Large-area terrace joint-cutting-free construction method

Through the combination of the ware-hopping method and sponge strips, the problems of low construction efficiency, high cost and inconvenient operation in large-area floor construction are solved, and efficient floor construction without later cutting is achieved, which significantly improves construction efficiency and reduces cost.

CN119195432AInactive Publication Date: 2024-12-27CHINA MCC5 GROUP CORP LTD
View PDF 12 Cites 0 Cited by

Patent Information

Application Number
CN202411484796.2
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-10-23
Publication Date
2024-12-27
Estimated Expiration
Not applicable · inactive patent

AI Technical Summary

Technical Problem

In traditional large-area floor construction, there are problems such as low construction efficiency, high overall cost and inconvenient operation. Especially during the cutting process, uneven cutting and sewage pollution are prone to occur, and it is difficult to cut against the wall.

Method used

The warehouse splitting method is used to separate the warehouse and sponge strips are pasted on the side of the concrete. The adjacent floor is connected by sponge strips to reduce expansion and cracks and avoid later cut operations.

Benefits of technology

It significantly improves construction efficiency, reduces overall costs, and avoids sewage and operational inconvenience caused by cutting joints. As an occupancy, the sponge strips play a crack-proof role after pouring concrete, and there is no need to cut the joints later.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119195432A_ABST
    Figure CN119195432A_ABST
Patent Text Reader

Abstract

The invention discloses a joint-cutting-free construction method for a large-area floor, which comprises the following steps of: dividing the large-area floor into bins, and dividing all bin sections into a construction section I and a construction section II; formwork erecting and concrete pouring are carried out according to the bin dividing sections, and adjacent bin dividing plates are poured in a staggered mode; after construction of the first-section terrace is completed, a sponge strip is pasted to an upper opening of the concrete side face of the first-section terrace, and then concrete pouring of the second-section terrace is conducted. According to the method, the concrete expansion cracks are greatly reduced by adopting the skip method construction, meanwhile, the sponge strips are matched, the sponge strips are used as occupancy at the kerfs, after concrete pouring is completed, the adjacent terraces are connected through the sponge strips, the effect of expansion joints can be achieved, the anti-cracking effect is remarkable, later-period kerfs are not needed, and the construction efficiency is improved. And compared with a traditional joint cutting process, the operation is greatly simplified, the construction efficiency is greatly improved, the overall cost is reduced, and the application prospect is good.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of building decoration construction, and in particular to a large-area floor construction method without seam cutting, and in particular to a large-area floor construction method without post-cutting and with high construction efficiency. Background Art

[0002] Large-scale floor construction will occur in basement garages, factory floors and other places. The floor base is basically reinforced concrete, and the most common surface materials are corundum, epoxy self-leveling, and cement-based self-leveling. In order to prevent concrete shrinkage and cracks during reinforced concrete base construction, expansion joints are generally cut after the concrete is cast. Specifically, after a large area of ​​concrete is cast, the joints are generally cut every 2-3 days. The spacing between expansion joints is generally not more than 6m×6m, the joint width is 3-5mm, and the joint depth is 1 / 3 to 1 / 2 of the floor thickness. Before cutting, the lines are drawn first, and then the joints are cut with a cutting machine. Small cutting machines are used for parts with insufficient operating surfaces. Traditional joint cutting not only has the possibility of not cutting straight, but also produces sewage during the cutting process, polluting the floor. At the same time, it is difficult to cut the position close to the wall, and there is a problem of inflexible operation.

[0003] Therefore, it is of great practical significance to develop a large-area floor construction method that does not require post-cutting, is simple to operate, has high construction efficiency and low overall cost. Summary of the invention

[0004] Due to the above-mentioned defects in the prior art, the present invention provides a large-area floor construction method that does not require subsequent cutting, is simple to operate, has high construction efficiency and low overall cost, thereby overcoming the defects of large-area floor construction cutting, such as low construction efficiency, high overall cost and inconvenient operation.

[0005] A large-area floor cutting-free construction method comprises the following steps:

[0006] (1) For large-area floor, all sections are divided into construction section 1 and construction section 2. The skipping section method is used for pouring construction, and expansion cracks are reduced through construction measures;

[0007] (2) Formwork and concrete pouring shall be carried out according to the compartment sections, and adjacent compartment sections shall be poured at different times;

[0008] (3) After completing the construction of the first floor, stick a sponge strip on the upper part of the concrete side, and then pour the second floor concrete.

[0009] The present invention provides a large-area floor cutting-free construction method, which adopts the skipping bin construction method to greatly reduce concrete expansion cracks. At the same time, it is coordinated with sponge strips, and the sponge strips are used as occupiers at the cutting joints. After the concrete pouring is completed, adjacent floors are connected by sponge strips, which can play the role of expansion joints. The anti-cracking effect is significant, and there is no need for subsequent cutting. Compared with the traditional cutting process, the operation is greatly simplified, the construction efficiency is greatly improved, the overall cost is reduced, and the application prospect is good.

[0010] As the preferred technical solution:

[0011] In the large-area floor cutting-free construction method as described above, the compartment seams of the compartments are no larger than 6m×6m.

[0012] In the large-area floor cutting-free construction method as described above, the height of the sponge strip is 1 / 3 to 1 / 2 of the floor thickness.

[0013] In the large-area floor cutting-free construction method as described above, the compartment division is completed according to the column spacing.

[0014] In the large-area floor cutting-free construction method as described above, the thickness of the sponge strip is equal to the seam width, which is 5 mm.

[0015] The above technical solution is only a feasible technical solution of the present invention, and the protection scope of the present invention is not limited thereto. Those skilled in the art can reasonably adjust the specific design according to actual needs.

[0016] The above invention has the following advantages or beneficial effects:

[0017] (1) The large-area floor cutting-free construction method of the present invention adopts the skipping method to greatly reduce the expansion cracks of concrete;

[0018] (2) The large-area floor cutting-free construction method of the present invention uses sponge strips to replace post-cutting, saving costs and construction time;

[0019] (3) The large-area floor cutting-free construction method of the present invention does not require cutting and does not cause problems such as sewage, inconvenience in operation, and insufficient working surface of the local cutting machine caused by cutting, and has good application prospects. BRIEF DESCRIPTION OF THE DRAWINGS

[0020] The present invention and its features, appearance and advantages will become more apparent by reading the detailed description of non-limiting embodiments with reference to the following drawings. The same reference numerals indicate the same parts in all the drawings. The drawings are not drawn to scale, and emphasis is placed on illustrating the subject matter of the present invention.

[0021] Figure 1 This is the floor construction plan;

[0022] Figure 2 This is the floor construction elevation drawing;

[0023] Among them, 1 is the first section of floor construction, 2 is the second section of floor construction, and 3 is the sponge strip. DETAILED DESCRIPTION

[0024] The structure of the present invention is further described below in conjunction with the accompanying drawings and specific embodiments, but is not intended to limit the present invention.

[0025] Example 1

[0026] A large-area floor cutting-free construction method comprises the following steps:

[0027] (1) Large-area floors are divided into compartments according to column spacing. All compartments are divided into construction section 1 and construction section 2. The compartment gap is no larger than 6m×6m. The skip-compartment method is used during pouring to reduce expansion cracks through construction measures.

[0028] (2) Support formwork and pour concrete according to the compartment sections, and pour adjacent compartment sections at different times.

[0029] (3) If Figure 1~2 As shown, after the construction of one section of floor (i.e., floor construction section 1) is completed, a 5mm thick sponge strip 3 is pasted on the upper part of the concrete side, with a height of 1 / 3 to 1 / 2 of the floor thickness, and the second section of floor concrete (i.e., floor construction section 2) is poured.

[0030] The above-mentioned large-area floor cutting-free construction method has been put into practical use during the construction of the fifth phase of the Nicheng resettlement housing project, with good results.

[0031] It has been verified that the large-area floor cutting-free construction method of the present invention adopts the skip-bin construction method to greatly reduce concrete expansion cracks; the sponge strips are pasted instead of post-cutting, which saves costs and construction period; there is no need for cutting, and there are no problems caused by cutting, such as sewage, inconvenience in operation, and insufficient working surface of the local cutting machine, and the application prospect is good.

[0032] Those skilled in the art should understand that those skilled in the art can implement variations by combining the prior art and the above embodiments, which will not be described in detail here. Such variations do not affect the essential content of the present invention, and will not be described in detail here.

[0033] The above describes the preferred embodiments of the present invention. It should be understood that the present invention is not limited to the above-mentioned specific embodiments, and the devices and structures that are not described in detail should be understood to be implemented in a common manner in the art; any technician familiar with the art can use the above-disclosed methods and technical contents to make many possible changes and modifications to the technical solutions of the present invention without departing from the scope of the technical solutions of the present invention, or modify them into equivalent embodiments of equivalent changes, which does not affect the essential content of the present invention. Therefore, any simple modifications, equivalent changes and modifications made to the above embodiments based on the technical essence of the present invention without departing from the content of the technical solutions of the present invention are still within the scope of protection of the technical solutions of the present invention.

Claims

1. A large-area floor cutting-free construction method, characterized in that: The following steps are involved: (1) For large-area floor, all sections are divided into construction section 1 and construction section 2; (2) Formwork and concrete pouring shall be carried out according to the compartment sections, and adjacent compartment sections shall be poured at different times; (3) After completing the construction of the first floor, stick a sponge strip on the upper part of the concrete side, and then pour the second floor concrete.

2. A large-area floor cutting-free construction method according to claim 1, characterized in that: The partition gap of the partition is not larger than 6m×6m.

3. A large-area floor cutting-free construction method according to claim 1, characterized in that: The height of the sponge strip is 1 / 3 to 1 / 2 of the floor thickness.

4. A large-area floor cutting-free construction method according to claim 1, characterized in that: The compartment division is completed according to the column spacing.

5. A large-area floor cutting-free construction method according to claim 1, characterized in that: The thickness of the sponge strip is equal to the seam width.

Citation Information

Patent Citations

  • Seamless construction method of multi-layer super large-area reinforced concrete ground

    CN103225406A

  • Water-permeable concrete expansion joint structure and construction method thereof

    CN104480828A

  • V-shaped seam forming device and technology thereof

    CN108442937A

  • Large-area terrace division seam construction method capable of achieving continuous construction

    CN116378356A

  • Method for controlling skew straightness of tall and large special-shaped hyperboloid building

    CN116497941A