between the inner tube body 20 and the outer tube body 40.

[0041] like Figure 1 As shown, the outer diameter of the inner tube body 40 is set to be smaller than the diameter of the connecting hole 32, so that the inner tube body 40 can pass through the connecting hole 32 and be inserted into the tie-back tube 10. In this process, an annular channel 45 is formed between the inner tube body 40 and the connecting hole 32 in the radial direction to connect the tie-back tube 10 and the inner annulus 42.

[0042] Therefore, during the tie-back cementing operation, when the cementing mud is returned to the wellhead, the operator can insert the inner tube body 40 into the outer tube body 20. Since the cementing mud has not solidified at this time, the inner tube body 40 can smoothly move downward in the outer tube body 20, thereby being inserted into the tie-back tube 10 from the connecting hole, thereby forming an inner annulus 42 and an annular channel 45.

[0043] In this way, after the inner tube body 40 is inserted into the tie-back tube 10 , the operator can lower the outer tube body 20 so that the tie-back plug 30 at the lower end of the outer tube body 20 is re-seated on the tie-back tube 10 , thereby cutting off the connection between the tie-back tube 10 and the outer annulus 22 .

[0044] At this time, the operator can inject high-pressure fluid into the inner tube body 40. The high-pressure fluid can be, for example, drilling fluid. During the downward flow of the high-pressure fluid, the cementing mud in the inner tube body 40 will be pressed downward, and this pressure will be transmitted to the inner annulus 42 along the inner tube body 40, the annular channel 45 and the tie-back tube 10 in sequence, so that the cementing mud in the inner annulus 42 can be continuously squeezed upward to the wellhead.

[0045] Subsequently, the high pressure fluid is continuously injected, and the cementing mud continues to move toward the wellhead. Finally, with the continuous injection of the high pressure fluid, the cementing mud in the inner tube body 40 and the inner annulus 42 is completely returned to the wellhead and discharged.

[0046] In this process, since the tie-back plug 30 seals the tie-back tube 10 and cuts off the connection between the tie-back tube 10 and the outer annulus 22 , the above-mentioned flowback process will not affect the cementing mud in the outer annulus.

[0047] Preferably, during the process of lowering the outer tubular body 20, after the tie-back plug 30 is seated on the tie-back tube 10 for the first time, the operator can inject gas into the outer tubular body 10 to test the pressure inside the outer tubular body 20. When the pressure rises and can be maintained after the gas is injected, it means that the tie-back plug 30 can seal the tie-back tube 10. When the pressure cannot rise or cannot be maintained after rising, it means that the gas can flow into the outer annulus 22 through the outer tubular body 20. At this time, the tie-back plug 30 fails to seal the tie-back tube 10, and the outer tubular body 20 needs to be further adjusted.

[0048] This pressure test process can effectively prevent the outer annulus 22 from being connected to the inner tube body 40 after setting, thereby preventing high-pressure fluid from flowing into the outer annulus 22 and affecting the cementing mud in the outer annulus 22 .

[0049] In a preferred embodiment, an anti-overflow cylinder 50 is further provided at the upper end of the shaft 11. The anti-overflow cylinder 50 is configured in a cylindrical shape and is configured to be higher than the ground.

[0050] During the process of the outer tube body 20 or the inner tube body 40 entering the well, the fluid in the well may move toward the wellhead, and the speed of this movement is positively correlated with the lowering speed of the outer tube body 20 or the inner tube body 40. The anti-overflow tube 50 can prevent the fluid in the well from flowing out of the wellhead and escaping to the outside of the well during the process of the outer tube body 20 or the inner tube body 40 entering the well. This can avoid the pollution of the environment by the fluid in the well on the one hand, and prevent the waste of the fluid in the well on the other hand, which helps to save costs.

[0051] Furthermore, an anti-overflow umbrella 55 is also provided at the upper end of the anti-overflow cylinder 50. The anti-overflow umbrella 55 is configured to be conical, so that the size of the lower end connected to the anti-overflow cylinder 50 is smaller than the size of the upper end. It is easy to understand that the conical anti-overflow umbrella 55 can further improve the protection effect of the anti-overflow cylinder 50 and further reduce the risk of underground fluid leakage.

[0052] like Figure 1 As shown, a flow guide pipe 56 connected to the overflow prevention tube 50 is also provided outside the overflow prevention tube 50. A vibrating screen (not shown) is also provided at the free end 561 of the flow guide pipe 56. Thus, when high-pressure fluids such as cementing mud or drilling fluid are discharged back to the wellhead, they will flow into the overflow prevention tube 50, and then flow to the vibrating screen through the flow guide pipe 56. At this time, the vibrating screen can purify the cementing mud or drilling fluid, thereby facilitating the recycling of the cementing mud or drilling fluid, thereby further saving cementing costs.

[0053] It should be noted that other purification devices may be connected to the vibrating screen to further purify the cementing mud or drilling fluid, which is not limited in the present invention.

[0054] like Figure 1 As shown, in a preferred embodiment, a first through hole 562 is provided on the side wall of the anti-overflow cylinder 50, and a second through hole 564 is provided on the side wall of the outer tube body at the same height as the first through hole 562. At the same time, one end of the flow guide tube 56 away from the vibrating screen is arranged to be connected to the first through hole 562, so that the flow guide tube 56 is connected to the side wall of the anti-overflow cylinder 50.

[0055] This connection method can avoid connecting the guide pipe 56 to the upper end of the overflow prevention tube 50, thereby avoiding the guide pipe 56 occupying the opening at the upper end of the overflow prevention tube 50, thereby affecting the injection of high-pressure fluid. On the other hand, compared with the method of connecting the guide pipe 56 to the overflow prevention tube 50, this arrangement can effectively reduce the length of the guide pipe 56 and the difficulty of arranging the guide pipe 56 and the vibrating screen.

[0056] like Figure 1 As shown, a blowout preventer 60 is further provided between the overflow prevention tube 50 and the outer tube body 20. The blowout preventer 60 can control the opening and closing of the outer annulus 22, so that when the high-pressure fluid is injected, the outer annulus 22 can be closed, thereby preventing the factors such as downhole pressure fluctuation from interfering with the cementing mud in the outer annulus 22, causing the cementing mud in the outer annulus 22 to be ejected from the wellbore 11.

[0057] Furthermore, the blowout preventer 60 is arranged at the lower side of the first through hole 562. In this way, when the returned cementing mud or high-pressure fluid flows from the first through hole 562 to the flow guide pipe 56, the blowout preventer 60 can cut off the outer annulus 22 on both sides of the first through hole 562, thereby preventing the cementing mud or high-pressure fluid from flowing back into the well from the outer annulus 22, causing contamination to the cementing mud in the outer annulus 22 and affecting the cementing quality.

[0058] In addition, if Figure 1 As shown, the tie-back cementing device 100 for oil wells of the present invention further includes a carrier 70 disposed on the upper side of the overflow prevention cylinder 50. A hanger (not shown) is also disposed on the carrier 70. Thus, the operator can control the movement of the outer tube body 20 and the inner tube body 40 through the hanger, thereby reducing the difficulty of the operation.

[0059] The working process of the tie-back cementing device 100 for an oil well according to the present invention is briefly described below.

[0060] The tie-back cementing device 100 for oil wells of the present invention is used to implement tie-back cementing operations. In the tie-back cementing operation, the operator first needs to connect the tie-back plug 30 to the lower end of the outer tube 20, and lower the tie-back plug 30 into the wellbore 11 together with the outer tube 20 until the tie-back plug 30 sits on the tie-back tube 10.

[0061] After the return plug 30 is seated on the return tube 10, the operator can lift the outer tube body 20, and then build the platform 70 and the hanger on the upper side of the wellhead. After the platform 70 and the hanger are set up, the operator can set the overflow prevention tube 50 at the wellhead, and then connect the guide pipe 56 and the vibrating screen to the overflow prevention tube 50 and the side wall of the outer tube body 20.

[0062] At this time, cementing mud is injected into the outer pipe body 20, and then the cementing mud is returned from the outer annulus 22 to the wellhead, and then flows to the vibrating screen through the guide pipe 56 for recovery.

[0063] After the cementing mud is returned from the outer annulus 22 to the wellhead, the operator needs to lower the inner tube body 40 into the outer tube body 20 before the cementing mud solidifies, until the outer tube body 20 is inserted into the tie-back tube 10, and then lower the outer tube body 20 so that the tie-back plug 30 sits on the tie-back tube 10 again.

[0064] Finally, the operator can inject high-pressure liquid into the inner tube body 40 , so as to squeeze the cementing mud in the inner annulus 42 and the inner tube body 20 to the wellhead and discharge it through the guide pipe 56 .

[0065] Finally, it should be noted that the above is only a preferred embodiment of the present invention and does not constitute any limitation to the present invention. Although the present invention has been described in detail with reference to the aforementioned embodiments, it is still possible for a person skilled in the art to modify the technical solutions described in the aforementioned embodiments, or to replace some of the technical features therein by equivalents. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present invention shall be included in the protection scope of the present invention.

Claims

1. A tie-back cementing device (100) for an oil well, comprising: A tie-back tube (10) disposed in a wellbore (11); An outer tubular body (20) capable of being inserted into a wellbore, an outer annulus (22) being formed between the outer tubular body and the wellbore, and, A tie-back plug (30) is arranged below the outer tube body, and the tie-back plug can be seated on the tie-back tube to cut off the connection between the tie-back tube and the outer annulus. A connecting hole (32) connecting the outer tube body and the tie-back tube is arranged in the tie-back plug. The device further comprises an inner tube body (40), wherein the inner tube body can be inserted into the outer tube body so as to form an inner annulus (42) between the inner tube body and the outer tube body. The outer diameter of the inner tube body is set to be smaller than the diameter of the connecting hole, so that the inner tube body can pass through the connecting hole and form an annular channel (45) between the connecting hole and the inner tube body to connect the return tube and the inner annulus and allow fluid to flow.

2. The tie-back cementing device for oil wells according to claim 1, characterized in that: An overflow prevention cylinder (50) is also arranged at the upper end of the wellbore. The overflow prevention cylinder is arranged in a cylindrical shape and is arranged to be higher than the ground.

3. The tie-back cementing device for oil wells according to claim 2, characterized in that: An anti-overflow umbrella (55) is also arranged at the upper end of the anti-overflow cylinder. The anti-overflow umbrella is arranged in a conical shape so that the size of the lower end connected to the anti-overflow cylinder is smaller than the size of the upper end.

4. The tie-back cementing device for oil wells according to claim 3, characterized in that: A flow guide pipe (56) connected to the overflow prevention cylinder is also arranged outside the overflow prevention cylinder, and a vibrating screen is also arranged at the free end of the flow guide pipe.

5. The tie-back cementing device for oil wells according to claim 4, characterized in that: A first connecting hole (562) is provided on the side wall of the overflow prevention tube, and a second connecting hole (564) is provided on the side wall of the outer tube body at the same height as the first connecting hole. One end of the flow guide pipe away from the vibrating screen is arranged to be in communication with the first connecting hole, so that the flow guide pipe is connected to the side wall of the overflow prevention cylinder.

6. The tie-back cementing device for oil wells according to claim 5, characterized in that: A blowout preventer (60) is also arranged between the overflow prevention tube and the outer tube body, and the blowout preventer is arranged at the lower side of the first connecting hole.

7. The tie-back cementing device for oil wells according to claim 6, characterized in that: It also includes a carrier (70) arranged on the upper side of the overflow prevention tube, and a hanger is also arranged on the carrier.

8. A tie-back cementing method, performed using the tie-back cementing device for an oil well according to any one of claims 1 to 7, the method comprising: Step 1: Install an overflow prevention cylinder at the wellhead, and build a platform and a hanger on the upper side of the overflow prevention cylinder; Step 2: Connect the tie-back plug to the lower end of the outer tube body, and lower the tie-back plug into the wellbore together with the outer tube body until the tie-back plug sits on the tie-back tube; Step 3: lift the outer tube body by a certain distance, so that a gap connecting the tie-back tube and the outer annulus is formed between the tie-back plug and the tie-back tube in the vertical direction; Step 4: inject cementing mud into the outer tube body, and the cementing mud will flow to the outer annulus through the outer tube body, the connecting hole, the tie-back tube and the gap in sequence, and then return to the wellhead through the outer annulus. At this time, the outer annulus is filled with cementing mud; Step 5: inserting the inner tube into the outer tube until the inner tube is inserted into the return tube; Step 6: lower the outer tube body until the tie-back plug is seated on the tie-back tube again, cutting off the connection between the tie-back tube and the outer annulus; Step 7: Open a first connecting hole and a second connecting hole on the side wall of the overflow prevention tube and the outer tube body and connect the guide pipe and the vibrating screen; Step 8: close the blowout preventer and inject drilling fluid into the inner pipe body until all the cementing mud in the outer pipe body and the inner pipe body is discharged from the inner annulus and the guide pipe; Step nine: lift the inner tube body out of the outer tube body and wait for the cementing mud in the outer annulus to solidify.

9. The tie-back cementing method according to claim 8, characterized in that: In step 2, after the return plug is seated in the return tube, gas is introduced into the outer tube body to perform seal verification.

10. The tie-back cementing method according to claim 8, characterized in that: In step three, the outer tube is lifted up by a distance of 20-40 cm.