Concrete structure engineering construction quality monitoring device

By introducing monitoring probe traction climbing mechanism and clamping mechanism into the concrete detector, the problem of insufficient detection convenience of high-altitude concrete structures is solved, efficient and stable concrete structure inspection is achieved, the detection range is expanded and the monitoring efficiency is improved .

CN119322169APending Publication Date: 2025-01-17南阳市宛城区工程质量监督站
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411564735.7
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-11-05
Publication Date
2025-01-17

AI Technical Summary

Technical Problem

The existing concrete structure detectors have insufficient probe detection convenience in the detection of concrete structures at higher locations, which leads to the need for climbing equipment, which increases the difficulty and risk of detection.

Method used

A concrete structure engineering construction quality monitoring device is designed, using a monitoring probe traction climbing mechanism, combined with a servo motor and a driving motor, the probe traction climbing is realized through air negative pressure and plastic rollers, which can move stably on the concrete surface and adapt to different Surface roughness and speed up detection through multiple probes simultaneously.

Benefits of technology

It realizes efficient inspection on the surface of vertical or horizontal concrete structures, expands the inspection range, avoids missed inspections in areas that cannot be reached by manual labor, and improves the efficiency of concrete project quality monitoring.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119322169A_ABST
    Figure CN119322169A_ABST
Patent Text Reader

Abstract

The invention discloses a concrete structure engineering construction quality monitoring device, relates to the technical field of engineering quality monitoring equipment, and provides the following scheme that the concrete structure engineering construction quality monitoring device comprises a concrete detector, and a monitoring probe traction climbing mechanism is arranged at the tail end of a probe of the concrete detector; two monitoring probe clamping ends are arranged on the front side surface of the monitoring probe traction climbing mechanism; the concrete detector comprises a detector body and 2-3 cable joints fixed on the end face of the front side of the detector body. According to the technical scheme, the climbing mechanism and the clamping mechanism are arranged for assistance, so that the monitoring probe of the concrete detector can climb to the vertical and even horizontal concrete structure surface while being clamped, the concrete detection range can be expanded, and the detection efficiency is improved. The problem of leak detection due to the fact that a concrete area cannot be reached manually is avoided, and in addition, the concrete engineering quality monitoring efficiency is improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of engineering quality monitoring equipment, and in particular to a concrete structure engineering construction quality monitoring device. Background Art

[0002] According to GB50204-2015 "Concrete Structure Engineering Construction Quality Acceptance Code", the quality acceptance of concrete structure sub-division engineering construction, in addition to the visual quality should be qualified, the structural entity inspection must also be qualified. Structural entity inspection. It is mainly carried out on representative parts involving the safety of concrete structures, including three major items: ① concrete strength, ② steel bar protective layer thickness, ③ structural position and size deviation. For finished and semi-finished concrete structures, they are generally tested by concrete detectors, which are mainly composed of a body and a probe. The inspector holds the probe in hand and touches the concrete surface to obtain concrete data in the form of ultrasound. However, in actual use, for higher and vertical concrete structures, the height limits the convenience of probe detection, resulting in the need for inspectors to climb with the help of ladders to contact the high concrete surface. Summary of the invention

[0003] In view of the defects in the above-mentioned background technology that the probe of the line-stage concrete quality monitoring device needs to be handheld for detection and cannot directly monitor the concrete structure at a higher position, a technical solution content of a concrete structure engineering construction quality monitoring device is provided.

[0004] It includes a concrete detector, a monitoring probe traction climbing mechanism is arranged at the probe end of the concrete detector, and two monitoring probe clamping ends are arranged on the front side surface of the monitoring probe traction climbing mechanism;

[0005] The concrete detector includes a detector body and 2-3 cable connectors fixed on the front end face of the detector body. A transmission harness of at least 10m in length is plugged into the port of the cable connector, and a monitoring probe is connected to the end of the transmission harness away from the cable connector. Since the monitoring probe traction climbing mechanism has the ability to drive the probe to climb along the wall, and the user can basically stand still, a transmission harness of at least 10m in length is required to adapt to the operation of the monitoring probe traction climbing mechanism, and on the other hand, it can reduce the distance the user follows and walks. Moreover, 2-3 cable connectors are set on the concrete detector in order to be able to connect 2-3 probes at the same time, so that the 2-3 monitoring probe traction climbing mechanisms can drive 2-3 probes for detection at the same time, thereby speeding up the detection speed of the concrete structure.

[0006] The monitoring probe traction climbing mechanism includes a support plate, a silicone frame fixed to a circle around the edge of the rear surface of the support plate, and a wind tube fixed to the middle area inside the support plate, a servo motor is fixed in the inner cavity of the wind tube, and the output shaft of the servo motor is connected to the turbofan blade through a coupling, and a driving motor is installed at the four corner positions of the support plate, and the output shaft of the driving motor is connected to the plastic roller through a coupling; wherein, due to the different roughness of the surface of the concrete structure, the wind force generated by the turbofan blades and the servo motor is insufficient to support any action of the climbing mechanism, therefore, in the replacement scheme, the servo motor can be replaced by a high-frequency motor to provide a faster rotation speed for the turbofan, thereby providing a greater downward force for the climbing mechanism, and a metal filter can be set at the air inlet port of the wind tube to prevent the wind tube from inhaling debris on the surface of the concrete structure, causing damage to the turbofan blades.

[0007] Specifically, the operation of the servo motor and the drive motor is controlled by the detector body. The output shaft of the drive motor drives the plastic roller to roll synchronously, and the servo motor drives the turbofan blades to rotate at high speed, thereby extracting the air between the support plate and the silicone frame to form a negative pressure. The generation of negative pressure allows the support plate to be adsorbed on the concrete surface, and the plastic roller drives the clamping end of the monitoring probe and the clamped monitoring probe to move, so as to achieve the purpose of detecting the concrete by moving on the concrete surface.

[0008] The detector body controls the operation of the servo motor and the drive motor. The output shaft of the drive motor drives the plastic roller to roll synchronously, and the servo motor drives the turbofan blades to rotate at high speed, thereby extracting the air between the support plate and the silicone frame to form a negative pressure. The generation of negative pressure allows the support plate to be adsorbed on the concrete surface, and the plastic roller drives the clamping end of the monitoring probe and the clamped monitoring probe to move. If the surface of the concrete structure is relatively rough and has large potholes, the silicone frame is designed to be in the central control state, and the silicone frame can be inflated. Therefore, a servo air pump can be installed on the upper surface of the support plate. By expanding the hollow silicone frame, it has the ability to deform freely, so as to adapt to the concrete structure with a relatively rough surface and large potholes, allowing the monitoring probe to pull the climbing mechanism to climb the wall stably.

[0009] The monitoring probe clamping end includes a servo electric cylinder fixedly connected to the front side surface of the support plate, a fixed seat fixed to the top end surface of the servo electric cylinder, and a movable seat arranged above the fixed seat, the telescopic end of the servo electric cylinder is connected to a telescopic shaft penetrating the fixed seat, and the top end of the telescopic shaft is fixedly connected to the bottom surface of the movable seat;

[0010] Specifically, after turning on the detector body, straighten the transmission harness, and place the monitoring probe between the clamp arms. Use the control button on the detector body to control the telescopic end of the servo electric cylinder to drive the telescopic shaft to move downward. In the process of pulling the movable seat downward, the pulling arm and the bent rod are driven to expand outward. On the contrary, when the telescopic shaft moves upward, the pulling arms approach each other, and the bent rods also approach each other, thereby forcing the clamp arms to approach each other to clamp the monitoring probe. Among them, since the probe needs to contact the surface of the concrete structure or maintain a millimeter-level spacing, the clamp arm can change the clamping position of the probe before detection. With the help of a vernier caliper, measure the spacing between the end of the probe and the surface of the concrete structure after the monitoring probe is pulled and attached to the surface of the concrete structure by the climbing mechanism, so as to obtain the applicable detection spacing according to the different concrete structures and expand its applicable scenarios.

[0011] Among them, a guide column is fixed on both the front and rear sides of the bottom surface of the movable seat, the bottom end of the guide column is fixedly connected to the top surface of the fixed seat, a connecting plate passes through the outer ring of the guide column, and a bent rod is hinged at both ends of the left and right ends of the connecting plate. Two pulling arms are intersected on the top surface of the movable seat, the top end of the pulling arm is hinged with a clamp arm, and the top end of the pulling arm is hinged to the bottom end of the clamp arm.

[0012] In the above-mentioned technical solution of the concrete structure engineering construction quality monitoring device, preferably: a display screen is installed on the top surface of the detector body, and a plurality of control buttons are arranged in the area on the right side of the display screen on the top surface of the detector body.

[0013] In the above-mentioned technical solution of the concrete structure engineering construction quality monitoring device, preferably: the monitoring probe is located in the area between the clamp arms and is clamped by the clamp arms, and the detection end face of the monitoring probe is flush with the rear end face of the silicone frame and contacts the concrete surface to be detected.

[0014] In the above-mentioned technical solution of the device for monitoring the construction quality of concrete structure engineering, preferably: a circular hole for the air duct to pass through is opened in the inner middle area of ​​the support plate, the rear end face of the air duct is flush with the rear side end face of the support plate, and notches for fixing the drive motor are provided at the four corners of the support plate.

[0015] In the above-mentioned technical solution of the concrete structure engineering construction quality monitoring device, preferably: the rear side surface of the outer ring of the plastic roller is flush with the rear end face of the silicone frame, and 4 fixing plates are fixed in a circular array on the inner cavity side wall of the air duct, and one end of the fixing plates that are gathered together is fixedly connected to the outer shell surface of the servo motor.

[0016] In the above-mentioned technical solution of the device for monitoring the construction quality of concrete structure engineering, preferably: the front and rear end surfaces of the air duct are both in an open state, and the rotation direction of the turbofan blades forces the air on the rear side of the support plate to flow to the front side, thereby forming a negative pressure on the rear surface of the support plate and the inner area of ​​the silicone frame and adsorbing on the concrete surface.

[0017] In the above-mentioned technical solution of the device for monitoring the construction quality of concrete structure engineering, preferably: the front end face of the silicone frame is adhered to the rear surface of the support plate along the edge shape of the support plate by an adhesive, and there is a gap of 1-3 mm between the rear end face of the silicone frame and the concrete surface for air to enter from the gap.

[0018] In the technical solution of the above-mentioned concrete structure engineering construction quality monitoring device, preferably: a through hole for the telescopic shaft to pass through is opened inside the fixing seat, and a sliding bearing is arranged inside the through hole.

[0019] In the technical solution of the above-mentioned concrete structure engineering construction quality monitoring device, preferably: protrusions are fixed on both left and right sides of the top surface of the movable seat, and the inside of the protrusion is hinged to the bottom end of the pulling arm through an axle pin.

[0020] In the above-mentioned technical solution of the device for monitoring the construction quality of concrete structure engineering, preferably: a layer of silicone sheet is adhered and fixed to the surfaces of the sides of the clamp arms that are close to each other by adhesive.

[0021] It can be seen from the above technical solution that the present invention provides a concrete structure engineering construction quality monitoring device. Compared with the prior art, the present invention has the following beneficial effects:

[0022] In the technical solution of the present invention, by providing an auxiliary climbing mechanism and a clamping mechanism, the monitoring probe of the concrete detector can climb onto the vertical or even horizontal surface of the concrete structure while being clamped, thereby expanding the concrete detection range and avoiding the problem of missed detection in concrete areas that cannot be reached by humans. In addition, the efficiency of concrete engineering quality monitoring is improved. BRIEF DESCRIPTION OF THE DRAWINGS

[0023] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the following briefly introduces and describes the drawings required for use in the embodiments of the present invention or the description of the prior art. Obviously, the drawings described below are only some embodiments of the present invention, and for ordinary technicians in this field, other drawings can be obtained based on these drawings without creative work.

[0024] Figure 1 It is the overall structural diagram of the concrete engineering quality monitoring organization;

[0025] Figure 2 This is a schematic diagram of the monitoring probe's traction and climbing mechanism;

[0026] Figure 3 This is a schematic diagram of the clamping end of the monitoring probe;

[0027] Figure 4 A schematic diagram of a concrete testing instrument.

[0028] Attached Figure 1 -Attached Figure 4 The corresponding relationship of the parts is as follows:

[0029] 1. Concrete detector; 11. Detector body; 12. Cable connector; 13. Transmission harness; 14. Monitoring probe; 2. Monitoring probe traction climbing mechanism; 21. Support plate; 22. Air cylinder; 23. Servo motor; 24. Drive motor; 25. Plastic roller; 26. Turbofan blade; 27. Silicone frame; 3. Monitoring probe clamping end; 31. Servo electric cylinder; 32. Fixed seat; 33. Telescopic shaft; 34. Pulling arm; 35. Clamp arm; 36. Bending rod; 37. Movable seat; 38. Connecting plate; 39. Guide column. DETAILED DESCRIPTION

[0030] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the embodiments described below are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0031] In order to more clearly explain and illustrate the technical solution and implementation of the present invention, preferred specific embodiments for implementing the technical solution of the present invention are introduced below.

[0032] Embodiment: A preferred technical solution for a concrete structure engineering construction quality monitoring device:

[0033] Refer to the instruction manual Figure 1 As shown: it includes a concrete detector 1, a monitoring probe traction climbing mechanism 2 is arranged at the probe end of the concrete detector 1, and two monitoring probe clamping ends 3 are arranged on the front side surface of the monitoring probe traction climbing mechanism 2;

[0034] Refer to the instruction manual Figure 4 As shown: the concrete detector 1 includes a detector body 11, and 2-3 cable connectors 12 fixed on the front end surface of the detector body 11, a transmission harness 13 of at least 10m in length is plugged into the port of the cable connector 12, and a monitoring probe 14 is connected to the end of the transmission harness 13 away from the cable connector 12;

[0035] Refer to the instruction manual Figure 2 As shown: the monitoring probe traction climbing mechanism 2 includes a support plate 21, a silicone frame 27 fixed to the edge of the rear surface of the support plate 21, and a wind tube 22 fixed to the middle area inside the support plate 21. A servo motor 23 is fixed in the inner cavity of the wind tube 22. The output shaft of the servo motor 23 is connected to a turbofan blade 26 through a coupling. A driving motor 24 is installed at the four corner positions of the support plate 21. The output shaft of the driving motor 24 is connected to a plastic roller 25 through a coupling.

[0036] Refer to the instruction manual Figure 3 As shown: the monitoring probe clamping end 3 includes a servo electric cylinder 31 fixedly connected to the front side surface of the support plate 21, a fixed seat 32 fixed to the top end surface of the servo electric cylinder 31, and a movable seat 37 arranged above the fixed seat 32. The telescopic end of the servo electric cylinder 31 is connected to a telescopic shaft 33 that penetrates the fixed seat 32, and the top end of the telescopic shaft 33 is fixedly connected to the bottom surface of the movable seat 37;

[0037] Refer to the instruction manual Figure 3 As shown: a guide column 39 is fixed on both sides of the front and rear of the bottom surface of the movable seat 37, the bottom end of the guide column 39 is fixedly connected to the top surface of the fixed seat 32, a connecting plate 38 passes through the outer ring of the guide column 39, and a bent rod 36 is hinged at both ends of the left and right ends of the connecting plate 38, and two pulling arms 34 are intersected on the top surface of the movable seat 37, and a clamp arm 35 is hinged at the top of the pulling arm 34, and the top of the pulling arm 34 is hinged to the bottom end of the clamp arm 35.

[0038] Refer to the instruction manual Figure 4 As shown: a display screen is installed on the top surface of the detector body 11, and a plurality of control buttons are arranged in the area on the right side of the display screen on the top surface of the detector body 11. The monitoring probe 14 is located in the area between the clamp arms 35 and is clamped by the clamp arms 35. The detection end face of the monitoring probe 14 is flush with the rear end face of the silicone frame 27 and contacts the concrete surface to be detected.

[0039] Refer to the instruction manual Figure 2As shown: a circular hole for the air supply tube 22 to pass through is provided in the inner middle area of ​​the support plate 21, the rear end face of the air supply tube 22 is flush with the rear side end face of the support plate 21, and the four corners of the support plate 21 are provided with notches for fixing the drive motor 24. The rear surface of the outer ring of the plastic roller 25 is flush with the rear side end face of the silicone frame 27, and four fixing plates are fixed in a circular array on the inner cavity side wall of the air supply tube 22, and one end of the fixing plates gathered together is fixedly connected to the outer shell surface of the servo motor 23. The front and rear end faces of the air supply tube 22 are both in an open state, and the rotation direction of the turbofan blade 26 forces the air on the rear side of the support plate 21 to flow to the front side, thereby forming a negative pressure on the rear side surface of the support plate 21 and the inner area of ​​the silicone frame 27, and adsorbing on the concrete surface. The front end surface of the silicone frame 27 is adhered to the rear surface of the support plate 21 along the edge shape of the support plate 21 by adhesive, and there is a gap of 1-3 mm between the rear end surface of the silicone frame 27 and the concrete surface for air to enter from the gap.

[0040] Refer to the instruction manual Figure 3 As shown: a through hole is opened inside the fixed seat 32 for the telescopic shaft 33 to pass through, and a sliding bearing is arranged inside the through hole. Bumps are fixed on both sides of the top surface of the movable seat 37, and the inside of the bumps is hinged to the bottom end of the pulling arm 34 through an axle pin; a layer of silicone sheet is fixed to the side surface of the clamp arms 35 that are close to each other by adhesive.

[0041] According to the above-mentioned preferred technical solution, the workflow of the technical solution is described as follows:

[0042] After turning on the detector body 11, straighten the transmission harness 13 and place the monitoring probe 14 between the clamp arms 35. The telescopic end of the servo electric cylinder 31 is controlled by the control button on the detector body 11 to drive the telescopic shaft 33 to move downward. In the process of pulling the movable seat 37 downward, the pulling arm 34 and the bent rod 36 are driven to expand outward. On the contrary, when the telescopic shaft 33 moves upward, the pulling arms 34 approach each other, and the bent rod 36 also approach each other, thereby forcing the clamp arms 35 to approach each other to clamp the monitoring probe 14.

[0043] The detector body 11 controls the operation of the servo motor 23 and the drive motor 24. The output shaft of the drive motor 24 drives the plastic roller 25 to roll synchronously, and the servo motor 23 drives the turbofan blades 26 to rotate at high speed, thereby extracting the air between the support plate 21 and the silicone frame 27 to form a negative pressure. The generation of negative pressure allows the support plate 21 to be adsorbed on the concrete surface, and the plastic roller 25 drives the monitoring probe clamping end 3 and the clamped monitoring probe 14 to move, so as to detect the concrete surface by moving on the concrete surface.

[0044] The present invention is not limited to the above-mentioned optimal implementation mode. Anyone should be aware that any structural changes made under the inspiration of the present invention, and any technical solutions that are the same or similar to the present invention, fall within the protection scope of the present invention. Finally, it should be noted that the structures, proportions, sizes, etc. illustrated in the drawings of this specification are only used to match the contents disclosed in the specification for people familiar with this technology to understand and read, and are not used to limit the restrictive conditions that can be implemented in this application, so they have no technical substantive significance. Any structural modification, change in proportional relationship or adjustment of size, without affecting the effects that can be produced by this application and the purposes that can be achieved, should still fall within the scope that can be covered by the technical content disclosed in this application.

Claims

1. A device for monitoring the construction quality of a concrete structure engineering project, comprising a concrete detector (1), characterized in that: The probe end of the concrete detector (1) is provided with a monitoring probe traction climbing mechanism (2), and the front surface of the monitoring probe traction climbing mechanism (2) is provided with two monitoring probe clamping ends (3); The concrete detector (1) comprises a detector body (11), and 2-3 cable connectors (12) fixed on the front end surface of the detector body (11), a transmission wire bundle (13) of at least 10 m in length is plugged into the port of the cable connector (12), and a monitoring probe (14) is connected to the end of the transmission wire bundle (13) away from the cable connector (12); The monitoring probe traction climbing mechanism (2) comprises a support plate (21), a silicone frame (27) fixed to a circle around the edge of the rear surface of the support plate (21), and a wind tube (22) fixed to the middle area inside the support plate (21), a servo motor (23) is fixed in the inner cavity of the wind tube (22), the output shaft of the servo motor (23) is connected to a turbofan blade (26) via a coupling, and a driving motor (24) is installed at each of the four corner positions of the support plate (21), and the output shaft of the driving motor (24) is connected to a plastic roller (25) via a coupling; The monitoring probe clamping end (3) comprises a servo electric cylinder (31) fixedly connected to the front side surface of the support plate (21), a fixed seat (32) fixed to the top end surface of the servo electric cylinder (31), and a movable seat (37) arranged above the fixed seat (32), the telescopic end of the servo electric cylinder (31) is connected to a telescopic shaft (33) penetrating the fixed seat (32), and the top end of the telescopic shaft (33) is fixedly connected to the bottom surface of the movable seat (37); A guide column (39) is fixed on both the front and rear sides of the bottom surface of the movable seat (37); the bottom end of the guide column (39) is fixedly connected to the top surface of the fixed seat (32); a connecting plate (38) passes through the outer ring of the guide column (39); a bent rod (36) is hinged at both the left and right ends of the connecting plate (38); two pulling arms (34) are intersected on the top surface of the movable seat (37); a clamp arm (35) is hinged at the top end of the pulling arm (34); and the top end of the pulling arm (34) is hinged to the bottom end of the clamp arm (35).

2. A concrete structure engineering construction quality monitoring device according to claim 1, characterized in that: A display screen is installed on the top surface of the detector body (11), and a plurality of control buttons are arranged in an area on the right side of the display screen on the top surface of the detector body (11).

3. A concrete structure engineering construction quality monitoring device according to claim 1, characterized in that: The monitoring probe (14) is located in the area between the clamp arms (35) and is clamped by the clamp arms (35). The detection end surface of the monitoring probe (14) is flush with the rear end surface of the silicone frame (27) and is in contact with the concrete surface to be detected.

4. A concrete structure engineering construction quality monitoring device according to claim 1, characterized in that: A circular hole through which the air supply tube (22) passes is provided in the middle area of ​​the support plate (21); the rear end surface of the air supply tube (22) is flush with the rear end surface of the support plate (21); and notches for fixing the drive motor (24) are provided at the four corners of the support plate (21).

5. A concrete structure engineering construction quality monitoring device according to claim 1, characterized in that: The rear surface of the outer ring of the plastic roller (25) is flush with the rear end surface of the silicone frame (27), and four fixing plates are fixed in a circular array on the inner cavity side wall of the air cylinder (22), and one end of the fixing plates gathered together is fixedly connected to the outer shell surface of the servo motor (23).

6. A concrete structure engineering construction quality monitoring device according to claim 1, characterized in that: The front and rear end surfaces of the air duct (22) are both in an open state, and the rotation direction of the turbofan blades (26) forces the air on the rear side of the support plate (21) to flow to the front side, thereby forming a negative pressure on the rear side surface of the support plate (21) and the inner area of ​​the silicone frame (27), and adsorbing it on the concrete surface.

7. A concrete structure engineering construction quality monitoring device according to claim 1, characterized in that: The front end surface of the silicone frame (27) is adhered to the rear surface of the support plate (21) along the edge shape of the support plate (21) by an adhesive, and there is a gap of 1-3 mm between the rear end surface of the silicone frame (27) and the concrete surface to allow air to enter through the gap.

8. A concrete structure engineering construction quality monitoring device according to claim 1, characterized in that: A through hole for the telescopic shaft (33) to pass through is provided inside the fixing seat (32), and a sliding bearing is provided inside the through hole.

9. A concrete structure engineering construction quality monitoring device according to claim 1, characterized in that: The top surface of the movable seat (37) is fixed with protrusions on both the left and right sides, and the interior of the protrusion is hinged to the bottom end of the pulling arm (34) through an axle pin.

10. A concrete structure engineering construction quality monitoring device according to claim 1, characterized in that: A layer of silicone sheet is adhered and fixed to the surfaces of one side of the clamp arms (35) that are close to each other by adhesive.