Mine filling material conveying device
By designing a mine filling material conveying device combining conveying units and discharge units, the problems of long filling time, high cost and large labor investment in traditional filling technology are solved, and an efficient and cost-saving filling process is achieved.
Patent Information
- Application Number
- CN202411521233.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-10-29
- Publication Date
- 2025-03-25
- Estimated Expiration
- 2044-10-29
AI Technical Summary
In traditional mine filling technology, it is difficult to gradually fill the holes in the filling material, resulting in a long filling process, high cost, and a large amount of manpower is required to participate in the demolition and reorganization of the pipeline.
A mine filling material conveying device is designed, including a conveying unit and a discharge unit. By combining material mixing rack, opening and closing rack, storage rack, conveying telescopic rack and swinging rack, regional material filling is realized, reducing manpower participation and pipeline removal and modification.
It improves filling efficiency, shortens filling time, reduces labor cost investment, and realizes the filling process without workers dismantling and renovating conveying telescopic frames.
Smart Images

Figure CN119177876B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of mine filling material conveying, in particular to a mine filling material conveying device. Background Art
[0002] Mine filling refers to the process of filling or refilling the voids below the surface with corresponding ore waste or useless ore during mining, so as to maintain the stability of surface or underground projects, reduce surface subsidence and support projects, and achieve the purpose of environmental protection and resource utilization.
[0003] Traditional mine filling is to use filling equipment to mix coal gangue, fly ash and other materials evenly to form filling materials, and then transport the filling materials to the mouth of the cavity to be filled, and then use assembled pipes to transport the filling materials to the depth of the cavity. As the filling area increases, the assembled pipes are dismantled, and the cross-sectional area of the cavity is larger than the cross-sectional area of the pipes. Therefore, it is difficult to gradually fill the cavity using only pipes with fixed angles. A large amount of filling materials accumulates at the pipe mouth and slowly flows to the edge of the cavity over time. Therefore, during the filling process, it is necessary to stop for a period of time after each large amount of filling to give the filling materials time to flow. The entire filling process takes a long time, and after each filling material solidifies, workers are required to gradually dismantle the pipes and pipe support structures, which increases the investment in labor costs and further increases the time spent on filling. Summary of the invention
[0004] In view of the above problems, the embodiment of the present application provides a mine filling material conveying device to solve the technical problems of increasing the time spent on filling and increasing the filling cost in the related art. In order to achieve the above purpose, the embodiment of the present application provides the following technical solutions.
[0005] A mine filling material conveying device according to an embodiment of the present application includes a conveying unit and a discharge unit. The discharge unit is arranged on the conveying unit and is used to fill the filling material into the void of the mine.
[0006] The conveying unit includes a transport vehicle, a material mixing frame is fixedly installed on the upper end of the transport vehicle, a loading frame is fixedly installed on the transport vehicle, an opening and closing frame is arranged on the left side of the material mixing frame, a storage frame is arranged on the left end of the material mixing frame and on the left side of the opening and closing frame, and a discharge unit is fixedly installed on the left end of the storage frame.
[0007] The discharging unit comprises a conveying pump, a conveying pump is fixedly installed on the left end of the storage rack, a conveying telescopic rack is fixedly installed on the left end of the conveying pump, a swinging discharging rack is arranged on the left end of the conveying telescopic rack, and a reciprocating pusher is arranged on the left side of the storage rack.
[0008] By cooperating with the telescopic conveying frame that can be extended and retracted back and forth in the left and right directions and the swinging discharge frame that can swing back and forth in the front and back directions, the interior of the mine is filled with materials in an area. The reciprocating pusher drives the telescopic conveying frame to extend and retract, and during the extension and retraction process of the telescopic conveying frame, it drives the swinging discharge frame to swing forward and backward to discharge materials.
[0009] According to an embodiment of the present invention, the material mixing rack includes a mixing tank, a mixing tank is fixedly installed on the left side of the upper end of the transport vehicle, a mixing screw is rotatably connected to the middle of the mixing tank, a material separation circular plate is fixedly installed on the inner wall of the mixing tank and on the left side of the mixing screw, a mixing rod is evenly fixedly installed on the arc-shaped outer end of the mixing screw, a motor 1 is fixedly installed on the right end of the mixing tank through a motor seat, the output shaft of motor 1 is fixedly connected to the mixing screw through a coupling, and a toggle rod is fixedly installed on the left outer end of the mixing screw.
[0010] According to an embodiment of the present invention, the loading rack includes a loading barrel, a loading barrel is fixedly installed on the right end of the transport vehicle, a conveying screw is rotatably connected to the middle of the loading barrel, the lower end of the loading barrel is open, an inclined drop pipe is fixedly installed on the upper left end of the loading barrel, a gear group is fixedly installed on the right end of the stirring screw, a pulley 1 is fixedly installed on the upper end of the gear group, a pulley 2 is fixedly installed on the upper end of the conveying screw, and pulley 2 is connected to pulley 1 through a belt transmission.
[0011] According to an embodiment of the present invention, the opening and closing frame includes a material separation circular plate, a material separation circular plate is fixedly installed on the left side inside the material mixing frame, a discharge groove is provided at the lower end of the material separation circular plate, an annular groove is provided at the right end of the material separation circular plate, a fan-shaped baffle is connected in a sliding manner in the annular groove, the fan-shaped baffle is coaxial with the material separation circular plate, a control rod is hinged at the right end of the fan-shaped baffle through a pin shaft, an arc groove matching the control rod is provided on the fan-shaped baffle plate, a torsion spring is sleeved on the pin shaft, one end of the torsion spring is fixedly connected to the control rod, and the other end of the torsion spring is fixedly connected to the fan-shaped baffle, a vortex spring is fixedly installed in the material separation circular plate, a rotating cylinder is rotatably connected to the middle part of the material separation circular plate, the end of the vortex spring is fixedly connected to the rotating cylinder, an annular limit groove is provided at the right outer end of the rotating cylinder, a traction wire rope is fixedly installed on the surface of the annular limit groove, and one end of the traction wire rope passes through the material separation circular plate and is fixedly connected to the fan-shaped baffle.
[0012] According to an embodiment of the present invention, the material storage rack includes a material storage tank, a material storage tank is fixedly installed on the left end of the stirring tank, a rotating column is fixedly installed on the left end of the stirring screw, the rotating column and the material separation circular plate, the rotating column and the fan-shaped baffle, and the rotating column and the rotating cylinder are all rotatably connected, an arc-shaped flip plate is evenly fixedly installed on the outer end of the rotating column, a discharge port is opened at the left end of the material storage tank, and a conveying pump is fixedly installed on the left end of the discharge port.
[0013] According to an embodiment of the present invention, the conveying telescopic frame includes a fixed pipe sleeve, a fixed pipe sleeve is fixedly installed on the left end of the conveying pump, a support frame 1 is fixedly installed on the lower end of the fixed pipe sleeve, the outer end of the fixed pipe sleeve is connected to the mobile pipe sleeve 1 in a sliding manner, the outer end of the mobile pipe sleeve 1 is connected to the mobile pipe sleeve 2 in a sliding manner, the mobile pipe sleeve 1 cannot be detached from the fixed pipe sleeve, the mobile pipe sleeve 2 cannot be detached from the mobile pipe sleeve 1, and the lower ends of the mobile pipe sleeve 1 and the mobile pipe sleeve 2 are respectively fixedly installed with the support frame 2 and the support frame 3.
[0014] According to an embodiment of the present invention, the swinging discharge rack includes a ball head tube, the left end of the movable tube sleeve 2 is hinged with the ball head tube, the upper end of the ball head tube is fixedly installed with an inverted L-shaped control support rod with a telescopic structure on the right side of the horizontal section, the middle part of the control support rod is hinged to the movable tube sleeve 2, the upper end of the movable tube sleeve 2 is rotatably connected with a cylindrical cam, the groove on the cylindrical cam is connected with a sliding block in a sliding fit manner, and the sliding block is hinged to the control support rod.
[0015] According to an embodiment of the present invention, the support frame one includes an inverted T-shaped plate, the inverted T-shaped plate is fixedly installed on the lower end of the fixed pipe sleeve, the lower outer end of the inverted T-shaped plate is connected to the movable frame plate in a sliding manner, the lower outer end of the movable frame plate is connected to the T-shaped plate in a sliding manner, an insertion hole is opened in the middle of the movable frame plate, and a double-round-headed conical block is inserted into the insertion hole. The structure of support frame two is the same as that of support frame three and support frame one.
[0016] According to an embodiment of the present invention, an auxiliary traction frame is also provided on the left side of the storage rack, and the auxiliary traction frame includes a winding drum, the top of the storage tank is rotatably connected to the winding drum, the rear end of the storage tank is fixedly installed with motor 2 through a motor seat, the output shaft of motor 2 is fixedly connected to the winding drum through a coupling, sprocket 1 is fixedly installed at the rear end of the cylindrical cam, sprocket 2 is fixedly installed at the left end of the winding drum, sprocket 1 and sprocket 2 are connected by a toothed chain belt transmission, and the diameter of sprocket 2 is larger than the diameter of sprocket 1.
[0017] According to an embodiment of the present invention, the reciprocating pushing member is a linkage frame, which includes a right-angle bracket, a right-angle bracket is fixedly installed on the upper end of the storage tank, an electric telescopic rod is fixedly installed on the lower end of the horizontal section of the right-angle bracket, a fixed cylinder is fixedly installed on the telescopic end of the electric telescopic rod, a tilting rod is hinged at the lower end of the fixed cylinder, and the end of the tilting rod is hinged to the left end of the second moving pipe sleeve; the surface of the winding drum is symmetrically fixedly connected with two traction steel wire ropes, and the ends of the two traction steel wire ropes on the front and rear sides are fixedly connected to the upper ends of the second moving pipe sleeve on the front and rear sides.
[0018] It can be seen from the above technical solutions that the present invention has the following advantages:
[0019] 1. In the present invention, the material stirring rack, the opening and closing rack and the storage rack cooperate to transport the evenly stirred filling material to the storage rack for storage through the opening and closing rack, and continue to mix and stir the filling material mixture through the material stirring rack, and separate the storage rack and the material stirring rack through the opening and closing rack, and control the discharging position of the swinging discharging rack through the reciprocating pusher, and the swinging discharging rack rotates back and forth during the discharging process to increase the discharging range, and while the swinging discharging rack reciprocates back and forth to discharge the material, the conveying telescopic rack reciprocates in the left and right directions within a fixed length range until the area is completely filled, and then the conveying telescopic rack and the swinging discharging rack move to fill the next area until the mine is completely filled. During the entire filling process, there is no need for workers to dismantle and modify the conveying telescopic rack, which reduces the time spent on filling the voids, improves the filling efficiency of the filling equipment, reduces the number of auxiliary workers, and reduces the investment in labor costs.
[0020] 2. In the present invention, the mixed raw materials in the mixing tank are stirred by a stirring screw, and the opening and closing of the discharge chute is controlled by the forward and reverse rotation of the stirring screw, thereby controlling the transportation of the filling raw materials, and the unstressed control rod is restored to its initial state through the cooperation of the volute spring, the rotating cylinder and the traction wire rope.
[0021] 3. In the present invention, the conveying screw is driven by the gear set on the stirring screw to rotate forward or reversely, thereby controlling the raw materials to be conveyed upward into the stirring tank or conveyed downward to continue to be piled up with the raw materials. When the conveying screw rotates in the reverse direction, the raw material discharge equipment retained in the upper barrel continues to be piled up with the raw materials for easy storage, thereby avoiding the situation where a small amount of raw materials is retained in the upper barrel for a long time and cannot be used due to moisture.
[0022] 4. In the present invention, the completely stirred mixed raw materials are stored in the storage tank, and the stirring screw drives the rotating column and the arc-shaped flip plate to rotate to stir the mixed raw materials in the storage rack to prevent the mixed raw materials from being separated into solid and liquid after being left standing for a period of time, thereby ensuring the quality of the filling raw materials.
[0023] 5. In the present invention, the sliding block is driven to move back and forth on the horizontal plane by the cylindrical cam, thereby driving the control support rod to rotate, and the control support rod drives the ball head tube to swing back and forth to control the discharge range of the mixed raw materials. At the same time, the winding drum rotates synchronously with the cylindrical cam. With the cooperation of the electric telescopic rod, the mobile pipe sleeve moves back and forth in the left and right directions. In the whole discharge process, partitioned discharge is performed.
[0024] In addition to the technical problems solved by the embodiments of the present application described above, the technical features that constitute the technical solutions, and the beneficial effects brought about by the technical features of these technical solutions, other technical problems that can be solved by a mine filling material conveying device provided in the embodiments of the present application, other technical features included in the technical solutions, and the beneficial effects brought about by these technical features will be further described in detail in the specific implementation methods. BRIEF DESCRIPTION OF THE DRAWINGS
[0025] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on the provided drawings without paying creative work.
[0026] Figure 1 A schematic diagram of a main-view stereoscopic structure provided according to an embodiment of the present invention is shown.
[0027] Figure 2 A schematic diagram of a main cross-sectional plane structure provided according to an embodiment of the present invention is shown.
[0028] Figure 3 Shows Figure 2 A local enlarged view of location N.
[0029] Figure 4 Shows Figure 2 A local enlarged view of point M.
[0030] Figure 5 A schematic diagram of a top plan structure provided according to an embodiment of the present invention is shown.
[0031] Figure 6 A schematic diagram of a rear-view plane structure provided according to an embodiment of the present invention is shown.
[0032] Figure 7 A schematic diagram of the main stereoscopic structure of the arc groove and the control rod is shown.
[0033] Figure 8 A schematic diagram of the three-dimensional structure of the discharge chute and the fan-shaped baffle is shown as viewed from above.
[0034] Fig. 9 A schematic diagram of the right side sectional plan structure of the scroll spring and the rotating cylinder is shown.
[0035] The above drawings include the following reference numerals:
[0036] 1. Conveying unit; 11. Transport vehicle; 12. Material mixing frame; 121. Mixing tank; 122. Mixing screw; 123. Mixing rod; 124. Motor 1; 125. Toggle rod; 13. Loading rack; 131. Loading barrel; 132. Conveying screw; 133. Dropping pipe; 134. Gear set; 135. Pulley 1; 136. Pulley 2; 137. Belt 1; 14. Opening and closing frame; 141. Material separation circular plate; 142. Discharging trough; 143. Annular groove; 144. Fan-shaped baffle; 145. Control rod; 146. Arc groove; 148. Volute spring; 149. Rotating cylinder; 1491. Traction wire rope 1; 15. Storage rack; 151. Storage tank; 152. Rotating column; 153. Arc flip plate; 154. Discharging port; 2. Discharging unit ;21. Conveying pump;22. Conveying telescopic frame;221. Fixed pipe sleeve;222. Support frame one;2221. Inverted T-shaped plate;2222. Moving frame plate;2223. T-shaped plate;2224. Double round head cone block;223. Moving pipe sleeve one;224. Moving pipe sleeve two;225. Support frame two;226. Support frame three;23. Swinging discharge frame;231. Ball head pipe;232. Control support rod;2321. Sprocket one;2322. Sprocket two;2323. Toothed chain belt;233. Cylindrical cam;234. Sliding block;24. Auxiliary traction frame;241. Winding drum;242. Motor two;243. Traction wire rope two;25. Linkage frame;251. Right angle bracket;252. Electric telescopic rod;253. Fixed cylinder;254. Tilt rod. DETAILED DESCRIPTION
[0037] In order to make the above-mentioned objects, features and advantages of the present invention more obvious and easy to understand, the specific embodiments of the present invention are described in detail below in conjunction with the accompanying drawings. In the following description, many specific details are set forth to facilitate a full understanding of the present invention. However, the present invention can be implemented in many other ways different from those described herein, and those skilled in the art can make similar improvements without violating the connotation of the present invention, so the present invention is not limited by the specific embodiments disclosed below.
[0038] See also Figure 1 , Figure 3 , Figure 7 , Figure 8 and Fig. 9A mine filling material conveying device comprises a conveying unit 1 and a discharging unit 2. The discharging unit 2 is arranged on the conveying unit 1 and is used to fill the filling material into the void of the mine; the conveying unit 1 comprises a transport vehicle 11, a material mixing frame 12 is fixedly installed on the upper end of the transport vehicle 11, a loading frame 13 is fixedly installed on the transport vehicle 11, an opening and closing frame 14 is arranged on the left side of the material mixing frame 12, a storage frame 15 is arranged on the left end of the material mixing frame 12 and on the left side of the opening and closing frame 14, and a material storage frame 15 is arranged on the left end of the material mixing frame 12. A discharge unit 2 is fixedly installed; the discharge unit 2 includes a conveying pump 21, a conveying pump 21 is fixedly installed on the left end of the storage rack 15, a conveying telescopic frame 22 is fixedly installed on the left end of the conveying pump 21, a swing discharge rack 23 is arranged on the left end of the conveying telescopic frame 22, an auxiliary traction frame 24 is arranged on the left side of the storage rack 15, and a reciprocating pusher is arranged on the left side of the storage rack 15 and on the right side of the auxiliary traction frame 24; the opening and closing frame 14 includes a material separation circular plate 141, and a material stirring frame 12 is fixedly installed on the left side of the material stirring frame 12 The material separation circular plate 141 has a discharge groove 142 at the lower end thereof, an annular groove 143 at the right end thereof, a fan-shaped baffle 144 is connected in a sliding manner in the annular groove 143, the fan-shaped baffle 144 is coaxial with the material separation circular plate 141, a control rod 145 is hingedly connected to the right end of the fan-shaped baffle 144 through a pin shaft, an arc-shaped groove 146 cooperating with the control rod 145 is formed on the fan-shaped baffle 144, a torsion spring is sleeved on the pin shaft, and one end of the torsion spring is connected to the control rod 1 45 is fixedly connected, the other end of the torsion spring is fixedly connected to the fan-shaped baffle 144, a vortex spring 148 is fixedly installed in the material separation circular plate 141, a rotating cylinder 149 is rotatably connected to the middle of the material separation circular plate 141, the end of the vortex spring 148 is fixedly connected to the rotating cylinder 149, an annular limiting groove is provided at the right outer end of the rotating cylinder 149, a traction wire rope 1491 is fixedly installed on the surface of the annular limiting groove, and the end of the traction wire rope 1491 passes through the material separation circular plate 141 and is fixedly connected to the fan-shaped baffle 144.
[0039] First, the transport vehicle 11 is transported to the depth of the mine, and the raw materials required for filling are transported to the vicinity of the transport vehicle 11. At this time, the raw materials are sent to the material mixing rack 12 for mixing through the loading rack 13, and the opening and closing rack 14 is opened to transport the completely mixed raw materials to the storage rack 15 for storage, and the raw materials are continued to be mixed and stirred through the material mixing rack 12. The storage rack 15 and the material mixing rack 12 are separated by the opening and closing rack 14, and the mixed raw materials in the storage rack 15 are transported to the conveying telescopic rack 22 through the conveying pump 21, and the raw materials are discharged into the mine through the swinging discharge rack 23. The discharging position of the swinging discharge rack 23 is controlled by the reciprocating pusher and the auxiliary traction rack 24, so that the swinging discharge rack 23 discharges the materials in a serpentine trajectory, and the mine is filled with partitioned materials. When the area is filled, the auxiliary traction rack 24 is connected to the transport vehicle 11. The auxiliary traction frame 24 and the swing discharge frame 23 are pulled to fill the next area until the mine is completely filled. When the material mixing frame 12 rotates forward, the material partition circular plate 141 is in a closed state, and the mixed raw materials cannot be discharged to the storage frame 15. When the material mixing frame 12 rotates reversely, the material mixing frame 12 drives the control rod 145 which is perpendicular to the fan-shaped baffle 144 in the initial state to move, thereby driving the fan-shaped baffle 144 to move. After the fan-shaped baffle 144 rotates a certain angle, the discharge chute 142 opens, and the completely mixed raw materials are discharged from the material mixing frame 12. When the material mixing frame 12 rotates forward, the mixed raw materials in the material mixing frame 12 are stirred, and the unstressed control rod 145 is restored to its initial state through the cooperation of the volute spring 148, the rotating cylinder 149 and the traction wire rope 1491.
[0040] See also Figure 2 and Figure 3The material mixing frame 12 includes a mixing tank 121, a mixing tank 121 is fixedly installed on the left side of the upper end of the transport vehicle 11, a mixing screw 122 is rotatably connected to the middle of the mixing tank 121, a material separation circular plate 141 is fixedly installed on the inner wall of the mixing tank 121 and located on the left side of the mixing screw 122, a mixing rod 123 is evenly fixedly installed on the arc-shaped outer end of the mixing screw 122, a motor 124 is fixedly installed on the right end of the mixing tank 121 through a motor seat, an output shaft of the motor 124 is fixedly connected to the mixing screw 122 through a coupling, and a toggle rod 125 is fixedly installed on the left outer end of the mixing screw 122; the mixing screw 122 is driven to rotate by the motor 124, so as to mix the mixed materials in the mixing tank 121. When the stirring screw 122 rotates in the opposite direction, the toggle rod 125 on the stirring screw 122 drives the control rod 145 to move, thereby driving the fan-shaped baffle 144 to move, so that the discharge chute 142 is opened, and the fan-shaped baffle 144 drives the traction wire rope 1491 to move, thereby driving the rotating cylinder 149 to rotate, and then driving the volute spring 148 to reel, and the completely mixed raw materials are discharged from the stirring tank 121. When the stirring screw 122 rotates forward, the mixed raw materials in the stirring tank 121 are stirred. When the control rod 145 is no longer subjected to force, the fan-shaped baffle 144 no longer drives the volute spring 148 to reel. At this time, the reaction force of the volute spring 148 drives the fan-shaped baffle 144 and the control rod 145 to return to their initial state.
[0041] See also Figure 1 and Figure 2 The loading rack 13 includes a loading barrel 131, a loading barrel 131 is fixedly installed on the right end of the transport vehicle 11, a conveying screw 132 is rotatably connected to the middle of the loading barrel 131, the lower end of the loading barrel 131 is open, an inclined drop pipe 133 is fixedly installed on the upper left end of the loading barrel 131, a gear set 134 is fixedly installed on the right end of the stirring screw 122, a pulley 135 is fixedly installed on the upper end of the gear set 134, a pulley 136 is fixedly installed on the upper end of the conveying screw 132, and the pulley 136 is connected to the pulley 135 through a belt 137; the conveying screw 132 is driven to rotate by the gear set 134 on the stirring screw 122 , the raw materials are transported upward to the drop pipe 133 and finally enter the mixing tank 121. When the mixing screw 122 rotates forward, the conveying screw 132 rotates forward to transport the raw materials upward to the mixing tank 121. When the mixing screw 122 rotates reversely, the conveying screw 132 rotates reversely, so that the raw material discharge equipment retained in the upper barrel 131 continues to be piled up with the raw materials for easy storage, avoiding a small amount of raw materials from being retained in the upper barrel 131 for a long time, thereby being unable to be used due to moisture. During the whole process, the loading time is longer than the unloading time, that is, the time length of the forward rotation of the mixing screw 122 is longer than the time length of the reverse rotation of the mixing screw 122.
[0042] The gear set 134 includes a driving gear, a driving gear is fixedly installed on the right end of the stirring screw 122, a driven gear is rotatably connected to the right end of the stirring tank 121 and located on the upper side of the driving gear, the driven gear is meshed with the driving gear, a bevel gear 1 is fixedly installed on the right end of the driven gear, a bevel gear 2 is rotatably connected to the left end of the loading barrel 131 and meshed with the bevel gear 1, a spur gear 1 is fixedly installed on the upper end of the bevel gear 2, a spur gear 2 is rotatably connected to the left end of the loading barrel 131 and located in front of the spur gear 1, the spur gear 2 is meshed with the spur gear 1, and the upper end of the spur gear 2 is fixedly connected to the pulley 1 135.
[0043] See also Figure 2 and Figure 3 The material storage rack 15 includes a material storage tank 151, a material storage tank 151 is fixedly installed on the left end of the stirring tank 121, a rotating column 152 is fixedly installed on the left end of the stirring screw 122, the rotating column 152 and the material separation circular plate 141, the rotating column 152 and the fan-shaped baffle 144, and the rotating column 152 and the rotating cylinder 149 are all rotatably connected, an arc-shaped flip plate 153 is evenly fixedly installed on the outer end of the rotating column 152, a discharge port 154 is opened on the left end of the material storage tank 151, and a conveying pump 21 is fixedly installed on the left end of the discharge port 154; the completely stirred mixed raw materials are stored through the material storage tank 151, and the stirring screw 122 drives the rotating column 152 and the arc-shaped flip plate 153 to rotate, so as to stir the mixed raw materials in the material storage rack 15 to prevent the mixed raw materials from being separated into solid and liquid after being left standing for a period of time.
[0044] See also Figure 2 The conveying telescopic frame 22 includes a fixed pipe sleeve 221, a fixed pipe sleeve 221 is fixedly installed on the left end of the conveying pump 21, a support frame 1 222 is fixedly installed on the lower end of the fixed pipe sleeve 221, the outer end of the fixed pipe sleeve 221 is connected to a mobile pipe sleeve 1 223 in a sliding manner, the outer end of the mobile pipe sleeve 1 223 is connected to a mobile pipe sleeve 2 224 in a sliding manner, and the lower ends of the mobile pipe sleeve 1 223 and the mobile pipe sleeve 2 224 are respectively fixedly installed with a support frame 225 and a support frame 3 226, the mobile pipe sleeve 1 223 cannot be detached from the fixed pipe sleeve 221, and the mobile pipe sleeve 2 224 cannot be detached from the mobile pipe sleeve 1 223; the mixed raw materials are conveyed at different distances by the cooperation of the mobile pipe sleeve 224, the mobile pipe sleeve 1 223 and the fixed pipe sleeve 221.
[0045] Continue reading Figure 2The swinging discharge rack 23 includes a ball head tube 231, the left end of the movable tube sleeve 224 is hinged with the ball head tube 231, the upper end of the ball head tube 231 is fixedly installed with an inverted L-shaped control support rod 232 with a telescopic structure on the right side of the horizontal section, the middle part of the control support rod 232 is hinged with the movable tube sleeve 224, the upper end of the movable tube sleeve 224 is rotatably connected with a cylindrical cam 233, the groove on the cylindrical cam 233 is connected with a sliding block 234 in a sliding fit manner, and the sliding block 234 is hinged with the control support rod 232; the sliding block 234 is driven to move in the front and rear directions by the cylindrical cam 233, thereby driving the control support rod 232 to rotate, and the control support rod 232 drives the ball head tube 231 to rotate, thereby increasing the discharge range of the mixed raw materials.
[0046] See also Figure 4 The support frame 1 222 includes an inverted T-shaped plate 2221, an inverted T-shaped plate 2221 is fixedly installed at the lower end of the fixed pipe sleeve 221, the lower outer end of the inverted T-shaped plate 2221 is connected to a movable frame plate 2222 in a sliding manner, and the lower outer end of the movable frame plate 2222 is connected to a T-shaped plate 2223 in a sliding manner. An insertion hole is opened in the middle of the movable frame plate 2222, and a double round-headed conical block 2224 is inserted into the insertion hole; the double round-headed conical block 2224 is added or reduced between the inverted T-shaped plate 2221 and the T-shaped plate 2223 as needed to achieve the purpose of supporting the fixed pipe sleeve 221 and avoid the situation where it cannot be supported when it moves to a concave or convex part of the mine tunnel. The structure of the support frame 2 25 is the same as that of the support frame 3 226 and the support frame 1 222.
[0047] See also Figure 2 and Figure 5 The auxiliary traction frame 24 includes a winding drum 241, the top of the storage tank 151 is rotatably connected with the winding drum 241, the rear end of the storage tank 151 is fixedly installed with a motor 242 through a motor seat, the output shaft of the motor 242 is fixedly connected to the winding drum 241 through a coupling, and the surface of the winding drum 241 is symmetrically fixedly connected with a traction wire rope 243, and the ends of the traction wire rope 243 on the front and rear sides are fixedly connected to the upper ends of the front and rear sides of the mobile pipe sleeve 224; the winding drum 241 is driven to rotate by the motor 242, so that the traction wire rope 243 is wound, and the mobile pipe sleeve 224 is pulled to change the discharge position of the mixed raw materials.
[0048] See also Figure 2 and Figure 5The reciprocating pusher is a linkage frame 25, which includes a right-angle bracket 251. The right-angle bracket 251 is fixedly installed on the upper end of the storage tank 151, and an electric telescopic rod 252 is fixedly installed on the lower end of the horizontal section of the right-angle bracket 251. A fixed cylinder 253 is fixedly installed on the telescopic end of the electric telescopic rod 252. A tilting rod 254 is hinged at the lower end of the fixed cylinder 253, and the end of the tilting rod 254 is hinged to the left end of the mobile sleeve 224; the fixed cylinder 253 is driven up and down by the electric telescopic rod 252, thereby driving the tilting rod 254 to move while changing its tilt angle, and the tilting rod 254 drives the mobile sleeve 224 to move right and left.
[0049] See also Figure 2 and Figure 6 A sprocket 1 2321 is fixedly installed at the rear end of the cylindrical cam 233, and a sprocket 2 2322 is fixedly installed at the left end of the winding drum 241. The sprocket 1 2321 and the sprocket 2 2322 are connected to each other through a toothed chain belt 2323. The diameter of the sprocket 2 2322 is larger than the diameter of the sprocket 1 2321. The winding drum 241 drives the sprocket 2 2322 to rotate, and with the cooperation of the toothed chain belt 2323, the sprocket 1 2321 rotates together, thereby driving the cylindrical cam 233 to rotate.
[0050] The reel 241 is driven to rotate forward by the forward rotation of the motor 242, thereby driving the traction wire rope 243 to reel up and driving the mobile sleeve 224 to move rightward. At the same time, the motor 242 drives the sprocket 2322 to rotate. With the cooperation of the toothed chain belt 2323, the sprocket 1 2321 drives the cylindrical cam 233 to rotate, thereby driving the ball head tube 231 to swing back and forth. When the motor 242 rotates in the reverse direction, the electric telescopic rod 252 drives the fixed cylinder 253 to move downward, thereby driving the tilting rod 254 to move and tilt, driving the mobile sleeve 224 to move leftward. Move, and at the same time, the motor 242 continues to drive the ball head tube 231 to swing back and forth. In the whole discharging process, zoned discharging is carried out, and the telescopic conveying frame 22 moves back and forth in the fixed area. At the same time, the swinging discharging frame 23 swings in the front and back directions throughout the whole process to carry out zoned material laying. It should be noted that when the motor 242 rotates forward to drive the traction wire rope 243 to reel in, the electric telescopic rod 252 drives the fixed cylinder 253 to move upward, and correspondingly, when the electric telescopic rod 252 drives the fixed cylinder 253 to move downward, the traction wire rope 243 is unwound.
[0051] In addition, the reciprocating driving member can also adopt a hydraulic push rod, which drives the movable sleeve 224 to move back and forth. When the hydraulic push rod drives the movable sleeve 224 to move slightly left and right, the motor 242 drives the cylindrical cam 233 to rotate, thereby driving the ball head tube 231 to swing back and forth. At the same time, the winding drum 241 winds up the traction wire rope 243 to assist in pulling the movable sleeve 224 to move right.
[0052] Working principle of the present invention: Step 1: First, the device is transported to the deep of the mine by the transport vehicle 11, and the raw materials required for filling are transported to the vicinity of the transport vehicle 11. At this time, the raw materials are sent to the material mixing rack 12 for mixing through the loading rack 13, and the opening and closing rack 14 is opened to transport the completely mixed raw materials to the storage rack 15 for storage, and the raw materials are continued to be mixed and stirred through the material mixing rack 12.
[0053] Step 2: The material storage rack 15 and the material mixing rack 12 are separated by the opening and closing rack 14 , and the mixed raw materials in the material storage rack 15 are transported to the transport telescopic rack 22 by the transport pump 21 .
[0054] The third step: discharge the raw materials into the mine through the swinging discharge rack 23, and control the discharge position of the swinging discharge rack 23 through the reciprocating pusher and the auxiliary traction frame 24, so that the conveying telescopic frame 22 can cooperate with the swinging discharge rack 23 that swings back and forth in the front and rear directions when it is extended and retracted left and right, so as to carry out regional material laying and filling inside the mine. When the area is fully laid, the conveying telescopic frame 22 and the swinging discharge rack 23 are transported to the next area for material laying and filling by the transport vehicle 11 until the mine is completely filled.
[0055] In the description of the present invention, it is necessary to understand that the terms "center", "middle", "up", "down", "front", "back", "left", "right", "top", "bottom", "inside", "outside", "end", "axial", "circumferential" and the like indicate orientations or positional relationships based on the orientations or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply that the referred device or element must have a specific orientation, be constructed and operated in a specific orientation, and therefore should not be understood as a limitation on the present invention.
[0056] In addition, the terms "first", "second", "number one", "number two", "one", "two" are used for descriptive purposes only and cannot be understood as indicating or implying relative importance or implicitly indicating the number of the indicated technical features. In the description of the present invention, "multiple" means at least two, such as two, three, etc., unless otherwise clearly and specifically limited.
[0057] In the description of the present invention, it is also necessary to explain that, unless otherwise clearly specified and limited, the terms "set", "connect", "install", and "connect" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection, a sliding connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or it can be indirectly connected through an intermediate medium, or it can be the internal communication of two components. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.
[0058] The embodiments of this specific implementation method are all preferred embodiments of the present invention, and are not intended to limit the protection scope of the present invention. Therefore, all equivalent changes made based on the structure, shape, and principle of the present invention should be included in the protection scope of the present invention.
Claims
1. A mine filling material conveying device, characterized in that , comprising a conveying unit (1) and a discharging unit (2), wherein the discharging unit (2) is arranged on the conveying unit (1) and is used to fill the filling material into the cavity of the mine; The conveying unit (1) comprises a transport vehicle (11), a material mixing frame (12) is fixedly mounted on the upper end of the transport vehicle (11), a loading frame (13) is fixedly mounted on the transport vehicle (11), an opening and closing frame (14) is arranged on the left side of the material mixing frame (12), a material storage frame (15) is arranged at the left end of the material mixing frame (12) and on the left side of the opening and closing frame (14), and a material discharge unit (2) is fixedly mounted on the left end of the material storage frame (15); The discharge unit (2) comprises a delivery pump (21), the delivery pump (21) is fixedly mounted on the left end of the storage rack (15), a delivery telescopic rack (22) is fixedly mounted on the left end of the delivery pump (21), a swinging discharge rack (23) is arranged at the left end of the delivery telescopic rack (22), and a reciprocating pusher is arranged on the left side of the storage rack (15); The conveying telescopic frame (22) that telescopes back and forth in the left and right directions cooperates with the swinging material discharging frame (23) that swings back and forth in the front and back directions to carry out regional material paving and filling inside the mine cave, and the reciprocating pusher drives the conveying telescopic frame (22) to telescope, and during the telescopic process of the conveying telescopic frame (22), the swinging material discharging frame (23) is driven to swing in the front and back directions to discharge materials; The opening and closing frame (14) comprises a material separation circular plate (141), the material separation circular plate (141) is fixedly installed on the left side inside the material stirring frame (12), a material discharge groove (142) is provided at the lower end of the material separation circular plate (141), an annular groove (143) is provided at the right end of the material separation circular plate (141), a fan-shaped baffle (144) is connected in a sliding manner in the annular groove (143), the fan-shaped baffle (144) and the material separation circular plate (141) are coaxial, a control rod (145) is hinged at the right end of the fan-shaped baffle (144) through a pin shaft, and an arc-shaped groove (144) matching with the control rod (145) is provided on the fan-shaped baffle (144). 6), a torsion spring is sleeved on the pin shaft, one end of the torsion spring is fixedly connected to the control rod (145), and the other end of the torsion spring is fixedly connected to the fan-shaped baffle (144), a vortex spring (148) is fixedly installed in the material separation circular plate (141), a rotating cylinder (149) is rotatably connected to the middle of the material separation circular plate (141), and the end of the vortex spring (148) is fixedly connected to the rotating cylinder (149), and an annular limiting groove is provided at the right outer end of the rotating cylinder (149), and a traction wire rope (1491) is fixedly installed on the surface of the annular limiting groove, and the end of the traction wire rope (1491) passes through the material separation circular plate (141) and is fixedly connected to the fan-shaped baffle (144); The conveying telescopic frame (22) comprises a fixed pipe sleeve (221), the fixed pipe sleeve (221) is fixedly installed on the left end of the conveying pump (21), a support frame 1 (222) is fixedly installed on the lower end of the fixed pipe sleeve (221), the outer end of the fixed pipe sleeve (221) is connected to a mobile pipe sleeve 1 (223) in a sliding manner, the outer end of the mobile pipe sleeve 1 (223) is connected to a mobile pipe sleeve 2 (224) in a sliding manner, the mobile pipe sleeve 1 (223) cannot be separated from the fixed pipe sleeve (221), and the mobile pipe sleeve 2 (224) cannot be separated from the mobile pipe sleeve 1 (223), and the lower ends of the mobile pipe sleeve 1 (223) and the mobile pipe sleeve 2 (224) are respectively fixedly installed with a support frame 2 (225) and a support frame 3 (226); The swinging material discharging frame (23) comprises a ball head tube (231), the left end of the movable tube sleeve (224) is hinged with the ball head tube (231), the upper end of the ball head tube (231) is fixedly mounted with an inverted L-shaped control support rod (232) with a telescopic structure on the right side of the horizontal section, the middle part of the control support rod (232) is hinged with the movable tube sleeve (224), the upper end of the movable tube sleeve (224) is rotatably connected with a cylindrical cam (233), a sliding block (234) is connected in a sliding fit manner in a groove on the cylindrical cam (233), and the sliding block (234) is hinged with the control support rod (232).
2. A mine filling material conveying device according to claim 1, characterized in that: The material stirring rack (12) comprises a stirring tank (121), the stirring tank (121) is fixedly mounted on the left side of the upper end of the transport vehicle (11), a stirring screw (122) is rotatably connected to the middle of the stirring tank (121), a material separation circular plate (141) is fixedly mounted on the inner wall of the stirring tank (121) and located on the left side of the stirring screw (122), a stirring rod (123) is evenly fixedly mounted on the arc-shaped outer end of the stirring screw (122), a motor 1 (124) is fixedly mounted on the right end of the stirring tank (121) via a motor seat, an output shaft of the motor 1 (124) is fixedly connected to the stirring screw (122) via a coupling, and a toggle rod (125) is fixedly mounted on the left outer end of the stirring screw (122).
3. A mine filling material conveying device according to claim 1, characterized in that: The loading rack (13) comprises a loading barrel (131), the loading barrel (131) is fixedly mounted on the right end of the transport vehicle (11), a conveying screw (132) is rotatably connected to the middle of the loading barrel (131), the loading barrel (131) is open at the lower end, an inclined drop pipe (133) is fixedly mounted on the upper left end of the loading barrel (131), a gear set (134) is fixedly mounted on the right end of the stirring screw (122), a pulley 1 (135) is fixedly mounted on the upper end of the gear set (134), a pulley 2 (136) is fixedly mounted on the upper end of the conveying screw (132), and the pulley 2 (136) is connected to the pulley 1 (135) through a belt 1 (137).
4. A mine filling material conveying device according to claim 3, characterized in that: The material storage rack (15) comprises a material storage tank (151), the material storage tank (151) is fixedly mounted on the left end of the stirring tank (121), a rotating column (152) is fixedly mounted on the left end of the stirring screw (122), the rotating column (152) and the material separation circular plate (141), the rotating column (152) and the fan-shaped baffle (144), and the rotating column (152) and the rotating cylinder (149) are all rotatably connected, an arc-shaped flip plate (153) is evenly fixedly mounted on the outer end of the rotating column (152), a material discharge port (154) is opened on the left end of the material storage tank (151), and a conveying pump (21) is fixedly mounted on the left end of the material discharge port (154).
5. A mine filling material conveying device according to claim 2, characterized in that: The support frame 1 (222) comprises an inverted T-shaped plate (2221), the inverted T-shaped plate (2221) is fixedly mounted on the lower end of the fixed pipe sleeve (221), the lower outer end of the inverted T-shaped plate (2221) is connected to a movable frame plate (2222) in a sliding manner, the lower outer end of the movable frame plate (2222) is connected to a T-shaped plate (2223) in a sliding manner, an insertion hole is opened in the middle of the movable frame plate (2222), and a double round-headed conical block (2224) is inserted into the insertion hole. The support frame 2 (225) has the same structure as the support frame 3 (226) and the support frame 1 (222).
6. A mine filling material conveying device according to claim 4, characterized in that: An auxiliary traction frame (24) is also provided on the left side of the material storage frame (15), the auxiliary traction frame (24) comprising a winding drum (241), the top of the material storage tank (151) is rotatably connected to the winding drum (241), a second motor (242) is fixedly mounted on the rear end of the material storage tank (151) via a motor seat, an output shaft of the second motor (242) is fixedly connected to the winding drum (241) via a coupling, a sprocket wheel 1 (2321) is fixedly mounted on the rear end of the cylindrical cam (233), a second sprocket wheel (2322) is fixedly mounted on the left end of the winding drum (241), the first sprocket wheel (2321) and the second sprocket wheel (2322) are transmission-connected via a toothed chain belt (2323), and the diameter of the second sprocket wheel (2322) is greater than the diameter of the first sprocket wheel (2321).
7. A mine filling material conveying device according to claim 6, characterized in that: The reciprocating pusher is a linkage frame (25), which comprises a right-angle bracket (251), the upper end of the storage tank (151) is fixedly mounted with the right-angle bracket (251), the lower end of the horizontal section of the right-angle bracket (251) is fixedly mounted with an electric telescopic rod (252), the telescopic end of the electric telescopic rod (252) is fixedly mounted with a fixed cylinder (253), the lower end of the fixed cylinder (253) is hinged with a tilting rod (254), the end of the tilting rod (254) is hinged with the left end of the second moving pipe sleeve (224); the surface of the winding drum (241) is symmetrically fixedly connected with the second traction wire rope (243), the ends of the second traction wire rope (243) on the front and rear sides are fixedly connected with the upper ends of the second moving pipe sleeve (224) on the front and rear sides.
Citation Information
Patent Citations
Goaf building solid material regeneration filling slurry preparation and filling integrated system and filling process
CN114618338A
Goaf building solid material regeneration filling slurry preparation and filling integrated system
CN217042146U