Block type underground comprehensive pipe gallery

Through block design and height adjustment connection slot, the problem of low connection intensity and height of the existing underground comprehensive pipe galleries is solved, and the effect of highly adjusting construction efficiency of the pipe gallery unit is improved.

CN119352568AInactive Publication Date: 2025-01-24FUZHOU PLANNING DESIGN & RES INST

Patent Information

Application Number
CN202411920757.2
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-12-25
Publication Date
2025-01-24
Estimated Expiration
Not applicable · inactive patent

AI Technical Summary

Technical Problem

When connecting the upper corridor and the lower corridor, the steel plate connection strength in the middle is low and requires welding, so the construction efficiency is low. At the same time, the height of the vertical beam partition space is not easy to adjust, which affects the construction efficiency.

Method used

A block-type underground comprehensive pipe gallery design is adopted. The pipe gallery unit is composed of block splicing box culverts connected through connecting plug-ins. The block splicing box culverts are equipped with height adjustment connection grooves on the side to achieve adjustable height; the upper prefabricated gallery body and The lower prefabricated corridor is connected through connecting convex strips and butt chute, which does not require welding and simplifies construction.

Benefits of technology

The height of the pipe gallery unit block is adjustable, which simplifies the construction process, reduces the need for welding, and improves construction efficiency.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119352568A_ABST
    Figure CN119352568A_ABST
Patent Text Reader

Abstract

The invention discloses a block type underground comprehensive pipe gallery, and belongs to the technical field of underground comprehensive pipe galleries, the block type underground comprehensive pipe gallery comprises a plurality of pipe gallery units arranged in the extending direction of the pipe gallery, each pipe gallery unit comprises at least two block splicing box culvert bodies connected through connecting plug-ins, and the side faces of the block splicing box culvert bodies are provided with a plurality of height adjusting connecting grooves arranged side by side; the block splicing box culvert body comprises an upper prefabricated corridor body and a lower prefabricated corridor body, a connecting protruding strip of the lower prefabricated corridor body is arranged in a butt joint sliding groove of the upper prefabricated corridor body, and at least one positioning mechanism is arranged in the upper prefabricated corridor body. By the adoption of the block type underground comprehensive pipe gallery, construction is easy, the relative height of the block splicing box culvert bodies can be adjusted, and construction of specific engineering is facilitated.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of underground integrated pipe corridors, and in particular to a block-type underground integrated pipe corridor. Background Art

[0002] Underground utility corridors are public tunnels built underground in cities for laying municipal pipelines such as electricity, communications, radio and television, and water supply. Underground utility corridors can effectively prevent the zipper road phenomenon, so that technicians do not need to repeatedly dig up the road surface. They can repair, maintain, expand and transform various pipelines in the corridors, and greatly reduce the time for pipeline repairs.

[0003] After searching, the publication number CN211257071U discloses a prefabricated pipe gallery, which includes a plurality of pipe gallery body prefabricated parts spliced ​​in sequence along the radial direction of the pipe gallery corridor; wherein each pipe gallery body prefabricated part includes an upper gallery body and a lower gallery body; wherein the upper gallery body includes a first cross beam, a first vertical beam, a first embedded steel plate and a first adhesive layer; wherein the lower gallery body includes a second cross beam, a second vertical beam, a second embedded steel plate and a second adhesive layer, the second vertical beam is connected to the second cross beam, and is arranged in the middle and both sides of the second cross beam, the second embedded steel plate is arranged on the peripheral side of the second vertical beam, and is located at one end of the second vertical beam away from the second cross beam, and the second adhesive layer is arranged at one end of the second vertical beam away from the second cross beam; wherein the first embedded steel plate is welded to the second embedded steel plate, and the first adhesive layer is adhered to the second adhesive layer, so that the first vertical beam is connected to the second vertical beam, and the upper gallery body is at the top of the lower gallery body. The prefabricated pipe gallery has strong deformation resistance and good waterproof performance.

[0004] But there are still the following problems: (1) Although the upper and lower corridors are combined by splicing, the middle part is connected and fixed with steel plates, which has low connection strength and requires welding, resulting in low construction efficiency.

[0005] (2) Multiple vertical beams are used to separate the space. However, since the integrated pipe corridor contains pipes and pipelines such as electricity, communications, and water supply, they need to be arranged at different heights. The various functional compartments do not have the function of height adjustment, and they need to be cast on site or prefabricated with box culverts of specific shapes, which affects the construction efficiency. Summary of the invention

[0006] The purpose of the present invention is to provide a block-type underground comprehensive pipeline corridor to solve the above-mentioned technical problems.

[0007] To achieve the above-mentioned object, the present invention provides a block-type underground comprehensive pipe gallery, including a plurality of pipe gallery units arranged along the extension direction of the pipe gallery, the pipe gallery unit including at least two block splicing box culverts connected by connecting plug-ins, and a plurality of parallel height adjustment connection grooves are arranged on the side of the block splicing box culvert; The block splicing box culvert body comprises an upper prefabricated gallery body and a lower prefabricated gallery body, the connecting convex strips of the lower prefabricated gallery body are arranged in the docking slide grooves of the upper prefabricated gallery body, and at least one positioning mechanism is arranged in the upper prefabricated gallery body.

[0008] Preferably, the upper prefabricated gallery body and the lower prefabricated gallery body are both U-shaped structures, and height-adjusting connecting grooves are provided on the outer sides of the upper prefabricated gallery body and the lower prefabricated gallery body.

[0009] Preferably, the cross section of the height adjustment connecting groove is trapezoidal, T-shaped or L-shaped; When the cross section of the height adjustment connection groove is trapezoidal, the cross section of the connection plug-in is butterfly-shaped; When the cross section of the height adjustment connection groove is T-shaped, the cross section of the connection plug-in is I-shaped; When the cross section of the height adjustment connecting groove is L-shaped, the directions of the height adjustment connecting grooves of the upper prefabricated gallery body and the lower prefabricated gallery body are opposite, and the cross section of the connecting plug-in is Z-shaped.

[0010] Preferably, the side wall of the upper prefabricated gallery is provided with a pouring through hole, and the side wall of the lower prefabricated gallery is provided with a pouring blind hole, and the pouring through hole and the pouring blind hole are arranged opposite to each other.

[0011] Preferably, the side wall of the upper prefabricated gallery is provided with a T-shaped positioning channel, and the positioning mechanism includes a tightening rod, which is arranged in the vertical channel of the T-shaped positioning channel, and one end of the transverse channel of the T-shaped positioning channel is communicated with the interior of the upper prefabricated gallery, and a threaded sleeve is arranged in the transverse channel of the T-shaped positioning channel, and a pushing screw is arranged in the threaded sleeve, one end of the pushing screw is provided with an operating part, and the other end of the pushing screw is arranged to be inclined, the upper end of the tightening rod is inclined, and the lower end of the tightening rod is provided with an engaging groove.

[0012] Preferably, the cross-section of the connecting convex strip at the upper end of the lower prefabricated gallery is trapezoidal, and the connecting convex strip and the opposite surface of the docking groove are provided with meshing lines, which are matched with the meshing groove and are sawtooth, wave or pulse shaped.

[0013] Preferably, the contact surfaces of the upper prefabricated gallery body and the lower prefabricated gallery body are both provided with at least one first sealing groove, and a first sealing strip is provided in the first sealing groove.

[0014] Preferably, at least one second sealing groove is provided on both sides of the upper prefabricated gallery body and the lower prefabricated gallery body, and a second sealing strip is provided in the second sealing groove.

[0015] Preferably, a water storage chamber is provided at the bottom of the lower prefabricated gallery, a water inlet hole is provided at the upper portion of the water storage chamber, and a bucket-shaped lower portion of the water storage chamber is provided with a water outlet.

[0016] Preferably, at least one support installation groove is provided at the bottom of the lower prefabricated corridor, the cross-section of the support installation groove is trapezoidal, at least one support prefabricated part is provided in the support installation groove, the support prefabricated part is a C-shaped structure or a human-shaped structure or a strip, a slider is provided on the top of the support prefabricated part, mounting parts are provided on both sides of the slider, and the mounting parts are installed in the support slide groove by bolts.

[0017] Therefore, the present invention adopts the above-mentioned block-type underground comprehensive pipe gallery, which has the following beneficial effects: (1) The adjacent block splicing box culverts in the pipe gallery unit are connected by connecting plugs. A number of parallel height adjustment connecting grooves are arranged on the side of the block splicing box culvert to achieve the relative height adjustment of the adjacent block splicing box culverts.

[0018] (2) The block splicing box culvert body includes an upper prefabricated gallery body and a lower prefabricated gallery body. The connecting convex strip of the lower prefabricated gallery body is arranged in the docking slide groove of the upper prefabricated gallery body. At least one positioning mechanism is arranged in the upper prefabricated gallery body. No welding is required, the construction is simple, and the construction period is shortened.

[0019] The technical solution of the present invention is further described in detail below through the accompanying drawings and embodiments. BRIEF DESCRIPTION OF THE DRAWINGS

[0020] Figure 1 This is a schematic diagram of a block-type underground comprehensive pipe gallery structure of the present invention; Figure 2 This is an exploded view of the block splicing box body of the present invention; Figure 3 This is a schematic diagram of the structure of the connecting convex strips of the present invention; Figure 4 This is a schematic diagram of the second sealing groove arrangement position structure of the present invention; Figure 5 This is a schematic diagram of the structure of the first sealing groove setting position of the present invention; Figure 6 This is a schematic diagram of the construction process of the positioning mechanism of the present invention; Figure 7 It is a schematic diagram of the supporting prefabricated structure of the human figure of the present invention; Figure 8 This is a schematic diagram of the water storage chamber structure of the present invention; Fig. 9 This is a schematic diagram of the I-shaped connecting plug structure of the present invention; Fig.10 It is a schematic diagram of the Z-shaped connecting plug structure of the present invention.

[0021] Reference numerals 1. Block splicing box culvert body; 11. Height adjustment connecting groove; 12. Upper prefabricated gallery; 121. Docking slide groove; 122. Casting through hole; 123. T-shaped positioning channel; 13. Lower prefabricated gallery; 131. Connecting convex strip; 132. Casting blind hole; 133. Engaging pattern; 134. Water storage cavity; 135. Water inlet hole; 136. Water outlet; 137. Support installation groove; 14. First sealing groove; 15. Second sealing groove; 2. Connecting plug-in; 3. Positioning mechanism; 31. Tightening rod; 311. Engaging groove; 32. Threaded sleeve; 33. Push screw; 331. Operating part; 4. Support prefabricated part; 41. Sliding block; 42. Installation part. DETAILED DESCRIPTION

[0022] In the description of the present invention, it should be noted that the terms "upper", "lower", "inside", "outside", etc. indicate positions or positional relationships based on the positions or positional relationships shown in the accompanying drawings, or the positions or positional relationships in which the invented product is usually placed when in use. They are only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as a limitation on the present invention. In the description of the present invention, it should also be noted that, unless otherwise clearly specified and limited, the terms "set", "install", and "connect" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or it can be an indirect connection through an intermediate medium, or it can be a connection between the two elements. For those of ordinary skill in the art, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.

[0023] The embodiments of the present invention are described in detail below in conjunction with the accompanying drawings.

[0024] Example 1 like Figure 1 As shown, a block-type underground comprehensive pipe gallery includes a plurality of pipe gallery units arranged along the extension direction of the pipe gallery, and the pipe gallery unit includes three block splicing box culverts 1 connected by connecting plug-ins 2 (the number and height position of the block splicing box culverts 1 are determined according to the specific functional zoning of the pipe gallery), and the three block splicing box culverts 1 are used to set cables, water pipes and gas pipes in turn.

[0025] like Figure 2-Figure 5As shown, the block splicing box culvert 1 includes an upper prefabricated gallery 12 and a lower prefabricated gallery 13, both of which are U-shaped structures, and the contact surfaces of the upper prefabricated gallery 12 and the lower prefabricated gallery 13 are provided with two first sealing grooves 14, and the first sealing grooves 14 are provided with first sealing strips to achieve waterproofing at the splicing of the upper prefabricated gallery 12 and the lower prefabricated gallery 13. A second sealing groove 15 is provided on both sides of the upper prefabricated gallery 12 and the lower prefabricated gallery 13, and the second sealing strip is provided in the second sealing groove 15 to achieve waterproofing of the adjacent block splicing box culvert 1.

[0026] The side wall of the upper prefabricated gallery 12 is provided with a pouring through hole 122, and the side wall of the lower prefabricated gallery 13 is provided with a pouring blind hole 132, and the pouring through hole 122 is arranged opposite to the pouring blind hole 132. The outer sides of the upper prefabricated gallery 12 and the lower prefabricated gallery 13 are both provided with a height adjustment connecting groove 11. In this embodiment, the cross section of the height adjustment connecting groove 11 is a trapezoid, and the cross section of the connecting plug 2 is a butterfly shape. The connecting convex strip 131 of the lower prefabricated gallery 13 is arranged in the docking slide groove 121 of the upper prefabricated gallery 12, and four positioning mechanisms 3 are arranged in the upper prefabricated gallery 12. The positioning mechanism 3 includes a tightening rod 31, a T-shaped positioning channel 123 is provided on the side wall of the upper prefabricated gallery 12, the tightening rod 31 is arranged in the vertical channel of the T-shaped positioning channel 123, one end of the transverse channel of the T-shaped positioning channel 123 is connected to the interior of the upper prefabricated gallery 12, a threaded sleeve 32 is provided in the transverse channel of the T-shaped positioning channel 123, a pushing screw 33 is provided in the threaded sleeve 32, one end of the pushing screw 33 is provided with an operating part 331, the other end of the pushing screw 33 is arranged to be inclined, the upper end of the tightening rod 31 is inclined, and the lower end of the tightening rod 31 is provided with an engagement groove 311. The specific construction process is as follows: like Figure 6 As shown, the lower prefabricated gallery 13 is fixed in the foundation pit, and the upper prefabricated gallery 12 is placed with its opening facing upward. The tightening rod 31 is inserted into the vertical channel of the T-shaped positioning channel 123, and is tightened and positioned by pushing the screw 33. The upper prefabricated gallery 12 is slid downward from one side of the lower prefabricated gallery 13 to the other side until the upper prefabricated gallery 12 and the lower prefabricated gallery 13 correspond to each other up and down, and the pushing screw 33 is loosened. Under the action of gravity, the tightening rod 31 falls and is relatively arranged to the connecting convex strip 131, and the pushing screw 33 is rotated to tighten and position, thereby realizing the assembly of the upper prefabricated gallery 12 and the lower prefabricated gallery 13, and then the pouring through hole 122 is cast, thereby improving the connection strength, and the structure and construction process are simple.

[0027] The cross-section of the connecting ridge 131 at the upper end of the lower prefabricated gallery 13 is trapezoidal, and the connecting ridge 131 and the opposite surface of the docking groove 121 are provided with meshing lines 133, which are adapted to the meshing groove 311 and are serrated, wavy or pulse-shaped, thereby increasing the lateral damping force and improving the connection strength.

[0028] like Figure 8 As shown, a water storage chamber 134 is provided at the bottom of the lower prefabricated gallery 13, a water inlet hole 135 is provided at the upper part of the water storage chamber 134, and a water outlet 136 is provided at the lower part of the water storage chamber 134 in a bucket shape for draining excess water in the gallery. Two support installation grooves 137 are provided in parallel at the bottom of the lower prefabricated gallery 13, and the cross section of the support installation grooves 137 is trapezoidal, and two support prefabricated members 4 are provided in the support installation grooves 137, and the support prefabricated members 4 are C-shaped structures and strips, as shown in FIG. Figure 7 As shown, it can also be set to a human shape, a slider 41 is set on the top of the supporting prefabricated part 4, and mounting parts 42 are set on both sides of the slider 41. The mounting parts 42 are installed in the supporting slide groove by bolts, which are used to support the box culvert body 1 spliced ​​in blocks of different heights. The supporting prefabricated part 4 can have a predetermined height according to actual conditions, or a strip prefabricated part with an adjustable height can be set in the middle of the supporting prefabricated part 4, and bolts are used to connect it to achieve height adjustment of the supporting prefabricated part.

[0029] Example 2 The difference between this embodiment and embodiment 1 is that the cross section of the height adjustment connecting groove 11 is T-shaped. Fig. 9 As shown, the connecting plug 2 has an I-shaped cross section.

[0030] Example 3 The difference between this embodiment and embodiment 1 is that the cross section of the height adjustment connecting groove 11 is L-shaped. Fig.10 As shown, the height adjustment connection grooves 11 of the upper prefabricated gallery body 12 and the lower prefabricated gallery body 13 are in opposite directions, and the connecting plug-in 2 has a Z-shaped cross section.

[0031] Finally, it should be noted that the above embodiments are only used to illustrate the technical solution of the present invention rather than to limit it. Although the present invention has been described in detail with reference to the preferred embodiments, those skilled in the art should understand that they can still modify or replace the technical solution of the present invention with equivalents, and these modifications or equivalent replacements cannot cause the modified technical solution to deviate from the spirit and scope of the technical solution of the present invention.

Claims

1. A block-type underground integrated pipe gallery, comprising a plurality of pipe gallery units arranged along the extension direction of the pipe gallery, characterized in that: The pipe gallery unit comprises at least two block splicing box culverts connected by connecting plug-ins, and a plurality of parallel height adjustment connecting grooves are arranged on the side of the block splicing box culvert; The block splicing box culvert body comprises an upper prefabricated gallery body and a lower prefabricated gallery body, the connecting convex strips of the lower prefabricated gallery body are arranged in the docking slide grooves of the upper prefabricated gallery body, and at least one positioning mechanism is arranged in the upper prefabricated gallery body.

2. The block-type underground comprehensive pipe gallery according to claim 1 is characterized in that: The upper prefabricated gallery body and the lower prefabricated gallery body are both U-shaped structures, and height-adjusting connecting grooves are arranged on the outer sides of the upper prefabricated gallery body and the lower prefabricated gallery body.

3. The block-type underground comprehensive pipe gallery according to claim 2 is characterized in that: The cross section of the height adjustment connection groove is trapezoidal, T-shaped or L-shaped; When the cross section of the height adjustment connection groove is trapezoidal, the cross section of the connection plug-in is butterfly-shaped; When the cross section of the height adjustment connection groove is T-shaped, the cross section of the connection plug-in is I-shaped; When the cross section of the height adjustment connecting groove is L-shaped, the directions of the height adjustment connecting grooves of the upper prefabricated gallery body and the lower prefabricated gallery body are opposite, and the cross section of the connecting plug-in is Z-shaped.

4. The block-type underground comprehensive pipe gallery according to claim 3 is characterized in that: The side wall of the upper prefabricated gallery is provided with a pouring through hole, and the side wall of the lower prefabricated gallery is provided with a pouring blind hole, and the pouring through hole and the pouring blind hole are arranged opposite to each other.

5. The block-type underground comprehensive pipe gallery according to claim 4 is characterized in that: A T-shaped positioning channel is provided on the side wall of the upper prefabricated gallery body. The positioning mechanism includes a tightening rod, which is arranged in the vertical channel of the T-shaped positioning channel. One end of the transverse channel of the T-shaped positioning channel is communicated with the interior of the upper prefabricated gallery body. A threaded sleeve is provided in the transverse channel of the T-shaped positioning channel. A pushing screw is provided in the threaded sleeve. An operating part is provided at one end of the pushing screw. The other end of the pushing screw is arranged to be inclined. The upper end of the tightening rod is inclined, and the lower end of the tightening rod is provided with an engaging groove.

6. The block-type underground comprehensive pipe gallery according to claim 5 is characterized in that: The cross section of the connecting convex strip at the upper end of the lower prefabricated gallery is trapezoidal, and the opposite surfaces of the connecting convex strip and the docking groove are provided with meshing lines, which are matched with the meshing groove and are sawtooth, wave or pulse shaped.

7. The block-type underground comprehensive pipe gallery according to claim 6 is characterized in that: The contact surfaces of the upper prefabricated gallery body and the lower prefabricated gallery body are both provided with at least one first sealing groove, and a first sealing strip is provided in the first sealing groove.

8. The block-type underground comprehensive pipe gallery according to claim 7 is characterized in that: At least one second sealing groove is arranged on both sides of the upper prefabricated gallery body and the lower prefabricated gallery body, and a second sealing strip is arranged in the second sealing groove.

9. The block-type underground comprehensive pipe gallery according to claim 8 is characterized in that: A water storage cavity is arranged at the bottom of the lower prefabricated gallery, a water inlet hole is arranged at the upper part of the water storage cavity, and a bucket-shaped arrangement and a water outlet are arranged at the lower part of the water storage cavity.

10. The block-type underground comprehensive pipe gallery according to claim 9 is characterized in that: At least one support installation groove is arranged at the bottom of the lower prefabricated corridor, the cross-section of the support installation groove is trapezoidal, at least one support prefabricated part is arranged in the support installation groove, the support prefabricated part is a C-shaped structure or a human-shaped structure or a strip, a slider is arranged on the top of the support prefabricated part, mounting parts are arranged on both sides of the slider, and the mounting parts are installed in the support slide groove by bolts.

Citation Information

Patent Citations

  • Prefabricated pipe gallery

    CN211257071U

  • Sample pool and device for detecting multiple water quality indexes

    CN109580898A

  • Waterfront L-shaped comprehensive pipe gallery

    CN117661624A

  • Split type pipe gallery

    CN211816411U

  • Concrete pipe pile butt joint structure

    CN220888626U

Cited By

  • Underground comprehensive pipe gallery with rainwater regulation and storage function

    CN121781626A