Municipal construction cast-in-place pile construction platform with high stability
By designing detection mechanisms, proofreading detection mechanisms and protective components on the cast-in-place pile construction platform for municipal construction, the problem of shaking and collapse caused by too many people during the construction process of the platform was solved, and precise control of construction workers and construction safety were achieved. improvement.
Patent Information
- Application Number
- CN202411256819.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-09
- Publication Date
- 2025-01-21
AI Technical Summary
During the construction process, the existing municipal construction cast-injected pile construction platform shakes or collapses due to too many personnel, and the stability of use is poor, making it difficult to accurately control construction personnel, resulting in construction safety issues.
A cast-in-place pile construction platform for municipal construction including a detection mechanism, a proofreading detection mechanism and protective components is designed. The detection mechanism records the weight and facial images of construction workers through pressure sensors and acquisition cameras. The calibration and detection mechanism performs further calibration through calibration pressure sensors and calibration cameras. The protective components accurately control the entry of construction workers through infrared sensors and partitions.
By accurately recording and proofreading the information of construction personnel, precise control of construction personnel is achieved, which improves the stability of use and construction safety of the cast-in-place pile construction platform for municipal construction.
Smart Images

Figure CN119332910A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of construction platforms, and more particularly to a municipal construction cast-in-place pile construction platform with high stability. Background Art
[0002] The cast-in-place pile construction platform is usually erected at a certain height, providing a stable working platform for construction workers and effectively preventing the risk of workers falling from heights. Secondly, it improves the working environment. The working environment on the platform is relatively safer and more stable, which helps to reduce accidental injuries during the construction process.
[0003] In the existing public documents, the patent with patent announcement number CN219930944U discloses an integrated operation platform for bored pile guide pipes. The integrated operation platform of the device has a simple structure, is easy to manufacture, has a stable structure, is convenient and safe to use, can effectively keep the bored pile construction site tidy and orderly, and can effectively recycle flushing wastewater. It has strong practicality and is suitable for use in integrated construction sites such as housing construction, municipal administration, and water conservancy. However, the platform has the following defects.
[0004] When the platform is used for the municipal construction bored pile construction platform, although the construction operation can be realized through the municipal construction bored pile construction platform, during the construction process, due to the large number of construction personnel, the excessive number of personnel will cause the municipal construction bored pile construction platform to shake or even collapse. Therefore, it is difficult to accurately control the construction personnel, resulting in poor stability of the municipal construction bored pile construction platform, which is very likely to cause construction safety problems. Therefore, it is necessary to propose a municipal construction bored pile construction platform with high stability. Summary of the invention
[0005] In order to overcome the above-mentioned defects of the prior art, the present invention provides a municipal construction cast-in-place pile construction platform with high stability.
[0006] To achieve the above-mentioned purpose, the present invention provides the following technical solutions: a municipal construction bored pile construction platform with high stability, comprising a platform, a stair frame and two guard frames, wherein the stair frame is fixed on one side of the platform, and the two guard frames are fixed on the inclined surface of the stair frame, and a detection mechanism is installed at the bottom end of the stair frame; the detection mechanism comprises a support plate fixedly installed at the bottom end of the stair frame, and a pressure sensor is fixedly connected to the top end of the support plate, and a pressure plate is fixedly installed at the top end of the pressure sensor, and guide blocks fixedly connected to the support plate are provided on both sides of the pressure sensor, and the two guide blocks are vertically slidably connected to the pressure plate; a corner block fixedly connected to the support plate is installed on one side of each guide block, and the corner block is slidably connected to the pressure plate, and a support plate is welded on one side of one of the guard frames; A reduction motor is fixedly connected to one end of the support plate, and a collection camera is fixedly installed on the output end of the reduction motor; a proofreading and detecting mechanism is installed on the inner wall of the stair frame plate; and a protective component is installed on the top of the platform.
[0007] Preferably, the platform and the stair frame are both made of stainless steel, and the pressure plate is slidably connected to the stair frame, the two corner blocks are slidably connected to the pressure plate, and the cross-sectional shape of the corner block is set to be L-shaped, the acquisition camera is rotatably connected to the guardrail, and the two guardrails are symmetrically arranged about the middle of the stair frame. Preferably, a plurality of support frames are fixedly connected to the bottom end of the platform and close to its edge line, and a reinforcing plate is welded to the bottom end of each support frame, and the reinforcing plate is used to support the support frame.
[0008] When this technology is used, construction workers can step on the pressure plate, which slides down along the two guide blocks. The pressure plate is pressed on the pressure sensor, and the support plate is supported by the stair frame. The pressure sensor provides vertical pressure sensing to the bottom of the pressure plate, and the weight of the construction workers can be recorded through the pressure sensor. The support plate supports the reduction motor, and the collection camera rotates downward to collect the construction worker's face and record the facial image.
[0009] Preferably, the calibration and detection mechanism comprises a plurality of treading support plates fixedly mounted on the inner wall of the stair frame; a calibration pressure sensor is fixedly mounted on the top of one of the treading support plates, a retest plate is fixedly connected to the top of the calibration pressure sensor, a guide plate is welded on one side of the retest plate, and a guide bar is fixedly connected to the other side of the retest plate; the guide bar and the guide plate are both slidably connected to the treading support plate; a reinforcement bracket is welded on the top of the guard frame, a controller is fixedly mounted on one side of the reinforcement bracket, two sleeve blocks are welded on the other side of the reinforcement bracket, and a rotating shaft is rotatably connected to the inner wall of the sleeve block; a driving motor is coaxially connected to one end of the rotating shaft, and the driving motor is fixedly connected to the reinforcement bracket, and a sleeve block fixedly connected to the rotating shaft is provided between the two sleeve blocks; a calibration camera is fixedly mounted on the bottom end of the sleeve block, the guide plate and the retest plate are both slidably connected to the stair frame, and the guide plate and the retest plate are both made of stainless steel, the two sleeve blocks are symmetrically arranged about the sleeve block, and the sleeve block and the sleeve block are both made of stainless steel.
[0010] When this technology is used, the construction workers continue to step on multiple pedal support plates, and continue to step on the retest board with both feet, and the retest board carries the guide bar downward. The retest board realizes pressure sensing on the calibration pressure sensor. When the pressure value sensed by the calibration pressure sensor is the same as the pressure sensor value sensed on the controller. At the same time, the guard frame supports the reinforcement bracket, and the drive motor drives the shaft to rotate. The shaft carries the socket block to rotate downward, and the socket block carries the calibration camera to rotate downward. When the face image passes through the controller to make the image sensed by the acquisition camera the same, the transmission motor is started through the controller.
[0011] Preferably, the protection component includes a enclosure plate fixedly mounted on the top of the platform; a sliding frame is welded to one side of the enclosure plate, and the inner wall of the sliding frame is rotatably connected to a screw, a transmission motor for driving the screw to rotate is fixedly mounted on one end of the sliding frame, a threaded sleeve is threadedly connected to the outer wall of the screw, and a partition is welded to the top of the threaded sleeve; an infrared sensor is fixedly mounted on one side of the partition, and the infrared sensor is made of stainless steel, the outer wall of the threaded sleeve and the partition are both slidably connected to the sliding frame, and the vertical cross-sectional shape of the partition is set to be rectangular.
[0012] When this technology is used, the transmission motor drives the screw to rotate forward, the screw rotates inside the sliding frame, the threaded sleeve carries the partition to move left, and the partition carries the infrared sensor to move left. When the partition is no longer blocked in the gap between the enclosure and the guardrail, and when the infrared sensor does not sense the left side of the construction personnel, the transmission motor is started through the controller to drive the screw to reverse, the threaded sleeve carries the partition to move right, the infrared sensor can realize the right movement operation, and the partition continues to be located in the gap between the guardrail and the enclosure to realize the blocking operation.
[0013] Technical effects and advantages of the present invention: 1. The present invention adopts a detection mechanism. Construction workers can step on the pressure plate. The pressure plate slides down along the two guide blocks. At the same time, the pressure plate moves down along the inner walls of the two corner blocks. The pressure plate is squeezed on the pressure sensor. The reduction motor drives the collection camera to rotate vertically downward. The collection camera rotates downward to collect the faces of the construction workers. The collection can be accurately controlled to enter the top of the platform for construction, thereby improving the use stability of the municipal construction bored pile construction platform and improving construction safety.
[0014] 2. The present invention uses the proofreading and testing mechanism. When the construction personnel continue to step on the multiple treading support plates and continue to step on the retesting plate with both feet, the retesting plate carries the guide bar downward. Both the guide plate and the guide bar move downward along the outer wall of the treading support plate. The retesting plate realizes pressure sensing on the proofreading pressure sensor. The pressure value sensed by the proofreading pressure sensor is the same as the pressure sensor value sensed on the controller. The rotating shaft carries the socket block to rotate downward. The socket block carries the proofreading camera to rotate downward. When the face image is the same as the image sensed by the acquisition camera through the controller, the transmission motor is started through the controller. In this way, the partition can be opened after proofreading again to allow the construction personnel to be located on the top of the platform.
[0015] 3. The present invention adopts a protective component. The transmission motor drives the screw to rotate forward, and the screw rotates inside the sliding frame. The threaded sleeve carries the partition to move left, and the partition carries the infrared sensor to move left. The construction personnel can enter the top of the platform. When the infrared sensor does not sense the left side of the construction personnel, the transmission motor is started by the controller to drive the screw to reverse, and the partition carries the infrared sensor to move right. In this way, the construction personnel entering the top of the platform can be accurately controlled.
[0016] The above multiple effects interact with each other. First, the pressure plate squeezes on the pressure sensor, and the collection camera rotates downward to collect the face of the construction worker. Secondly, the face image is made the same as the image sensed by the collection camera through the controller, and then the transmission motor is started through the controller. Then the partition carries the infrared sensor to the left to allow the personnel to enter the platform for construction, and then it is moved left again to reset. In summary, the construction personnel can be accurately controlled to enter the surface of the platform, which improves the stability of the use of the municipal construction cast-in-place pile construction platform, improves the construction safety, and is safer to use. BRIEF DESCRIPTION OF THE DRAWINGS
[0017] Figure 1 It is a schematic diagram of the overall structure of the municipal construction bored pile construction platform with high stability according to the present invention.
[0018] Figure 2 It is a schematic diagram of the partial structure of the connection between the stair frame and the guard frame of the present invention.
[0019] Figure 3 It is a schematic diagram of the partial structure of the connection between the support plate and the pressure sensor of the present invention from a front view.
[0020] Figure 4 It is a schematic diagram of the local structure of the connection between the support plate and the reduction motor of the present invention.
[0021] Figure 5 It is a schematic diagram of the vertical cross-section structure of a municipal construction bored pile construction platform with high stability according to the present invention.
[0022] Figure 6It is a schematic diagram of the local structure of the vertical section at the connection between the re-test plate and the guide plate of the present invention.
[0023] Figure 7 It is a schematic diagram of the local structure of the vertical section of the connection between the reinforcement bracket and the sleeve block of the present invention.
[0024] Figure 8 It is a schematic diagram of the front structural view of the protection component of the present invention.
[0025] The accompanying drawings are marked as follows: 1. platform; 2. stair frame; 3. guardrail; 4. support plate; 5. pressure sensor; 6. pressure plate; 7. guide block; 8. corner block; 9. support plate; 10. reduction motor; 11. acquisition camera; 12. support frame; 13. reinforcement plate; 14. pedal support plate; 15. calibration pressure sensor; 16. re-test plate; 17. guide plate; 18. guide strip; 19. reinforcement bracket; 20. sleeve block; 21. rotating shaft; 22. driving motor; 23. sleeve block; 24. calibration camera; 25. enclosure; 26. sliding frame; 27. screw; 28. transmission motor; 29. threaded sleeve block; 30. partition; 31. infrared sensor; 32. controller. DETAILED DESCRIPTION
[0026] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0027] As attached Figure 1-8 A high-stability municipal construction bored pile construction platform is shown. The high-stability municipal construction bored pile construction platform is equipped with a detection mechanism, a proofreading detection mechanism, and a protective component. The settings of each mechanism and component can accurately control the construction personnel entering the surface of the platform, improve the use stability of the municipal construction bored pile construction platform, improve the construction safety, and make it safer to use. The specific structural settings of each mechanism and component are as follows.
[0028] In this technical solution, as shown in the attached Figure 1-4As shown, the stair frame 2 is fixed on one side of the platform 1, and two guard frames 3 are fixed on the inclined surface of the stair frame 2. A detection mechanism is installed at the bottom end of the stair frame 2; the detection mechanism includes a support plate 4 fixedly installed at the bottom end of the stair frame 2, and a pressure sensor 5 is fixedly connected to the top of the support plate 4, and a pressure plate 6 is fixedly installed on the top of the pressure sensor 5, and guide blocks 7 fixedly connected to the support plate 4 are provided on both sides of the pressure sensor 5, and the two guide blocks 7 are vertically slidably connected to the pressure plate 6; a corner block 8 fixedly connected to the support plate 4 is installed on one side of each guide block 7, and the corner block 8 is slidably connected to the pressure plate 6, and a support plate 9 is welded on one side of one of the guard frames 3.
[0029] One end of the support plate 9 is fixedly connected to a reduction motor 10, and a collection camera 11 is fixedly installed at the output end of the reduction motor 10; a proofreading and detecting mechanism is installed on the inner wall of the stair frame plate 2; and a protective component is installed on the top of the platform 1.
[0030] In this technical solution, as shown in the attached Figure 1 As shown, a plurality of support frames 12 are fixedly connected to the bottom end of the platform 1 and near its edge line, and a reinforcement plate 13 is welded to the bottom end of each support frame 12. The reinforcement plate 13 is used to support the support frame 12, so that the plurality of support frames 12 can be supported separately by the plurality of reinforcement plates 13. The plurality of support frames 12 support the bottom of the platform 1, thereby increasing the stability of the platform 1.
[0031] In this technical solution, as shown in the attached Figure 5-7 As shown, the proofreading and detecting mechanism comprises a plurality of treading support plates 14 fixedly mounted on the inner wall of the stair frame plate 2; a proofreading pressure sensor 15 is fixedly mounted on the top of one of the treading support plates 14, a retest plate 16 is fixedly connected to the top of the proofreading pressure sensor 15, and a guide plate 17 is welded on one side of the retest plate 16, and a guide bar 18 is fixedly connected on the other side of the retest plate 16; the guide bar 18 and the guide plate 17 are both slidably connected to the treading support plate 14; a reinforcing bracket 19 is welded on the top of the guard frame 3, and a controller 32 is fixedly mounted on one side of the reinforcing bracket 19, and two sleeve blocks 20 are welded on the other side of the reinforcing bracket 19, and the inner wall of the sleeve block 20 is rotatably connected to a rotating shaft 21; one end of the rotating shaft 21 is coaxially connected to a driving motor 22, and the driving motor 22 is fixedly connected to the reinforcing bracket 19, and a sleeve block 23 fixedly connected to the rotating shaft 21 is provided between the two sleeve blocks 20; A calibration camera 24 is fixedly installed at the bottom end of the socket block 23, and the guide plate 17 and the re-measurement plate 16 are both slidably connected to the stair frame plate 2, and the guide plate 17 and the re-measurement plate 16 are both made of stainless steel. The two socket blocks 20 are symmetrically arranged about the socket block 23, and the socket blocks 23 and the socket blocks 20 are both made of stainless steel.
[0032] In this technical solution, as shown in the attached Figure 1-8As shown, the protection component includes a panel 25 fixedly mounted on the top of the platform 1; a sliding frame 26 is welded to one side of the panel 25, and a screw 27 is rotatably connected to the inner wall of the sliding frame 26, a transmission motor 28 for driving the screw 27 to rotate is fixedly mounted on one end of the sliding frame 26, a threaded sleeve 29 is threadedly connected to the outer wall of the screw 27, and a partition 30 is welded to the top of the threaded sleeve 29; an infrared sensor 31 is fixedly mounted on one side of the partition 30, and the infrared sensor 31 is made of stainless steel, the outer wall of the threaded sleeve 29 and the partition 30 are both slidably connected to the sliding frame 26, and the vertical cross-sectional shape of the partition 30 is set to be rectangular.
[0033] The working principle of the municipal construction cast-in-place pile construction platform of the present invention is as follows: Step 1, when the present invention is tested, multiple support frames 12 are supported respectively by multiple reinforcement plates 13, and multiple support frames 12 support the bottom of the platform 1 to increase the stability of the platform 1, and are connected to the injection pile construction position in the hole above the platform 1. Construction workers can step on the pressure plate 6, and the pressure plate 6 slides down along the two guide blocks 7. At the same time, the pressure plate 6 moves down along the inner wall of the two corner blocks 8, and the pressure plate 6 is squeezed on the pressure sensor 5. The support plate 4 is supported by the stair frame plate 2. The support plate 4 provides support force to the pressure sensor 5, and the pressure sensor 5 provides vertical pressure sensing to the bottom of the pressure plate 6, so that the weight of the construction workers can be recorded by the pressure sensor 5. At the same time, the guard frame 3 supports the support plate 9, and the support plate 9 supports the reduction motor 10. The reduction motor 10 drives the acquisition camera 11 to rotate vertically downward. The acquisition camera 11 rotates downward to collect the face of the construction worker and record the facial image, so that the facial image of the construction worker and the weight of the construction worker can be recorded on the controller 32.
[0034] Step 2, when the present invention performs the calibration and detection mechanism, the construction personnel continue to step on the multiple treading support plates 14, and continue to step on the retest plate 16 with both feet, the retest plate 16 drives the guide plate 17 to move downward, and at the same time, the retest plate 16 carries the guide bar 18 to move downward. The guide plate 17 and the guide bar 18 both move downward along the outer wall of the treading support plate 14, and the retest plate 16 realizes pressure sensing on the calibration pressure sensor 15, when the pressure value sensed by the calibration pressure sensor 15 is the same as the pressure value sensed by the pressure sensor 5 on the controller 32. At the same time, the guard frame 3 supports the reinforcement bracket 19, and the driving motor 22 drives the rotating shaft 21 to rotate, the rotating shaft 21 rotates inside the two sleeve blocks 20, and the rotating shaft 21 carries the sleeve block 23 to rotate downward, and the sleeve block 23 carries the calibration camera 24 to rotate downward, and the calibration camera 24 can collect the face image. When the face image is made the same as the image sensed by the acquisition camera 11 through the controller 32, the transmission motor 28 is started through the controller 32.
[0035] Step 3, when the present invention performs the protection assembly, the transmission motor 28 drives the screw 27 to rotate forward, and the screw 27 rotates inside the slide frame 26. At the same time, the screw 27 carries the threaded sleeve 29 to move left under the action of the thread transmission force, and the threaded sleeve 29 carries the partition 30 to move left, and the partition 30 carries the infrared sensor 31 to move left. When the partition 30 is no longer blocked in the gap between the enclosure 25 and the guard frame 3, the construction personnel can enter the top of the platform 1. When the infrared sensor 31 does not sense the left side of the construction personnel, then Then, the transmission motor 28 is started through the controller 32 to drive the screw 27 to reverse. The screw 27 carries the threaded sleeve 29 to move right under the action of the thread transmission force, and the threaded sleeve 29 carries the partition 30 to move right. The partition 30 carries the infrared sensor 31 to move right. The infrared sensor 31 can realize the right movement operation, and the partition 30 continues to be located in the gap between the guard frame 3 and the enclosure 25 to realize the blocking operation. In this way, the construction personnel entering the top of the platform 1 can be accurately controlled to prevent the personnel who exceed the standard or do not meet the requirements from entering the site at will.
[0036] Step 4: When the municipal bored piles are constructed according to the present invention, the construction personnel can perform the construction and pouring operation on the municipal bored piles on the top of the platform 1, perform the encapsulation operation on the column, and complete the municipal bored pile construction operation.
[0037] The contents not described in detail in the specification belong to the prior art known to those skilled in the art, and the model parameters of each electrical appliance are not specifically limited, and conventional equipment can be used. In this technical solution, the electrical control components not mentioned are not shown in the figure because they belong to the prior art and will not be described here.
[0038] The above are only preferred embodiments of the present invention and are not intended to limit the present invention. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the present invention should be included in the protection scope of the present invention.
Claims
1. A municipal construction bored pile construction platform with high stability, comprising a platform (1), a staircase frame (2) and two guardrails (3), characterized in that: The stair frame (2) is fixed on one side of the platform (1), the two guard frames (3) are fixed on the upper inclined surface of the stair frame (2), and a detection mechanism is installed at the bottom end of the stair frame (2); The detection mechanism comprises a support plate (4) fixedly mounted on the bottom end of the stair frame plate (2), and a pressure sensor (5) is fixedly connected to the top end of the support plate (4), and a pressure plate (6) is fixedly mounted to the top end of the pressure sensor (5), and guide blocks (7) fixedly connected to the support plate (4) are provided on both sides of the pressure sensor (5), and the two guide blocks (7) are vertically slidably connected to the pressure plate (6); A corner block (8) fixedly connected to the support plate (4) is installed on one side of each guide block (7), and the corner block (8) is slidably connected to the pressure plate (6), and a support plate (9) is welded on one side of one of the guard frames (3); One end of the support plate (9) is fixedly connected to a reduction motor (10), and an acquisition camera (11) is fixedly mounted on the output end of the reduction motor (10); The inner wall of the stair frame plate (2) is provided with a calibration and detection mechanism; A protection component is installed on the top of the platform (1).
2. The municipal construction bored pile construction platform with high stability according to claim 1 is characterized by: The platform (1) and the stair frame (2) are both made of stainless steel, and the pressure plate (6) is slidably connected to the stair frame (2).
3. The municipal construction bored pile construction platform with high stability according to claim 1 is characterized by: The two corner blocks (8) are both slidably connected to the pressure plate (6), and the cross-sectional shape of the corner block (8) is set to be L-shaped.
4. The high-stability municipal construction cast-in-place pile construction platform according to claim 1 is characterized by: The acquisition camera (11) is rotatably connected to the guard frame (3), and the two guard frames (3) are symmetrically arranged about the middle of the stair frame (2).
5. The municipal construction bored pile construction platform with high stability according to claim 1 is characterized by: A plurality of support frames (12) are fixedly connected to the bottom end of the platform (1) and close to the edge line thereof, and a reinforcing plate (13) is welded to the bottom end of each support frame (12), and the reinforcing plate (13) is used to support the support frame (12).
6. The high-stability municipal construction bored pile construction platform according to claim 1 is characterized by: The calibration and detection mechanism comprises a plurality of tread support plates (14) fixedly mounted on the inner wall of the stair frame plate (2); A calibration pressure sensor (15) is fixedly mounted on the top of one of the pedal support plates (14), a retest plate (16) is fixedly connected to the top of the calibration pressure sensor (15), a guide plate (17) is welded to one side of the retest plate (16), and a guide strip (18) is fixedly connected to the other side of the retest plate (16); The guide strip (18) and the guide plate (17) are both slidably connected to the pedal support plate (14); A reinforcement bracket (19) is welded to the top of the guard frame (3), and a controller (32) is fixedly mounted on one side of the reinforcement bracket (19), and two sleeve blocks (20) are welded to the other side of the reinforcement bracket (19), and the inner wall of the sleeve block (20) is rotatably connected to a rotating shaft (21); One end of the rotating shaft (21) is coaxially connected to a driving motor (22), and the driving motor (22) is fixedly connected to the reinforcement bracket (19), and a sleeve block (23) fixedly connected to the rotating shaft (21) is provided between the two sleeve blocks (20); A calibration camera (24) is fixedly mounted on the bottom end of the sleeve block (23).
7. The high-stability municipal construction bored pile construction platform according to claim 6 is characterized by: The guide plate (17) and the retest plate (16) are both slidably connected to the stair frame plate (2), and the guide plate (17) and the retest plate (16) are both made of stainless steel.
8. The high-stability municipal construction bored pile construction platform according to claim 6 is characterized by: The two sleeve blocks (20) are symmetrically arranged with respect to the sleeve block (23); the sleeve block (23) and the sleeve block (20) are both made of stainless steel.
9. The high-stability municipal construction cast-in-place pile construction platform according to claim 1 is characterized by: The protection assembly comprises a panel (25) fixedly mounted on the top of the platform (1); A sliding frame (26) is welded to one side of the enclosure plate (25), and a screw rod (27) is rotatably connected to the inner wall of the sliding frame (26); a transmission motor (28) for driving the screw rod (27) to rotate is fixedly mounted to one end of the sliding frame (26); a threaded sleeve (29) is threadedly connected to the outer wall of the screw rod (27), and a partition plate (30) is welded to the top end of the threaded sleeve (29); An infrared sensor (31) is fixedly mounted on one side of the partition (30), and the infrared sensor (31) is made of stainless steel.
10. The high-stability municipal construction cast-in-place pile construction platform according to claim 9, characterized in that: The outer wall of the threaded sleeve block (29) and the partition plate (30) are both slidably connected to the sliding frame (26), and the vertical cross-section of the partition plate (30) is set to be rectangular.
Citation Information
Patent Citations
Cast-in-place pile and guide pipe integrated operation platform
CN219930944U