Aerobic treatment method and system for landfill treatment

Through real-time comparison of virtual site models and actual construction information and analysis of twin data platforms, the inaccuracy of construction progress management and the synchronization of environmental monitoring and construction progress in landfill management are solved, and landfill management is realized Refined and environmentally friendly management improves the accuracy and environmental safety of construction progress management.

CN119158881APending Publication Date: 2024-12-20POWERCHINA CONSTR GRP
View PDF 11 Cites 0 Cited by

Patent Information

Application Number
CN202411200021.8
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-29
Publication Date
2024-12-20

AI Technical Summary

Technical Problem

Construction progress management lacks accuracy in landfill management, and environmental monitoring and construction progress are difficult to synchronize. The existing methods lack flexibility and adaptability when dealing with complex environments, and cannot achieve refined and intelligent management.

Method used

Using virtual field model to real-time comparison of actual construction information, a digital twin environment is constructed through BIM model and three-dimensional site layout model, synchronization points and daily average progress comparison are set, and environmental information and dynamic adjustment information are analyzed using the twin data platform, and feedback and Adjustment method.

Benefits of technology

It improves the accuracy and response speed of construction progress management, enhances environmental safety, realizes timely identification and early warning of environment and construction progress, and improves the project's environmentally friendly management capabilities.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119158881A_ABST
    Figure CN119158881A_ABST
Patent Text Reader

Abstract

The invention discloses an aerobic treatment method and system for landfill treatment, and relates to the technical field of garbage treatment.The aerobic treatment method comprises the following steps that actual environment information is collected, a virtual field model is constructed, and virtual construction information is predicted through the virtual field model; monitoring actual construction information, and comparing the actual construction information with the virtual construction information to obtain dynamic adjustment information; and inputting the actual environment information and the dynamic adjustment information into a twin data platform, analyzing the received data through the twin data platform, and outputting feedback information and an adjustment method. According to the method, the virtual field model is constructed and compared with the actual construction information in real time, dynamic synchronization of the virtual environment and the actual environment is achieved, the digital twinning environment is created, and the system can calculate the difference percentage in time by setting the synchronization point and comparing the daily progress, so that the construction progress deviation is accurately quantified.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of garbage treatment, in particular to an aerobic treatment method and system for landfill management. Background Art

[0002] With the rapid development of society, the amount of domestic waste in my country's cities and towns has also soared. At present, landfill is still the main way to deal with waste. However, the garbage in the landfill generally exceeds the designed storage capacity. Long-term overload operation leads to greater environmental risks and safety hazards in the landfill. Therefore, it is of great significance to carry out ecological restoration projects for domestic waste landfills to make them quickly and stably.

[0003] Aerobic stabilization technology can accelerate the decomposition of biodegradable organic matter in garbage by microorganisms and reduce greenhouse gas emissions, so it has attracted much attention in landfill management. However, traditional aerobic stabilization technology is not associated with intelligent equipment, information transmission is not timely, aerobic remediation effects are not intuitive, and control methods are not accurate. It cannot solve the problems of uneven gas distribution and insufficient oxygen reaction. In addition, the construction efficiency of aerobic facilities is low, which easily leads to repeated work and waste of resources and costs.

[0004] At present, aerobic treatment methods for landfill management face many challenges in their implementation. First, the real-time synchronization and accurate comparison between virtual models and actual construction conditions have not been effectively solved, resulting in a lack of accuracy and timeliness in construction progress management. Secondly, the collection and analysis of environmental monitoring data are often carried out in isolation, making it difficult to form an organic connection with the construction progress and management effects, limiting the timely identification and early warning of environmental risks. Furthermore, existing methods lack sufficient flexibility and adaptability when dealing with complex and changing construction environments, and are unable to dynamically adjust construction strategies according to real-time conditions. Therefore, it is urgent to develop an aerobic treatment method for landfill management that can integrate virtual field models, real-time monitoring, and dynamic adjustment to achieve refined, intelligent, and environmentally friendly management of landfill management. Summary of the invention

[0005] In view of the problems existing in the existing aerobic treatment and system for landfill management, the present invention is proposed.

[0006] Therefore, the problem to be solved by the present invention is that the management of construction progress lacks accuracy.

[0007] In order to solve the above technical problems, the present invention provides the following technical solutions:

[0008] In a first aspect, an embodiment of the present invention provides an aerobic treatment method for landfill management, which comprises the following steps:

[0009] Collecting actual environment information, building a virtual site model, and predicting virtual construction information through the virtual site model;

[0010] Monitoring actual construction information, and then comparing the actual construction information with the virtual construction information to obtain dynamic adjustment information;

[0011] The actual environment information and the dynamic adjustment information are input into the twin data platform, the received data is analyzed by the twin data platform, and feedback information and adjustment methods are output.

[0012] As a preferred solution of the aerobic treatment method for landfill management of the present invention, wherein: the virtual site model includes a BIM model and a three-dimensional site layout model;

[0013] The method for constructing the BIM model includes:

[0014] Establish a landfill entity model through modeling software, and establish corresponding family libraries for all sub-models of the entity model;

[0015] Unify all sub-models together to obtain the BIM model;

[0016] Use detection tools to identify collision problems in the BIM model, and then adjust the parametric components in the family library;

[0017] Until the BIM model meets the design specifications;

[0018] The method for constructing the three-dimensional site layout model includes:

[0019] Collecting geographic environmental data of the site through a geographic information system;

[0020] The geographical environment data is input into the modeling software, and a three-dimensional site layout model is established through the modeling software.

[0021] As a preferred solution of the aerobic treatment method for landfill management of the present invention, the method for constructing the virtual site model includes:

[0022] Establish a standard coordinate system and adjust the BIM model and 3D site layout model according to the standard coordinate system;

[0023] Import the BIM model into the 3D site layout model;

[0024] Check the integration of the BIM model and the site model. When the sub-model detection result is misaligned, adjust the parametric components until the sub-model detection result is aligned. When the sub-model detection result is aligned, output the virtual site model.

[0025] As a preferred solution of the aerobic treatment method for landfill management of the present invention, when comparing the actual construction information with the virtual construction information, the specific steps include:

[0026] Mark the key phases of the construction phase as synchronization points and mark the same synchronization points in the simulation software;

[0027] Make a schedule of X days and mark the synchronization points as T 1 , T 2 ,……,T N , N<X;

[0028] Collect actual construction information at the end of each day and compare the actual progress with the virtual construction information;

[0029] Calculate the difference percentage between the actual progress and the planned progress, and determine whether the difference percentage is equal to 0. If the determination result is equal to 0, no dynamic adjustment is performed; if the determination result is not equal to 0, dynamic adjustment is performed.

[0030] Repeat the monitoring of actual progress every day and calculate the new difference percentage. When the new difference percentage is not equal to 0, the virtual construction information is updated through dynamic adjustment;

[0031] The calculation formula of the difference percentage is expressed as:

[0032] D t =P t -A t ;

[0033] Where D t Expressed as percentage difference, P t It is expressed as the planned progress of the tth day, A t Expressed as the actual progress on day t;

[0034] When D t When it is >0, it means that the actual progress lags behind the planned progress;

[0035] When D t When <0, it means the actual progress is ahead of the planned progress.

[0036] As a preferred embodiment of the aerobic treatment method for landfill management of the present invention, the dynamic adjustment step includes:

[0037] Recalculate the average daily progress required to reach the next synchronization point based on the actual progress;

[0038] Input the new daily average progress into the simulation software and use the simulation software to adjust the catch-up plan or slowdown plan;

[0039] The calculation formula of the average daily progress is expressed as:

[0040]

[0041] In the formula, R t It is expressed as the average daily progress, t is the current day, P Tn Expressed as the percentage of the planned progress from the current to the next synchronization point, T n Indicates the number of days until the next synchronization point.

[0042] As a preferred solution of the aerobic treatment method for landfill management of the present invention, the analysis step of the twin data platform includes analyzing the actual environmental information and analyzing the dynamic adjustment information, wherein;

[0043] The steps of analyzing the actual environment information by the twin data platform include:

[0044] Preset data types and establish corresponding security thresholds based on the data types;

[0045] When the actual environment information corresponding to a certain data type exceeds the safety threshold, the data type is recorded and the collection interval is shortened;

[0046] This data type is classified into mild, moderate, and severe according to the degree of exceeding the safety threshold;

[0047] The step of analyzing the dynamic adjustment information by the twin data platform includes:

[0048] Query whether there is a record of the data type at present. If so, combine the actual environment information corresponding to the data type with the dynamic adjustment information to predict whether the actual environment information reaches the safety threshold. If not, re-update the dynamic adjustment information until the safety threshold is reached. If so, predict whether the actual environment information corresponding to the remaining data types reaches the safety threshold. Stop prediction after all the safety thresholds are reached.

[0049] As a preferred solution of the aerobic treatment method for landfill management of the present invention, wherein: the feedback information includes a comparison between the actual progress and the planned progress, the identified potential risks and risk levels, and the adjustment method includes progress adjustment suggestions and risk mitigation measures;

[0050] The feedback information and the adjustment method are output to a visual display device.

[0051] In a second aspect, an embodiment of the present invention provides an aerobic treatment system for landfill management, which includes: a data acquisition module, a model building module, an analysis and comparison module, and an evaluation module;

[0052] The data acquisition module is used to collect various environmental data on site and collect actual environmental information;

[0053] The model building module is used to build a BIM model and a three-dimensional site layout model, and integrate the two models to output a virtual site model;

[0054] The analysis and comparison module is used to compare the actual construction information with the virtual construction information, analyze the difference between the actual situation and the prediction, and generate dynamic adjustment information;

[0055] The evaluation module is used to analyze the actual environment information and the dynamic adjustment information, and output feedback information and adjustment methods.

[0056] In a third aspect, an embodiment of the present invention provides a computer device, including a memory and a processor, wherein the memory stores a computer program, wherein: when the processor executes the computer program, any step of the above-mentioned aerobic treatment method for landfill management is implemented.

[0057] In a fourth aspect, an embodiment of the present invention provides a computer-readable storage medium having a computer program stored thereon, wherein: when the computer program is executed by a processor, any step of the above-mentioned aerobic treatment method for landfill management is implemented.

[0058] The beneficial effects of the present invention are as follows: by constructing a virtual site model and comparing it with the actual construction information in real time, dynamic synchronization of the virtual and actual environments is achieved, and a highly accurate digital twin environment is created by combining the BIM model and the three-dimensional site layout model. By setting synchronization points and daily progress comparisons, the system can timely calculate the difference percentage, thereby accurately quantifying the construction progress deviation, which not only improves the accuracy of progress management, but also greatly improves the response speed.

[0059] Integrate environmental monitoring data and construction progress management into the twin data platform. By presetting data types and safety thresholds, the system can automatically identify environmental risks and adjust data collection frequency according to the degree of risk. At the same time, the environmental data analysis results are combined with dynamic adjustment information to predict the potential impact of construction adjustments on the environment. Dynamic adjustment information is updated preferentially through data types that exceed the safety threshold, which greatly improves the environmental safety of the project. BRIEF DESCRIPTION OF THE DRAWINGS

[0060] In order to more clearly illustrate the technical solutions of the embodiments of the present invention, the following briefly introduces the drawings required for describing the embodiments. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without creative work. Among them:

[0061] Figure 1 Flowchart of aerobic treatment method for landfill remediation.

[0062] Figure 2 Infographic of collected data for aerobic treatment methods used in landfill remediation. DETAILED DESCRIPTION

[0063] In order to make the above-mentioned purposes, features and advantages of the present invention more obvious and easy to understand, the specific implementation methods of the present invention are described in detail below in conjunction with the drawings of the specification. Obviously, the described embodiments are part of the embodiments of the present invention, but not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary persons in the art without creative work should fall within the scope of protection of the present invention.

[0064] In the following description, many specific details are set forth to facilitate a full understanding of the present invention, but the present invention may also be implemented in other ways different from those described herein, and those skilled in the art may make similar generalizations without violating the connotation of the present invention. Therefore, the present invention is not limited to the specific embodiments disclosed below.

[0065] Secondly, the term "one embodiment" or "embodiment" as used herein refers to a specific feature, structure, or characteristic that may be included in at least one implementation of the present invention. The term "in one embodiment" that appears in different places in this specification does not necessarily refer to the same embodiment, nor does it refer to a separate or selective embodiment that is mutually exclusive with other embodiments.

[0066] The present invention is described in detail with reference to schematic diagrams. When describing the embodiments of the present invention, for the sake of convenience, the cross-sectional diagrams showing the device structure will not be partially enlarged according to the general scale, and the schematic diagrams are only examples, which should not limit the scope of protection of the present invention. In addition, in actual production, the three-dimensional dimensions of length, width and depth should be included.

[0067] At the same time, in the description of the present invention, it should be noted that the directions or positional relationships indicated by the terms "upper, lower, inner and outer" are based on the directions or positional relationships shown in the drawings, and are only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific direction, be constructed and operated in a specific direction, and therefore cannot be understood as limiting the present invention. In addition, the terms "first, second or third" are only used for descriptive purposes and cannot be understood as indicating or implying relative importance.

[0068] In the present invention, unless otherwise clearly specified and limited, the terms "install, connect, connect" should be understood in a broad sense, for example: it can be a fixed connection, a detachable connection or an integral connection; it can also be a mechanical connection, an electrical connection or a direct connection, or it can be indirectly connected through an intermediate medium, or it can be the internal communication of two components. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.

[0069] Example 1

[0070] Reference Figure 1 and Figure 2 , which is the first embodiment of the present invention, provides an aerobic treatment method for landfill management, comprising the following steps:

[0071] S1. Collecting actual environment information, building a virtual site model, and predicting virtual construction information through the virtual site model.

[0072] The virtual site model includes a BIM model and a three-dimensional site layout model;

[0073] The method for constructing the BIM model includes:

[0074] Establish a landfill entity model through modeling software, and establish corresponding family libraries for all sub-models of the entity model;

[0075] Unify all sub-models together to obtain the BIM model;

[0076] Use detection tools to identify collision problems in the BIM model, and then adjust the parametric components in the family library;

[0077] Until the BIM model meets the design specifications;

[0078] When constructing the BIM model, use GPS equipment and 3D laser scanners (such as Leica RTC360) to conduct a full-scale scan of the landfill to obtain accurate 3D data of terrain, landforms and existing facilities. At the same time, use drones (such as DJI Phantom 4RTK) for aerial photography to obtain a bird's-eye view of the landfill and surrounding environment information. Autodesk Revit2024 is selected as the main modeling software, and the point cloud data obtained from GPS and laser scanners are imported into Revit. Use Revit's terrain tools to create an accurate terrain model based on the point cloud data. According to the design drawings and field data, the main structures of the landfill, such as the leachate collection system, gas collection system, and cover layer, are established, and corresponding family libraries are created for each sub-model, such as the leachate collection pipe family, the gas collection well family, and the cover layer material family. All sub-models are imported into the main project file, and the link function of Revit is used to ensure the correct association and positioning between the sub-models. Use Autodesk Navisworks 2024 Perform collision detection, export collision reports, identify conflict points in the BIM model, return to Revit, and adjust the parametric components in the family library according to the collision report. For example, adjust the routing of the leachate collection pipeline to avoid conflict with the gas collection well. Repeat this process until all collision issues are resolved.

[0079] The method for constructing the three-dimensional site layout model includes:

[0080] Collecting geographic environmental data of the site through a geographic information system;

[0081] Inputting the geographical environment data into modeling software, and establishing a three-dimensional site layout model through the modeling software;

[0082] When constructing the 3D site layout model, ArcGIS Pro 2.9 was selected as the main GIS software, LiDAR (Light Detection and Ranging) technology was used to obtain a high-precision digital elevation model (DEM), and a Leica ALS80 laser scanner was used for aerial LiDAR scanning to obtain point cloud data.

[0083] The method for constructing the virtual site model comprises:

[0084] Establish a standard coordinate system and adjust the BIM model and 3D site layout model according to the standard coordinate system;

[0085] Import the BIM model into the 3D site layout model;

[0086] Check the integration of the BIM model and the site model. If the sub-model detection result is not aligned, adjust the parametric components until the sub-model detection result is aligned. If the sub-model detection result is aligned, output the virtual site model.

[0087] Adopting the WGS84 / UTM projection coordinate system, which is a universal coordinate system, and the real-time dynamic (RTK) measurement method, a Trimble R12i GNSS receiver was used to set at least 4 control points on the landfill site. Open Autodesk Revit 2024, load the previously created BIM model, apply the "shared coordinate system" function, align the model to the actual geographic location, and import the BIM model into the 3D site layout model.

[0088] S2. Monitor actual construction information, and then compare the actual construction information with the virtual construction information to obtain dynamic adjustment information.

[0089] When comparing the actual construction information with the virtual construction information, the specific steps include:

[0090] Mark the key phases of the construction phase as synchronization points and mark the same synchronization points in the simulation software;

[0091] Make a schedule of X days and mark the synchronization points as T 1 、T 2 ,……,T N , N<X;

[0092] Collect actual construction information at the end of each day and compare the actual progress with the virtual construction information;

[0093] Calculate the difference percentage between the actual progress and the planned progress, and determine whether the difference percentage is equal to 0. If the determination result is equal to 0, no dynamic adjustment is performed; if the determination result is not equal to 0, dynamic adjustment is performed.

[0094] Repeat the monitoring of actual progress every day and calculate the new difference percentage. When the new difference percentage is not equal to 0, the virtual construction information is updated through dynamic adjustment;

[0095] The calculation formula of the difference percentage is expressed as:

[0096] D t =P t -A t ;

[0097] Where D t Expressed as percentage difference, P t It is expressed as the planned progress of the tth day, A tExpressed as the actual progress on day t;

[0098] When D t When it is >0, it means that the actual progress lags behind the planned progress;

[0099] When D t When <0, it means the actual progress is ahead of the planned progress;

[0100] In the specific implementation, for example, a 30-day construction schedule is formulated, and key synchronization points are set: the 5th day, the 10th day, and the 20th day. A detailed work plan and progress target are formulated for each time period. After that, the actual progress data is collected at the end of each day, and the actual progress is compared with the planned progress. The difference percentage between the actual progress and the planned progress is calculated. For example, at the end of the first day, the planned completion rate is 20%, and the actual completion rate is 10%, with a difference of 10%. Based on the actual progress, dynamic adjustments need to be made;

[0101] Among them, Figure 2 As shown, when monitoring actual construction information, different actual data are also collected through a variety of different sensors to ensure the normal operation of the construction.

[0102] The step of dynamic adjustment includes:

[0103] Recalculate the average daily progress required to reach the next synchronization point based on the actual progress;

[0104] Input the new daily average progress into the simulation software and use the simulation software to adjust the catch-up plan or slowdown plan;

[0105] The calculation formula for the average daily progress is expressed as:

[0106]

[0107] In the formula, R t It is expressed as the average daily progress, t is the current day, P Tn Expressed as the percentage of the planned progress from the current to the next synchronization point, T n The number of days to the next synchronization point;

[0108] For example, if 90% of the work needs to be completed in the remaining 4 days, the daily average progress should be 22.5%. The newly calculated daily average progress is input into the simulation software, and the simulation software automatically adjusts the subsequent schedule and resource allocation. The simulation software generates a feasible catch-up plan based on the new progress requirements, evaluates the feasibility and cost of various adjustment plans, selects the best plan and implements it;

[0109] Continue to monitor actual progress daily and make dynamic adjustments if new deviations emerge.

[0110] S3. Input the actual environment information and the dynamic adjustment information into the twin data platform, analyze the received data through the twin data platform, and output feedback information and adjustment methods.

[0111] The analysis step of the twin data platform includes analyzing the actual environment information and analyzing the dynamic adjustment information, wherein;

[0112] The steps of analyzing the actual environment information by the twin data platform include:

[0113] Preset data types and establish corresponding security thresholds based on the data types;

[0114] When the actual environment information corresponding to a certain data type exceeds the safety threshold, the data type is recorded and the collection interval is shortened;

[0115] This data type is classified into mild, moderate, and severe according to the degree of exceeding the safety threshold;

[0116] When analyzing the actual environment, the preset data types and corresponding security thresholds are expressed in a table as follows:

[0117] Table 1: Schematic diagram of preset data types and security thresholds:

[0118] Serial number Data Types Safety threshold 1 Methane concentration 5% 2 Leachate water level 2 meters 3 Groundwater pH The safety threshold range is 6.5-8.5 4 Landfill surface settlement 50 cm / year

[0119] If the methane concentration is detected to reach 6.2%, the system will mark "methane concentration" as an abnormal state and shorten the sampling interval of this data type. In this example, the sampling interval of methane concentration will be shortened from 60 minutes to 30 minutes. Secondly, the minimum sampling interval is set to 5 minutes to prevent too frequent sampling;

[0120] According to the degree of exceeding the safety threshold, the anomaly is divided into mild, moderate and severe. Mild: exceeding the safety threshold by no more than 10%; moderate: exceeding the safety threshold by 10%-30%; severe: exceeding the safety threshold by more than 30%. In this case, the methane concentration of 6.2% exceeds the safety threshold of 5%, which is 24%, so it is classified as a moderate anomaly.

[0121] The step of analyzing the dynamic adjustment information by the twin data platform includes:

[0122] Query whether the data type currently has records. If so, combine the actual environment information corresponding to the data type with the dynamic adjustment information to predict whether the actual environment information is within the safety threshold. If not, re-update the dynamic adjustment information until the safety threshold is reached. If so, predict whether the actual environment information corresponding to the remaining data types reaches the safety threshold. Stop prediction until all of them reach the safety threshold.

[0123] The system queries the current abnormal data types. In this case, it is found that the "methane concentration" is in an abnormal state. For each abnormal data type, the system combines the actual environmental information with possible dynamic adjustment measures to predict future environmental changes. For example, the system may consider increasing the gas extraction rate as an adjustment measure. Assume that the prediction model shows that increasing the gas extraction rate by 20% may reduce the methane concentration to 5.5% within 4 hours. If the prediction results show that the adjusted environmental information still does not reach the safety threshold, the system will readjust the parameters and conduct a new round of predictions. In this case, the system may try to increase the gas extraction rate by 25%, and predict that the methane concentration may drop to 4.9% within 6 hours, reaching the safety threshold.

[0124] The feedback information includes the comparison between the actual progress and the planned progress, the identified potential risks and risk levels, and the adjustment methods include progress adjustment suggestions and risk mitigation measures;

[0125] The feedback information and the adjustment method are output to a visual display device.

[0126] In summary, by building a virtual site model and comparing it with the actual construction information in real time, dynamic synchronization of the virtual and actual environments is achieved. By combining the BIM model and the three-dimensional site layout model, a highly accurate digital twin environment is created. By setting synchronization points and daily progress comparisons, the system can calculate the difference percentage in a timely manner, thereby accurately quantifying the construction progress deviation, which not only improves the accuracy of progress management, but also greatly improves the response speed.

[0127] Integrate environmental monitoring data and construction progress management into the twin data platform. By presetting data types and safety thresholds, the system can automatically identify environmental risks and adjust data collection frequency according to the degree of risk. At the same time, the environmental data analysis results are combined with dynamic adjustment information to predict the potential impact of construction adjustments on the environment. Dynamic adjustment information is updated preferentially through data types that exceed the safety threshold, which greatly improves the environmental safety of the project.

[0128] Example 2

[0129] Based on the first embodiment, this embodiment further provides an aerobic treatment system for landfill management, including: a data acquisition module, a model building module, an analysis and comparison module, and an evaluation module;

[0130] The data acquisition module is used to collect various environmental data on site and collect actual environmental information;

[0131] The model building module is used to build a BIM model and a three-dimensional site layout model, and integrate the two models to output a virtual site model;

[0132] The analysis and comparison module is used to compare the actual construction information with the virtual construction information, analyze the difference between the actual situation and the prediction, and generate dynamic adjustment information;

[0133] The evaluation module is used to analyze the actual environment information and the dynamic adjustment information, and output feedback information and adjustment methods.

[0134] This embodiment also provides a computer device, which is suitable for the aerobic treatment method for landfill management, including a memory and a processor; the memory is used to store computer executable instructions, and the processor is used to execute computer executable instructions to implement the aerobic treatment method for landfill management as proposed in the above embodiment.

[0135] The computer device may be a terminal, and the computer device includes a processor, a memory, a communication interface, a display screen and an input device connected via a system bus. The processor of the computer device is used to provide computing and control capabilities. The memory of the computer device includes a non-volatile storage medium and an internal memory. The non-volatile storage medium stores an operating system and a computer program. The internal memory provides an environment for the operation of the operating system and the computer program in the non-volatile storage medium. The communication interface of the computer device is used to communicate with an external terminal in a wired or wireless manner, and the wireless manner can be achieved through WIFI, an operator network, NFC (near field communication) or other technologies. The display screen of the computer device may be a liquid crystal display screen or an electronic ink display screen, and the input device of the computer device may be a touch layer covering the display screen, or a key, trackball or touchpad provided on the housing of the computer device, or an external keyboard, touchpad or mouse, etc.

[0136] This embodiment also provides a storage medium on which a computer program is stored. When the program is executed by a processor, the aerobic treatment method for landfill management proposed in the above embodiment is implemented.

[0137] The storage medium proposed in this embodiment and the data storage method proposed in the above embodiment belong to the same inventive concept. The technical details not fully described in this embodiment can be found in the above embodiment, and this embodiment has the same beneficial effects as the above embodiment.

[0138] Example 3

[0139] On the basis of the previous two embodiments, this embodiment provides an aerobic treatment method for landfill management. In order to verify the beneficial effects of the present invention, scientific demonstration is carried out through simulation experiments.

[0140] Comparative example: The progress is adjusted manually based on human experience, and only the BIM model and the three-dimensional site layout model are built, and the two models cannot be combined.

[0141] Object of investigation: a landfill with an area of ​​10 hectares; Experimental period: 90 days; Key indicators: construction schedule deviation, methane concentration control, leachate water level control, number of environmental risk events and decision response time.

[0142] Table 2: Schematic diagram of simulation test results

[0143] index Example 1 Comparative Example Final construction schedule deviation +0 days +8 days Average methane concentration 2.8% 4.2% Average leachate level 1.2 m 1.7 m Number of environmental risk events 1 time 8 times Average decision response time 1.2h 11h

[0144] It can be seen from Table 2 that the results of the final construction period progress deviation show that Example 1 is more accurate and efficient in the progress management group, and Example 1 can ensure that the method is more effective in environmental risk control through the setting of safety thresholds, and greatly reduce the frequency of environmental risks.

[0145] It should be noted that the above embodiments are only used to illustrate the technical solutions of the present invention rather than to limit it. Although the present invention has been described in detail with reference to the preferred embodiments, those skilled in the art should understand that the technical solutions of the present invention can be modified or replaced by equivalents without departing from the spirit and scope of the technical solutions of the present invention, which should all be included in the scope of the present invention.

Claims

1. An aerobic treatment method for landfill management, characterized in that: The following steps are included: Collecting actual environment information, building a virtual site model, and predicting virtual construction information through the virtual site model; Monitoring actual construction information, and then comparing the actual construction information with the virtual construction information to obtain dynamic adjustment information; The actual environment information and the dynamic adjustment information are input into the twin data platform, the received data is analyzed by the twin data platform, and feedback information and adjustment methods are output.

2. The aerobic treatment method for landfill management according to claim 1, characterized in that: The virtual site model includes a BIM model and a three-dimensional site layout model; The method for constructing the BIM model includes: Establish a landfill entity model through modeling software, and establish corresponding family libraries for all sub-models of the entity model; Unify all sub-models together to obtain the BIM model; Use detection tools to identify collision problems in the BIM model, and then adjust the parametric components in the family library; Until the BIM model meets the design specifications; The method for constructing the three-dimensional site layout model includes: Collecting geographic environmental data of the site through a geographic information system; The geographical environment data is input into the modeling software, and a three-dimensional site layout model is established through the modeling software.

3. The aerobic treatment method for landfill management as claimed in claim 2, characterized in that: The method for constructing the virtual site model comprises: Establish a standard coordinate system and adjust the BIM model and 3D site layout model according to the standard coordinate system; Import the BIM model into the 3D site layout model; Check the integration of the BIM model and the site model. When the sub-model detection result is misaligned, adjust the parametric components until the sub-model detection result is aligned. When the sub-model detection result is aligned, output the virtual site model.

4. The aerobic treatment method for landfill management according to claim 3, characterized in that: When comparing the actual construction information with the virtual construction information, the specific steps include: Mark the key phases of the construction phase as synchronization points and mark the same synchronization points in the simulation software; Make a schedule for X days and mark the synchronization points as T1, T2, ..., T N , N<X; Collect actual construction information at the end of each day and compare the actual progress with the virtual construction information; Calculate the difference percentage between the actual progress and the planned progress, and determine whether the difference percentage is equal to 0. If the determination result is equal to 0, no dynamic adjustment is performed; if the determination result is not equal to 0, dynamic adjustment is performed. Repeat the monitoring of actual progress every day and calculate the new difference percentage. When the new difference percentage is not equal to 0, the virtual construction information is updated through dynamic adjustment; The calculation formula of the difference percentage is expressed as: D t =P t -A t ; Where D t Expressed as percentage difference, P t It is expressed as the planned progress of the tth day, A t Expressed as the actual progress on day t; When D t When it is >0, it means that the actual progress lags behind the planned progress; When D t When <0, it means the actual progress is ahead of the planned progress.

5. The aerobic treatment method for landfill management according to claim 4, characterized in that: The step of dynamic adjustment includes: Recalculate the average daily progress required to reach the next synchronization point based on the actual progress; Input the new daily average progress into the simulation software and use the simulation software to adjust the catch-up plan or slowdown plan; The calculation formula for the average daily progress is expressed as: In the formula, R t It is expressed as the average daily progress, t is the current day, P Tn Expressed as the percentage of the planned progress from the current to the next synchronization point, T n Expressed as the number of days until the next synchronization point.

6. The aerobic treatment method for landfill management according to claim 5, characterized in that: The analysis step of the twin data platform includes analyzing the actual environment information and analyzing the dynamic adjustment information, wherein; The steps of analyzing the actual environment information by the twin data platform include: Preset data types and establish corresponding security thresholds based on the data types; When the actual environment information corresponding to a certain data type exceeds the safety threshold, the data type is recorded and the collection interval is shortened; This data type is classified into mild, moderate, and severe according to the degree of exceeding the safety threshold; The step of analyzing the dynamic adjustment information by the twin data platform includes: Query whether there is a record of the data type at present. If so, combine the actual environment information corresponding to the data type with the dynamic adjustment information to predict whether the actual environment information reaches the safety threshold. If not, re-update the dynamic adjustment information until the safety threshold is reached. If so, predict whether the actual environment information corresponding to the remaining data types reaches the safety threshold. Stop prediction after all the safety thresholds are reached.

7. The aerobic treatment method for landfill management according to claim 6, characterized in that: The feedback information includes the comparison between the actual progress and the planned progress, the identified potential risks and risk levels, and the adjustment methods include progress adjustment suggestions and risk mitigation measures; The feedback information and the adjustment method are output to a visual display device.

8. An aerobic treatment system for landfill management, based on the aerobic treatment method for landfill management according to any one of claims 1 to 7, characterized in that: It includes data collection module, model building module, analysis and comparison module, and evaluation module; The data acquisition module is used to collect various environmental data on site and collect actual environmental information; The model building module is used to build a BIM model and a three-dimensional site layout model, and integrate the two models to output a virtual site model; The analysis and comparison module is used to compare the actual construction information with the virtual construction information, analyze the difference between the actual situation and the prediction, and generate dynamic adjustment information; The evaluation module is used to analyze the actual environment information and the dynamic adjustment information, and output feedback information and adjustment methods.

9. A computer device comprising a memory and a processor, wherein the memory stores a computer program, wherein: When the processor executes the computer program, the steps of the aerobic treatment method for landfill management according to any one of claims 1 to 7 are implemented.

10. A computer-readable storage medium having a computer program stored thereon, characterized in that: When the computer program is executed by a processor, the steps of the aerobic treatment method for landfill management described in any one of claims 1 to 7 are implemented.

Citation Information

Patent Citations

  • BIMbased metro construction method

    CN106202723A

  • Three-dimensional digital model-based hydraulic and hydropower engineering progress monitoring method

    CN107273640A

  • Underground diaphragm wall construction method based on BIM technology

    CN111062081A

  • Construction process management and control method based on digital twinning

    CN113110313A

  • Engineering project management method, device and system based on digital twinning

    CN113626914A