Electric power insulator and preparation process thereof
Through the combination of ceramic umbrella and deformation sleeve and the use of connecting chains and rubber columns, the gap and collision damage problems of power insulators during assembly and use are solved, and rapid assembly, stable connection and safety performance are improved.
Patent Information
- Application Number
- CN202411588942.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-11-08
- Publication Date
- 2025-01-14
- Estimated Expiration
- Not applicable · inactive patent
AI Technical Summary
Existing electric insulators are prone to gaps during assembly, and are easily broken and damaged by collision during windy weather or vibration, making it difficult to quickly disassemble and maintain.
The design of ceramic umbrella combined with deformation sleeve is adopted to achieve rapid assembly and disassembly through the rotating connection of studs and nuts, and enhance stability and safety through the use of connecting chains and rubber columns to reduce collision risks.
The rapid assembly and disassembly of insulators is achieved, which eliminates gaps, enhances the stability and safety performance of insulators, and avoids breakage and shedding problems caused by collisions.
Smart Images

Figure CN119314755A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of insulators, and more particularly to a power insulator and a preparation process thereof. Background Art
[0002] An insulator is a device installed between conductors of different potentials or between a conductor and a grounding member, and is capable of withstanding voltage and mechanical stress. There are many types of insulators with different shapes. Although the structures and appearances of different types of insulators are quite different, they are all composed of two major parts: an insulating member and a connecting fitting. When using an insulator, when the length is increased as needed, multiple insulators need to be assembled and connected. However, when assembling, the insulators are all connected to each other, which may result in gaps. In windy weather or vibration, multiple insulators may collide with each other and be broken or damaged. Therefore, the present application provides a power insulator and a preparation process thereof. Summary of the invention
[0003] In order to overcome the deficiencies of the prior art, the present invention provides a power insulator and a preparation process thereof, which can accelerate the assembly process of multiple insulators, facilitate disassembly and maintenance, eliminate gaps between them and avoid collision damage.
[0004] The technical solution adopted by the present invention to solve its technical problem is:
[0005] An electric insulator comprises a ceramic umbrella and two deformable sleeves, the outer end of each deformable sleeve is rotatably connected to a nut, the two deformable sleeves are filled with studs and the studs are connected to the nuts, the upper and lower ends of the ceramic umbrella are formed with a clamping cavity, the outer end of the stud is fixedly connected to a connecting plate, and the inner end of each stud is fixedly connected to a conical bottom with a diameter greater than that of the deformable sleeve;
[0006] An inner through hole is provided between the two engaging cavities, a lifting ring is formed at the inner end of each stud, and a connecting chain is connected between the two lifting rings.
[0007] The upper and lower ends of the ceramic umbrella are both provided with a plurality of clamping holes, each of which is filled with a rubber column, and the diameter of the clamping hole increases gradually from the outside to the inside.
[0008] A process for preparing a power insulator, the process comprising the following steps:
[0009] S1: Connect the connecting chain to the two lifting rings, insert the connecting chain into the inner through hole, and the two deformation sleeves are respectively located in the two engaging cavities;
[0010] S2: Tighten the nut to move the stud outward, driving the bottom of the cone surface to squeeze the deformation sleeve outward, so that the deformation sleeve is deformed and expanded, and then tightly attached to the clamping cavity to achieve fixation;
[0011] S3: Weld the connecting plate to the outer end of the stud and fix the rubber pad on the outer surface of the connecting plate;
[0012] S4: Clean the outer surface of the ceramic umbrella and the welding slag to complete the preparation.
[0013] A preparation device is used in the preparation process, which includes a vertical frame rotatably connected to a vertical shaft, the upper and lower sides of the vertical shaft are provided with threads with opposite rotation directions, the upper and lower sides of the vertical shaft are connected to clamps, the two clamps are slidably connected to suspension rods and springs are fixed between the suspension rods and the clamps, and magnets are fixed to the inner ends of the two suspension rods.
[0014] The inner side of the clamping plate is rotatably connected with a nut buckle sleeved on the suspension rod, the outer wall of the nut buckle is fixedly connected with a gear ring, and the clamping plate is rotatably connected with a gear meshing with the gear ring.
[0015] The vertical frame is rotatably connected to the left end of the mounting frame, and the right end of the mounting frame is rotatably connected to the side shaft. Two clamping claws are arranged on the upper and lower sides of the side shaft, the two inner clamping claws are fixedly connected to the mounting frame, and the two outer clamping claws are respectively connected to the upper and lower sides of the side shaft, and the upper and lower sides of the side shaft are provided with threads with opposite rotation directions; the inner end of the clamping claw is formed with a positioning edge higher than the inner side surface of the clamping claw. BRIEF DESCRIPTION OF THE DRAWINGS
[0016] The present invention is further described in detail below with reference to the accompanying drawings and specific implementation methods.
[0017] Figure 1 It is a structural schematic diagram of the insulator in the present invention;
[0018] Figure 2 It is a schematic diagram of the structure inside the insulator of the present invention;
[0019] Figure 3 It is a structural schematic diagram of the conical bottom in the present invention;
[0020] Figure 4 It is a structural schematic diagram of the ceramic umbrella in the present invention;
[0021] Figure 5 It is a schematic diagram of the structure of the deformation sleeve in the present invention;
[0022] Figure 6 It is a schematic diagram of the structure of the connecting chain in the present invention;
[0023] Figure 7 It is a structural schematic diagram of the preparation device in the present invention;
[0024] Figure 8 It is a structural schematic diagram of the vertical frame in the present invention;
[0025] Fig. 9 It is a schematic diagram of the structure of the rubber sleeve in the present invention;
[0026] Fig.10 It is a structural schematic diagram of a nut buckle in the present invention;
[0027] Fig.11 It is a schematic diagram of the structure of the clamping jaws in the present invention;
[0028] In the figure: ceramic umbrella 01; inner perforation 02; engaging cavity 03; clamping hole 04; stud 05; lifting eye 06; deformation sleeve 07; nut 08; protective pad 09; conical bottom 10; connecting chain 11; connecting plate 12; rubber pad 13; rubber column 14; crossbeam 15; cross shaft 16; clamping arm 17; rubber sleeve 18; telescopic rod 19; vertical frame 20; vertical shaft 21; clamping plate 22; nut buckle 23; gear ring 24; gear 25; magnet 27; hanging rod 28; mounting frame 29; side shaft 30; clamping claw 31; positioning edge 32. DETAILED DESCRIPTION
[0029] See attached Figures 1 to 6 From the structure shown, it can be understood that an exemplary operation process of the rapid assembly of the present application is:
[0030] A power insulator comprises a ceramic umbrella 01 and two deformable sleeves 07, each of the outer ends of the deformable sleeves 07 is rotatably connected to a nut 08, the two deformable sleeves 07 are filled with studs 05 and the studs 05 are connected to the nuts 08, the upper and lower ends of the ceramic umbrella 01 are formed with a snap-fitting cavity 03, the outer ends of the studs 05 are fixedly connected to a connecting plate 12, and the inner ends of each stud 05 are fixedly connected to a conical bottom 10 having a diameter greater than that of the deformable sleeve 07; when preparing the insulator, by twisting the nut 08, the studs 05 are extended outward, so that the conical bottom 10 squeezes the deformable sleeve 07, so that the deformable sleeve 07 is expanded outward and fits on the inner wall of the snap-fitting cavity 03, thereby using the conical bottom 10 to hold the deformable sleeve 07 is clamped on the inner wall of the locking cavity 03, so that the stud 05 can be quickly fixed, and the stud 05 can be clamped in the locking cavity 03 to complete the connection with the ceramic umbrella 01. Then, when the number of insulators needs to be increased, the two adjacent connecting plates 12 can be fitted and then connected by bolts to achieve the connection between the two connecting plates 12. The above method can be used to connect and assemble the insulators, thereby extending the length of the insulator, thereby increasing the distance between the cable and the connecting bracket, increasing the safety distance, and improving the safety performance. When performing maintenance, the nut 08 can be loosened to retract the stud 05 into the locking cavity 03, and the deformation sleeve 07 can be pulled out for replacement.
[0031] See attached Figures 1 to 6 From the structure shown, it can be understood that an exemplary operation process of increasing the safety performance of the present application is:
[0032] An inner through hole 02 is provided between the two engaging cavities 03, and a lifting ring 06 is formed at the inner end of each stud 05, and a connecting chain 11 is connected between the two lifting rings 06; when the two studs 05 are extended outward by tightening the nut 08, the distance between the two studs 05 can be increased, so that the two lifting rings 06 tighten the connecting chain 11. During daily use, when encountering wind and sand that causes the cable to shake and touch the ceramic umbrella 01 or stones to hit the ceramic umbrella 01, when the ceramic umbrella 01 is broken, the two studs 05 can still be connected together by the connecting chain 11, thereby preventing the cable from falling off after the ceramic umbrella 01 is broken, thereby achieving a stable connection between the bracket and the cable, and preventing the cable from being separated from the bracket due to the breakage of the ceramic umbrella 01.
[0033] See attached Figures 1 to 6 From the structure shown, it can be understood that an exemplary operation process of increasing the stability performance of the present application is:
[0034] The upper and lower ends of the ceramic umbrella 01 are provided with a plurality of clamping holes 04, each of which is filled with a rubber column 14, and the diameter of the clamping hole 04 gradually increases from the outside to the inside; when the two ceramic umbrellas 01 are assembled, the rubber column 14 can be filled into the clamping hole 04 on one of the ceramic umbrellas 01, and then the other end of the rubber column 14 is extended into the clamping hole 04 on the other ceramic umbrella 01, and then when the two connecting plates 12 are connected, the two ceramic umbrellas 01 are squeezed with the rubber column 14, so that the end of the rubber column 14 can be deformed after being squeezed and fill the clamping hole 04, and the rubber column 14 can be clamped by utilizing the structure of the clamping hole 04 with a large inside and a small outside, so that the rubber column 14 can be utilized to increase the support between the two ceramic umbrellas 01 and increase the stability between the two ceramic umbrellas 01.
[0035] See attached Figures 1 to 6 From the structure shown, it can be understood that an exemplary operation process of reducing collision in the present application is:
[0036] The outer surface of the connecting plate 12 is fixedly connected with a rubber pad 13. When the two connecting plates 12 are connected, the rubber pad 13 can achieve buffering and filling between the two connecting plates 12, so that the two connecting plates 12 fit more closely, avoiding the hidden danger of small collisions between the two connecting plates 12 due to vibration and being transmitted to the ceramic umbrella 01, causing cracks.
[0037] See attached Figures 1 to 6 From the structure shown, it can be understood that an exemplary operation process of the present application to avoid scratching the ceramic umbrella 01 is:
[0038] The lower end face of the nut 08 is fixedly connected with a protective pad 09; when the nut 08 is tightened, the protective pad 09 can be placed between the nut 08 and the ceramic umbrella 01, thereby preventing the lower end face of the nut 08 from directly contacting the ceramic umbrella 01 and causing scratches, thereby preventing the ceramic umbrella 01 from cracking easily due to scratches.
[0039] A process for preparing a power insulator, the process comprising the following steps:
[0040] S1: Connect the connecting chain 11 to the two lifting rings 06, so that the connecting chain 11 passes through the inner through hole 02, and the two deformation sleeves 07 are respectively located in the two engaging cavities 03;
[0041] S2: Tighten the nut 08 to move the stud 05 outwards, driving the conical bottom 10 to press the deformation sleeve 07 outwards, so that the deformation sleeve 07 is deformed and expanded, and then closely adheres to the engaging cavity 03 to achieve fixation;
[0042] S3: Weld the connecting plate 12 to the outer end of the stud 05 and fix the rubber pad 13 to the outer surface of the connecting plate 12;
[0043] S4: Clean the outer surface of the ceramic umbrella 01 and the welding slag to complete the preparation.
[0044] See attached Figures 1 to 11 From the structure shown, it can be understood that an exemplary operation process of installing the connection chain 11 of the present application is:
[0045] A preparation device is used in the preparation process, which includes a vertical frame 20 rotatably connected to a vertical shaft 21, wherein the upper and lower sides of the vertical shaft 21 are provided with threads of opposite rotation directions, and the upper and lower sides of the vertical shaft 21 are connected to clamps 22, and the two clamps 22 are slidably connected to a suspension rod 28, and a spring is fixed between the suspension rod 28 and the clamps 22, and the inner ends of the two suspension rods 28 are fixed with magnets 27; one of the studs 05 is adsorbed on the magnet 27 located above, so that the other stud 05 hangs down naturally, thereby vertically straightening the connecting chain 11, and then the ceramic umbrella 01 can be moved downward and upward, so that the stud 05 located below passes through the inner through-hole 02, and then the vertical shaft 21 can be rotated so that the vertical shaft 21 drives the two clamps 22 to slide close to each other on the vertical frame 20, so that the two clamps 22 clamp the ceramic umbrella 01 from the upper and lower sides, and at this time, the stud 05 located below will be adsorbed on the magnet 27 located below, thereby completing the process of inserting the connecting chain 11 into the inner through-hole 02.
[0046] See attached Figures 1 to 11 From the structure shown, it can be understood that an exemplary operation process of tightening the nut 08 of the present application is:
[0047] The inner side of the clamping plate 22 is rotatably connected with a nut buckle 23 sleeved on the suspension rod 28, and a toothed ring 24 is fixedly connected to the outer wall of the nut buckle 23. A gear 25 meshing with the toothed ring 24 is rotatably connected to the clamping plate 22. After the nut 08 located above is connected to the stud 05 located above, the stud 05 is adsorbed on the magnet 27 located above. After the ceramic umbrella 01 is sleeved on the connecting chain 11, when the stud 05 located below passes through the ceramic umbrella 01, the nut 08 located below is connected to the stud 05 located below. 5, and then by clamping the two clamping plates 22, the two nut buckles 23 are respectively sleeved on the two nuts 08, and then the motor is used to drive the rotation of the gear 25, so that the gear 25 engages the gear ring 24 to drive the nut buckle 23 to rotate, so that the nut buckle 23 tightens the nut 08, and when the nut 08 is tightened to make the stud 05 extend outward, it will push the suspension rod 28 outward to slide, so that the suspension rod 28 compresses the spring, and when the insulation is removed after the assembly is completed, the spring will drive the suspension rod 28 to reset, preparing for subsequent assembly work.
[0048] See attached Figures 1 to 11 From the structure shown, it can be understood that an exemplary operation process of the rapid positioning of the present application is:
[0049] The vertical frame 20 is rotatably connected to the left end of the mounting frame 29, and the right end of the mounting frame 29 is rotatably connected to the side shaft 30. Two clamping claws 31 are arranged on the upper and lower sides of the side shaft 30. The two inner clamping claws 31 are fixedly connected to the mounting frame 29, and the two outer clamping claws 31 are respectively connected to the upper and lower sides of the side shaft 30. The upper and lower sides of the side shaft 30 are provided with threads with opposite rotation directions; the two connecting plates 12 are respectively clamped between the two clamping claws 31 on the upper and lower sides, so as to fix the positions of the two connecting plates 12. After the nut 08 is tightened, the ceramic umbrella 01 can be moved between the two connecting plates 12. At this time, the outer ends of the two studs 05 are in contact with the two connecting plates 12, so as to achieve rapid positioning. Then, a welding gun can be used to weld the two connecting plates 12 to the outer ends of the two studs 05 respectively to complete the connection.
[0050] In addition, the inner end of the clamp 31 is formed with a positioning edge 32 that is higher than the inner side surface of the clamp 31. When clamping the connecting plate 12, the positioning edge 32 can be used to limit the clamping depth of the connecting plate 12 so that the middle positioning of the connecting plate 12 after clamping can be stably aligned with the stud 05, thereby enabling more accurate welding and positioning.
[0051] See attached Figures 1 to 11 From the structure shown, it can be understood that an exemplary operation process of clamping the ceramic umbrella 01 of the present application is:
[0052] The vertical frame 20 is fixedly connected with a telescopic rod 19, and the telescopic rod 19 is fixedly connected with a crossbeam 15. The crossbeam 15 is rotatably connected with a cross shaft 16. It is assumed that there are threads with opposite rotation directions on both sides of the cross shaft 16. Clamp arms 17 are respectively connected to both sides of the cross shaft 16, and a rubber sleeve 18 is fixedly connected to the inner side of each clamp arm 17. The crossbeam 15 is driven to extend outward by the telescopic rod 19, and then the ceramic umbrella 01 is moved between the two clamp arms 17. Then, the two rubber sleeves 18 are brought close to each other to clamp the ceramic umbrella 01 by the rotation of the cross shaft 16. Then, the crossbeam 15 can be reset to move the ceramic umbrella 01 between the two clamping plates 22, so that the upper and lower ends of the ceramic umbrella 01 are respectively aligned with the two nut buckles 23, so as to facilitate clamping. After the nuts 08 are tightened, the vertical frame 20 can be rotated to drive the assembled ceramic umbrella 01 to move between the two clamped connecting plates 12, thereby completing the automatic conversion and connection of the processing procedures.
Claims
1. A power insulator, characterized in that: The invention comprises a ceramic umbrella (01) and two deformable sleeves (07), wherein the outer end of each deformable sleeve (07) is rotatably connected to a nut (08), the two deformable sleeves (07) are filled with studs (05) and the studs (05) are connected to the nuts (08), the upper and lower ends of the ceramic umbrella (01) are formed with engaging cavities (03), the outer ends of the studs (05) are fixedly connected to a connecting plate (12), and the inner ends of each stud (05) are fixedly connected to a conical bottom (10) having a diameter greater than that of the deformable sleeve (07).
2. The power insulator according to claim 1, characterized in that: An inner through hole (02) is provided between the two engaging cavities (03), a lifting ring (06) is formed at the inner end of each stud (05), and a connecting chain (11) is connected between the two lifting rings (06).
3. The power insulator according to claim 2, characterized in that: The ceramic umbrella (01) is provided with a plurality of clamping holes (04) at both upper and lower ends, each clamping hole (04) is filled with a rubber column (14), and the diameter of the clamping hole (04) gradually increases from the outside to the inside.
4. The power insulator according to claim 3, characterized in that: A rubber pad (13) is fixedly connected to the outer surface of the connecting plate (12).
5. The power insulator according to claim 4, characterized in that: A protection pad (09) is fixedly connected to the lower end surface of the nut (08).
6. A process for preparing a power insulator, characterized in that: The process includes the following steps: S1: Connect the connecting chain (11) to the two lifting rings (06), so that the connecting chain (11) is inserted into the inner through hole (02), and the two deformation sleeves (07) are respectively located in the two engaging cavities (03); S2: Tightening the nut (08) causes the stud (05) to move outward, driving the conical bottom (10) to press the deformation sleeve (07) outward, so that the deformation sleeve (07) is deformed and expanded, and then tightly attached to the engaging cavity (03) to achieve fixation; S3: Weld the connecting plate (12) to the outer end of the stud (05) and fix the rubber pad (13) to the outer surface of the connecting plate (12); S4: Clean the outer surface of the ceramic umbrella (01) and the welding slag to complete the preparation.
7. The preparation process according to claim 6, characterized in that: A preparation device is used in the preparation process, the device comprising a vertical frame (20) rotatably connected to a vertical shaft (21), the vertical shaft (21) having threads with opposite rotation directions on the upper and lower sides, the vertical shaft (21) having clamping plates (22) connected to the upper and lower sides, the two clamping plates (22) having hanging rods (28) slidably connected thereto, a spring being fixed between the hanging rods (28) and the clamping plates (22), and magnets (27) being fixed to the inner ends of the two hanging rods (28).
8. The preparation process according to claim 7, characterized in that: The inner side of the clamping plate (22) is rotatably connected with a nut buckle (23) sleeved on the suspension rod (28), the outer wall of the nut buckle (23) is fixedly connected with a gear ring (24), and the clamping plate (22) is rotatably connected with a gear (25) meshing with the gear ring (24).
9. The preparation process according to claim 8, characterized in that: The vertical frame (20) is rotatably connected to the left end of the mounting frame (29), and the right end of the mounting frame (29) is rotatably connected to the side shaft (30). Two clamping claws (31) are arranged on the upper and lower sides of the side shaft (30), the two inner clamping claws (31) are fixedly connected to the mounting frame (29), and the two outer clamping claws (31) are respectively connected to the upper and lower sides of the side shaft (30), and the upper and lower sides of the side shaft (30) are provided with threads with opposite rotation directions; the inner end of the clamping claw (31) is formed with a positioning edge (32) higher than the inner side surface of the clamping claw (31).
10. The preparation process according to claim 9, characterized in that: The vertical frame (20) is fixedly connected with a telescopic rod (19), the telescopic rod (19) is fixedly connected with a crossbeam (15), the crossbeam (15) is rotatably connected with a cross shaft (16), the two sides of the cross shaft (16) are assumed to have threads with opposite rotation directions, the two sides of the cross shaft (16) are respectively connected with clamping arms (17), and the inner side of each clamping arm (17) is fixedly connected with a rubber sleeve (18).