Load control management method and related device
By determining and processing the protocol conversion points of the data transmission ladder in the power grid, analyzing the status and using message middleware to process it, the problems of peak load and power overload are solved, and the regulation capability and power supply reliability of the power grid are improved.
Patent Information
- Application Number
- CN202411106294.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-13
- Publication Date
- 2024-12-06
AI Technical Summary
The traditional grid scheduling model cannot effectively solve the problems of peak load power distribution and overload, resulting in insufficient peak-to-valley regulation capacity of the power grid and low power supply reliability, especially under the influence of natural climate.
By determining the protocol conversion point location of the data transmission ladder, analyzing status information, confirming the fault status, and completing data transmission through the backup data transmission ladder, using message middleware to process storage and functional interactions, ensuring the reliability and orderliness of data transmission.
It has realized the precise load control and power management of Taiwan's district, improved the peak and valley regulation capacity of the power grid and asset utilization rate, ensured the reliability of power supply, and reduced the frequent failures caused by natural climate and frequent start-stop of high-power equipment.
Smart Images

Figure CN119093418A_ABST
Abstract
Description
Technical Field
[0001] The present invention belongs to the technical field of fault judgment of electric power communication equipment, and specifically relates to a load control management method and related devices. Background Art
[0002] As of 2021, the power grid under the jurisdiction of Tacheng Power Grid has basically formed a grid structure dominated by a chain structure, with transitional grid connection modes such as ring network and radiation coexisting. The total length of the transmission lines in the whole network is 5,346.7664 kilometers. The electrified load is connected to the power grid on a large scale. The disordered electricity consumption has caused the seasonal peak load of the lines to become increasingly prominent, and the proportion of overload and heavy load has continued to increase; and affected by the natural climate such as the Maitas wind zone, the main grid flashover failures are frequent in spring and autumn, and high-power electrical equipment is frequently started and stopped, affecting the reliability of power supply.
[0003] The traditional dispatching model can no longer solve the above problems. Accurate control of load and power management in substations, orderly handling of peak load power distribution, and power overload issues have become the inevitable choice to improve the peak and valley regulation capabilities of the power grid and the utilization rate of power grid assets. Summary of the invention
[0004] The purpose of the present invention is to provide a load control management method and a related device to solve the above-mentioned problems. In a first aspect, a load control management method is provided, comprising: determining the positions of protocol conversion points on each data transmission ladder on a target control architecture, wherein any two of the protocol conversion points constitute one data transmission ladder, and each of the data transmission ladders contains two or more of the protocol conversion points;
[0005] analyzing status information of the data transmission ladder;
[0006] confirming whether the data transmission ladder corresponding to the status information is in a fault state; when the data transmission ladder corresponding to the status information is in a fault state, the first protocol conversion point of the data transmission ladder will form a second data transmission ladder with other protocol conversion points;
[0007] Acquire the data to be transmitted on the data transmission step of the fault state;
[0008] The positions of the various protocol conversion points on the second data transmission ladder are confirmed, and the transmission of the data to be transmitted is completed through the second data transmission ladder.
[0009] Furthermore, it also includes:
[0010] Determining target function items on the protocol conversion points, wherein at least one of the target function items can enable functional interaction between two adjacent protocol conversion points;
[0011] Detecting the operating status information of the target function item;
[0012] When the operating status information indicates that the corresponding target function item is in a fault state, the target control architecture will issue intervention information.
[0013] Furthermore, it also includes:
[0014] The target function items include a target storage function item, and it is confirmed whether the target storage function item of each of the protocol conversion points matches the message middleware, wherein the message middleware is controlled by the target storage function item.
[0015] Furthermore, it also includes:
[0016] Detecting the gatekeeper status of the last protocol conversion point of the data transmission ladder;
[0017] When the network gate is in a fault state, the data being transmitted is stored in the message middleware.
[0018] Furthermore, it also includes:
[0019] Determine a packaging function item in the target storage function item, wherein the packaging function item includes at least one file conversion function;
[0020] The running status information of the target storage function item is detected, and when the status information indicates that the corresponding packaging function item is in a fault state, the information to be packaged enters the message middleware.
[0021] In a second aspect, a device for a load control management method is provided, comprising:
[0022] A determination unit: determining the position of the protocol conversion points on each data transmission ladder on the target control architecture, wherein any two of the protocol conversion points constitute one data transmission ladder, and each of the data transmission ladders contains two or more of the protocol conversion points;
[0023] An analyzing unit: analyzing the state information of the data transmission ladder, confirming whether the data transmission ladder corresponding to the state information is in a fault state, and when the data transmission ladder corresponding to the state information is in a fault state, the first protocol conversion point of the data transmission ladder will form a second data transmission ladder with other protocol conversion points;
[0024] An acquisition unit is configured to acquire the data to be transmitted on the data transmission step in the fault state, confirm the positions of each protocol conversion point on the second data transmission step, and complete the transmission of the data to be transmitted through the second data transmission step.
[0025] According to a third aspect, an electronic device is provided, comprising a memory and a processor, wherein the processor is configured to implement the steps of the load control management method as described in any one of the first aspects when executing a computer program stored in the memory.
[0026] In a fourth aspect, a computer-readable storage medium is provided, on which a computer program is stored. When the computer program is executed by a processor, the steps of the load control management method as described in any one of the first aspects are implemented.
[0027] The above technical solution ensures accurate control of load and power management in the substation, solves the problems of orderly handling of peak load power distribution and power overload, improves the peak-valley regulation capability of the power grid and the utilization rate of power grid assets, and also solves the problems of frequent flashover failures in the main grid in spring and autumn and frequent start and stop of high-power electrical equipment due to the influence of natural climate such as the Maitas wind zone, thus ensuring power supply reliability. BRIEF DESCRIPTION OF THE DRAWINGS
[0028] Figure 1 A flow chart of a load control management method provided in an embodiment of the present application;
[0029] Figure 2 A schematic structural block diagram of a load control management device provided in an embodiment of the present application;
[0030] Figure 3 A schematic structural block diagram of an electronic device based on a load control management method provided in an embodiment of the present application;
[0031] Figure 4 A schematic structural block diagram of a computer-readable storage medium based on load control management provided in an embodiment of the present application. DETAILED DESCRIPTION
[0032] In order to make the purpose, technical solution and advantages of the present invention more clearly understood, the present invention is further described in detail below in conjunction with the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are only used to explain the present invention and are not used to limit the present invention.
[0033] Reference Figure 1, a load control management method is provided for an embodiment of the present application, comprising: S110 determining the position of the protocol conversion point on each data transmission ladder on the target control architecture, wherein any two of the protocol conversion points constitute one data transmission ladder, and each of the data transmission ladders contains two or more of the protocol conversion points;
[0034] Exemplarily, the target control architecture is generally used to control the load power management system of the control station area, which is mainly used to manage the power load regulation and coordination of a certain area;
[0035] The protocol conversion point refers to the virtual signal coordinates representing each load power storage and transmission point controlled by the load power management system. The virtual signal coordinates correspond to the load power storage and transmission points one by one and are responsible for controlling the power load and balance indication of the storage and transmission points.
[0036] The data transmission ladder is composed of the first and last two protocol conversion points. There may be N data protocol conversion points between the first and last two protocol conversion points, but they only constitute one data transmission ladder. Because the data transmission of the protocol conversion point directly reflects and controls the power load and load balance, data transmission needs to form a backup and model to better guide the negative power balance work;
[0037] S120, analyzing the status information of the data transmission ladder, and confirming whether the data transmission ladder corresponding to the status information is in a fault state;
[0038] Exemplarily, the first and last two protocol conversion points on the data transmission ladder are analyzed for obstacles. If they are in an obstacle state, the originally set data transmission ladder is invalidated; the remaining protocol conversion points do not need to be analyzed; when the data transmission ladder corresponding to the state information is displayed in a fault state, the first protocol conversion point of the data transmission ladder will form a second data transmission ladder with the other protocol conversion points;
[0039] S130, obtaining the data to be transmitted on the data transmission step in the fault state;
[0040] confirming the positions of each protocol conversion point on the second data transmission ladder, and completing the transmission of the data to be transmitted through the second data transmission ladder;
[0041] Furthermore, it also includes:
[0042] Determining target function items on the protocol conversion points, wherein at least one of the target function items can enable functional interaction between two adjacent protocol conversion points;
[0043] Detecting the operating status information of the target function item;
[0044] When the operation status information indicates that the corresponding target function item is in a fault state, the target control architecture will issue intervention information;
[0045] Exemplarily, the second transmission ladder is an information transmission line composed of the first protocol conversion point and all other protocol conversion points that may reach the tail protocol conversion point except the transmission ladder in the fault state at the same time, and the most important feature is that time division multiple access and code division multiple access communication methods are adopted; further, it also includes:
[0046] The target function items include a target storage function item, confirming whether the target storage function item of each protocol conversion point matches the message middleware, wherein the message middleware is controlled by the target storage function item;
[0047] Exemplarily, when there are obstacles at the first and last two protocol conversion points, the stored information cannot be obtained from the storage function project. Equipped with message middleware, not only solves the problem of storage failure or information failure, but also solves the problem of data loss caused by a large amount of data flowing at the same time. The message middleware currently used is rabbitMQ, which is an open source message broker and queue server with high throughput and persistence capabilities;
[0048] Furthermore, it also includes:
[0049] Detecting the gatekeeper status of the last protocol conversion point of the data transmission ladder;
[0050] When the network gate is in a fault state, the data being transmitted is stored in the message middleware.
[0051] Furthermore, it also includes:
[0052] Determine a packaging function item in the target storage function item, wherein the packaging function item includes at least one file conversion function;
[0053] The running status information of the target storage function item is detected, and when the status information indicates that the corresponding packaging function item is in a fault state, the information to be packaged enters the message middleware.
[0054] In a second aspect, a device for a load control management method is provided, comprising: 201 a determination unit: determining the position of a protocol conversion point on each data transmission ladder on a target control architecture, wherein any two of the protocol conversion points constitute one data transmission ladder, and each of the data transmission ladders contains two or more of the protocol conversion points;
[0055] 202 Analysis unit: Analyze the state information of the data transmission ladder, confirm whether the data transmission ladder corresponding to the state information is in a fault state, when the data transmission ladder corresponding to the state information is in a fault state, the first protocol conversion point of the data transmission ladder will form a second data transmission ladder with other protocol conversion points;
[0056] 203 Acquisition unit: acquires the data to be transmitted on the data transmission ladder in the fault state, confirms the position of each protocol conversion point on the second data transmission ladder, and completes the transmission of the data to be transmitted through the second data transmission ladder.
[0057] In a third aspect, an electronic device is provided, comprising a memory 410 and a processor 420, wherein the processor is configured to implement the steps of the load control management method as described in any one of the first aspects when executing a computer program 411 stored in the memory.
[0058] In a fourth aspect, a computer-readable storage medium 500 is provided, on which a computer program 511 is stored. When the computer program is executed by a processor, the steps of the load control management method as described in any one of the first embodiments are implemented.
[0059] The above technical solution ensures accurate control of load and power management in the substation, solves the problems of orderly handling of peak load power distribution and power overload, improves the peak-valley regulation capability of the power grid and the utilization rate of power grid assets, and also solves the problems of frequent flashover failures in the main grid in spring and autumn and frequent start and stop of high-power electrical equipment due to the influence of natural climate such as the Maitas wind zone, thus ensuring power supply reliability.
[0060] It should be noted that, in this document, relational terms such as first and second, etc. are merely used to distinguish one entity or operation from another entity or operation, and do not necessarily require or imply any actual relationship or order between these entities or operations.
[0061] Moreover, the terms "comprises," "includes," or any other variations thereof are intended to cover non-exclusive inclusion, such that a process, method, article, or apparatus that includes a series of elements includes not only those elements, but also other elements not explicitly listed, or also includes elements inherent to such process, method, article, or apparatus. Without further limitations, the elements defined by the sentence "comprises one..." do not exclude the presence of additional identical elements in the process, method, article, or apparatus that includes the elements.
[0062] The above embodiments are only used to illustrate the technical solutions of the present invention rather than to limit the same. Although the present invention has been described in detail with reference to the aforementioned embodiments, those skilled in the art should understand that the technical solutions described in the aforementioned embodiments may still be modified, or some of the technical features may be replaced by equivalents. However, these modifications or replacements do not deviate the essence of the corresponding technical solutions from the spirit and scope of the technical solutions of the embodiments of the present invention.
Claims
1. A load control management method, characterized in that: include: Determine the position of the protocol conversion point on each data transmission ladder on the target control architecture, wherein any two of the protocol conversion points constitute one data transmission ladder, and each of the data transmission ladder contains two or more of the protocol conversion points; analyzing status information of the data transmission ladder; confirming whether the data transmission step corresponding to the status information is in a fault state; When the data transmission ladder corresponding to the state information is in a fault state, the first protocol conversion point of the data transmission ladder will form a second data transmission ladder with other protocol conversion points; Acquire the data to be transmitted on the data transmission step in the fault state; The positions of the various protocol conversion points on the second data transmission ladder are confirmed, and the transmission of the data to be transmitted is completed through the second data transmission ladder.
2. The method according to claim 1, characterized in that: Also includes: Determining target function items on the protocol conversion points, wherein at least one of the target function items can enable functional interaction between two adjacent protocol conversion points; Detecting the operating status information of the target function item; When the operating status information indicates that the corresponding target function item is in a fault state, the target control architecture will issue intervention information.
3. The method according to claim 1 or 2, characterized in that: Also includes: The target function items include a target storage function item, and it is confirmed whether the target storage function item of each of the protocol conversion points matches the message middleware, wherein the message middleware is controlled by the target storage function item.
4. The method according to claim 1 or 3, characterized in that: Also includes: Detecting the gatekeeper status of the last protocol conversion point of the data transmission ladder; When the network gate is in a fault state, the data being transmitted is stored in the message middleware.
5. The method according to claim 3, characterized in that: Also includes: Determine a packaging function item in the target storage function item, wherein the packaging function item includes at least one file conversion function; The running status information of the target storage function item is detected, and when the status information indicates that the corresponding packaging function item is in a fault state, the information to be packaged enters the message middleware.
6. A device for a load control management method, characterized in that: include: A determination unit: determining the position of the protocol conversion points on each data transmission ladder on the target control architecture, wherein any two of the protocol conversion points constitute one data transmission ladder, and each of the data transmission ladders contains two or more of the protocol conversion points; An analyzing unit: analyzing the state information of the data transmission ladder, confirming whether the data transmission ladder corresponding to the state information is in a fault state, and when the data transmission ladder corresponding to the state information is in a fault state, the first protocol conversion point of the data transmission ladder will form a second data transmission ladder with other protocol conversion points; An acquisition unit is configured to acquire the data to be transmitted on the data transmission step in the fault state, confirm the positions of each protocol conversion point on the second data transmission step, and complete the transmission of the data to be transmitted through the second data transmission step.
7. An electronic device, comprising a memory and a processor, characterized in that: The processor is used to implement the steps of the load control management method according to any one of claims 1 to 5 when executing the computer program stored in the memory.
8. A computer-readable storage medium having a computer program stored thereon, characterized in that: When the computer program is executed by a processor, the steps of the load control management method according to any one of claims 1 to 5 are implemented.