Safety helmet with construction progress real-time monitoring function
The safety helmet with a micro camera and integrated construction management system addresses the limitations of traditional monitoring by providing real-time, automated data processing and analysis, enhancing construction progress visibility and management accuracy.
Patent Information
- Application Number
- CN202411208637.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-30
- Publication Date
- 2024-12-06
- Estimated Expiration
- Not applicable · inactive patent
AI Technical Summary
Traditional construction progress monitoring relies on manual records, leading to labor-intensive processes, human errors, incomplete data collection, and limited monitoring range, making it difficult to capture real-time construction site dynamics, especially in large and complex projects.
A safety helmet with a micro camera and integrated construction management system, including data acquisition, storage, analysis, display, and verification modules, enabling real-time monitoring and automated data processing to enhance construction progress visibility and accuracy.
The helmet system provides comprehensive, real-time monitoring and accurate data analysis, reducing human errors and optimizing construction management by ensuring timely decision-making and adaptability to site changes, thus improving project efficiency and quality.
Smart Images

Figure CN119073693A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the field of building construction management, and in particular to a safety helmet with a real-time monitoring function for construction progress. Background Art
[0002] In modern engineering construction, the management and monitoring of construction progress is an important guarantee for the success of the project. Traditional construction progress monitoring mainly relies on manual records by on-site personnel and regular inspections by management. This method is not only labor-intensive, but also easily affected by human factors, such as recording errors, information lags, and poor communication, which may lead to problems such as progress delays and cost overruns. In addition, traditional construction monitoring methods are difficult to capture the actual situation of the construction site in real time, and it is difficult for management to grasp the construction progress in a timely manner, which affects the accuracy and timeliness of decision-making.
[0003] With the development of information technology, intelligent monitoring systems based on the Internet of Things (IoT), artificial intelligence (AI) and big data technologies are gradually being applied to the construction industry. These technologies improve the ability to collect and process construction site data through automated means, can monitor construction progress in real time, and provide data analysis support. However, most intelligent monitoring systems on the market still have some shortcomings, such as incomplete data collection, inaccurate analysis results, and inability to display construction progress in real time. In addition, existing systems usually use fixed micro cameras for monitoring, with a limited monitoring range, and cannot flexibly capture dynamic changes on the construction site. Especially in large and complex engineering projects, the limitations of fixed monitoring equipment are particularly obvious. Summary of the invention
[0004] Based on the above background, the purpose of the present invention is to provide a safety helmet with real-time monitoring function of construction progress, so as to solve the technical problems existing in the background technology that the traditional construction progress monitoring method relies on manual records, the monitoring is not comprehensive, the data is lagging, and the monitoring range is limited.
[0005] In order to achieve the above-mentioned object of the invention, the present invention provides the following technical solutions:
[0006] A safety helmet with a real-time monitoring function for construction progress, comprising a helmet body, a micro camera and a construction management system, wherein the micro camera is located on the top of the helmet body, connected to the helmet body, and connected to a network of the construction management system;
[0007] The construction management system includes a central data network;
[0008] The central data network includes data collection and storage module, data analysis and decision support module, data display and visualization module, real-time comparison module and side verification module;
[0009] The micro camera is connected to the data acquisition and storage module through a wireless network, the data acquisition and storage module is connected to the data analysis and decision support module through the cloud, the data analysis and decision support module is connected to the data display and visualization module through an API interface, the data display and visualization module is connected to the real-time comparison module through an internal network, and the real-time comparison module is connected to the side verification module through database access.
[0010] Furthermore, the central data network also includes an automatic power-off unit, which is connected to the power interface of the micro camera. When the workers leave work, the automatic power-off unit will automatically disconnect the power connection of the micro camera to reduce unnecessary energy consumption.
[0011] Furthermore, the micro camera has a 360° panoramic shooting function, which is used to monitor the construction site in all directions, capture construction images around the workers, and transmit them to the central data network, providing basic visual data support for monitoring and analyzing the construction progress.
[0012] Furthermore, the data acquisition and storage module is used to receive data transmitted by the micro camera, store the data in a database, perform necessary preprocessing and classification, and expand the database to facilitate subsequent data analysis and decision support modules to learn about construction progress judgment and improve the accuracy of construction progress judgment.
[0013] Furthermore, the data analysis and decision support module includes the building model of the current construction progress, the building model of the next construction cycle and the building model of the completed construction. It uses big data, artificial intelligence and other technologies to conduct in-depth analysis and learning on the data stored in the data acquisition and storage module, explore the value behind the data, identify the project progress reflected by the data through data analysis, and provide scientific decision support for the project management.
[0014] Furthermore, the data display and visualization module is used to display the analysis results of the data analysis and decision support module in the form of charts, etc., so that project-related personnel can intuitively understand the progress of the project.
[0015] Furthermore, the real-time comparison module is used to track the construction progress in real time and compare and analyze it with the planned progress. The project management can use the real-time comparison module to promptly understand the construction progress, discover progress deviations and take measures to adjust them. The real-time comparison module also has the function of dynamically adjusting the construction plan to adapt to changes in the actual situation on site.
[0016] Furthermore, the side verification module provides accurate verification of the construction progress by comparing the material consumption on that day with the construction progress, and generates a report for reference by the project management team.
[0017] Furthermore, the data display and visualization module supports access via mobile devices, so that project-related personnel can view construction progress data anytime and anywhere and make decisions.
[0018] Combined with the above technical solutions, the beneficial effects brought by the present invention are analyzed as follows:
[0019] The invention provides a safety helmet with a real-time monitoring function of construction progress, comprising a helmet body, a micro camera and a construction management system, wherein the micro camera is located on the top of the helmet body, connected to the helmet body, and connected to the construction management system network; the construction management system comprises a central data network; the central data network comprises a data acquisition and storage module, a data analysis and decision support module, a data display and visualization module, a real-time comparison module and a side verification module; the micro camera is connected to the data acquisition and storage module through a wireless network, the data acquisition and storage module is connected to the data analysis and decision support module through a cloud, the data analysis and decision support module is connected to the data display and visualization module through an API interface, the data display and visualization module is connected to the real-time comparison module through an internal network, and the real-time comparison module is connected to the side verification module through database access.
[0020] By installing a micro camera on the top of the cap body and connecting the micro camera to the construction management system network, real-time monitoring of the construction progress is achieved, which greatly improves the accuracy of the construction management system's monitoring of the on-site progress. The micro camera can fully capture the construction images around the workers and transmit these images to the data acquisition and storage module of the central data network in real time. The data acquisition and storage module stores and preprocesses the received image data to ensure the integrity and availability of the data. Subsequently, the data analysis and decision support module conducts in-depth analysis of the stored data through cloud connection, uses artificial intelligence and big data technology to identify the current construction progress, and provides decision support for the management. The analysis results are presented in an intuitive chart form through the data display and visualization module, so that project-related personnel can clearly understand the construction progress. At the same time, the real-time comparison module is connected through the internal network to track the construction progress in real time, and compare it with the planned progress, and timely discover and adjust any progress deviation. The side verification module compares and analyzes the consumption of construction materials and the actual progress through database access, and further calibrates the judgment of the construction progress. Overall, the present invention realizes the full process automation management from data acquisition, storage, analysis to display and verification, reduces human errors, optimizes the construction management process, and provides reliable data support for scientific decision-making of engineering projects. Overall, the present invention realizes the full process automated management from data collection, storage, analysis to display and verification, reduces human errors, optimizes the construction management process, and provides reliable data support for scientific decision-making of engineering projects.
[0021] Compared with the existing technology, the present invention realizes the full process automated management from data collection, storage, analysis to display and verification, reduces human errors, optimizes the construction management process, and provides reliable data support for scientific decision-making of engineering projects.
[0022] Other features and advantages of the present invention will be described in the following description, and partly become apparent from the description, or understood by practicing the present invention. The purpose and other advantages of the present invention are realized and obtained by the structures particularly pointed out in the description, claims and drawings. BRIEF DESCRIPTION OF THE DRAWINGS
[0023] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on the provided drawings without paying creative work.
[0024] Figure 1 It is a schematic diagram of the overall structure of the present invention;
[0025] Figure 2 It is a schematic diagram of the positions of the cap body and the micro camera of the present invention;
[0026] Figure 3 It is a schematic diagram of the implementation process of the central data network of the present invention.
[0027] In the figure: 1. Cap body; 2. Micro camera; 3. Construction management system; 301. Central data network; 301-1. Collection and storage module; 301-2. Data analysis and decision support module; 301-3. Data display and visualization module; 301-4. Real-time comparison module; 301-5. Side verification module; 301-6. Automatic power-off unit. DETAILED DESCRIPTION
[0028] The technical solution of the present invention will be described clearly and completely below in conjunction with the accompanying drawings. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0029] In the description of the present invention, it should be noted that the terms "center", "upper", "lower", "left", "right", "vertical", "horizontal", "inner", "outer", etc., indicating the orientation or positional relationship, are based on the orientation or positional relationship shown in the drawings, and are only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as limiting the present invention. In addition, the terms "first", "second", and "third" are used for descriptive purposes only, and cannot be understood as indicating or implying relative importance.
[0030] In the description of the present invention, it should be noted that, unless otherwise clearly specified and limited, the terms "installed", "connected", and "connected" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or it can be indirectly connected through an intermediate medium, or it can be the internal communication of two components. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.
[0031] The embodiments are described in detail below with reference to the accompanying drawings: Figure 1 It is a schematic diagram of the overall structure of the present invention; Figure 2 It is a schematic diagram of the positions of the cap body 1 and the micro camera 2 of the present invention; Figure 3 It is a schematic diagram of the implementation process of the central data network 301 of the present invention.
[0032] Example 1
[0033] This embodiment provides a safety helmet with a real-time monitoring function for construction progress. Figures 1 to 3 .
[0034] like Figure 1 As shown, a safety helmet with a real-time monitoring function for construction progress includes a helmet body 1, a micro camera 2 and a construction management system 3. Figure 2 As shown, the micro camera 2 is located on the top of the cap body 1, the micro camera 2 is connected to the cap body 1, and the micro camera 2 is connected to the construction management system 3 network; Figure 3As shown, the construction management system 3 includes a central data network 301; the central data network 301 includes a data acquisition and storage module 301-1, a data analysis and decision support module 301-2, a data display and visualization module 301-3, a real-time comparison module 301-4 and a side verification module 301-5; the micro camera 2 is connected to the data acquisition and storage module 301-1 through a wireless network, the data acquisition and storage module 301-1 is connected to the data analysis and decision support module 301-2 through the cloud, the data analysis and decision support module 301-2 is connected to the data display and visualization module 301-3 through an API interface, the data display and visualization module 301-3 is connected to the real-time comparison module 301-4 through an internal network, and the real-time comparison module 301-4 is connected to the side verification module 301-5 through a database access connection.
[0035] By installing a micro camera 2 on the top of the cap body 1 and connecting the micro camera 2 to the construction management system 3 network, real-time monitoring of the construction progress is achieved, which greatly improves the accuracy of the construction management system 3 in monitoring the on-site progress. The micro camera 2 can fully capture the construction images around the workers and transmit these images to the data acquisition and storage module 301-1 of the central data network 301 in real time. The data acquisition and storage module 301-1 stores and preprocesses the received image data to ensure the integrity and availability of the data. Subsequently, the data analysis and decision support module 301-2 conducts in-depth analysis of the stored data through cloud connection, uses artificial intelligence and big data technology to identify the current construction progress, and provides decision support for the management. The analysis results are presented in the form of intuitive charts through the data display and visualization module 301-3, so that project-related personnel can clearly understand the construction progress. At the same time, the real-time comparison module 301-4 tracks the construction progress in real time through the internal network connection, and compares it with the planned progress, and promptly discovers and adjusts any progress deviation. The side verification module 301-5 compares and analyzes the consumption of construction materials and the actual progress through database access, and further calibrates the judgment of the construction progress. Overall, the present invention realizes the full process of automated management from data collection, storage, analysis to display and verification, reduces human errors, optimizes the construction management process, and provides reliable data support for scientific decision-making of engineering projects. Overall, the present invention realizes the full process of automated management from data collection, storage, analysis to display and verification, reduces human errors, optimizes the construction management process, and provides reliable data support for scientific decision-making of engineering projects. Overall, the present invention realizes the full process of automated management from data collection, storage, analysis to display and verification, reduces human errors, optimizes the construction management process, and provides reliable data support for scientific decision-making of engineering projects.
[0036] Furthermore, the central data network 301 also includes an automatic power-off unit 301-6, which is connected to the power interface of the micro camera 2. When the workers leave work, the automatic power-off unit 301-6 will automatically disconnect the power connection of the micro camera 2 to reduce unnecessary energy consumption.
[0037] By integrating the automatic power-off unit 301-6 in the central data network 301, the system can intelligently manage the power status of the micro camera 2, avoiding energy waste caused by the continuous operation of the micro camera 2 during unnecessary time periods. At the same time, the setting of the automatic power-off unit 301-6 ensures that the micro camera 2 can work normally during construction, and automatically turns off the power after the working hours, further improving the energy management efficiency of the system, extending the service life of the equipment, and reducing maintenance costs. The application of the automatic power-off unit 301-6 optimizes the overall energy efficiency of the construction management system 3, making the system more environmentally friendly and energy-saving while achieving real-time monitoring.
[0038] Among them, the micro camera 2 supports two battery life modes: wired charging and battery replacement, ensuring that the real-time monitoring of the construction progress can be continued in an environment with long-term construction or unstable power supply. Through wired charging, the micro camera 2 can be charged within a fixed time period, which is suitable for a relatively stable working environment; while the battery replacement method provides a flexible solution for situations where the on-site conditions are complex or it is difficult to supply power for a long time. The combination of the two battery life modes allows the micro camera 2 to maintain reliable operation in different construction scenarios.
[0039] Furthermore, the micro camera 2 has a 360° panoramic shooting function, which is used to monitor the construction site in all directions, capture construction images around the workers, and transmit them to the central data network 301, providing basic visual data support for monitoring and analyzing the construction progress.
[0040] Through the 360° panoramic shooting function of the micro camera 2, the micro camera 2 can cover all angles of the construction site, avoiding the occurrence of blind spots in monitoring, thereby ensuring that all key construction activities are recorded. These captured images will be transmitted to the central data network 301 in real time as basic visual data support for construction progress monitoring and analysis. By providing complete and continuous visual data, the micro camera 2 provides a reliable data source for the data acquisition and storage module 301-1, making subsequent data analysis and decision-making more accurate and comprehensive, and ultimately improving the accuracy of construction progress monitoring and the overall efficiency of construction management.
[0041] Furthermore, the data acquisition and storage module 301-1 is used to receive data transmitted by the micro camera 2, and store the data in the database, perform necessary preprocessing and classification, and expand the database to facilitate the subsequent data analysis and decision support module 301-2 to learn the construction progress judgment and improve the accuracy of the construction progress judgment.
[0042] The data acquisition and storage module 301-1 is not only responsible for receiving and storing data, but also performs necessary preprocessing and classification of the data. These preprocessing operations include data cleaning, formatting, and preliminary screening to ensure the quality and integrity of the data. By classifying and storing the processed data, the data acquisition and storage module 301-1 effectively expands the capacity and content of the database, providing rich data resources for subsequent analysis. The expanded database provides a more comprehensive and accurate learning sample for the data analysis and decision support module 301-2, so that the algorithm for judging the construction progress can make more accurate judgments with the support of more data, thereby significantly improving the accuracy of the judgment of the construction progress.
[0043] Furthermore, the data analysis and decision support module 301-2 includes the building model of the current construction progress, the building model of the next construction cycle and the building model of the completed construction. It uses big data, artificial intelligence and other technologies to conduct in-depth analysis and learning on the data stored in the data collection and storage module 301-1, explore the value behind the data, identify the project progress reflected by the data through data analysis, and provide scientific decision support for the project management.
[0044] The data analysis and decision support module 301-2 is not just a simple data processing, it also identifies the actual project progress reflected by the data through in-depth mining of construction data. Based on these analysis results, the data analysis and decision support module 301-2 can dynamically generate a construction progress model that is highly matched with the actual situation. Among them, the building model of the current construction progress is used to reflect the actual progress of the current project; the building model of the next construction cycle helps predict and plan the future construction phase; the building model of the completed construction provides a global target reference to ensure that the project progresses towards the established final goal. Through the interaction of these models and the analysis of big data, the system can identify potential progress deviations, resource allocation problems and construction bottlenecks. Finally, the data analysis and decision support module 301-2 converts these analysis results into intuitive and scientific decision support information for reference by the project management. Based on these analyses, the management can formulate more accurate construction plans, adjust resource allocation, and optimize the construction process, thereby improving the overall construction efficiency and quality of the project. In general, the data analysis and decision support module 301-2 not only improves the monitoring accuracy of the construction progress, but also provides a solid data foundation for scientific decision-making, making the entire project management process more intelligent and efficient.
[0045] Furthermore, the data display and visualization module 301 - 3 is used to display the analysis results of the data analysis and decision support module 301 - 2 in the form of charts, etc., so that project-related personnel can intuitively understand the progress of the project.
[0046] The data display and visualization module 301-3 simplifies the information transmission and understanding process by visualizing complex data analysis results, so that project participants at different levels, including management and on-site personnel, can quickly and accurately obtain key information on the construction progress. Through this visual display method, project-related personnel can more easily identify the progress status of the current project, potential delay risks, and resource allocation. In addition, the form of charts can intuitively compare the current construction progress with the planned progress, help to promptly discover and correct progress deviations, and ensure that the project can be completed on time and with quality. In short, the data analysis and decision support module 301-2 displays the analysis results in an intuitive and easy-to-understand form, improves the efficiency of information transmission, assists the project management to make scientific decisions, and ultimately improves the management level and execution efficiency of the entire construction project.
[0047] Furthermore, the real-time comparison module 301-4 is used to track the construction progress in real time and compare and analyze it with the planned progress. The project management level can use the real-time comparison module 301-4 to timely understand the construction progress, discover progress deviations and take measures to adjust them. The real-time comparison module 301-4 also has the function of dynamically adjusting the construction plan to adapt to changes in the actual situation on site.
[0048] Real-time comparison module 301-4 helps management maintain overall control of the project during the construction process through continuous progress tracking and analysis, and reduces construction delays caused by unexpected situations. Through automated data processing and analysis, real-time comparison module 301-4 can quickly respond to changes on the construction site, dynamically optimize the construction plan, and ensure that the project progress is always within controllable range. Overall, real-time comparison module 301-4 provides real-time and accurate construction progress information to project management, and optimizes the construction plan through dynamic adjustment functions, so that the project can efficiently and flexibly respond to various challenges.
[0049] Furthermore, the side verification module 301 - 5 provides accurate verification of the construction progress by comparing the material consumption on that day with the construction progress, and generates a report for reference by the project management team.
[0050] The side check module 301-5 ensures that the evaluation of the construction progress is not only based on time and task completion, but also combines the actual situation of resource use by comparing and analyzing the actual material consumption with the expected progress. This double verification mechanism can effectively detect possible deviations in the construction process, such as excessive or insufficient use of materials, and then adjust the progress evaluation. In addition, the report generated by the side check module 301-5 provides detailed reference information for the project management, enabling them to have a more comprehensive understanding of the progress of the project and ensure the synchronization of resource use and construction progress. Through precise verification, management can better control the allocation and use of project resources, avoid construction delays caused by material waste or shortage, and thus optimize the management and control of the entire construction process. Overall, the side check module 301-5 provides a more accurate verification method for the construction progress through a comprehensive analysis of material consumption and progress, and provides reliable data support for management decisions.
[0051] Furthermore, the data display and visualization module 301 - 3 supports access via mobile devices, so that project-related personnel can view the construction progress data and make decisions anytime and anywhere.
[0052] The data display and visualization module 301-3 supports access from mobile devices, which greatly improves the flexibility and responsiveness of project management. Managers are no longer limited to obtaining information in the office or on designated computer terminals, but can monitor project progress in real time through mobile devices such as mobile phones and tablets. No matter where they are, project-related personnel can immediately obtain the latest construction data and make key decisions based on real-time information. This anytime, anywhere access capability is particularly suitable for complex engineering projects. When site conditions or construction plans change, management can quickly understand the situation and make timely adjustments to avoid potential delays or waste of resources. By supporting access from mobile devices, the data display and visualization module 301-3 greatly enhances the efficiency and effectiveness of project management, providing a strong guarantee for the smooth progress of the project.
Claims
1. A safety helmet with a real-time monitoring function for construction progress, characterized in that: The safety helmet with a real-time construction progress monitoring function comprises a helmet body (1), a micro camera (2) and a construction management system (3), wherein the micro camera (2) is located on the top of the helmet body (1), the micro camera (2) is connected to the helmet body (1), and the micro camera (2) is connected to the construction management system (3) through a network; The construction management system (3) includes a central data network (301); The central data network (301) includes a data collection and storage module (301-1), a data analysis and decision support module (301-2), a data display and visualization module (301-3), a real-time comparison module (301-4) and a side verification module (301-5); The micro camera (2) is connected to the data acquisition and storage module (301-1) via a wireless network, the data acquisition and storage module (301-1) is connected to the data analysis and decision support module (301-2) via a cloud, the data analysis and decision support module (301-2) is connected to the data display and visualization module (301-3) via an API interface, the data display and visualization module (301-3) is connected to the real-time comparison module (301-4) via an internal network, and the real-time comparison module (301-4) is connected to the side verification module (301-5) via a database access connection.
2. The safety helmet with real-time monitoring function of construction progress according to claim 1 is characterized by: The central data network (301) also includes an automatic power-off unit (301-6), which is connected to the power interface of the micro camera (2). When the worker leaves work, the automatic power-off unit (301-6) will automatically disconnect the power connection of the micro camera (2) to reduce unnecessary energy consumption.
3. The safety helmet with real-time construction progress monitoring function according to claim 1 is characterized in that: The micro camera (2) has a 360° panoramic shooting function and is used to monitor the construction site in all directions, capture construction images around the workers, and transmit them to the central data network (301), providing basic visual data support for monitoring and analyzing the construction progress.
4. The safety helmet with real-time construction progress monitoring function according to claim 1 is characterized by: The data acquisition and storage module (301-1) is used to receive data transmitted by the micro camera (2), store the data in a database, perform necessary preprocessing and classification, and expand the database, so as to facilitate the subsequent data analysis and decision support module (301-2) to learn the construction progress judgment and improve the accuracy of the construction progress judgment.
5. The safety helmet with real-time construction progress monitoring function according to claim 1 is characterized by: The data analysis and decision support module (301-2) includes a building model of the current construction progress, a building model of the next construction cycle, and a building model of completed construction. It uses big data, artificial intelligence and other technologies to conduct in-depth analysis and learning of the data stored in the data collection and storage module (301-1), explore the value behind the data, identify the project progress reflected by the data through data analysis, and provide scientific decision support for the project management level.
6. The safety helmet with real-time construction progress monitoring function according to claim 1 is characterized by: The data display and visualization module (301-3) is used to display the analysis results of the data analysis and decision support module (301-2) in the form of charts, etc., so that project-related personnel can intuitively understand the progress of the project.
7. The safety helmet with real-time construction progress monitoring function according to claim 1 is characterized by: The real-time comparison module (301-4) is used to track the construction progress in real time and compare and analyze it with the planned progress. The project management can use the real-time comparison module (301-4) to timely understand the construction progress, find progress deviations and take measures to adjust them. The real-time comparison module (301-4) also has the function of dynamically adjusting the construction plan to adapt to changes in the actual situation on site.
8. The safety helmet with real-time construction progress monitoring function according to claim 1 is characterized by: The side verification module (301-5) provides accurate verification of the construction progress by comparing the material consumption on the day with the construction progress, and generates a report for reference by the project management team.
9. The safety helmet with real-time construction progress monitoring function according to claim 6, characterized in that: The data display and visualization module (301-3) supports access via mobile devices, so that project-related personnel can view construction progress data anytime and anywhere and make decisions.