Alternating current and direct current power grid expansion planning method and device considering new energy bearing capacity

The robust expansion planning model constructed through the DDPG algorithm solves the impact of uncertainty in new energy output on AC and DC grid planning, improves the flexibility and reliability of the power grid, and ensures that the extremes and errors can be effectively dealt with after the access of new energy. Scene.

CN119026941APending Publication Date: 2024-11-26STATE GRID SICHUAN ELECTRIC POWER CORP ELECTRIC POWER RES INST +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411078021.5
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-07
Publication Date
2024-11-26

AI Technical Summary

Technical Problem

The existing technology fails to effectively consider the impact of uncertainty in new energy output on the expansion planning of AC and DC power grids, resulting in the planned power grid operating unreliable in extreme and error scenarios.

Method used

Using a robust expansion planning method based on DDPG algorithm, the robust expansion of AC and DC power grid is constructed by calculating the average interval normalized risk indicators and comprehensive equivalent cost indicators of bus voltage, combined with line construction decision variables and new energy output fluctuations. Plan the model and optimize the line construction plan of the AC and DC power grid to cope with the extreme and error scenarios of new energy output.

Benefits of technology

It improves the flexibility, economy and reliability of the AC and DC power grid after new energy access, ensuring the stable operation of the power grid in extreme and error scenarios, and meeting actual operation needs.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119026941A_ABST
    Figure CN119026941A_ABST
Patent Text Reader

Abstract

The invention discloses an alternating current and direct current power grid expansion planning method and device considering new energy bearing capacity, and relates to the field of power grid expansion planning, and the method is characterized in that an average interval normalization risk index and a comprehensive equivalent cost index are multiplied, and the sum value of the multiplication result and the comprehensive equivalent cost index is minimum; the function serves as a first objective function of AC-DC power grid planning; minimizing a line construction decision variable, an operation variable and a new energy output fluctuation quantity during AC / DC power grid planning as a second objective function of AC / DC power grid planning; determining a first constraint condition of the second objective function; according to the first objective function, the second objective function and the first constraint condition, establishing an AC / DC power grid robust extension planning model; and under a first constraint condition, a DDPG algorithm is called to solve the AC / DC power grid robust extension planning model, and an extension planning scheme of AC / DC power grid line construction considering new energy output is obtained.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the field of power grid expansion planning, and more specifically, it relates to an AC / DC power grid expansion planning method and device taking into account the new energy carrying capacity. Background Art

[0002] Traditional transmission planning is based on deterministic information and does not take into account the uncertainty of renewable energy output, resulting in insufficient ability of the planned AC and DC power grid to cope with faults. Therefore, it is critical to deal with uncertainty in the power system. For the processing of uncertainty factors in power grid planning problems, existing technologies mainly use stochastic planning methods and robust planning methods. Stochastic planning simulates uncertainty, but the amount of calculation is large and the applicability is limited; robust planning is based on the worst scenario decision, does not require probability distribution, has high computational efficiency, and is therefore widely used.

[0003] AC / DC grid expansion planning is a high-dimensional nonlinear integer programming problem, which contains multiple deterministic or uncertain variables, multiple complex constraints, and the dimensions are usually high. As the complexity of the system structure increases, the difficulty of solving such planning problems increases accordingly. The main solutions include mathematical optimization and meta-heuristic optimization. Mathematical optimization algorithms show good accuracy and convergence in solving convex optimization problems, but for complex AC / DC grid planning, it may face problems of difficulty in solving and large amount of calculation. Meta-heuristic optimization algorithms are random search strategies generated based on the simulation of some natural phenomena and evolutionary principles (survival of the fittest) in nature, such as genetic algorithms, which have good adaptability, but may have unstable convergence and easy to fall into local optimal problems.

[0004] Therefore, how to consider the impact of the uncertainty of renewable energy output on the AC / DC grid expansion planning process is an urgent issue that needs to be addressed. Summary of the invention

[0005] The purpose of this application is to provide an AC / DC power grid expansion planning method and device that takes into account the renewable energy carrying capacity, which solves the problem that the prior art does not take into account the impact of the uncertainty of renewable energy output on the AC / DC power grid expansion planning process, resulting in the planned AC / DC power grid being unable to effectively cope with extreme scenarios and error scenarios of renewable energy output, thereby reducing the reliability of AC / DC power grid operation.

[0006] In a first aspect of the present application, a method for AC / DC power grid expansion planning considering new energy carrying capacity is provided, the method comprising:

[0007] According to the bus voltage of the AC and DC power grids, the average interval normalized risk index of the bus voltage is calculated;

[0008] The annual equivalent line construction investment cost index, operation and maintenance cost index, network loss cost index and reliability cost index of the AC and DC power grid are summed to obtain the comprehensive equivalent cost index of the AC and DC power grid;

[0009] The average interval normalized risk index and the comprehensive equivalent cost index are multiplied, and the sum of the multiplication result and the comprehensive equivalent cost index is minimized as the first objective function of AC and DC power grid planning;

[0010] The minimization of the line construction decision variables, operation variables and the fluctuation of renewable energy output in AC and DC power grid planning is used as the second objective function of AC and DC power grid planning.

[0011] Determine a first constraint condition of the second objective function; wherein the first constraint condition includes an operation constraint of an AC / DC power grid connected to the output of renewable energy, a construction constraint of a transmission line, and an operation constraint affected by the output of renewable energy;

[0012] Establishing a robust expansion planning model for AC and DC power grids according to the first objective function, the second objective function and the first constraint condition;

[0013] Under the first constraint, the DDPG algorithm is called to solve the robust expansion planning model of AC and DC power grids, and an expansion planning scheme for the construction of AC and DC power grid lines considering the output of renewable energy is obtained.

[0014] In one implementation, the method further includes:

[0015] Obtain multiple extreme scenario sets of new energy output, where each extreme scenario set corresponds to a maximum output of a new energy;

[0016] The first constraint condition is optimized according to the maximum output of the new energy corresponding to each extreme scenario set to obtain the second constraint condition; wherein the second constraint condition includes the operation constraint of the AC and DC power grids when the new energy has the maximum output, the construction constraint of the transmission line, and the operation constraint affected by the maximum output of the new energy;

[0017] Establishing a robust expansion planning model for AC and DC power grids according to a first objective function, a second objective function and a second constraint condition;

[0018] Under the second constraint, the DDPG algorithm is called to solve the robust expansion planning model of AC and DC power grids, and an expansion planning scheme for AC and DC power grid line construction considering the maximum output of new energy is obtained.

[0019] In one implementation, the operation constraints of the AC and DC power grids, the construction constraints of the transmission lines, and the operation constraints of the maximum output impact of new energy sources are all linear functions.

[0020] In one implementation, the reliability cost index is determined in the following manner: a sum of a wind abandonment cost index and a load shedding cost index of a busbar of an AC / DC power grid is used as the reliability cost index.

[0021] In one implementation, the reliability cost indicator is expressed as:

[0022] Among them, K W is the unit wind curtailment cost; P W,i With P EENS ,i are the abandoned air volume and load shedding volume at busbar i, K EENS is the cost per unit of expected power shortage.

[0023] In one implementation, the average interval normalized risk index of the bus voltage is determined by: determining the interval normalized risk index of the bus at the ith location;

[0024] According to the sum of the number of generators and lines, the total number of buses in the AC and DC power grids and the interval normalized risk index, the average interval normalized risk index of the bus voltage is calculated.

[0025] In a second aspect of the present application, there is provided an AC / DC power grid expansion planning device considering the new energy carrying capacity, the device comprising:

[0026] An index calculation module, used to calculate an average interval normalized risk index of the bus voltage according to the bus voltage of the AC and DC power grids;

[0027] A cost index calculation module is used to sum up the annual equivalent line construction investment cost index, operation and maintenance cost index, network loss cost index and reliability cost index of the AC and DC power grid to obtain a comprehensive equivalent cost index of the AC and DC power grid;

[0028] A first objective function construction module is used to multiply the average interval normalized risk index and the comprehensive equivalent cost index, and minimize the sum of the multiplication result and the comprehensive equivalent cost index as the first objective function of AC and DC power grid planning;

[0029] The second objective function construction module is used to minimize the line construction decision variables, operation variables and new energy output fluctuation variables during AC and DC power grid planning as the second objective function of AC and DC power grid planning;

[0030] A constraint determination module is used to determine a first constraint of the second objective function; wherein the first constraint includes an operation constraint of an AC / DC power grid connected to a renewable energy output, a construction constraint of a transmission line, and an operation constraint affected by renewable energy output;

[0031] A model building module, used to establish an AC / DC power grid robust expansion planning model according to the first objective function, the second objective function and the first constraint condition;

[0032] The solution module is used to call the DDPG algorithm to solve the robust expansion planning model of the AC and DC power grid under the first constraint condition, and obtain an expansion planning scheme for the construction of AC and DC power grid lines considering the output of new energy.

[0033] In one implementation, the device further includes:

[0034] A scenario acquisition module is used to acquire multiple extreme scenario sets of new energy output, where each extreme scenario set corresponds to a maximum output of a new energy;

[0035] An optimization module is used to optimize the first constraint condition according to the maximum output of the new energy corresponding to each extreme scenario set to obtain a second constraint condition; wherein the second constraint condition includes the operation constraint of the AC and DC power grids when the new energy has the maximum output, the construction constraint of the transmission line, and the operation constraint affected by the maximum output of the new energy;

[0036] The model building module is also used to establish an AC / DC power grid robust expansion planning model according to the first objective function, the second objective function and the second constraint condition;

[0037] The solution module is also used to call the DDPG algorithm to solve the robust expansion planning model of the AC and DC power grid under the second constraint condition, and obtain an expansion planning scheme for the construction of AC and DC power grid lines when considering the maximum output of new energy.

[0038] In one implementation, the operation constraints of the AC and DC power grids, the construction constraints of the transmission lines, and the operation constraints of the maximum output impact of new energy sources are all linear functions.

[0039] In one implementation, the sum of the wind abandonment cost index and the load shedding cost index of the busbar of the AC / DC power grid is used as the reliability cost index.

[0040] Compared with the prior art, this application has the following beneficial effects:

[0041] 1. In the AC / DC power grid expansion planning method considering the new energy carrying capacity provided in the present application, first, the average interval normalized risk index of the bus voltage is calculated according to the bus voltage of the AC / DC power grid, and the flexibility in the AC / DC power grid expansion planning process is considered. Secondly, the annual equivalent line construction investment cost index, operation and maintenance cost index, network loss cost index and reliability cost index of the AC / DC power grid are summed to obtain the comprehensive equivalent cost index of the AC / DC power grid, which is used to analyze the economy in the AC / DC power grid expansion planning process. Therefore, the first objective function obtained based on the average interval normalized risk index and the comprehensive equivalent cost index takes into account the flexibility and economy of the AC / DC power grid expansion planning. Secondly, the minimization of line construction decision variables, operating variables and renewable energy output fluctuations during AC / DC power grid planning is used as the second objective function of AC / DC power grid planning. The error scenarios caused by the uncertainty of renewable energy output (such as different outputs of wind farms in different periods of time) are taken into account, thereby ensuring the reliability of AC / DC power grid operation in error scenarios. Therefore, the robust expansion planning model of AC / DC power grid constructed by combining the first objective function and the second objective function takes into account the flexibility, economy and reliability of the expansion planning process of AC / DC power grid, so that the expansion planning scheme obtained is more in line with the actual operation of AC / DC power grids with renewable energy access.

[0042] 2. In the AC / DC power grid expansion planning method considering the new energy carrying capacity provided in the present application, the minimization of the line construction decision variables, operating variables and the maximum output of new energy during AC / DC power grid planning is also considered as the second objective function of AC / DC power grid planning. The extreme scenarios brought about by the uncertainty of new energy output (such as the maximum output of wind farms) are considered, thereby ensuring the reliability of the operation of AC / DC power grids under extreme scenarios. Therefore, the robust expansion planning model of AC / DC power grids constructed by combining the first objective function and the third objective function takes into account the flexibility, economy and reliability in the expansion planning process of AC / DC power grids, so that the resulting expansion planning scheme is more in line with the actual operation of AC / DC power grids with new energy access. BRIEF DESCRIPTION OF THE DRAWINGS

[0043] The drawings described herein are used to provide a further understanding of the embodiments of the present application, constitute a part of the present application, and do not constitute a limitation on the embodiments of the present application. In the drawings:

[0044] Figure 1 A schematic flow chart of a method for AC / DC power grid expansion planning considering new energy carrying capacity provided in an embodiment of the present application;

[0045] Figure 2 An AC / DC power grid expansion planning architecture diagram based on the DDPG algorithm provided in an embodiment of the present application;

[0046] Figure 3 A schematic diagram of the scenario value space for the new energy output provided in the embodiment of the present application. DETAILED DESCRIPTION

[0047] In order to make the objectives, technical solutions and advantages of the present application more clearly understood, the present application is further described in detail below in conjunction with examples and drawings. The illustrative implementation scheme of the present application and its description are only used to explain the present application and are not intended to limit the present application.

[0048] It should be noted that the terms "include" or "may include" used in various embodiments of the present application indicate the presence of the function, operation or element applied for, and do not limit the addition of one or more functions, operations or elements. In addition, as used in various embodiments of the present application, the terms "include", "have" and their cognates are only intended to indicate specific features, numbers, steps, operations, elements, components or a combination of the foregoing items, and should not be understood as first excluding the presence of one or more other features, numbers, steps, operations, elements, components or a combination of the foregoing items or the possibility of adding one or more features, numbers, steps, operations, elements, components or a combination of the foregoing items.

[0049] In various embodiments of the present application, terms such as "first" and "second" are used for descriptive purposes only and should not be understood as indicating or implying relative importance or implicitly indicating the number of technical features indicated. Thus, a feature defined as "first" or "second" may explicitly or implicitly include one or more of the features. In the description of the present application, the meaning of "plurality" is two or more, unless otherwise clearly and specifically defined.

[0050] Please refer to Figure 1 , Figure 1 An AC / DC power grid expansion planning method considering new energy carrying capacity is provided in an embodiment of the present application, and the method includes:

[0051] S101, calculating an average interval normalized risk index of the bus voltage according to the bus voltage of the AC / DC power grid.

[0052] In this embodiment, the risk index ζ is normalized by the average interval of the bus voltage. ANRIV To evaluate the flexibility of the expansion planning scheme, specifically, the average interval normalized risk index of the bus voltage is determined in the following way: the interval normalized risk index of the bus at the ith location is determined; the average interval normalized risk index of the bus voltage is calculated based on the sum of the number of generators and lines, the total number of buses in the AC and DC power grids, and the interval normalized risk index.

[0053] The expression of the average interval normalized risk index is calculated as shown in formula (1): In the formula, ζ V,i,e is the interval normalized risk index at bus i, F is the sum of the number of generators and lines, and N is the total number of system buses. ANRIV The smaller the index is, the stronger the adaptability to power grid equipment outages is, and accordingly the better its flexibility is.

[0054] S102, summing up the annual equivalent line construction investment cost index, operation and maintenance cost index, network loss cost index and reliability cost index of the AC and DC power grid to obtain a comprehensive equivalent cost index of the AC and DC power grid.

[0055] In this embodiment, the interactive learning characteristics of the DDPG algorithm are utilized, the construction sequence of the lines is considered on the basis of the mixed integer programming model, and the economy, reliability, flexibility of the system, possible Nk failures, and the severity of equipment failures are comprehensively considered to construct a robust expansion planning model for AC and DC power grids that considers the uncertainty of new energy.

[0056] Therefore, this embodiment combines the annual equivalent line construction investment cost index C in , Operation and maintenance cost index C o , Network loss cost index C loss , convert the reliability indicator expected energy not supplied (EENS) into the reliability cost indicator C rel By solving the above four indicators, the comprehensive equivalent cost indicators of AC and DC power grids can be obtained.

[0057] S103, multiplying the average interval normalized risk index and the comprehensive equivalent cost index, minimizing the sum of the multiplication result and the comprehensive equivalent cost index as the first objective function of AC / DC power grid planning.

[0058] In this embodiment, the average interval normalized risk index and the comprehensive equivalent cost index calculated in steps S101 and S102 are combined, the average interval normalized risk index and the comprehensive equivalent cost index are multiplied, the sum of the multiplication result and the comprehensive equivalent cost index is minimized, and the expansion planning of the AC and DC power grid is performed with the minimum sum as the objective function, as shown in formula (2): min f(s τ )=(C in +C o +C loss +C rel )(1+ζ ANRIV ) (2)

[0059] The AC / DC grid expansion planning architecture diagram based on the DDPG algorithm is as follows: Figure 2As shown in the figure, the grid structure of AC and DC power grid is τ According to the construction status of the constructible line β l The action set A consists of all constructible lines. l is a binary variable, β l =1 means line l has been built, otherwise it has not been built. τ Rewards τ It is caused by action a τ The comprehensive equivalent cost of the new grid structure after execution is calculated, and then the action a is calculated according to the following formulas (3) and (4): τ Q value.

[0060]

[0061] Q eval (s τ ,a τ )←Q eval (s τ ,a τ )+α[Q max -Q eval (s τ ,a τ )] (4).

[0062] S104, minimizing the line construction decision variables, operation variables and new energy output fluctuation variables during AC and DC power grid planning is used as the second objective function of AC and DC power grid planning.

[0063] In this embodiment, due to the uncertainty caused by the access of new energy to the AC and DC power grid, before minimizing the line construction decision variables, operation variables and new energy output fluctuations during AC and DC power grid planning as the second objective function of the AC and DC power grid expansion planning, it is also necessary to determine the matrix form of the objective function and constraint conditions of the AC and DC power grid planning model after considering the uncertainty brought by the access of new energy, as shown in formula (5):

[0064] In formula (5), β represents the line construction decision variable during planning; γ represents the operating variables of the AC and DC power grid during planning, such as voltage, current, and generator active output; κ represents the output of new energy; w(β) is the construction constraint of the transmission line; g(γ,κ) and h(β,γ,κ) are the operating constraints of the system, including power flow constraints and generator output constraints. The uncertainty of new energy mainly affects the operating constraints. The operating constraints of the AC and DC power grid, the construction constraints of the transmission line, and the operating constraints affected by the maximum output of new energy are all linear functions, that is, w(β), g(γ,κ), and h(β,γ,κ) are all linear functions.

[0065] On the basis of formula (5), all the fluctuations of new energy output are used as error scenarios to determine the second objective function and the first constraint condition, as shown in formula (6):

[0066] In the formula, κ j is the jth new energy error scenario; γ j For the scene j The operating variables that can satisfy the constraints under the condition; t is the total number of error scenarios.

[0067] S105, determining a first constraint condition of the second objective function; wherein the first constraint condition includes an operation constraint of an AC / DC power grid connected to the output of renewable energy, a construction constraint of a transmission line, and an operation constraint affected by the output of renewable energy.

[0068] In this embodiment, combined with the above formula (6), it can be seen that the first constraint condition includes the operation constraint of the AC / DC power grid connected to the renewable energy output, the construction constraint of the transmission line, and the operation constraint affected by the renewable energy output.

[0069] S106: Establishing an AC / DC power grid robust expansion planning model according to the first objective function, the second objective function and the first constraint condition.

[0070] In this embodiment, by combining the second objective function and the first constraint condition contained in the above formula (6), and the first objective function shown in the above formula (2), a robust expansion planning model for the AC and DC power grids with respect to the fluctuation of the output of new energy after the access to new energy can be determined.

[0071] S107, under the first constraint condition, calling the DDPG algorithm to solve the AC / DC power grid robust expansion planning model, and obtaining an expansion planning scheme for the construction of AC / DC power grid lines taking into account the output of new energy.

[0072] In this embodiment, according to the iterative process of the reinforcement learning algorithm, the calculation of the comprehensive equivalent cost of the AC / DC power grid expansion planning model, the calculation of the action reward, and the interaction between the intelligent agent and the planning environment are considered, and a method for solving the expansion planning model of the AC / DC power grid considering the access of new energy sources based on the DDPG algorithm is proposed. This embodiment uses the DDPG algorithm to solve the robust expansion planning model of the AC / DC power grid, fully considering the construction sequence of the line, which greatly simplifies the solution process; at the same time, by using the two strategies of experience priority replay strategy and competitive deep valuation network, it ensures that the solution of large-scale AC / DC power grid planning can converge faster and more stably.

[0073] Secondly, the calculation of the comprehensive equivalent cost, the calculation of the action reward, and the interaction between the agent and the planning environment are conventional technical means of the DDPG algorithm, and this embodiment will not be elaborated on.

[0074] In summary of the embodiments described above, for the AC / DC power grid expansion planning method considering the new energy carrying capacity provided in the embodiments of the present application, the average interval normalized risk index of the bus voltage is first calculated based on the bus voltage of the AC / DC power grid, taking into account the flexibility in the AC / DC power grid expansion planning process. Secondly, the annual equivalent line construction investment cost index, operation and maintenance cost index, network loss cost index and reliability cost index of the AC / DC power grid are summed to obtain the comprehensive equivalent cost index of the AC / DC power grid, which is used to analyze the economy in the AC / DC power grid expansion planning process. Therefore, the first objective function obtained based on the average interval normalized risk index and the comprehensive equivalent cost index takes into account the flexibility and economy of the AC / DC power grid expansion planning. Secondly, the minimization of line construction decision variables, operating variables and renewable energy output fluctuations during AC / DC power grid planning is used as the second objective function of AC / DC power grid planning. The error scenarios caused by the uncertainty of renewable energy output (such as different outputs of wind farms in different periods of time) are taken into account, thereby ensuring the reliability of AC / DC power grid operation in error scenarios. Therefore, the robust expansion planning model of AC / DC power grid constructed by combining the first objective function and the second objective function takes into account the flexibility, economy and reliability of the expansion planning process of AC / DC power grid, so that the expansion planning scheme obtained is more in line with the actual operation of AC / DC power grids with renewable energy access.

[0075] In some embodiments, based on the second objective function of the model constructed under the condition of fluctuation of new energy output, the expansion planning scheme under the new energy extreme scenario set is also considered. In other words, when the new energy output is at its maximum, the expansion planning scheme can complete the stable operation of the supply and shortage of electricity when the new energy output is at its maximum. Therefore, the method also includes: obtaining multiple extreme scenario sets of new energy output, wherein each extreme scenario set corresponds to a new energy maximum output; optimizing the first constraint condition according to the maximum output of new energy corresponding to each extreme scenario set to obtain the second constraint condition; wherein the second constraint condition includes the operation constraint of the AC and DC power grid when the new energy output is at its maximum, the construction constraint of the transmission line, and the operation constraint affected by the maximum output of the new energy; establishing an AC and DC power grid robust expansion planning model according to the first objective function, the second objective function, and the second constraint condition; under the second constraint condition, calling the DDPG algorithm to solve the AC and DC power grid robust expansion planning model, and obtaining an expansion planning scheme considering the construction of AC and DC power grid lines when the new energy output is at its maximum.

[0076] In this embodiment, the extreme scenario set is completely representative of all scenarios in the value space. When the active outputs of all new energy fields in a scenario are fluctuation limit values, then it is an extreme scenario. Figure 3The value space of the two scenarios of new energy fields is given. For a certain line construction plan, the runtime parameters are adjusted to adapt it to the extreme scenario of new energy output and other new energy output scenarios.

[0077] Assume κ 1 ,κ 2 ,...,κ n are all extreme scenarios of renewable energy active output, respectively related to the runtime parameter γ 1 ,γ 2 ,...,γ n Correspondingly, n is the total number of extreme scenarios. For the constraints of the linear functions g(γ,κ) and h(β,γ,κ) at runtime, assume that they are:

[0078] Where B, C, D, E, and M are the coefficient matrices of constraint variables.

[0079] Due to κ 1 ,κ 2 ,...,κ n is all the extreme scenarios in the new energy output value space, then any new energy output error scenario κ in this space i can be represented by their linear combination, that is, we can find a set of real numbers t that are not all zero. 1 ,t 2 ,...,t n , where t i ∈[0,1], such that:

[0080] From this we can see that for any i∈[1,n], we have:

[0081]

[0082] therefore,

[0083]

[0084] Therefore, the model of formula (6) can be transformed into:

[0085] When performing robust planning, the operating constraints under the output limit scenarios of each renewable energy field are taken into account to obtain the objective function f for extended planning. final , the expression is as follows: Where, k is the number of extreme scenarios for the output of new energy fields; f i (s τ) is the comprehensive equivalent cost index of the extended planning scheme under the i-th extreme scenario.

[0086] Considering the uncertainty of new energy and the problem of wind abandonment. Reliability cost C rel The wind curtailment cost needs to be added and determined in the following way: the sum of the wind curtailment cost index and the load shedding cost index of the busbar of the AC and DC power grid is used as the reliability cost index. The expression of the reliability cost index is: Among them, K W is the unit wind curtailment cost; P W,i With P EENS,i are the wind abandonment and load shedding at busbar i, respectively, K EENS is the cost per unit of expected power shortage.

[0087] Normalized risk index of voltage interval ζ V,i The additional weight of makes the voltage at the bus with load and new energy units account for a larger proportion in the index. The expression is as follows:

[0088]

[0089] Add wind abandonment constraints to AC and DC grid operation constraints:

[0090] Define a new reward function to evaluate the optimization effect of this action on the grid structure. At the same time, this item will account for a larger proportion of the reward for the line deletion action, so as to better judge whether the line needs to be deleted. τ The specific expression of the reward function is as follows: Where: 1 With λ 2 is the weight coefficient, when action a τ When the line is deleted, λ 1 =0.2,λ 2 =0.8, when action a τ When the line is established, λ 1 =λ 2 =0.5; f base is the base cost; f final (s τ ) is the grid structure s τ The objective function value of .

[0091] Based on the embodiments described above, the minimization of the line construction decision variables, operation variables and maximum output of new energy during AC / DC power grid planning is also considered as the second objective function of AC / DC power grid planning. The extreme scenarios (such as the maximum output of wind farms) caused by the uncertainty of new energy output are considered, thereby ensuring the reliability of the operation of AC / DC power grids under extreme scenarios. Therefore, the robust expansion planning model of AC / DC power grids constructed by combining the first objective function and the third objective function takes into account the flexibility, economy and reliability in the expansion planning process of AC / DC power grids, so that the expansion planning scheme obtained is more in line with the actual operation of AC / DC power grids with new energy access.

[0092] Secondly, this embodiment also performs simulations on the IEEE RTS24 system and the IEEE New England 39 system to analyze and verify the application of the DDPG algorithm to the AC / DC grid expansion planning model, its improvement effect and the improvement of the new energy consumption situation.

[0093] (1) IEEE RTS24 system

[0094] The Monte Carlo method is used to randomly generate scenarios to simulate one year of operation in order to compare and analyze the various indicators of the expansion planning scheme.

[0095] Table 1 Comparison of robust planning and traditional planning results of AC and DC power grids in IEEE RTS24 system

[0096]

[0097] (2) IEEE New England 39 system

[0098] Table 2 Comparison of robust planning and traditional planning results of IEEE New England 39 system AC / DC power grid

[0099]

[0100]

[0101] The embodiment of the present application also provides an AC / DC power grid expansion planning device considering the new energy carrying capacity, which can be used to execute each step of the AC / DC power grid expansion planning method considering the new energy carrying capacity described in the above embodiment of the present invention. The device includes:

[0102] The index calculation module 410 is used to calculate the average interval normalized risk index of the bus voltage according to the bus voltage of the AC and DC power grids;

[0103] The cost index calculation module 410 is used to sum the annual equivalent line construction investment cost index, operation and maintenance cost index, network loss cost index and reliability cost index of the AC and DC power grid to obtain a comprehensive equivalent cost index of the AC and DC power grid;

[0104] A first objective function construction module 420 is used to multiply the average interval normalized risk index and the comprehensive equivalent cost index, and minimize the sum of the multiplication result and the comprehensive equivalent cost index as the first objective function of AC and DC power grid planning;

[0105] The second objective function construction module 430 is used to minimize the line construction decision variables, operation variables and new energy output fluctuation variables during AC and DC power grid planning as the second objective function of AC and DC power grid planning;

[0106] The constraint determination module 440 is used to determine the first constraint of the second objective function; wherein the first constraint includes the operation constraint of the AC and DC power grid connected to the new energy output, the construction constraint of the transmission line, and the operation constraint affected by the new energy output;

[0107] A model building module 450 is used to establish an AC / DC power grid robust expansion planning model according to the first objective function, the second objective function and the first constraint condition;

[0108] The solution module 460 is used to call the DDPG algorithm to solve the AC / DC power grid robust expansion planning model under the first constraint condition, and obtain an expansion planning scheme for the AC / DC power grid line construction considering the output of new energy.

[0109] An AC / DC power grid expansion planning device considering the new energy carrying capacity in the embodiment of the present application is similar to the above Figure 1 The AC / DC power grid expansion planning method considering the new energy carrying capacity shown is an invention based on the same concept. Through the detailed description of the AC / DC power grid expansion planning method considering the new energy carrying capacity provided in the above embodiment, technical personnel in this field can clearly understand the implementation process of the AC / DC power grid expansion planning device considering the new energy carrying capacity in this embodiment, so for the sake of brevity of the specification, it will not be repeated here.

[0110] It can be seen that for the AC / DC power grid expansion planning device considering the new energy carrying capacity provided in the embodiment of the present application, it first calculates the average interval normalized risk index of the bus voltage based on the bus voltage of the AC / DC power grid, taking into account the flexibility in the AC / DC power grid expansion planning process. Secondly, the annual equivalent line construction investment cost index, operation and maintenance cost index, network loss cost index and reliability cost index of the AC / DC power grid are summed to obtain the comprehensive equivalent cost index of the AC / DC power grid, which is used to analyze the economy in the AC / DC power grid expansion planning process. Therefore, the first objective function obtained based on the average interval normalized risk index and the comprehensive equivalent cost index takes into account the flexibility and economy of the AC / DC power grid expansion planning. Secondly, the minimization of line construction decision variables, operating variables and renewable energy output fluctuations during AC / DC power grid planning is used as the second objective function of AC / DC power grid planning. The error scenarios caused by the uncertainty of renewable energy output (such as different outputs of wind farms in different periods of time) are taken into account, thereby ensuring the reliability of AC / DC power grid operation in error scenarios. Therefore, the robust expansion planning model of AC / DC power grid constructed by combining the first objective function and the second objective function takes into account the flexibility, economy and reliability of the expansion planning process of AC / DC power grid, so that the expansion planning scheme obtained is more in line with the actual operation of AC / DC power grids with renewable energy access.

[0111] In some embodiments, the device also includes: a scenario acquisition module, which is used to obtain multiple extreme scenario sets of new energy output, wherein each extreme scenario set corresponds to a maximum output of a new energy; an optimization module, which is used to optimize the first constraint condition according to the maximum output of the new energy corresponding to each extreme scenario set to obtain a second constraint condition; wherein the second constraint condition includes the operating constraints of the AC and DC power grids when the new energy has maximum output, the construction constraints of the transmission lines, and the operating constraints affected by the maximum output of the new energy; the model construction module is also used to establish an AC and DC power grid robust expansion planning model according to the first objective function, the second objective function and the second constraint condition; the solution module is also used to call the DDPG algorithm to solve the AC and DC power grid robust expansion planning model under the second constraint condition, and obtain an expansion planning scheme for the construction of AC and DC power grid lines considering the maximum output of new energy.

[0112] In some embodiments, the operation constraints of the AC and DC power grids, the construction constraints of the transmission lines, and the operation constraints of the maximum output impact of new energy sources are all linear functions.

[0113] In some embodiments, the sum of the wind abandonment cost index and the load shedding cost index of the busbar of the AC / DC power grid is used as the reliability cost index.

[0114] The specific implementation methods described above further illustrate the purpose, technical solutions and beneficial effects of the present application in detail. It should be understood that the above description is only the specific implementation method of the present application and is not intended to limit the scope of protection of the present application. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the present application should be included in the scope of protection of the present application.

Claims

1. A method for planning the expansion of an AC / DC power grid considering the carrying capacity of new energy sources, characterized in that: include: According to the bus voltage of the AC and DC power grids, the average interval normalized risk index of the bus voltage is calculated; The annual equivalent line construction investment cost index, operation and maintenance cost index, network loss cost index and reliability cost index of the AC and DC power grid are summed to obtain the comprehensive equivalent cost index of the AC and DC power grid; The average interval normalized risk index and the comprehensive equivalent cost index are multiplied, and the sum of the multiplication result and the comprehensive equivalent cost index is minimized as the first objective function of AC and DC power grid planning; The minimization of the line construction decision variables, operation variables and the fluctuation of renewable energy output in AC and DC power grid planning is used as the second objective function of AC and DC power grid planning. Determine a first constraint condition of the second objective function; wherein the first constraint condition includes an operation constraint of an AC / DC power grid connected to the output of renewable energy, a construction constraint of a transmission line, and an operation constraint affected by the output of renewable energy; Establishing a robust expansion planning model for AC and DC power grids according to the first objective function, the second objective function and the first constraint condition; Under the first constraint, the DDPG algorithm is called to solve the robust expansion planning model of AC and DC power grids, and an expansion planning scheme for the construction of AC and DC power grid lines considering the output of renewable energy is obtained.

2. The method according to claim 1, characterized in that The method further comprises: Obtain multiple extreme scenario sets of new energy output, where each extreme scenario set corresponds to a maximum output of a new energy; The first constraint condition is optimized according to the maximum output of the new energy corresponding to each extreme scenario set to obtain the second constraint condition; wherein the second constraint condition includes the operation constraint of the AC and DC power grids when the new energy has the maximum output, the construction constraint of the transmission line, and the operation constraint affected by the maximum output of the new energy; Establishing a robust expansion planning model for AC and DC power grids according to a first objective function, a second objective function and a second constraint condition; Under the second constraint, the DDPG algorithm is called to solve the robust expansion planning model of AC and DC power grids, and an expansion planning scheme for AC and DC power grid line construction considering the maximum output of new energy is obtained.

3. The method according to claim 2, characterized in that The operation constraints of the AC and DC power grids, the construction constraints of the transmission lines, and the operation constraints of the maximum output impact of new energy are all linear functions.

4. The method according to claim 1, characterized in that: The reliability cost index is determined in the following manner: the sum of the wind abandonment cost index and the load shedding cost index of the busbar of the AC / DC power grid is used as the reliability cost index.

5. The method according to claim 4, characterized in that The expression of the reliability cost index is: Among them, K W is the unit wind curtailment cost; P W,i With P EENS,i are the wind abandonment and load shedding at busbar i, respectively, K EENS is the cost per unit of expected power shortage.

6. The method according to claim 1, characterized in that The average interval normalized risk index of the bus voltage is determined by: determining the interval normalized risk index of the bus at the i-th location; According to the sum of the number of generators and lines, the total number of buses in the AC and DC power grids and the interval normalized risk index, the average interval normalized risk index of the bus voltage is calculated.

7. An AC / DC power grid expansion planning device considering new energy carrying capacity, characterized in that: The device includes: An index calculation module, used to calculate an average interval normalized risk index of the bus voltage according to the bus voltage of the AC and DC power grids; A cost index calculation module is used to sum up the annual equivalent line construction investment cost index, operation and maintenance cost index, network loss cost index and reliability cost index of the AC and DC power grid to obtain a comprehensive equivalent cost index of the AC and DC power grid; A first objective function construction module is used to multiply the average interval normalized risk index and the comprehensive equivalent cost index, and minimize the sum of the multiplication result and the comprehensive equivalent cost index as the first objective function of AC and DC power grid planning; The second objective function construction module is used to minimize the line construction decision variables, operation variables and new energy output fluctuation variables during AC and DC power grid planning as the second objective function of AC and DC power grid planning; A constraint determination module is used to determine a first constraint of the second objective function; wherein the first constraint includes an operation constraint of an AC / DC power grid connected to a renewable energy output, a construction constraint of a transmission line, and an operation constraint affected by renewable energy output; A model building module, used to establish an AC / DC power grid robust expansion planning model according to the first objective function, the second objective function and the first constraint condition; The solution module is used to call the DDPG algorithm to solve the robust expansion planning model of the AC and DC power grid under the first constraint condition, and obtain an expansion planning scheme for the construction of AC and DC power grid lines considering the output of new energy.

8. The device according to claim 7, characterized in that The device also includes: A scenario acquisition module is used to acquire multiple extreme scenario sets of new energy output, where each extreme scenario set corresponds to a maximum output of a new energy; An optimization module is used to optimize the first constraint condition according to the maximum output of the new energy corresponding to each extreme scenario set to obtain a second constraint condition; wherein the second constraint condition includes the operation constraint of the AC and DC power grids when the new energy has the maximum output, the construction constraint of the transmission line, and the operation constraint affected by the maximum output of the new energy; The model building module is also used to establish an AC / DC power grid robust expansion planning model according to the first objective function, the second objective function and the second constraint condition; The solution module is also used to call the DDPG algorithm to solve the robust expansion planning model of the AC and DC power grid under the second constraint condition, and obtain an expansion planning scheme for the construction of AC and DC power grid lines when considering the maximum output of new energy.

9. The device according to claim 8, characterized in that The operation constraints of the AC and DC power grids, the construction constraints of the transmission lines, and the operation constraints of the maximum output impact of new energy are all linear functions.

10. The device according to claim 7, characterized in that The sum of the wind abandonment cost index and the load shedding cost index of the busbar of the AC / DC power grid is used as the reliability cost index.