Installation and detection device and system for fire pump on construction site
By introducing worm, transmission assembly and positioning structure into the fire pump detection device, one-handed operation and installation is achieved, which solves the inconvenience caused by the need to pull two tension ropes at the same time in the prior art, improves installation efficiency and reduces labor intensity.
Patent Information
- Application Number
- CN202411402457.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-10-09
- Publication Date
- 2025-01-14
AI Technical Summary
The existing fire pump detection device requires pulling two tension ropes at the same time, which leads to inconvenient installation process, consumes more time and increases labor intensity.
The device including a worm, a transmission assembly, a rotating component and a positioning structure is adopted. The worm drives the transmission assembly and the rotating component to rotate, and drives the positioning structure to move, thereby realizing one-handed operation and installation and reducing dependence on the tension rope.
The installation process is simplified, the labor intensity of personnel is reduced, the installation efficiency is improved, and the inconvenience of pulling two tension ropes at the same time is avoided.
Smart Images

Figure CN119308890A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of fire pump detection, and in particular to a construction site fire pump installation detection device and a system thereof. Background Art
[0002] At present, when replacing the pipeline with the pressure detection pipeline, it is usually necessary to use multiple bolts and flanges to disassemble it back and forth. Therefore, the flange hole position of the flange needs to be accurately located during installation. As a result, during the inspection of multiple fire pumps, not only is it time-consuming due to positioning, but it also requires continuous support for installation, which increases the labor intensity of personnel.
[0003] In order to solve the above problems, the prior art CN221054001U provides a detection device for a fire pump, including a fire pump body and a through pipe, both sides of the fire pump body are connected with pump pipes, both sides of the through pipe are fixedly connected with flanges, one side of the flange is in contact with the pump pipe, one side of the flange is evenly provided with a plurality of flange holes, the arc surface of the through pipe is connected with a connecting pipe, the upper end of the connecting pipe is connected with a pressure detection gauge, two sides of the two flanges close to each other are fixedly connected with two support rods, the arc surface of the support rod is provided with two limiting holes, the arc surfaces of the two support rods are slidably connected with two sliding frames, one side of the connecting plate is fixedly connected with a tension rope, and the other end of the tension rope is fixedly connected with the connecting pipe; this kind of detection device for a fire pump achieves the effect of supporting and positioning the through pipe flange and the pump pipe of the pressure detection gauge detected by the fire pump body, thereby avoiding the problem that personnel need to accurately support the through pipe to align the flange holes, which not only consumes more effort but also reduces the overall installation efficiency.
[0004] However, in the above-mentioned prior art, two tension ropes need to be pulled at the same time for use, which causes inconvenience in installation. Summary of the invention
[0005] The purpose of the present invention is to provide a construction site fire pump installation detection device, which solves the technical problem in the prior art that two tension ropes need to be pulled simultaneously for use, resulting in inconvenience in installation.
[0006] To achieve the above-mentioned purpose, the present invention adopts a construction site fire pump installation and detection device, including a fire pump body, a pump pipe, a connecting pipe, a pressure gauge, an installation box, a worm, a transmission assembly, a rotating component, a limit rod and two positioning structures, the pump pipe is fixedly connected to the fire pump body and is located at one end of the fire pump body, the connecting pipe is detachably connected to the pump pipe and is located at one end of the pump pipe, the pressure gauge is fixedly connected to the connecting pipe and is located at one end of the connecting pipe, the installation box is fixedly connected to the connecting pipe and is located at one end of the connecting pipe, the worm, the transmission assembly, the rotating component and the limit rod are respectively arranged on the installation box, the transmission assembly is rotatably connected to the worm and is located at one end of the worm, the rotating component is rotatably connected to the transmission assembly and is located at one end of the transmission assembly, and the two positioning structures are respectively connected to the limit rod and the rotating component sliding rod, and are symmetrically arranged at one end of the limit rod and the rotating component.
[0007] Wherein, the transmission assembly includes a worm wheel and a transmission gear, the worm wheel cooperates with the worm, and the transmission gear is fixedly connected to the worm wheel and is located at one end of the worm wheel.
[0008] Wherein, the rotating component includes a driving gear and a lead screw, the driving gear cooperates with the transmission gear, and the lead screw is fixedly connected to the driving gear and is located at one end of the driving gear.
[0009] Wherein, each positioning structure includes a frame and a positioning rod, the frame is slidably connected to the lead screw and the limit rod and is located at one end of the lead screw and the limit rod, and the positioning rod is fixedly connected to the frame and is located at one end of the frame.
[0010] Among them, the construction site fire pump installation and detection device also includes a filter bin, a drive disk, two mobile components, and two filter screens. The filter bin is fixedly connected to the connecting pipe and is located at one end of the connecting pipe. The drive disk, the two mobile components and the two filter screens are respectively arranged on the filter bin. The two mobile components are slidably connected to the drive disk and are symmetrically arranged at one end of the drive disk. Each filter screen is fixedly connected to the corresponding mobile component and is located at one end of the corresponding mobile component.
[0011] Wherein, the driving disk includes a disk body and a first gear, and the first gear is fixedly connected to the disk body and is located at one end of the disk body.
[0012] Wherein, each of the moving components includes a rack and a connecting frame, the rack cooperates with the first gear, and the connecting frame is fixedly connected to the rack and is located at one end of the rack.
[0013] The present invention also provides a construction site fire pump installation detection system, which is suitable for the construction site fire pump installation detection device as described above.
[0014] The present invention relates to a construction site fire pump installation and detection device and system thereof, wherein the installation box is fixedly connected to the connecting pipe and is located at one end of the connecting pipe, the worm, the transmission assembly, the rotating component and the limit rod are respectively arranged on the installation box, the transmission assembly is rotatably connected to the worm and is located at one end of the worm, the rotating component is rotatably connected to the transmission assembly and is located at one end of the transmission assembly, the two positioning structures are respectively connected to the limit rod and the rotating component sliding rod, and are symmetrically arranged at one end of the limit rod and the rotating component, the worm is rotated, the worm drives the transmission assembly to rotate, the transmission assembly drives the rotating component to rotate, and the rotating component drives the two positioning structures to move relative to each other through the limit rod, thereby moving them out of the installation box, so that the method can effectively solve the problem of needing to pull two tension ropes at the same time for use, which causes inconvenience in use during installation. BRIEF DESCRIPTION OF THE DRAWINGS
[0015] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.
[0016] Figure 1 It is a schematic structural diagram of the first embodiment of the present invention.
[0017] Figure 2 It is a structural schematic diagram of the connecting pipe of the present invention.
[0018] Figure 3 The present invention Figure 2 A magnified view of the structure at A.
[0019] Figure 4 It is a schematic structural diagram of the second embodiment of the present invention.
[0020] Figure 5 It is a front view of the second embodiment of the present invention.
[0021] Figure 6 The present invention Figure 5 Structural cross-sectional view of line BB.
[0022] Figure 7 It is a structural schematic diagram of the filter screen of the present invention.
[0023] Figure 8 2 is a schematic structural diagram of a positioning rod according to a third embodiment of the present invention.
[0024] Fig. 9 2 is a side view of a positioning rod according to a third embodiment of the present invention.
[0025] Fig.10 The present invention Fig. 9 Structural cross-sectional view of the CC line.
[0026] Fig.11 It is a structural schematic diagram of the transmission arm of the present invention.
[0027] 101-fire pump body, 102-pump pipe, 103-connecting pipe, 104-pressure gauge, 105-installation box, 106-worm, 107-limit rod, 108-worm wheel, 109-transmission gear, 110-drive gear, 111-screw, 112-frame, 113-positioning rod, 201-filter bin, 202-filter screen, 203-disk, 204-first gear, 205-rack, 206-connecting frame, 301-fixed cylinder, 302-servo motor, 303-support rod, 304-screw, 305-slide seat, 306-arm body, 307-fixed plate. DETAILED DESCRIPTION
[0028] Embodiments of the present invention are described in detail below. Examples of the embodiments are shown in the accompanying drawings. The embodiments described below with reference to the accompanying drawings are exemplary and are intended to be used to explain the present invention, but should not be construed as limiting the present invention.
[0029] The first embodiment of the present application is:
[0030] See also Figure 1 to Figure 3 ,in Figure 1 is a schematic structural diagram of a first embodiment of the present invention, Figure 2 is a schematic structural diagram of the connecting pipe of the present invention, Figure 3 The present invention Figure 2 A magnified view of the structure at A.
[0031] The present invention provides a construction site fire pump installation detection device, including a fire pump body 101, a pump pipe 102, a connecting pipe 103, a pressure gauge 104, an installation box 105, a worm 106, a limit rod 107, a worm wheel 108, a transmission gear 109, a driving gear 110, a lead screw 111, a frame 112 and a positioning rod 113. The above scheme solves the problem that two tension ropes need to be pulled at the same time for use, which causes inconvenience in use during installation.
[0032] According to the present specific embodiment, the pump pipe 102 is fixedly connected to the fire pump body 101 and is located at one end of the fire pump body 101. The connecting pipe 103 is detachably connected to the pump pipe 102 and is located at one end of the pump pipe 102. The pressure gauge 104 is fixedly connected to the connecting pipe 103 and is located at one end of the connecting pipe 103. The installation box 105 is fixedly connected to the connecting pipe 103 and is located at one end of the connecting pipe 103. The worm 106, the transmission assembly, the rotating component and the limiting rod 107 are respectively arranged on the installation box 105. The transmission assembly is rotationally connected to the worm 106 and is located at one end of the worm 106. The rotating component It is rotationally connected to the transmission component and is located at one end of the transmission component. The two positioning structures are respectively connected to the limit rod 107 and the sliding rod of the rotating part, and are symmetrically arranged at the limit rod 107 and one end of the rotating part. When the connecting pipe 103 is connected to the pump pipe 102, the worm 106 is rotated, and the worm 106 drives the transmission component to rotate, and the transmission component drives the rotating part to rotate. The rotating part drives the two positioning structures to move relative to each other through the limit rod 107, so as to move out of the installation box 105 and pass through the connecting pipe 103 and the pump pipe 102, so as to facilitate the positioning and installation of the connecting pipe 103 and the pump pipe 102 when they are connected.
[0033] Among them, the transmission assembly includes a worm wheel 108 and a transmission gear 109. The worm wheel 108 cooperates with the worm 106. The transmission gear 109 is fixedly connected to the worm wheel 108 and is located at one end of the worm wheel 108. The worm 106 drives the worm wheel 108 to rotate, and the worm wheel 108 drives the transmission gear 109 to rotate.
[0034] Secondly, the rotating component includes a driving gear 110 and a lead screw 111. The driving gear 110 cooperates with the transmission gear 109. The lead screw 111 is fixedly connected to the driving gear 110 and is located at one end of the driving gear 110. The transmission gear 109 drives the driving gear 110 to rotate, and the driving gear 110 drives the lead screw 111 to rotate.
[0035] At the same time, each positioning structure includes a frame 112 and a positioning rod 113. The frame 112 is slidably connected to the lead screw 111 and the limit rod 107, and is located at one end of the lead screw 111 and the limit rod 107. The positioning rod 113 is fixedly connected to the frame 112 and is located at one end of the frame 112. The lead screw 111 drives the frame 112 to move through the limit rod 107, and the frame 112 drives the positioning rod 113 to move.
[0036] A construction site fire pump installation and detection device using this embodiment is used in specific use. When the connecting pipe 103 is connected to the pump pipe 102, the worm 106 is rotated, and the worm 106 drives the worm wheel 108 to rotate, and the worm wheel 108 drives the transmission gear 109 to rotate, and the transmission gear 109 drives the drive gear 110 to rotate, and the drive gear 110 drives the lead screw 111 to rotate, and the lead screw 111 drives the two frames 112 to move relative to each other through the limit rod 107, and the two frames 112 drive the two positioning rods 113 to move relative to each other, and one of the positioning rods 113 passes through the connecting pipe 103 and the pump pipe 102, so as to facilitate the positioning and installation of the connecting pipe 103 and the pump pipe 102 when they are connected.
[0037] The second embodiment of the present application is:
[0038] Based on the first embodiment, please refer to 4~ Figure 7 ,in Figure 4 is a schematic structural diagram of a second embodiment of the present invention, Figure 5 is a front view of a second embodiment of the present invention, Figure 6 The present invention Figure 5 The structural cross-sectional view of the BB line, Figure 7 It is a structural schematic diagram of the filter screen of the present invention.
[0039] The present invention provides a construction site fire pump installation detection device, which also includes a filter bin 201, a drive disk, two mobile components, and two filter screens 202. The filter bin 201 is fixedly connected to the connecting pipe 103 and is located at one end of the connecting pipe 103. The drive disk, the two mobile components and the two filter screens 202 are respectively arranged on the filter bin 201. The two mobile components are slidably connected to the drive disk and are symmetrically arranged at one end of the drive disk. Each filter screen 202 is fixedly connected to the corresponding mobile component and is located at one end of the corresponding mobile component. Water quality is filtered through the two filter screens 202. The drive disk is rotated, and the drive disk drives the two mobile components to move relative to each other. The two mobile components drive the two filter screens 202 to move relative to each other, so that the filter aperture during filtration can be conveniently adjusted to adapt to different filtering conditions.
[0040] The driving disk includes a disk body 203 and a first gear 204. The first gear 204 is fixedly connected to the disk body 203 and is located at one end of the disk body 203. When the disk body 203 is rotated, the disk body 203 drives the first gear 204 to rotate.
[0041] Secondly, each of the moving components includes a rack 205 and a connecting frame 206. The rack 205 cooperates with the first gear 204. The connecting frame 206 is fixedly connected to the rack 205 and is located at one end of the rack 205. The first gear 204 drives the rack 205 to move, and the rack 205 drives the connecting frame 206 to move.
[0042] When using a construction site fire pump installation and detection device of this embodiment, water is filtered through the two filter screens 202, and the disk body 203 is rotated. The disk body 203 drives the first gear 204 to rotate, and the first gear 204 drives the two racks 205 to move relative to each other. The two racks 205 drive the two connecting frames 206 to move relative to each other, and the two connecting frames 206 drive the two filter screens 202 to move relative to each other in the filter bin 201, so that the filter aperture during filtration can be easily adjusted to adapt to different filtering conditions.
[0043] The third embodiment of the present application is:
[0044] Based on the second embodiment, please refer to 8~ Fig.11 ,in Figure 8 is a schematic structural diagram of a positioning rod according to a third embodiment of the present invention, Fig. 9 is a side view of a positioning rod according to a third embodiment of the present invention, Fig.10 The present invention Fig. 9 The structural cross-sectional view of the CC line, Fig.11 It is a structural schematic diagram of the transmission arm of the present invention.
[0045] The present invention provides a construction site fire pump installation detection device which also includes two fixing mechanisms, each of which includes a fixing cylinder 301, a servo motor 302, a transmission arm, a support rod 303 and two fixing arms, the fixing cylinder 301 is fixedly connected to the positioning rod 113 and is located at one end of the positioning rod 113, the servo motor 302, the transmission arm, the support rod 303 and the two fixing arms are respectively arranged on the fixing cylinder 301, one end of the transmission arm is fixedly connected to the servo motor 302 and is located at the servo motor At one end of 302, the two fixed arms are rotatably connected to the transmission arm and are symmetrically arranged at one end of the transmission arm, and the other ends of the two fixed arms are slidably connected to the support rod 303 and are symmetrically arranged at one end of the support rod 303. The servo motor 302 drives one end of the transmission arm to rotate, and the other end of the transmission arm drives the two fixed arms to move. At this time, the two fixed arms slide relatively on the support rod 303, thereby moving out of the fixed cylinder 301, so as to strengthen the connection between the connecting tube 103 and the pump tube 102.
[0046] The transmission arm includes a screw rod 304 and a slide seat 305 . The slide seat 305 is slidably connected to the screw rod 304 and is located at one end of the screw rod 304 . The screw rod 304 drives the slide seat 305 to move.
[0047] Secondly, each of the fixed arms includes an arm body 306 and a fixed plate 307. One end of the arm body 306 is rotatably connected to the slide seat 305 and is located at one end of the slide seat 305. The other end of the arm body 306 is rotatably connected to the fixed plate 307 and is located at one end of the fixed plate 307. The slide seat 305 drives the arm body 306 to move, and the arm body 306 drives the fixed plate 307 to move.
[0048] A construction site fire pump installation and detection device using this embodiment is used in specific use. When the positioning rod 113 passes through the connecting pipe 103 and the pump pipe 102, the servo motor 302 drives the screw 304 to rotate, and the screw 304 drives the slide 305 to move in the fixed cylinder 301. The slide 305 drives the two arms 306 to move, and the two arms 306 drive the two fixed plates 307 to move relative to each other on the two support rods 303 until one end of the two fixed plates 307 moves out of the fixed cylinder 301, thereby strengthening the connection between the connecting pipe 103 and the pump pipe 102.
[0049] The present invention also provides a construction site fire pump installation detection system, which is suitable for the construction site fire pump installation detection device as described above.
[0050] What is disclosed above is only a preferred embodiment of the present invention, and it certainly cannot be used to limit the scope of rights of the present invention. Ordinary technicians in this field can understand that all or part of the processes of the above embodiment and equivalent changes made according to the claims of the present invention still fall within the scope of the invention.
Claims
1. A construction site fire pump installation detection device, comprising a fire pump body, a pump pipe, a connecting pipe and a pressure gauge, wherein the pump pipe is fixedly connected to the fire pump body and is located at one end of the fire pump body, the connecting pipe is detachably connected to the pump pipe and is located at one end of the pump pipe, the pressure gauge is fixedly connected to the connecting pipe and is located at one end of the connecting pipe, characterized in that: It also includes an installation box, a worm, a transmission assembly, a rotating part, a limit rod and two positioning structures. The installation box is fixedly connected to the connecting tube and is located at one end of the connecting tube. The worm, the transmission assembly, the rotating part and the limit rod are respectively arranged on the installation box. The transmission assembly is rotatably connected to the worm and is located at one end of the worm. The rotating part is rotatably connected to the transmission assembly and is located at one end of the transmission assembly. The two positioning structures are respectively connected to the limit rod and the rotating part sliding rod, and are symmetrically arranged at the limit rod and one end of the rotating part.
2. The construction site fire pump installation detection device according to claim 1, characterized in that: The transmission assembly comprises a worm wheel and a transmission gear, wherein the worm wheel cooperates with the worm, and the transmission gear is fixedly connected to the worm wheel and is located at one end of the worm wheel.
3. The construction site fire pump installation detection device as claimed in claim 2, characterized in that: The rotating component comprises a driving gear and a lead screw. The driving gear cooperates with the transmission gear. The lead screw is fixedly connected to the driving gear and is located at one end of the driving gear.
4. The construction site fire pump installation detection device as claimed in claim 3, characterized in that: Each positioning structure includes a frame and a positioning rod. The frame is slidably connected to the lead screw and the limit rod and is located at one end of the lead screw and the limit rod. The positioning rod is fixedly connected to the frame and is located at one end of the frame.
5. The construction site fire pump installation detection device as claimed in claim 4, characterized in that: The construction site fire pump installation and detection device also includes a filter bin, a drive disk, two mobile components, and two filter screens. The filter bin is fixedly connected to the connecting pipe and is located at one end of the connecting pipe. The drive disk, the two mobile components and the two filter screens are respectively arranged on the filter bin. The two mobile components are slidably connected to the drive disk and are symmetrically arranged at one end of the drive disk. Each filter screen is fixedly connected to the corresponding mobile component and is located at one end of the corresponding mobile component.
6. The construction site fire pump installation detection device according to claim 5, characterized in that: The driving disc comprises a disc body and a first gear, wherein the first gear is fixedly connected to the disc body and is located at one end of the disc body.
7. The construction site fire pump installation detection device according to claim 6, characterized in that: Each of the moving components includes a rack and a connecting frame, the rack cooperates with the first gear, and the connecting frame is fixedly connected to the rack and is located at one end of the rack.
8. A construction site fire pump installation detection system, suitable for the construction site fire pump installation detection device as claimed in claim 1.
Citation Information
Patent Citations
A detection device for fire pump
CN221054001U