Bridge drainage and landscape lighting combined construction structure and method
By setting longitudinal water pipes and lamps as multi-section standard sections, assembled and installed on the lower part of the bridge, the problem of drainage and landscape lighting during bridge construction is solved, the number of installations of climbing vehicles is reduced, and the construction safety and aesthetics are improved , achieving improvements in the overall lighting effect of the bridge.
Patent Information
- Application Number
- CN202411494000.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-10-24
- Publication Date
- 2024-12-20
AI Technical Summary
During bridge construction, the successive construction of bridge deck drainage and landscape lighting caused shading problems, which could not achieve the overall lighting effect of the design, and there was a need for two high-rise vehicles to construct, which increased construction difficulty and safety hazards.
Longitudinal water receptacle pipes and lamps are set as multi-section standard sections, installed on the ground and installed on the lower part of the bridge through the climbing car. The lamps and longitudinal water receptacle pipes are connected through the joint connection between grooves and bumps to achieve fixed and sliding installation, reducing the climbing car Number of installations.
It reduces construction difficulty and safety risks, realizes the organic combination of bridge drainage and landscape lighting, improves night visibility and overall aesthetics, shortens construction period and reduces workload.
Smart Images

Figure CN119162922A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of bridge construction, and in particular to a construction structure and method for combining bridge drainage with landscape lighting. Background Art
[0002] With the continuous development of urban construction, the construction of bridge projects is also constantly raising higher requirements. Because of the many professions involved in the construction process, strong comprehensiveness and wide impact, modern bridges are often important landmarks and landscape elements in the city. In the process of bridge construction, the structure is an important guarantee for the functionality of the project, and bridge lighting is a necessary means to enhance the city's night image and charm. The combination of structure and beauty in the current bridge construction is an important direction of its development. Under such factors, it is necessary to continuously develop and improve the integration of construction technology between different professions in bridge construction to meet the growing functional and aesthetic needs.
[0003] For the bridge deck construction in the bridge project, the bridge deck drainage structure pipe opening is reserved during the structural construction of the concrete box girder or the prefabrication of the steel box girder. Due to the different construction professions, and the electrical engineering installation must be done by personnel holding electrician operation certificates to carry out wiring and installation, the drainage project will continue after the structural construction is completed, while the bridge landscape lighting construction will be relatively moved back. At this time, the same part needs to be constructed by two aerial platforms, and the drainage and lighting contents are constructed successively. There will be a problem of obstruction between the bridge deck drainage and landscape lighting constructed successively, and the overall lighting effect of the bridge expected by the design section cannot be achieved. Summary of the invention
[0004] In view of the above-mentioned defects in the prior art, a construction structure and method combining bridge drainage and landscape lighting are provided, which can reduce the installation of a aerial platform, reduce the construction difficulty and improve the construction safety.
[0005] The technical solution adopted by the present invention to solve the above technical problems is:
[0006] The construction method combining bridge drainage and landscape lighting is characterized by:
[0007] Set the longitudinal water collection pipe and lamps to multiple sections;
[0008] In the ground construction area, one or more sections of lighting fixtures are installed on a longitudinal water collection pipe to form a standard section;
[0009] A climbing work vehicle is used to install the standard section at the bottom of the bridge, and the lamps are connected to the junction box on the wall beam.
[0010] According to the above technical solution, the lamp is installed on the side of the longitudinal water collecting pipe located at the bridge pier.
[0011] According to the above technical solution, the longitudinal water collecting pipe and the lamp are set as standard sections of the same length; on the longitudinal water collecting pipe connected to the transverse drainage pipe, two sections of the lamp of corresponding length are cut from the standard section of the lamp and installed on the longitudinal water collecting pipe.
[0012] According to the above technical solution, the longitudinal water collecting pipe and the lamps use standard sections of the same length, and the length of the standard section ranges from 5 to 7 meters. At the same time as the standard section, the lamps in the standard section are connected to the junction box.
[0013] According to the above technical scheme, matching grooves and protrusions are respectively provided on adjacent surfaces of the lamp and the longitudinal water collecting tube, and the lamp is slidably connected to the longitudinal water collecting tube through the matching connection between the protrusion and the groove; and penetrating pin holes and pin grooves are provided on the grooves and the protrusions, and a limiting pin passes through the pin holes and pin grooves on the lamp and the longitudinal water collecting tube at the same time to achieve a fixed connection between the two.
[0014] According to the above technical solution, before using the aerial platform to install the standard section, the on-site ground conditions need to be inspected. If a loose address is encountered, the site needs to be hardened.
[0015] The construction structure combining bridge drainage and landscape lighting includes a bridge, and a drainage pipeline system and an electric circuit system are arranged on the bridge; the drainage pipeline system includes a longitudinal water collection pipeline arranged along the length direction of the bridge, and the electric circuit system includes lamps arranged along the length direction of the wall beam;
[0016] The characteristics are as follows: the longitudinal water collecting pipe and the lamp are arranged in multiple sections, and a lamp installation structure is provided between the longitudinal water collecting pipe and the lamp; a lamp matching its length is installed on each section of the longitudinal water collecting pipe, and the lamp is installed on the side of the longitudinal water collecting pipe located on the bridge pier, forming a standard section; the operator installs the standard section at the bottom of the bridge in sequence.
[0017] According to the above technical scheme, the drainage pipe system includes vertical downpipes arranged vertically, inspection ports arranged at the bottom ends of the vertical downpipes, transverse drainage pipes along the width direction of the bridge, and vertical drainage pipes located on the wall beam piers; a number of vertical downpipes are arranged at intervals along the length direction of the bridge, and the vertical downpipes are located inside the bridge, connecting the bridge deck and the bottom of the bridge; a longitudinal water collecting pipe is arranged at the bottom of the vertical downpipe, and is connected to all vertical downpipes through a four-way joint; a number of transverse drainage pipes are arranged on the longitudinal water collecting pipe, and are connected between the vertical drainage pipe and the longitudinal water collecting pipe.
[0018] According to the above technical scheme, the circuit system includes a junction box arranged in the wall beam anti-collision guardrail, a vertical wire threading hole penetrating the wall beam, and an electric wire connected between the junction box and the lamp; one end of the electric wire is connected to the junction box, and the end of the electric wire passes through the vertical wire threading hole and is connected to the lamp; a plurality of junction boxes are arranged at intervals along the length direction of the bridge, and one junction box corresponds to one or more lamps.
[0019] According to the above technical solution, the lamp installation structure includes a groove provided on the lamp, a protrusion provided on the longitudinal water collecting pipe, and a limit pin, the cross-sectional size of the groove increases from the outside to the inside, and the shape and size of the protrusion match the size of the groove; the groove and the protrusion are arranged throughout the length of the lamp;
[0020] A plurality of latch holes are provided on the back of the lamp in the groove, and a latch groove corresponding to the latch holes is provided on the protrusion; after the lamp is installed in place, the latch holes and the latch grooves are aligned, and the limiting latch is placed in the latch holes and the latch grooves at the same time; and the latch is limited by the backlight panel of the lamp.
[0021] The present invention has the following beneficial effects:
[0022] 1. The installation point of landscape lighting fixtures is converted from the traditional high-altitude cable tray to the longitudinal water collection pipe, and the lamps and longitudinal water collection pipes are constructed into standard sections. The assembly work of the standard sections is located on the ground, which realizes the conversion of the construction area of the lamps from high altitude to the ground, reducing the difficulty of construction. Secondly, without affecting the original functionality, the construction of bridge drainage and landscape lighting is organically combined, unified planning and construction management are relatively simpler, and the coordination work and possible problems in the original process are reduced. Finally, after the longitudinal water collection pipe and the lamp are combined, compared with the existing technology of installing lamps and longitudinal water collection pipes on both sides by climbing vehicles, one climbing vehicle installation is reduced. The combination of the two makes the bridge safer in various situations. Reasonable layout and installation can reduce potential safety hazards, reduce a certain amount of workload, avoid mutual interference and repeated operations, and may improve construction efficiency to a certain extent and shorten the overall construction period.
[0023] 2. The lamp is installed on the inner side of the longitudinal water collecting pipe, between the longitudinal water collecting pipe and the bridge pier. Compared with the prior art in which the lamp is installed on the bottom of the bridge flange plate, the lamp is prevented from being blocked by the longitudinal water collecting pipe. This can better improve nighttime visibility, show the shape of the bridge, make the whole more harmonious and beautiful, and enhance the image of the city or region.
[0024] The above description is only an overview of the technical solution of the present invention. In order to more clearly understand the technical means of the present invention and implement it according to the contents of the specification, the following is a detailed description of the preferred embodiments of the present invention in conjunction with the accompanying drawings. The specific implementation of the present invention is given in detail by the following embodiments and their accompanying drawings. BRIEF DESCRIPTION OF THE DRAWINGS
[0025] The drawings described herein are used to provide further understanding of the present invention and constitute a part of this application. The illustrative embodiments of the present invention and their descriptions are used to explain the present invention and do not constitute improper limitations on the present invention.
[0026] Figure 1 It is a structural schematic diagram of an embodiment provided by the present invention;
[0027] Figure 2 The schematic diagram of the connection between the longitudinal water collecting pipe and the lamp in the embodiment of the present invention is Figure 1 ;
[0028] Figure 3 is a schematic diagram of the connection between the standard segments of the embodiment provided by the present invention;
[0029] Figure 4 The schematic diagram of the connection between the longitudinal water collecting pipe and the lamp in the embodiment of the present invention is Figure 2 ;
[0030] Figure 5 It is a schematic diagram of the connection of the longitudinal water collecting pipe on the bridge according to the embodiment of the present invention;
[0031] Figure 6 It is a schematic diagram of the drainage pipeline system of an embodiment provided by the present invention in the length direction of the bridge;
[0032] Figure 7 It is a schematic diagram of a drainage pipeline system in the width direction of a bridge according to an embodiment of the present invention;
[0033] In the figure, 1. bridge; 2. longitudinal water collection pipeline; 3. lamp; 3-1. backlight panel; 4. lamp installation structure; 4-1. groove; 4-2. bump; 4-3. limit pin; 5. vertical downpipe; 6. inspection port; 7. horizontal drain pipe; 8. vertical drain pipe; 9. junction box; 10. vertical threading hole; 11. electric wire; 12. clamp; 13. standard section; 14. bridge pier. DETAILED DESCRIPTION
[0034] The following is combined with Figure 1-7 The principles and features of the present invention are described, and the examples are only used to explain the present invention and are not used to limit the scope of the present invention. In the following paragraphs, the present invention is described in more detail by way of example with reference to the accompanying drawings. The advantages and features of the present invention will become clearer according to the following description and claims. It should be noted that the drawings are all in a very simplified form and are not in precise proportions, and are only used to facilitate and clearly assist in explaining the purpose of the embodiments of the present invention.
[0035] It should be noted that when a component is referred to as being "fixed to" another component, it may be directly on the other component or there may also be a component centered. When a component is considered to be "connected to" another component, it may be directly connected to the other component or there may also be a component centered. When a component is considered to be "set on" another component, it may be directly set on the other component or there may also be a component centered. The terms "vertical", "horizontal", "left", "right" and similar expressions used herein are for illustrative purposes only.
[0036] Unless otherwise defined, all technical and scientific terms used herein have the same meaning as those commonly understood by those skilled in the art of the present invention. The terms used herein in the specification of the present invention are only for the purpose of describing specific embodiments and are not intended to limit the present invention. The term "and / or" used herein includes any and all combinations of one or more related listed items.
[0037] Reference Figure 1 to Figure 7 As shown, the construction structure of the bridge drainage combined with landscape lighting provided by the present invention.
[0038] Example 1
[0039] The invention comprises a bridge 1, on which a drainage pipe system and a circuit system are arranged; the drainage pipe system comprises a longitudinal water collecting pipe 2 arranged along the length direction of the bridge, and the circuit system comprises a lamp 3 arranged along the length direction of the wall beam.
[0040] The longitudinal water collecting pipe and the lamp are both arranged in multiple sections, and a lamp installation structure 4 is provided between the longitudinal water collecting pipe and the lamp; a lamp matching its length is installed on each section of the longitudinal water collecting pipe, and the lamp is installed on the side of the longitudinal water collecting pipe located on the bridge pier 14, forming a standard section 13; the operator sequentially installs the standard sections at the bottom of the bridge. The lamp and the longitudinal water collecting pipe are formed into standard sections on the ground, and the installation of the lamp is completed while the longitudinal water collecting pipe is installed; compared with the prior art, the lamp is installed separately at the bottom of the flange plate of the bridge, and only one aerial work vehicle operation is required to complete the installation of the lamp and the longitudinal water collecting pipe, which may improve the construction efficiency to a certain extent and shorten the overall construction period. Secondly, the construction area of the lamp is converted from high altitude to the ground, which reduces the construction difficulty and improves safety. Finally, the lamp is installed on the inner side of the longitudinal water collecting pipe, which is different from the prior art in that it is installed on the bottom of the bridge flange plate. This avoids the longitudinal water collecting pipe from blocking the light of the lamp, can better improve night visibility, show the shape of the bridge, make the overall look more harmonious and beautiful, and enhance the image of the city or region.
[0041] In Example 1, the drainage pipe system includes a vertical downpipe 5 arranged vertically, an inspection port 6 arranged at the bottom end of the vertical downpipe, a transverse drainage pipe 7 along the width direction of the bridge, and a vertical drainage pipe 8 located on the wall beam pier; a plurality of vertical downpipes are arranged at intervals along the length direction of the bridge, and the vertical downpipes are located inside the bridge, connecting the bridge deck and the bottom of the bridge; a longitudinal water collecting pipe is arranged at the bottom of the vertical downpipe, and is connected to all vertical downpipes through a four-way joint; a plurality of transverse drainage pipes are arranged on the longitudinal water collecting pipe, and are connected between the vertical drainage pipe and the longitudinal water collecting pipe.
[0042] In Example 1, the circuit system includes a junction box 9 provided in the wall beam anti-collision guardrail, a vertical threading hole 10 penetrating the wall beam, and a wire 11 connected between the junction box and the lamp; one end of the wire is connected to the junction box, and the wire passes through the vertical threading hole and is connected to the lamp; multiple junction boxes are arranged at intervals along the length of the bridge, and one junction box corresponds to one or more lamps. The circuit system can also take other forms, as long as it includes a lamp fixed on the longitudinal water collection pipe.
[0043] In Example 1, in order to reduce the construction difficulty, simplify the operation, and reduce the installation time to a certain extent, a preferred structure of a lamp installation structure is provided, wherein the lamp installation structure comprises a groove 4-1 provided on the lamp, a protrusion 4-2 provided on the longitudinal water collecting pipe, and a limit pin 4-3, wherein the cross-sectional size of the groove increases from the outside to the inside, and the shape and size of the protrusion match the size of the groove; the groove and the protrusion are arranged throughout the length of the lamp;
[0044] A plurality of latch holes are provided on the back of the lamp in the groove, and latch grooves corresponding to the latch holes are provided on the protrusion; after the lamp is installed in place, the latch holes and the latch grooves are aligned, and the limiting latch is placed in the latch holes and the latch grooves at the same time; and the latch is limited by the backlight panel 3-1 provided by the lamp to ensure that the latch cannot be detached from the latch holes and the latch grooves.
[0045] Other structural forms of lamp installation structures may also be used, for example, the lamp may be directly fixed to the longitudinal water collecting pipe by means of a clamp; or a hook may be provided on the longitudinal water collecting pipe and the lamp may be hung on the hook.
[0046] Example 2
[0047] The present invention also discloses a construction method combining bridge drainage and landscape lighting, comprising the following steps:
[0048] Step 1, construction preparation: Investigate the current ground conditions under the box beam. According to the site conditions, if there is a loose address, the site needs to be hardened to better meet the walking of equipment such as aerial platforms and ensure the safety of the construction process. At the same time, make preparations for the entry of on-site machinery and materials, mainly to prepare materials according to the length of the box beam of the bridge, mainly to determine the required length of the longitudinal water collection pipe at the bottom of the bridge flange plate and the required length of the corresponding landscape lighting lamps, arrange for the corresponding manufacturer to open the mold and produce the required longitudinal water collection pipe and lamps with lamp installation structure, make construction plan preparations, and ensure material supply.
[0049] The longitudinal water collection pipe and the lamp are set to standard sections of the same length; on the longitudinal water collection pipe connected to the horizontal drainage pipe, two sections of the lamp with corresponding lengths are cut from the standard section of the lamp and installed on the longitudinal water collection pipe. The lamp shell is cut to the required length on site, and the corresponding length of the lamp is modified to avoid the final assembly being too long or too short.
[0050] Preferably, the longitudinal water collecting pipe and the lamp adopt standard sections of the same length, the length of the standard section ranges from 5 to 7 meters, and the embodiment in the figure adopts 6 meters; at the same time as the standard section, the lamp in the standard section is connected to the junction box.
[0051] Step 2: In the ground construction area, install one or more sections of lamps on a longitudinal water collection pipe to form a standard section. Then, according to the position of the vertical threading hole at the bottom of the junction box reserved during the bridge construction process, the cables used to pass through the vertical threading holes on the spliced standard parts are prepared for the installation of components at the bottom of the box girder flange plate.
[0052] Step 3: Use a high-altitude work vehicle to install vertical downpipes in the flanges on both sides of the bridge, and use threaded plugs for the inspection ports at the bottom of the vertical downpipes; then install the standard section, and fix the pipe of the standard section to the flange plate at the bottom of the wall beam with a clamp 12, and connect it to the M16 expansion bolt at the bottom of the flange plate at the bottom of the wall beam through a 4mm thick steel plate clamp. Use cork pads to reversely fix the pipe to the bottom plate of the upper beam to prevent the pipe from loosening and displacement.
[0053] The pipes between the standard sections are connected by matching pipe sleeves, and the lamps between the standard sections are connected by cables, and waterproof treatment is done. Put the heat shrink tubing on the wire joints, shrink it by heating, and wrap the joints tightly, or use waterproof tape, first wrap a layer of electrical insulation tape clockwise around the wire joints, then tear the self-adhesive waterproof tape from the middle, wrap it clockwise with the inner part to tighten it, and finally wrap another layer of insulation tape.
[0054] Carry out the threading work at the reserved holes of the flange plate at the end of the box girder. The cable line should be run along the bottom of the beam. The pre-set cable line is introduced upward through the reserved hole into the junction box in the protective guardrail on the top of the beam. Use a cable bridge to fix the wiring at the bottom of the beam to prevent the cable from falling along the vertical hole after threading, which increases the subsequent work. If the cable falls off, it will be repaired by the hanging basket used during the construction of the anti-collision guardrail on the bridge.
[0055] After the installation of finished components of pipelines and lamps is completed, each beam section is used as a unit, and the existing temporary electricity during the construction process is utilized. A special distribution box is equipped to connect the temporary electricity, test the landscape lighting in the beam section, and promptly repair any parts that are not installed in place.
[0056] In this example, the installation point of the landscape lighting fixtures is converted from the traditional high-altitude cable tray to the longitudinal water collection pipe, and the lamps and longitudinal water collection pipes are constructed into standard sections. The assembly work of the standard sections is located on the ground, which realizes the conversion of the construction area of the lamps from high altitude to the ground, reducing the difficulty of construction. Secondly, without affecting the original functionality, the construction of bridge drainage and landscape lighting is organically combined, unified planning and construction management are relatively simpler, and the coordination work and possible problems in the original process are reduced. Finally, after the longitudinal water collection pipe and the lamp are combined, compared with the prior art of installing the lamps and longitudinal water collection pipes on both sides by a climbing vehicle, one climbing vehicle installation is reduced. The combination of the two makes the bridge safer in various situations. Reasonable layout and installation can reduce potential safety hazards, reduce a certain amount of workload, avoid mutual interference and repeated operations, and may improve construction efficiency to a certain extent and shorten the overall construction period.
[0057] In Example 2, in order to solve the problem of the illumination route of the bridge belly light, the lamp is installed on the side of the longitudinal water collecting pipe located at the bridge pier. The lamp is moved from the outside of the existing longitudinal water collecting pipe to the inside of the longitudinal water collecting pipe.
[0058] In Example 2, mutually matching grooves and protrusions are respectively provided on the adjacent surfaces of the lamp and the longitudinal water collecting pipe, and the lamp is slidably connected to the longitudinal water collecting pipe through the matching connection between the protrusion and the groove; and penetrating latch holes and latch grooves are provided on the grooves and the protrusions, and the limit latch simultaneously passes through the latch holes and latch grooves on the lamp and the longitudinal water collecting pipe to achieve a fixed connection between the two. The sliding installation of the lamp on the longitudinal water collecting pipe is achieved through the grooves and the protrusions, and the mutual movement between the protrusion and the groove is fixed by the latch, so that the lamp is fixed on the longitudinal water collecting pipe. This structure allows a large amount of preparatory work to be completed on the ground, reducing the difficulty of construction, simple operation, and reducing the time required for installation to a certain extent.
[0059] Preferably, when the longitudinal water collecting pipe and the lamp adopt the same length of the standard section of 6m, two latches are provided on the standard section, located at both ends of the standard section and 1m away from the end.
[0060] The above description is only a preferred embodiment of the present invention and does not limit the present invention in any form. Any ordinary technician in the industry can smoothly implement the present invention as shown in the drawings and described above. However, any equivalent changes, modifications and evolutions made by technicians familiar with the profession without departing from the scope of the technical solution of the present invention using the technical content disclosed above are all equivalent embodiments of the present invention. At the same time, any equivalent changes, modifications and evolutions made to the above embodiments based on the essential technology of the present invention are still within the protection scope of the technical solution of the present invention.
Claims
1. The construction method combining bridge drainage and landscape lighting is characterized by: Set the longitudinal water collection pipe and lamps to multiple sections; In the ground construction area, one or more sections of lighting fixtures are installed on a longitudinal water collection pipe to form a standard section; A climbing work vehicle is used to install the standard section at the bottom of the bridge, and the lamps are connected to the junction box on the wall beam.
2. The construction method combining bridge drainage and landscape lighting according to claim 1 is characterized by: The lamps are installed on the side of the longitudinal water collecting pipe located on the pier.
3. The construction method combining bridge drainage and landscape lighting according to claim 1 is characterized by: The longitudinal water collecting pipe and the lamp are set to standard sections of the same length; on the longitudinal water collecting pipe connected to the transverse drainage pipe, two sections of the lamp with corresponding lengths are cut from the standard section of the lamp and installed on the longitudinal water collecting pipe.
4. The construction method combining bridge drainage and landscape lighting according to claim 1 is characterized by: The longitudinal water collection pipe and lamps use standard sections of the same length, and the length of the standard section ranges from 5 to 7 meters. At the same time as the standard section, the lamps in the standard section are connected to the junction box.
5. The construction method combining bridge drainage and landscape lighting according to claim 1 is characterized by: Mutually matching grooves and protrusions are respectively provided on the adjacent surfaces of the lamp and the longitudinal water collecting pipe, and the lamp is slidably connected to the longitudinal water collecting pipe through the matching connection between the protrusion and the groove; and penetrating pin holes and pin grooves are provided on the groove and the protrusion, and a limiting pin passes through the pin holes and pin grooves on the lamp and the longitudinal water collecting pipe at the same time to achieve a fixed connection between the two.
6. The construction method combining bridge drainage and landscape lighting according to claim 1 is characterized by: Before using a aerial platform to install the standard section, it is necessary to inspect the ground conditions on site. If a loose address is encountered, the site must be hardened.
7. A construction structure combining bridge drainage and landscape lighting, including a bridge, on which a drainage pipeline system and an electric circuit system are arranged; the drainage pipeline system includes a longitudinal water collection pipeline arranged along the length direction of the bridge, and the electric circuit system includes lamps arranged along the length direction of the wall beam; Features: The longitudinal water collecting pipe and the lamps are arranged in multiple sections, and a lamp installation structure is provided between the longitudinal water collecting pipe and the lamps; a lamp matching its length is installed on each section of the longitudinal water collecting pipe, and the lamps are installed on the side of the longitudinal water collecting pipe located on the bridge pier, forming a standard section; the operating personnel install the standard section at the bottom of the bridge in sequence.
8. The construction structure combining bridge drainage and landscape lighting according to claim 7 is characterized by: The drainage pipe system includes vertical downpipes arranged vertically, inspection ports arranged at the bottom of the vertical downpipes, transverse drainage pipes along the width of the bridge, and vertical drainage pipes located on the wall beam piers; a number of vertical downpipes are arranged at intervals along the length of the bridge, and the vertical downpipes are located inside the bridge, connecting the bridge deck and the bottom of the bridge; the longitudinal water collection pipe is arranged at the bottom of the vertical downpipe and is connected to all vertical downpipes through a four-way joint; a number of transverse drainage pipes are arranged on the longitudinal water collection pipe and are connected between the vertical drainage pipe and the longitudinal water collection pipe.
9. The construction structure combining bridge drainage and landscape lighting according to claim 7 is characterized by: The circuit system includes a junction box arranged in the wall beam anti-collision guardrail, a vertical wire threading hole penetrating the wall beam, and wires connected between the junction box and the lamp; one end of the wire is connected to the junction box, and the wire passes through the vertical wire threading hole and is connected to the lamp; multiple junction boxes are arranged at intervals along the length direction of the bridge, and one junction box corresponds to one or more lamps.
10. The construction structure combining bridge drainage and landscape lighting according to claim 9 is characterized in that: The lamp installation structure comprises a groove arranged on the lamp, a protrusion arranged on the longitudinal water collecting pipe, and a limit pin, the cross-sectional size of the groove increases from the outside to the inside, and the shape and size of the protrusion match the size of the groove; the groove and the protrusion are arranged on the lamp through the length of the lamp; A plurality of latch holes are provided on the back of the lamp in the groove, and a latch groove corresponding to the latch holes is provided on the protrusion; after the lamp is installed in place, the latch holes and the latch grooves are aligned, and the limiting latch is placed in the latch holes and the latch grooves at the same time; and the latch is limited by the backlight panel of the lamp.