Monitoring and early warning system for electrical operation of power plant
By designing an electrical operation monitoring and early warning system in the power plant, monitoring and reminding operators in real time, the safety risk of operators entering the wrong compartment in the power plant is solved, and the effect of improving the safety of electrical operation is achieved.
Patent Information
- Application Number
- CN202410828149.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-06-25
- Publication Date
- 2024-12-03
- Estimated Expiration
- Not applicable · inactive patent
AI Technical Summary
In power plants, operators are prone to going into the wrong compartment due to the parallel operation and cross-work of units, which increases personal and equipment safety risks.
A monitoring and early warning system for electrical operations of power plants was designed. By adding early warning units and monitoring units, the position parameters and activity trajectories of operators are collected in real time, and the early warning evaluation value is generated based on the preset evaluation model, and the primary and secondary monitoring structures are established. Provide reminders and warnings to prevent misoperation.
It effectively reduces the probability of operators misoperation, improves the safety of electrical operations in the power plant, and protects personal and equipment safety.
Smart Images

Figure CN119068625A_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the technical field of electrical operation, and in particular to a monitoring and early warning system for electrical operation of a power plant. Background Art
[0002] At present, with the development of the electricity market, the demand for electricity is gradually increasing, the installed capacity of power plants is getting larger and larger, and the parallel operation of multiple units in a single power plant has gradually become the mainstream. The units are adjacent to each other, the distribution rooms are very close, different units share a distribution room, and the distribution cabinets of different units are more and more directly adjacent to each other in the same room.
[0003] Operators often work at the same time, which inevitably increases the chances of erroneous operation such as going to the wrong interval during electrical operations, leading to unsafe incidents that affect personal safety and equipment safety. Summary of the invention
[0004] The purpose of this application is: to solve the above-mentioned technical problems, this application provides a monitoring and early warning system for electrical operations of power plants, aiming to improve the safety of electrical operations of power plants and effectively prevent walking into the wrong compartment.
[0005] In some embodiments of the present application, an early warning unit and a monitoring unit are additionally provided, and an early warning evaluation value is generated for each distribution room according to a preset evaluation model. Based on all the early warning evaluation values, corresponding first-level monitoring structures and second-level monitoring structures are established to provide operation reminders for all distribution rooms and the distribution cabinets of each unit inside them, so as to prevent operators from going into the wrong intervals and making erroneous operations, thereby protecting personal and equipment safety.
[0006] In some embodiments of the present application, an early warning unit and a monitoring unit are used to collect the position parameter operation images of the operator in real time, monitor the activity trajectory of the operator in real time, and issue early warnings for possible abnormal operations in a timely manner to ensure the accuracy of the operator's operating behavior, reduce the probability of misoperation, and protect personal and equipment safety.
[0007] In some embodiments of the present application, a monitoring and early warning system for electrical operation of a power plant is provided, comprising:
[0008] The central control unit is used to establish an electronic monitoring map based on the parameters of all power distribution rooms in the plant area;
[0009] A monitoring unit, comprising a plurality of sub-monitoring modules, wherein the sub-monitoring modules are arranged in the power distribution room and are used to collect image data in the power distribution room;
[0010] An early warning unit, comprising a plurality of early warning units, wherein the early warning units are arranged in a power distribution room;
[0011] A single warning unit includes a primary warning module and multiple secondary warning modules. The primary warning module is arranged at the door of the power distribution room, and the secondary warning module is arranged on the door of the power distribution cabinet of the unit.
[0012] A terminal unit, comprising a plurality of terminal submodules, wherein the terminal submodules are used to receive task instructions;
[0013] The central control unit comprises:
[0014] The first processing module is used for electronic monitoring maps and generating early warning evaluation values for each power distribution room;
[0015] The first control module is used to set the working parameters of each warning unit according to all the warning evaluation values.
[0016] In some embodiments of the present application, the central control unit further includes:
[0017] The second processing module is used to generate task instructions according to the operation requirements and send the task instructions to the corresponding terminal submodule;
[0018] A third processing module is used to generate an expected activity trajectory according to the task instruction;
[0019] The personnel management module is used to obtain all personnel identity information and establish a personnel database;
[0020] The personnel management module is also used to generate a work evaluation value for each person based on all operation records.
[0021] In some embodiments of the present application, the first processing module is further used to:
[0022] Establish a distribution room array A, A = (a1, a2...an), where ai is the i-th distribution room and n is the number of distribution rooms;
[0023] Establish a primary monitoring structure based on all distribution room location parameters;
[0024] Select the target distribution room in sequence according to the distribution room sequence A;
[0025] Obtain the parameters of all the unit distribution cabinets in the target distribution room and establish a secondary monitoring structure for the target distribution room;
[0026] Generate the secondary monitoring structure of each power distribution room in turn;
[0027] Generate the association between the first-level monitoring structure and all the second-level monitoring structures;
[0028] Establish electronic monitoring maps.
[0029] In some embodiments of the present application, the first processing module is further used to:
[0030] Establish a distribution room array A, A = (a1, a2...an), where ai is the i-th distribution room and n is the number of distribution rooms;
[0031] Select the target distribution room in turn according to the distribution room sequence A, and generate the early warning evaluation value c of the target distribution room according to the preset evaluation model;
[0032]
[0033] Among them, e1 is the preset first weight coefficient; e2 is the preset second weight coefficient; bi is the reference value of the i-th equipment evaluation index; n1 is the number of equipment evaluation indicators, βi is the influencing factor of the i-th equipment evaluation index; di is the reference value of the i-th historical evaluation index; n2 is the number of historical evaluation indicators; αi is the influencing factor of the i-th historical evaluation index;
[0034] Generate the early warning evaluation values of all distribution rooms in sequence, and establish an early warning evaluation value sequence C, C = (c1, c2...cn), where ci is the i-th early warning evaluation value.
[0035] In some embodiments of the present application, the first control module is further used to:
[0036] Establish an early warning unit sequence F, F = (f1, f2...fn), where Fi is the early warning unit of the i-th distribution room, and n is the number of early warning units;
[0037] Preset a first warning evaluation value interval (C1, C2) and a second warning evaluation value interval (C2, C3);
[0038] If ci is in the first warning evaluation value interval, Fi is set to the first-level working mode;
[0039] If ci is in the second warning evaluation value interval, Fi is set to the second-level working mode.
[0040] In some embodiments of the present application, the third processing module is further used to:
[0041] Obtain the power distribution room to be operated and the power distribution cabinet of the unit to be operated according to the task instructions;
[0042] Generate expected activity trajectories and reminder instructions;
[0043] According to the reminder instruction, set the reminder parameters of the first-level warning module corresponding to the distribution room to be operated
[0044] According to the reminder instruction, set the reminder parameters of the secondary warning module corresponding to the power distribution cabinet of the unit to be operated;
[0045] Generate multiple feedback time nodes based on the expected activity trajectory;
[0046] The real-time data collected by the early warning unit and the monitoring unit are obtained according to the feedback time node to generate the actual activity trajectory;
[0047] Determine whether to generate warning instructions and operation records based on the actual activity trajectory and expected activity trajectory.
[0048] In some embodiments of the present application, the third processing module is further used to:
[0049] Establish progress evaluation model and position evaluation model;
[0050] Generate a real-time progress deviation evaluation value between the actual activity trajectory and the expected activity trajectory according to the progress evaluation model, and generate a progress warning instruction if the real-time progress deviation evaluation value is greater than a preset threshold;
[0051] According to the operation evaluation model and the actual activity trajectory, it is judged whether there is a position deviation. If there is a position deviation, an error operation warning instruction is generated.
[0052] In some embodiments of the present application, the personnel management module is also used to:
[0053] Based on the identity information of all personnel, establish a personnel identity label sequence G, G = (g1, g2...gm), where gi is the identity label of the i-th person; m is the number of personnel;
[0054] Generate the work evaluation value of each person in turn according to the preset operation evaluation model, and establish a work evaluation value sequence H, H = (h1, h2...hm), where hi is the work evaluation value of the i-th person;
[0055] Preset work evaluation value threshold h';
[0056] If hi<h', generate a stop work order for the i-th person.
[0057] In some embodiments of the present application, when generating the work evaluation value of each person, it includes:
[0058] The personnel identity label sequence G selects the target personnel to be evaluated in turn;
[0059] Generate the work evaluation value h of the target person to be evaluated according to the operation evaluation model;
[0060]
[0061] Among them, e3 is the preset third fixed coefficient, e4 is the preset fourth fixed coefficient, and e5 is the preset fifth fixed coefficient; m1 is the operation record of the target person to be evaluated; pi is the operation evaluation value of the i-th operation record of the target person to be evaluated; △p is the average value of all operation evaluation values, and m2 is the number of operation records in which the wrong unit distribution cabinet is selected;
[0062] Generate the work evaluation value of each person in turn.
[0063] Compared with the prior art, the monitoring and early warning system for electrical operation of a power plant in the embodiment of the present application has the following beneficial effects:
[0064] An early warning unit and a monitoring unit have been added, and an early warning evaluation value for each distribution room is generated according to the preset evaluation model. Based on all the early warning evaluation values, corresponding first-level and second-level monitoring structures are established to provide operation reminders for all distribution rooms and the distribution cabinets of each unit inside them, to prevent operators from going into the wrong intervals and making erroneous operations, thereby protecting personal and equipment safety.
[0065] Through the early warning unit and monitoring unit, the operator's position parameter operation image is collected in real time, the operator's activity trajectory is monitored in real time, and early warnings are issued in time for possible abnormal operations, ensuring the accuracy of the operator's operating behavior, reducing the probability of misoperation, and protecting personal and equipment safety. BRIEF DESCRIPTION OF THE DRAWINGS
[0066] Figure 1 It is a structural diagram of a monitoring and early warning system for electrical operations of a power plant in a preferred embodiment of the present application. DETAILED DESCRIPTION
[0067] The specific implementation methods of the present application are further described in detail below in conjunction with the accompanying drawings and examples. The following examples are used to illustrate the present application but are not intended to limit the scope of the present application.
[0068] In the description of the present application, it should be understood that the terms "center", "up", "down", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom", "inside", "outside", etc., indicating orientations or positional relationships, are based on the orientations or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present application and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore should not be understood as a limitation on the present application.
[0069] The terms "first" and "second" are used for descriptive purposes only and should not be understood as indicating or implying relative importance or implicitly indicating the number of the indicated technical features. Thus, a feature defined as "first" or "second" may explicitly or implicitly include one or more of the features. In the description of this application, unless otherwise specified, "plurality" means two or more.
[0070] In the description of this application, it should be noted that, unless otherwise clearly specified and limited, the terms "installed", "connected", and "connected" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or it can be indirectly connected through an intermediate medium, or it can be the internal communication of two components. For ordinary technicians in this field, the specific meanings of the above terms in this application can be understood according to specific circumstances.
[0071] like Figure 1 As shown, a monitoring and early warning system for electrical operation of a power plant according to a preferred embodiment of the present application includes:
[0072] The central control unit is used to establish an electronic monitoring map based on the parameters of all power distribution rooms in the plant area;
[0073] A monitoring unit, comprising a plurality of sub-monitoring modules, wherein the sub-monitoring modules are arranged in the power distribution room and are used to collect image data in the power distribution room;
[0074] The early warning department includes a plurality of early warning units, and the early warning units are arranged in the power distribution room;
[0075] A single warning unit includes a first-level warning module and multiple second-level warning modules. The first-level warning module is set at the door of the power distribution room, and the second-level warning module is set on the door of the unit power distribution cabinet;
[0076] A terminal unit, comprising a plurality of terminal submodules, wherein the terminal submodules are used to receive task instructions;
[0077] The central control unit includes:
[0078] The first processing module is used for electronic monitoring maps and generating early warning evaluation values for each power distribution room;
[0079] The first control module is used to set the working parameters of each warning unit according to all the warning evaluation values.
[0080] Specifically, the central control unit also includes:
[0081] The second processing module is used to generate task instructions according to the operation requirements and send the task instructions to the corresponding terminal submodule;
[0082] A third processing module is used to generate an expected activity trajectory according to the task instruction;
[0083] The personnel management module is used to obtain all personnel identity information and establish a personnel database;
[0084] The personnel management module is also used to generate a work evaluation value for each person based on all operation records.
[0085] Specifically, the monitoring submodule is preferably a camera device. When an operator enters or leaves the power distribution room, the camera function is turned on through infrared sensing to record.
[0086] Specifically, the secondary warning module is preferably a cabinet door press-type reminder device, which is installed on the power distribution cabinet of each unit. When it detects that a person presses the cabinet door switch signal, it will immediately feedback the signal, and automatically remind the staff by voice about the unit to which the secondary distribution cabinet belongs and related information such as operating precautions.
[0087] Specifically, the terminal submodule is preferably a device terminal held by the operator, including but not limited to an intercom device, a mobile phone, a computer, etc. The terminal submodule is used to receive operation task instructions.
[0088] Specifically, the first-level warning module is preferably an induction-type door entry reminder device, which is installed at the entrance of each distribution room. When a signal of a person entering is detected, the device will automatically remind the staff of the unit location and the name of the distribution room, and issue a cautious operation warning according to the safety level.
[0089] In a preferred embodiment of the present application, the first processing module is also used for:
[0090] Establish a distribution room array A, A = (a1, a2...an), where ai is the i-th distribution room and n is the number of distribution rooms;
[0091] Establish a primary monitoring structure based on all distribution room location parameters;
[0092] Select the target distribution room in sequence according to the distribution room sequence A;
[0093] Obtain the parameters of all the unit distribution cabinets in the target distribution room and establish a secondary monitoring structure for the target distribution room;
[0094] Generate the secondary monitoring structure of each power distribution room in turn;
[0095] Generate the association between the first-level monitoring structure and all the second-level monitoring structures;
[0096] Establish electronic monitoring maps.
[0097] Specifically, the first-level monitoring structure is composed of a first-level warning module and a monitoring sub-module installed in each distribution room. Its main function is to prevent people from walking into the wrong distribution room compartment.
[0098] The secondary monitoring structure is composed of a secondary warning module installed on each unit distribution cabinet in a single distribution room and a camera equipment installed in the distribution room. It is mainly to prevent personnel from opening the wrong unit distribution cabinet and correct the operator's erroneous operation.
[0099] Specifically, the first processing module is also used for:
[0100] Establish a distribution room array A, A = (a1, a2...an), where ai is the i-th distribution room and n is the number of distribution rooms;
[0101] Select the target distribution room in turn according to the distribution room sequence A, and generate the early warning evaluation value c of the target distribution room according to the preset evaluation model;
[0102]
[0103] Among them, e1 is the preset first weight coefficient; e2 is the preset second weight coefficient; bi is the reference value of the i-th equipment evaluation index; n1 is the number of equipment evaluation indicators, βi is the influencing factor of the i-th equipment evaluation index; di is the reference value of the i-th historical evaluation index; n2 is the number of historical evaluation indicators; αi is the influencing factor of the i-th historical evaluation index;
[0104] Generate the early warning evaluation values of all distribution rooms in sequence, and establish an early warning evaluation value sequence C, C = (c1, c2...cn), where ci is the i-th early warning evaluation value.
[0105] Specifically, equipment evaluation indicators include but are not limited to the number of distribution cabinets in the distribution room, the type of distribution cabinets, the spacing distance between distribution cabinets, the degree of confusion between distribution cabinets, and other parameters.
[0106] Specifically, the historical evaluation indicators include parameters such as the number of erroneous operations in the current distribution room, the operation frequency in the distribution room, and the consequences of failures caused by erroneous operations.
[0107] Specifically, the larger the warning rating value, the greater the possibility of people mistakenly entering the distribution room and making incorrect operations. The sensitivity of the corresponding warning unit should be higher to prevent operators from entering the wrong interval and making incorrect operations, thereby protecting personal and equipment safety.
[0108] In the preferred embodiment of the present application, the first control module is also used for:
[0109] Establish an early warning unit sequence F, F = (f1, f2...fn), where Fi is the early warning unit of the i-th distribution room, and n is the number of early warning units;
[0110] Preset a first warning evaluation value interval (C1, C2) and a second warning evaluation value interval (C2, C3);
[0111] If ci is in the first warning evaluation value interval, Fi is set to the first-level working mode;
[0112] If ci is in the second warning evaluation value interval, Fi is set to the second-level working mode.
[0113] Specifically, the first-level working mode means that the early warning unit only gives sound reminders to prevent the operator from entering the wrong compartment. The second-level working mode means that the first-level early warning module and the second-level early warning module in the early warning unit ensure that the operator enters the correct compartment through light display guidance, sound reminders and password verification at the corresponding position.
[0114] Specifically, the third processing module is also used for:
[0115] Obtain the power distribution room to be operated and the power distribution cabinet of the unit to be operated according to the task instructions;
[0116] Generate expected activity trajectories and reminder instructions;
[0117] According to the reminder instruction, set the reminder parameters of the first-level warning module corresponding to the distribution room to be operated
[0118] According to the reminder instruction, set the reminder parameters of the secondary warning module corresponding to the power distribution cabinet of the unit to be operated;
[0119] Generate multiple feedback time nodes based on the expected activity trajectory;
[0120] The real-time data collected by the early warning unit and the monitoring unit are obtained according to the feedback time node to generate the actual activity trajectory;
[0121] Determine whether to generate warning instructions and operation records based on the actual activity trajectory and expected activity trajectory.
[0122] Specifically, the reminder parameters of the first-level warning module include playing the name of the distribution room, issuing cautious operation warnings based on the safety level, and setting specific light colors to complete the guidance.
[0123] The reminder parameters of the secondary warning module include automatically reminding the staff by voice about the unit to which the secondary distribution cabinet belongs and related information such as operating precautions, and setting parameters such as specific light colors to complete the guidance.
[0124] Specifically, the third processing module is also used for:
[0125] Establish progress evaluation model and position evaluation model;
[0126] Generate a real-time progress deviation evaluation value between the actual activity trajectory and the expected activity trajectory according to the progress evaluation model, and generate a progress warning instruction if the real-time progress deviation evaluation value is greater than a preset threshold;
[0127] According to the operation evaluation model and the actual activity trajectory, it is judged whether there is a position deviation. If there is a position deviation, an error operation warning instruction is generated.
[0128] Specifically, when the operator fails to arrive at the designated area on time to perform the operation, a progress warning instruction is generated to remind the operator to complete the operation task in time.
[0129] Specifically, when an operator appears at the wrong location node, an erroneous operation instruction is generated to remind the operator in time to avoid loss of personnel and equipment.
[0130] In a preferred embodiment of the present application, the personnel management module is also used to:
[0131] Based on the identity information of all personnel, establish a personnel identity label sequence G, G = (g1, g2...gm), where gi is the identity label of the i-th person; m is the number of personnel;
[0132] Generate the work evaluation value of each person in turn according to the preset operation evaluation model, and establish a work evaluation value sequence H, H = (h1, h2...hm), where hi is the work evaluation value of the i-th person;
[0133] Preset work evaluation value threshold h';
[0134] If hi<h', generate a stop work order for the i-th person.
[0135] Specifically, when generating the work evaluation value of each person, it includes:
[0136] The personnel identity label sequence G selects the target personnel to be evaluated in turn;
[0137] Generate the work evaluation value h of the target person to be evaluated according to the operation evaluation model;
[0138]
[0139] Among them, e3 is the preset third fixed coefficient, e4 is the preset fourth fixed coefficient, and e5 is the preset fifth fixed coefficient; m1 is the operation record of the target person to be evaluated; pi is the operation evaluation value of the i-th operation record of the target person to be evaluated; △ p is the average value of all operation evaluation values, and m2 is the number of operation records in which the wrong unit distribution cabinet is selected;
[0140] Generate the work evaluation value of each person in turn.
[0141] Specifically, in the above embodiment, an operation evaluation model is established to evaluate the historical operation records of each operator, and employees who frequently make operating errors are suspended for re-education, thereby improving the accuracy of operators in performing tasks and reducing the probability of wrong intervals and erroneous operations, thereby protecting personal and equipment safety.
[0142] According to the first concept of the present application, an early warning unit and a monitoring unit are added, and an early warning evaluation value is generated for each distribution room according to a preset evaluation model. Based on all the early warning evaluation values, corresponding first-level monitoring structures and second-level monitoring structures are established to provide operation reminders for all distribution rooms and the distribution cabinets of each unit inside them, so as to prevent operators from going into the wrong intervals and making erroneous operations, thereby protecting personal and equipment safety.
[0143] According to the second concept of the present application, through the early warning unit and the monitoring unit, the position parameter operation image of the operator is collected in real time, the operator's activity trajectory is monitored in real time, and early warnings are given in time for possible abnormal operations, thereby ensuring the accuracy of the operator's operating behavior, reducing the probability of misoperation, and protecting personal and equipment safety.
[0144] The above is only a preferred implementation of the present application. It should be pointed out that for ordinary technicians in this technical field, several improvements and substitutions can be made without departing from the technical principles of the present application. These improvements and substitutions should also be regarded as the scope of protection of the present application.
Claims
1. A monitoring and early warning system for electrical operation of a power plant, characterized in that: include: The central control unit is used to establish an electronic monitoring map based on the parameters of all power distribution rooms in the plant area; A monitoring unit, comprising a plurality of sub-monitoring modules, wherein the sub-monitoring modules are arranged in the power distribution room and are used to collect image data in the power distribution room; An early warning unit, comprising a plurality of early warning units, wherein the early warning units are arranged in a power distribution room; A single warning unit includes a primary warning module and multiple secondary warning modules. The primary warning module is arranged at the door of the power distribution room, and the secondary warning module is arranged on the door of the power distribution cabinet of the unit. A terminal unit, comprising a plurality of terminal submodules, wherein the terminal submodules are used to receive task instructions; The central control unit comprises: The first processing module is used for electronic monitoring maps and generating early warning evaluation values for each power distribution room; The first control module is used to set the working parameters of each warning unit according to all the warning evaluation values.
2. The monitoring and early warning system for electrical operation of a power plant according to claim 1, characterized in that: The central control unit also includes: The second processing module is used to generate task instructions according to the operation requirements and send the task instructions to the corresponding terminal submodule; A third processing module is used to generate an expected activity trajectory according to the task instruction; The personnel management module is used to obtain all personnel identity information and establish a personnel database; The personnel management module is also used to generate a work evaluation value for each person based on all operation records.
3. The monitoring and early warning system for electrical operation of a power plant according to claim 2, characterized in that: The first processing module is also used for: Establish a distribution room array A, A = (a1, a2...an), where ai is the i-th distribution room and n is the number of distribution rooms; Establish a primary monitoring structure based on all distribution room location parameters; Select the target distribution room in sequence according to the distribution room sequence A; Obtain the parameters of all the unit distribution cabinets in the target distribution room and establish a secondary monitoring structure for the target distribution room; Generate the secondary monitoring structure of each power distribution room in turn; Generate the association between the first-level monitoring structure and all the second-level monitoring structures; Establish electronic monitoring maps.
4. The monitoring and early warning system for electrical operation of a power plant according to claim 3, characterized in that: The first processing module is also used for: Establish a distribution room array A, A = (a1, a2...an), where ai is the i-th distribution room and n is the number of distribution rooms; Select the target distribution room in turn according to the distribution room sequence A, and generate the early warning evaluation value c of the target distribution room according to the preset evaluation model; Among them, e1 is the preset first weight coefficient; e2 is the preset second weight coefficient; bi is the reference value of the i-th equipment evaluation index; n1 is the number of equipment evaluation indicators, βi is the influencing factor of the i-th equipment evaluation index; di is the reference value of the i-th historical evaluation index; n2 is the number of historical evaluation indicators; αi is the influencing factor of the i-th historical evaluation index; Generate the early warning evaluation values of all distribution rooms in sequence, and establish an early warning evaluation value sequence C, C = (c1, c2...cn), where ci is the i-th early warning evaluation value.
5. The monitoring and early warning system for electrical operation of a power plant according to claim 4, characterized in that: The first control module is also used for: Establish an early warning unit sequence F, F = (f1, f2...fn), where Fi is the early warning unit of the i-th distribution room, and n is the number of early warning units; Preset a first warning evaluation value interval (C1, C2) and a second warning evaluation value interval (C2, C3); If ci is in the first warning evaluation value interval, Fi is set to the first-level working mode; If ci is in the second warning evaluation value interval, Fi is set to the second-level working mode.
6. The monitoring and early warning system for electrical operation of a power plant according to claim 5, characterized in that: The third processing module is also used for: Obtain the power distribution room to be operated and the power distribution cabinet of the unit to be operated according to the task instructions; Generate expected activity trajectories and reminder instructions; According to the reminder instruction, set the reminder parameters of the first-level warning module corresponding to the distribution room to be operated According to the reminder instruction, set the reminder parameters of the secondary warning module corresponding to the power distribution cabinet of the unit to be operated; Generate multiple feedback time nodes based on the expected activity trajectory; The real-time data collected by the early warning unit and the monitoring unit are obtained according to the feedback time node to generate the actual activity trajectory; Determine whether to generate warning instructions and operation records based on the actual activity trajectory and expected activity trajectory.
7. The monitoring and early warning system for electrical operation of a power plant according to claim 6, characterized in that: The third processing module is also used for: Establish progress evaluation model and position evaluation model; Generate a real-time progress deviation evaluation value between the actual activity trajectory and the expected activity trajectory according to the progress evaluation model, and generate a progress warning instruction if the real-time progress deviation evaluation value is greater than a preset threshold; According to the operation evaluation model and the actual activity trajectory, it is judged whether there is a position deviation. If there is a position deviation, an error operation warning instruction is generated.
8. The monitoring and early warning system for electrical operation of a power plant according to claim 6, characterized in that: The personnel management module is also used for: Based on the identity information of all personnel, establish a personnel identity label sequence G, G = (g1, g2...gm), where gi is the identity label of the i-th person; m is the number of personnel; Generate the work evaluation value of each person in turn according to the preset operation evaluation model, and establish a work evaluation value sequence H, H = (h1, h2...hm), where hi is the work evaluation value of the i-th person; Preset work evaluation value threshold h'; If hi<h', generate a stop work order for the i-th person.
9. The monitoring and early warning system for electrical operation of a power plant according to claim 6, characterized in that: When generating the work evaluation value of each person, include: The personnel identity label sequence G selects the target personnel to be evaluated in turn; Generate the work evaluation value h of the target person to be evaluated according to the operation evaluation model; Among them, e3 is the preset third fixed coefficient, e4 is the preset fourth fixed coefficient, and e5 is the preset fifth fixed coefficient; m1 is the operation record of the target person to be evaluated; pi is the operation evaluation value of the i-th operation record of the target person to be evaluated; △ p is the average value of all operation evaluation values, and m2 is the number of operation records in which the wrong unit distribution cabinet is selected; Generate the work evaluation value of each person in turn.
Citation Information
Cited By
Intelligent risk perception early warning system based on IoT technology
CN120183117A